bush house buildings - king's college london · • if you’re working bush house and you...
TRANSCRIPT
Bush House buildings
Contractor Site induction
October 2017
Welcome
2
• Bush House is the newest complex to
the Strand Campus
• There are four buildings in the Bush
House complex, shown on the map.
• We are currently refurbishing three
buildings and the Lower Ground
which, when complete, will form an
integral part of the Strand Campus.
1
23
4
1. Bush House Centre Block
2. North East Wing
3. Melbourne House
4. South East Wing
5. Courtyard (with access to the Lower Ground when complete)
5
3
• Centre Block is occupied and
operational , however work
continue in the other buildings
of the complex and in the
Courtyard and the Lower
Ground below the complex
• We’ve put many measures in
place to keep you, your
colleagues and visitors safe, but
it’s important that you take
extra care and notice of the
safety signs around the site.
• Evacuation maps are on each
floor, so please take the time to
understand your emergency exit
route out of the building
Your safety – your responsibility
Site safety rules
4
• If you see this sign anywhere
around Bush House buildings,
please don’t enter the area.
In an emergency
5
• Once at your muster point
please report to your line
manager.
• Do not re-enter the building
until you’re told it’s safe by
an Evacuation Marshall or
Evacuation Controller.
• The fire alarm will be tested
every Friday at 3pm.
In an emergency
6
• You can release access controlled doors by breaking the
glass in the green emergency boxes
• We have installed fire curtains to help stop fire
spreading, which function as follows:
• when the fire alarm first sounds, if there is fire
curtain located immediately next to the activated
smoke head, it will deploy a third of the way down
the door
• after five minutes, the curtains will fully cover the
door
• if the curtain has come down fully before you’ve
left the building, you can release it using the
override button
In an emergency – if you need help
7
• If you’re working Bush House and you have any physical impairment which will limit
your ability to evacuate the building without help, you should have a personal
emergency evacuation plan (PEEP) agreed with your line manager/key contact
before entering the building.
• There’s guidance
available on
developing a personal
emergency
evacuation plan here
(King’s login
required)
Your evacuation marshals & first aiders
8
• A list of the Evacuation Marshals for the different floors can be found here:
Evacuation Marshals & Controllers
• The role of Evacuation Controller will be undertaken by the Security team
based at Bush House.
• You can find your nearest first aider here:
First Aiders list
• Reception/Security will also be able to give you the contact details for your
nearest first aider.
Estates & Facilities Procedures
9
The following work requires at least 24 hours notice
• Access to ceiling voids
• Work involving noisy or dusty procedures
• Work requiring isolation of fire detectors
• Working with or altering building fabric
Do NOT move or disconnect any security devices without prior notification
and approval of the Estates & Facilities and Security Departments.
• Hand tools and plant must be 110v and PAT tested
• Trailing leads must be covered in high visibility tape
• ALL equipment must be provided by you and may NOT be left in any
building
• In the event of unscheduled work/unforeseen circumstances staff need to
be aware of the conditions of the risk assessment.
Permit to Work
10
To obtain a Permit to Work You MUST supply a Method Statement and Risk Assessment to Estates & Facilities at least 24 hours prior to works commencing.
• You must have completed a contractors site induction within the last 12 months (this document).
• You must have authorisation from Estates & Facilities to start work. • Permits are issued from the Estates & Facilities Shift Office in Room K-2.47,
Level -2 King’s Building Works requiring PERMIT TO WORK include:
o Work in confined spaces o Work in operational laboratories o Hot works o Work on high or low voltage electrical systems o Work on fire alarm or emergency lighting systems o Work on roofs o Work in an excavation o Work with asbestos o Work involving the erection of a scaffold or tower scaffold
No such work should commence without authorisation from Estates & Facilities.
Permit to Work
11
No works will be allowed to begin without: • A RISK ASSESSMENT and a METHOD STATEMENT, specific to the task at
hand; • Viewing and discussing the ASBESTOS REGISTER with the Estates &
Facilities Department on site; • Wearing Personal Protective Equipment (PPE) suitable to the task, or as site
rules indicate;
The College CANNOT accommodate storage of materials/ tools within the buildings. • Tools/materials should be stored in work area compounds. These are to be
agreed and assigned (if necessary) in advance. • ANY tools/materials left unattended can be disposed of WITHOUT notice • Discuss any combustible or explosive articles with the Estates & Facilities
Department before they are brought on site. • Oxy/acetylene is NOT allowed on College premises
Permit to Access
12
Permission to Access Permits are designed for managing contractors carrying out low risk activities around the College estate.
Tasks that may be covered by Permission to Access Permit includes: • Routine Planned Maintenance • Visual Site Surveys • Utility Meter Readings etc.
All activities are carried out on a risk based approach which will determine the level of controls required. • To obtain a permission to access permit you must have completed a
contractors site induction (this document). • You must have authorisation from Estates & Facilities to start work. • Permits are issued from the SECURITY, Main Gate, Strand Building Security
Room, 020 7848 1024 /2000
Contractors rules must be obeyed at all times
Use of Sub-Contractors
13
If your contract with the College allows the use of sub-contractors the following
is required:
• Your managers and/or foremen must ensure that all subcontracted personnel
attend a King’s College London Induction.
• Inductions may be arranged by contacting the Estates & Facilities Shift Office
on Ext. 020 7848 2908
• Personnel found working on site without having attended an induction and
not covered by a valid permit may suspended from site without notice.
Safe System of Work
14
Due to the age and nature of our buildings, many of them may contain asbestos containing materials (ACM’s).
Below gives an example of the type of activity which requires viewing the Asbestos Register:
• Access to ceiling voids • Working with or altering building
fabric • Entering Plant Areas or riser spaces
This list is not exhaustive, please discuss with your permit issuer prior to starting works.
Site Security
15
• You will be issued with an ID CARD upon completion of the Induction process.
• Your ID card must be visible at ALL times and returned to the Strand Building Security Control Room upon leaving site.
ACCESS CONTROL o DO NOT leave external doors open and unattended. o DO NOT let anyone in without asking them to produce their pass. o Inform SECURITY on 020 7848 1024 if Access Control doors need to be
kept open or if a Fire Door needs to be used.
SECURITY o Scaffolds and builders’ lifts must not be accessible out of hours, security
measures must be agreed before erection of the equipment. o Ladders must be secure when not in use o Inform Security if you require out of hours or weekend working. o DO NOT leave waste anywhere onsite e.g. in stairwells, corridors,
cleaners cupboards etc.
Key Bush House Contacts
16
• Victoria Tidboald – Assistant Director of Campus Operations –
Arts and Sciences. 07796 993 403
• Scott Maskell – Project Services Mobilisation Manager
07506 830 307
• Mike Gowers – Hard Services Team Leader
07557 564086
• Janice Savage – Senior Duty Manager
07825 758840
• Roger Chapman – Duty Manager
07796175916
My safety – my responsibility
17
Please:
• Confirm that you’ve read and understood this briefing
• Confirm that you know where your muster point is
• Confirm that you know who your evacuation marshal is
Induction Acknowledgement
18
Bush House Complex
Building…………………………………………..
Company Name………………………………...
First Name SurnameInduction
DateMobile
NumberSignature