1 International Telecommunication Union ITU – Business case for Access - OGS Yogyakarta , Indonesia, 27-29 June 2009 ITU-D Regional Development Forum for the Asia Pacific Region NGN and Broadband, Opportunities and Challenges Business Planning Case for Access Yogyakarta, (Indonesia), 27-29 July 2009 Oscar González Soto ITU Consultant Expert Spain [email protected] International Telecommunication Union 2 ITU – Business case - OGS Yogyakarta , Indonesia, 27-29 June 2009 Agenda Context and case study definition Access assessment Business evaluation

Upload: phungdiep

Post on 12-Jun-2018

212 views

Category:

Documents


0 download

TRANSCRIPT

1

InternationalTelecommunicationUnionITU – Business case for Access - OGSYogyakarta , Indonesia, 27-29 June 2009

ITU-D Regional Development Forum for the Asia Pacific Region

NGN and Broadband, Opportunities and Challenges

Business Planning Case for Access

Yogyakarta, (Indonesia), 27-29 July 2009

Oscar González SotoITU Consultant Expert

Spain [email protected]

InternationalTelecommunicationUnion 2ITU – Business case - OGSYogyakarta , Indonesia, 27-29 June 2009

Agenda

• Context and case study definition

• Access assessment

• Business evaluation

2

InternationalTelecommunicationUnion 3ITU – Business case - OGSYogyakarta , Indonesia, 27-29 June 2009

Planning project for Access Evolution: Questions and issues

Does access enhancement for NGN profit in developing countries?

What reusability may be expected in fixed access infrastructure?

How much to invest in access for BB?

How CAPEX and OPEX change with NGN and xDSL?

What benefits may be addressed by convergence?

Others…………?

InternationalTelecommunicationUnion 4ITU – Business case - OGSYogyakarta , Indonesia, 27-29 June 2009

Planning project for Access Evolution: Project context and objectives

• Context for access evolution planning

• Developing countries are now faced with the a challenge of migrating

from existing PSTN networks in urban areas to advanced NGN

networks capable to provide multimedia services under limited

financial conditions.

• Access network segment is playing a key role for provisioning of

Broadband services, being dominant in investments (> than 50% of

total network). This implies the need to learn and share know-how on

processes, network studies and business planning activities.

• TOT and ITU have agreed to undertake a joint case study for the

most convenient evolution of the access towards BB with multi-play

capabilities and share results with countries in the Region

3

InternationalTelecommunicationUnion 5ITU – Business case - OGSYogyakarta , Indonesia, 27-29 June 2009

Planning project for Access Evolution: Project context and objectives

• Access project objectivesFollowing previous context and agreement, the next objectives were

defined for this project:

• To undertake network assessment and audit for the status of the existing copper access network infrastructure in Bangkok

• Evaluate dynamic migration models over time towards target solution to support triple play services with at least 8 Mbps

• To provide guidelines and recommendations on current access network capability toward NGN including network upgrading, NGN planning and deployment of ICT-based services over the access network

• To extract generic conclusions and experiences with applicability to other countries of the Region

InternationalTelecommunicationUnion 6ITU – Business case - OGSYogyakarta , Indonesia, 27-29 June 2009

Planning project for Access Evolution: Project activities for OSP and NGN

Activity 1: Objectives and Market analysis

Activity 2: Physical network evaluation

Activity 3: Functional network evaluation

Activity 5: Assessment for OSP enhancement

Activity 5: Identification of issues , scenarios and target solutions for NGN

Activity 6: NGN model development

Activity 7: Gathering T/E inputs

Activity 8: Model implementation on tool

Activity 9: NGN Business evaluation

Activity 10: What-if analysis

Activity 11:Recommendations on Planning and Migration

Activity 4: Operations and processes

P1: Access network infrastructure evaluation P2: NGN access network Planning

Activity 1: Objectives and Market analysisActivity 1: Objectives and Market analysis

Activity 2: Physical network evaluationActivity 2: Physical network evaluation

Activity 3: Functional network evaluationActivity 3: Functional network evaluation

Activity 5: Assessment for OSP enhancement

Activity 5: Assessment for OSP enhancement

Activity 5: Identification of issues , scenarios and target solutions for NGNActivity 5: Identification of issues , scenarios and target solutions for NGN

Activity 6: NGN model developmentActivity 6: NGN model development

Activity 7: Gathering T/E inputsActivity 7: Gathering T/E inputs

Activity 8: Model implementation on toolActivity 8: Model implementation on tool

Activity 9: NGN Business evaluationActivity 9: NGN Business evaluation

Activity 10: What-if analysisActivity 10: What-if analysis

Activity 11:Recommendations on Planning and MigrationActivity 11:Recommendations on Planning and Migration

Activity 4: Operations and processesActivity 4: Operations and processes

P1: Access network infrastructure evaluation P2: NGN access network Planning

4

InternationalTelecommunicationUnion 7ITU – Business case - OGSYogyakarta , Indonesia, 27-29 June 2009

Planning project for Access Evolution: OSP architecture

Structure of the OSP Access Network at initial status

SDF

SDF

SDF

FDF

FDF

main cable

branching cablesdrop line

MDF

.

.

.

.

SDF

drop line..

.

.

.

.

RegionalExchange

LD network Primary OSP network Distribution OSP network

NTBA

LocalExchange

MDF Main Distribution FrameFDF Feeder Distribution FrameSDF Subscriber Distribution Frame

SDF

ISDNbasic rate

FOOpticalInterface

AN:DLCDSLAMMSAN

InternationalTelecommunicationUnion 8ITU – Business case - OGSYogyakarta , Indonesia, 27-29 June 2009

Agenda

• Context and case study definition

• Access assessment

• Business evaluation

5

InternationalTelecommunicationUnion 9ITU – Business case - OGSYogyakarta , Indonesia, 27-29 June 2009

Planning project for Access Evolution: Assessment on access : BKK areas under analysis

• Following diagram illustrates geographically the 4 BKK metropolitan areas that are the object of the study with selection of Area 3 for techno–economic evaluations

InternationalTelecommunicationUnion 10ITU – Business case - OGSYogyakarta , Indonesia, 27-29 June 2009

Planning project for Access Evolution: Assessment on access

• Taking as a base the operational lines that generate revenues, the following diagram illustrates the ratios of different Network Elements (NE) at A3 as a characterization of the access structure.

NE ratios per operational line in BKK A3

1,00

0,21 0,15

2,82

1,86

1,24

0

0,5

1

1,5

2

2,5

3

Population Cable Installedlines

Operationlines

ADSL inst. ADSLoper.

NE

Rat

io

6

InternationalTelecommunicationUnion 11ITU – Business case - OGSYogyakarta , Indonesia, 27-29 June 2009

Planning project for Access Evolution: Assessment on access

Physical network characterization

Transmission for the utilization of high frequencies in access copper cables is done by the measurement of Signal to Noise ratio (SNR)measured in dBs. Attenuation of transmission signal increases as a function of characteristics in order of importance:

The length of cable

Cable gauge and material

Amount of crosstalk between adjacent cables (function of cable

age, isolation, humidity and filling degree)

Cable discontinuities through the path (function of the historical

connection practices)

Noise gathered by induction of electromagnetic sources at

customer premises or along the cable path (i.e.: radio emission,

electrical power, etc. as a function of the Electromagnetic

Compatibility practices)

InternationalTelecommunicationUnion 12ITU – Business case - OGSYogyakarta , Indonesia, 27-29 June 2009

Planning project for Access Evolution: Assessment on access

OSP LL Distribution

0

20

40

60

80

100

.5 1.5 2.5 3.5 5.0Distance (Km)

% <

D

Thai BKK Italy UK USA

• LL length distribution within the A1 and A3 of Bangkok shows a relatively good shape due to the population settlements around nucleus and good historical practices in topology design

7

InternationalTelecommunicationUnion 13ITU – Business case - OGSYogyakarta , Indonesia, 27-29 June 2009

Planning project for Access Evolution: Assessment on access

xDSL reachability (ADSL & VDSL)

0,00

10,00

20,00

30,00

40,00

50,00

60,00

0 1 2 3 4 5 6 7Km

Cap

acit

y M

bp

s

Limit capacity Engineering capacity

• Capabilities of the xDSL technologies including both ADSL and VDSL are given in the diagram below as a function of the distance: Blue line gives the maximum theoretical capacity in Mbps with cables at lab conditions while the red line illustrates the engineering capability at real conditions of the field

InternationalTelecommunicationUnion 14ITU – Business case - OGSYogyakarta , Indonesia, 27-29 June 2009

Planning project for Access Evolution: Assessment on access

Cable gauge

0,00

10,00

20,00

30,00

40,00

50,00

60,00

70,00

80,00

90,00

.4 .5 .65

Diameter (mm)

Rat

io

Aerial Underg.

• Cable gauges in A1 and A3 are dominant for .4 and .5 mm. as indicated in the diagram thus limiting the data rates at the high end of the loop

8

InternationalTelecommunicationUnion 15ITU – Business case - OGSYogyakarta , Indonesia, 27-29 June 2009

Planning project for Access Evolution: Assessment on access

OSP Age

05

101520253035404550

5.0 10.0 15.0 20.0 30.0

Years

% >

Underg. Aerial

• Cable ages in A1 and A3 follow the distribution indicated with significant proportion of cables at the end or close to the end of life cycle (more than 15 years) that should be enhanced

InternationalTelecommunicationUnion 16ITU – Business case - OGSYogyakarta , Indonesia, 27-29 June 2009

Planning project for Access Evolution: Outcome on OSP assessment

• Outside plant in access has important reusability for xDSL solutionsneeding enhancement for wider deployment of 8 Mbps services mainly in the secondary section and new remote unite associated to the cabinets

• It is recommended to have OSP information and inventory in digital and integrated form by use of the applications associated to the OSS

• It is recommended to have a wide characterization of the local loopproperties by use measurements with proper sampling techniques for a first step characterization and use of specific testing equipment for massive measurement later.

• In order to avoid multiple sequential civil works it is recommended to agree among different players for a common deployment in shared mode(i.e.: common works with assigned ducts per operator or even shared ducts options)

9

InternationalTelecommunicationUnion 17ITU – Business case - OGSYogyakarta , Indonesia, 27-29 June 2009

Agenda

• Context and case study definition

• Access assessment

• Business evaluation

InternationalTelecommunicationUnion 18ITU – Business case - OGSYogyakarta , Indonesia, 27-29 June 2009

Planning project for Access Evolution: Access Modelling: Global migration scenarios

PMO

NGN at AN and Dual Play

NGN at AN and Triple Play

NGN at user CPE over FTTH

NGN at customers GW and triple play

Scena

rio 1

Scenario 2

Scenario 3

Scenario n

Access migration scenarios are defined by the evolution betweenthe pair of originating (Present Mode of Operation) and destination network configurations

10

InternationalTelecommunicationUnion 19ITU – Business case - OGSYogyakarta , Indonesia, 27-29 June 2009

Planning project for Access Evolution: Access Modelling: Specific migration scenarios for NGN

PMO

Separate networks

NGN at AN and Dual Play

NGN at AN and Triple Play

Without OSP enhancement

Scen

ario

NGN DP

Scenario

NGN OSP1

Scenario NGN OSP2

Scenario NGN

OSP3

NGN at AN and Triple PlayWithout OSP enhancement

for all

NGN at AN and Triple PlayWith OSP enhancement

for dense areas

Access migration scenarios evaluated in the case study as the most convenient for the current country situation

InternationalTelecommunicationUnion 20ITU – Business case - OGSYogyakarta , Indonesia, 27-29 June 2009

• Historical configuration to be modeled as scenario S1 or Present Mode of Operation (PMO ) with separated voice and data networks and the following functional elements

Planning project for Access Evolution: Functional scenarios

LD circuit netTransmissioncircuitAN

Voice

PSTN Switching

Customers

OSP conditioning

Voice service

Dataservice

CPEvoice

CPE data

modem

O&M

Transmissiondata LD data netData BRAS

AN Aggreg.DSLAM

OSS/BSS

11

InternationalTelecommunicationUnion 21ITU – Business case - OGSYogyakarta , Indonesia, 27-29 June 2009

Planning project for Access Evolution: Functional scenarios

• New configuration to be modeled as scenarios S2, S3, S4, S5 or NGN with convergence of network and services at the access node either with provisioning of dual play: VoIP and BB internet or triple play adding IPTV

LD NGN net

Planning, Design &

engineering

Transmissionedge

AN Multiservice

MSAN

NGN Equipment

Router

Customers

OSP cable

Video servers equipment

Voiceservice

Dataservice

Videoservice

CPEvoice

CPE data+video

Installation and commissioning

OSP civil

NGSS O&M

OSP conditioning

NGN segments

InternationalTelecommunicationUnion 22ITU – Business case - OGSYogyakarta , Indonesia, 27-29 June 2009

Planning project for Access Evolution: Network structure for NGN based deployments

• New deployments of ADSL receiving service through an IP based network with access by MSANs connected to a metroLAN and an IP Core towards the Gateway to Internet as described in the reference diagram

Copper line

Splitter

ADSLModem

Customer

IP Core ISP

NIX

WWW

IIG

Internet

BRAS/TSGIP Access

Network/MetroLAN

PC

AccessSW

AGGSW

DSLAM/MSAN

12

InternationalTelecommunicationUnion 23ITU – Business case - OGSYogyakarta , Indonesia, 27-29 June 2009

Planning project for Access Evolution Business evaluations

General assumption for the evaluations (I)

• Analysis period for the evaluations of 10 years in order to be able to see the life-cycle effects of different network element types

• Standard reference financial parameters for discount rates of 10% during the evaluation period and long term perpetuity rate to evaluate terminal values of network (3%)

• Life cycles for NE: of 4 years for CPEs, 6 years for AN, 6 to 8 years for core nodes and 20 years for OSP

• Existing installed equipments not at the end of life-cycle at the start of the period thus requiring substitution at the corresponding life expiration

InternationalTelecommunicationUnion 24ITU – Business case - OGSYogyakarta , Indonesia, 27-29 June 2009

Planning project for Access Evolution Business evaluations

Assumptions for BKK Area 3 (II)

• Population of 2,383.811 inhabitants at end 2008

• Population density of 3.833 at year 2008

• Customer density: 569 customers per Km2 at 2008

• Initial Market share at the country: 56% for fixed lines and 36% for

ADSL lines

• Potential market in lines for TOT 460.000 at year 10

• ADSL LL length for 8 Mbps. guarantee: 2 Km or 1,43 geographical radius

• Average number of cables per operational line 1,86

• Proportion of reachable LL for BB 8 Mbps. 45%

• Proportion Aerial/underground distribution network: 70/30

13

InternationalTelecommunicationUnion 25ITU – Business case - OGSYogyakarta , Indonesia, 27-29 June 2009

Planning project for Access Evolution Business evaluations

Assumptions for BKK Area 3 (III)

• Migration speed towards NGN at a medium pace in 3 years with rates of 20/60/20 that is feasible in a region (note that is not feasible in all regions at the same time for financial and know-how limitations)

• Tariffs for voice service decreasing 5% per year

• Tariffs for data service of 1000 baths/month for BB access of 8 Mbps and decreasing 3% per year

• Tariffs for IPTV equivalent to current market silver type: 750 bahts

• Pricing Access Nodes for an initial configuration of voice /data ports: 80/20

• Company financed CPEs for users: 30% for traditional, 50% for new voice/data and 60% for new IPTV.

InternationalTelecommunicationUnion 26ITU – Business case - OGSYogyakarta , Indonesia, 27-29 June 2009

Planning project for Access Evolution Business evaluations: Triple play

• Evolution of services demand projected with the mentioned assumptions for voice, BB internet and IPTV with VOD as a function of customer geographical coverage that depends on the level of OSP enhancement

Service Demands

0,00

50000,00

100000,00

150000,00

200000,00

250000,00

300000,00

350000,00

400000,00

450000,00

500000,00

Y0 Y1 Y2 Y3 Y4 Y5 Y6 Y7 Y8 Y9 Y10Year

Co

nn

ecti

on

s

no OSP enhance, iptv All cases, voice

All cases, data high level enhance, iptv

medium level enhance, iptv

14

InternationalTelecommunicationUnion 27ITU – Business case - OGSYogyakarta , Indonesia, 27-29 June 2009

Planning project for Access Evolution Business evaluations: Triple play

• Global project evaluator: Net Present Value (NPV) at perpetuity rate shows a gain for al NGN alternatives that is high higher as wider enhancement of OSP and more customers reached for BB services and IPTV. Thus new revenues and convergence economy of scale largely compensate the high OSP investments

NPV for PMO and 4 NGN scenarios

0,00

500,00

1000,00

1500,00

2000,00

2500,00

Y0 Y1 Y2 Y3 Y4 Y5 Y6 Y7 Y8 Y9 Y10 Year

Cu

rren

cy U

nits

medium speed NPV (Perpetuity Rate) no migration NPV (Perpetuity Rate)no OSP enhance NPV (Perpetuity Rate) high level enhance NPV (Perpetuity Rate)medium level enhance NPV (Perpetuity Rate)

InternationalTelecommunicationUnion 28ITU – Business case - OGSYogyakarta , Indonesia, 27-29 June 2009

Planning project for Access Evolution Business evaluations: Triple play

• Differential NPV at perpetuity rate trough time: gain after year 3 justifies the

important investments in OSP and access modernization with NPV increasing

through time in proportion to the number of reachable customers that

generate new revenues

Differential NPV for NGN MS alternatives with triple play

-200,00

-100,00

0,00

100,00

200,00

300,00

400,00

500,00

600,00

700,00

800,00

Y0 Y1 Y2 Y3 Y4 Y5 Y6 Y7 Y8 Y9 Y10

Year

Cur

renc

y U

nits

NPV diff. no OSP enhance NPV diff. medium enhance NPV diff. high enhance

15

InternationalTelecommunicationUnion 29ITU – Business case - OGSYogyakarta , Indonesia, 27-29 June 2009

Planning project for Access Evolution Business evaluations: Triple play

• Capital expenditure shows a different profile at the 4 scenarios due to the

important investments at the transition years in OSP modernization, new

integrated Access Nodes and renovation of multiservice CPEs but converging

at medium term when modernization completed

Expenditure for NGN triple play scenarios and PMO

0,00

5000,00

10000,00

15000,00

20000,00

25000,00

30000,00

35000,00

40000,00

Y0 Y1 Y2 Y3 Y4 Y5 Y6 Y7 Y8 Y9 Y10 Year

Cu

rren

cy U

nits

medium speed Capital Expenditure no OSP enhance Capital Expenditure

high level enhance Capital Expenditure medium level enhance Capital Expenditure

InternationalTelecommunicationUnion 30ITU – Business case - OGSYogyakarta , Indonesia, 27-29 June 2009

Planning project for Access Evolution Business evaluations: Triple play

• Differential expenditure and revenues with the PMO illustrates the

importance of migration towards NGN with a high capacity access network to

benefit from the new revenues and positioning for competition

Differntial Revenue and Expenditures for NGN triple play alternatives versus PMO

-20000,00

-10000,00

0,00

10000,00

20000,00

30000,00

40000,00

50000,00

60000,00

70000,00

80000,00

90000,00

Y0 Y1 Y2 Y3 Y4 Y5 Y6 Y7 Y8 Y9 Y10

Year

Cu

rren

cy U

nits

Revenue no OSP enhance Revenue medium enhanceRevenue high enhance Expenditure no OSP enhanceExpenditure Medium enhance Expenditure high enhance

16

InternationalTelecommunicationUnion 31ITU – Business case - OGSYogyakarta , Indonesia, 27-29 June 2009

Planning project for Access Evolution Business evaluations: Triple play

• Diagram provides the services revenues evolution through time as function of the assumptions taken. Voice revenues will decrease due to tariff deterioration by high competition and BB internet and IPTV will increase due to the number of incorporated customers. At period end data and IPTV services revenues will be dominant (66%) over voice even with a lower penetration

Services revenues per MS triple play scenario

0,00

10000,00

20000,00

30000,00

40000,00

50000,00

60000,00

70000,00

80000,00

90000,00

100000,00

Y0 Y1 Y2 Y3 Y4 Y5 Y6 Y7 Y8 Y9 Y10Year

Cu

rren

cy u

nit

s

no OSP enhance, iptv all cases, voice all cases, data no OSP enhance, VOD high level enhance, iptv high level enhance, VOD medium level enhance, iptv medium level enhance, VOD

InternationalTelecommunicationUnion 32ITU – Business case - OGSYogyakarta , Indonesia, 27-29 June 2009

Planning project for Access Evolution Business evaluations: Triple play

• Diagram illustrates the investment per category of network elements in percentage for the accumulated value in the 10 years period in the scenario of full network enhancement. The three main investments correspond to the modernization of secondary network, the provisioning of new CPEs with video capability and the remote multiservice nodes to reach all population

CAPEX Distribution (%) per goup type of NE

Edge6% Core

12%

Data term9%

Video term21%

historical access4%

MS remote14%

OSP Primary cable2%

OSP Primary civil6%

OSP Secondary cable 7%

OSP secondary civil13%

Transformation projects

2%

Co-located MS4%

17

InternationalTelecommunicationUnion 33ITU – Business case - OGSYogyakarta , Indonesia, 27-29 June 2009

Planning project for Access Evolution Business evaluations: Triple play

• Diagram shows the operational costs in percentage per category of elements subject to operation and maintenance expenses considered in the 10 years period. Operation and maintenance for the equipments and activities at the network periphery are the main contributors to the expenses with customer service and remote nodes taking the lead

OPEX distribution (%) per group type of elements

Edge7%

Core12%

historical access

11%historical terminals

6%

custom service18%

conditioning8%

interconnection8%

MS remote access

16%

video terminal5%

data terminal3%

Co-located MS Access

6%

InternationalTelecommunicationUnion 34ITU – Business case - OGSYogyakarta , Indonesia, 27-29 June 2009

Planning project for Access Evolution Business sensitivity to tariffs:Triple play

• Differential NPV between the three scenarios per level of OSP modernization illustrates the sensitivity to the tariffs of IPTV and VOD services. But even with a reduction to half project is positive after year 4 due to the efficiency of convergence and economies of scale in triple play

NPV for NGN triple play alternatives and video tariffs reduced 50%

-300,00

-200,00

-100,00

0,00

100,00

200,00

300,00

400,00

Y0 Y1 Y2 Y3 Y4 Y5 Y6 Y7 Y8 Y9 Y10

Year

Cu

rren

cy U

nits

NPV diff. no OSP enhance NPV diff. medium enhance NPV diff. high enhance

18

InternationalTelecommunicationUnion 35ITU – Business case - OGSYogyakarta , Indonesia, 27-29 June 2009

Planning project for Access Evolution Business evaluations: Migration steps

-S1.-PD NGN

-S2.-PD Video

-S3.-Engin. AN

-S4.-OSP design

-S5.-OSP Deployment

-S6.-AN & Trans. deployment

-S7.-Video Platf. deployment

-S8.-OSS/BSS deployment

-S9.-Integ., Test, Valid

-S10.-Service trials

-S11.-Service deployment

-S12.-.Project Lead & Direction

Steps Year 1 Year 3Year 2

• Example of project design and execution. Should be in close collaboration to Equipment, Content and Service providers

InternationalTelecommunicationUnion 36ITU – Business case - OGSYogyakarta , Indonesia, 27-29 June 2009

Planning project for Access Evolution Business evaluations: Outcome

• Access modernization for NGN solutions to allow triple play services (at 8

Mbps.) show an important increase in the Net Present Value of the network

due to the convergence efficiencies and position the company for a higher

revenues and competition level in the market

• Introduction of IPTV and VOD should be based on negotiations with content

providers that provide attractive and high quality content in order to assure

important customer adoption rates and loyalty.

• Quality of Service, Service Availability, Customer Care and Sustained Bit

Rate (i.e.: all path dimensioning at 80% of peak rate) guarantee are the

decisive factors for a customer to select a new provider or remain at the

current one.

• Customer Care platform is recommended with traffic dimensioning ensuring

rapid response to calls and with differentiation of service per customer class,

history of previous customer calls and SLA.

19

InternationalTelecommunicationUnion 37ITU – Business case - OGSYogyakarta , Indonesia, 27-29 June 2009

Planning project for Access Evolution Business evaluations: Outcome

• Further studies and sensitivity analysis recommended for the access scenarios include the following ones:

A) Lower density cases in suburban scenarios in order to analyze up to which density and services mix the current conclusions of this study could be maintained.

B) New architectures with IP closer to the customer at an all IP CPE that allows for services end-to-end IP, cost reduction in the node but higher investments in customer CPE renovation

C) FTTH for services requiring 30 or 100 Mbps according to customer density services demand and OSP status versus VDSL solutions

D) Infrastructure sharing modeling and business evaluation for cases as well as for a common underground renovation/installation of ducts at a single shot for all involved companies (Telecom, CATV, Electricity, etc.)

InternationalTelecommunicationUnion 38ITU – Business case - OGSYogyakarta , Indonesia, 27-29 June 2009

New service revenues pay for the required infrastructure enhancement for high speeds

High impact of economy of scale benefits for convergence in multiservice triple play

Powerful modeling and support tools needed to optimize evolution

Planning project for Access Evolution : Conclusions