by - trl · 0-200 kn/m 2. initial calibration was against a precision bourdon type gauge; using...
TRANSCRIPT
TRANSPORT and ROAD
RESEARCH LABORATORY
Department of the Environment
TRRL REPORT LR 472
EXPERIMENTAL WORK ON LARGE STEEL
PIPELINE AT KIRTLING
by
J.J. Trott and J. Gaunt
(Appendix 2 by P. Nath)
Pavement Design Division
Structures Department
Transport and Road Research Laboratory
Crowthorne, Berkshire
1972
Ownership of the Transport Research Laboratory was transferred from the Department of Transport to a subsidiary of the Transport Research Foundation on l S t April 1996.
This report has been reproduced by permission of the Controller of HMSO. Extracts from the text may be reproduced, except for commercial purposes, provided the source is acknowledged.
CONTENTS
Abstract
1. Introduction
2. Details of pipeline
3. Details of experiment
3.1 Experimental layout
3.2 Instrumentation
3.3 Tests during installation of pipe
3.4 Static surcharge loading tests
3.5 Vehicle loading tests
3.6 Tests at Moulton Crossing
3.7 Measurements of the road pavement deflection
4. Results
4.1 Pipe deflections
4.1.1 During backfill and surcharge loading
4.1.2 During vehicle loading (first series)
4. 1.3 During vehicle loading (second series)
4.1.4 Measurements at the Moulton Crossing
4.2 Strains in pipe wall
4.3 Pressures around and above pipe
4.3.1 During backfilling and surcharge loading
4.3.2 During vehicle loading (first series)
4.3.3 During vehicle loading (second series)
4.4 Results of soil tests to BS 1377 : 1967 on sand backfill and natural ground
4.5 Deflection studies on road pavement
5. Discussion of results
5.1 Loadings applied to the pipe
5.2 Horizontal soil pressure, and modulus of soil reaction
5.3 Comparison of horizontal and vertical pressures
5.4 Comparison of calculated horizontal deflection with observed value
5.5 Impact factors from test vehicle
5.6 Comparison of measured stresses and deflections with values calculated using the finite element method
6. Conclusions
7. Acknowledgements
8. References
9. Appendix 1 - Comparison of the stiffness of the original road structure, and the reinstatement over the pipeline
9.1 Description of test
9.2 Tests at Kirtling
Page
1
1
2
2
2
3
3
3
4
4
4
4
4
4
4
5
5
5
5
5
6
6
6
6
7
7
7
7
8
9
9
10
11
11
I1
11
11
10.
CONTENTS (continued)
9.3 Tests at Moulton
9.4 Discussion of results
Appendix 2 - Application of finite element analysis to the calculation of stresses and deflections in pipelines
10.1
10.2
10.3
10.4
10.5
Introduction
The finite element method
Application to pipelines
Application to the pipe-line at Kirtling
Conclusions from a comparison of experimental and theoretical results
Page
12
12
12
12
12
13
13
14
Q CROWN COPYRIGHT 1972
Extracts from the text may be reproduced
provided the source is acknowledged
EXPERIMENTAL WORK ON LARGE STEEL
PIPELINE AT KIRTLING
ABSTRACT
The Underground Pipes Group at the Laboratory is carrying out work to determine the loads on buried pipelines, and their effects on the pipes concerned. As part of the programme a steel pipeline was instru- mented where it passes under a minor road, and observations were made during the backfilling and subsequent loading tests in the period between October 1970 and June 1971. The pipes are 1.83 m in diameter, with a wall thickness of 12.7 mm. Over the test length sand was used for bed- ding the pipe and for backfilling the trench, the crown of the pipe being 1.60 mm below road level.
This report gives the results of soil pressure measurements around and above the pipe, changes in the internal diameter, and strain in the pipe wall around the circumference.
The measured deflections were small (no more than 4.0 millimetres at any stage), as were the strains in the pipe wall. Comparisons are made with calculated deflections by the Spangler formula, and by a finite element analysis.
1. INTRODUCTION
There is at present a lack of detailed information on the design and performance of large diameter thin-walled
'flexible' steel pipelines. The American Spangler formula 1, although used to predict the deflection of flexible
pipes under load, is thought to give a conservative value for design purposes.
In the Autumn of 1969, through the cooperation of the Consultants, Binnie & Partners, the Laboratory
was given the opportunity to study the installation of a large diameter steel pipe-line near Newmarket. It was
thought that a detailed programme of tests would provide useful information on the structuraI performance
of the pipe-line and provide data for a verification of the Spangler formula and of relatively new structural
design methods. The project provided an opportunity to check the electronic measuring systems to be used
in later experimental work. The work was carried out as part of a general programme of research on under-
ground pipes.
It is hoped to continue some of these measurements over a period of one to two years, during which
time the pipeline should have been emptied and filled several times.
2. DETAILS OF PIPELINE
The pipeline section chosen for the experiment forms part of the Ely Ouse-Essex water scheme, where
untreated water is carried in a steel pipe of 1.83 m diameter buried at an average cover depth of 1.2 m.
The individual sections of pipeline are 9 m long and comprise two welded semi-circular sections of
12.7 mm thick rolled steel. A bituminous sheathing 6.4 mm thick is applied to both the interior and exterior
of the pipe, with a fibre glass layer incorporated in the outer sheath for added strength during handling.
The pipeline sections are connected by socket joints, which are arc-welded at both sides following installation
in the trench.
The general specification called for the pipes to be laid in a trench 2.75 m wide, on a shaped sand bed
forming a bedding angle of 30 ° from the vertical diameter as shown in Fig. 1. The sand was continued as
side-fill for 150 mm above the horizontal diameter, and backfill was then continued with excavated material.
At road crossings, however, concrete bedding and surround was specified with lean concrete backfill above
this, extending to the underside of the road pavement. A small vibrating tamper was used to compact the
sand around the sides of the pipe, and a pedestrian operated vibrating roller compacted the back-fill above
the level of the crown. Material was compacted in nominal 250 mm layers.
3. DETAILS OF EXPERIMENT
3.1 Experimental layout
It was decided to attempt both deflection and strain measurements in the pipe, and to measure soil
pressures around the pipe, for both static backfill loading conditions and for dynamic loading due to vehicles.
To obtain vehicle loading, it was necessary to locate the instrumented section at a road crossing and, although
a trunk or major road would have been preferable, at the time the experiment was proposed the only available
site was across a minor road at Kirtling (near Newmarket). Here the pipeline crosses obliquely under the road
at a depth of 1.6 m below the finished surface, at an angle of 52 ° with the road centre line. Due to the prob-
ability of obtaining very small deflections with the lean concrete bedding and backfill specified for a road
crossing, it was decided to replace the lean concrete with sand for the purpose of the experiment. Thus the
experimental section of pipe was bedded in sand and this material was continued as backfill up to the level
of the road base. The strain and deflection measurements were confined to two circumferential elements of
the pipe 1.98 m apart, corresponding to the average wheel track of a commercial vehicle. The elements were
spaced equally about the centre of a 9 m length of pipe and, when installed, one ring was under the centre
line Of the road and the other under the near side. With this configuration the maximum effect was likely
to be 'obtained from dynamic vehicle loads.
Due to the oblique angle of the pipe crossing, the road was widened on both sides for short lengths in
order that a vehicle could be driven across the trench normal to the line of pipe. The layout is shown in
Fig. 1. The soil pressure measurements were made in the plane of ring A on Fig. 1.
An air-valve chamber was sited in the pipeline near to the road crossing, and this allowed access to the
pipe for the purpose of carrying out deflection measurements, and for leading out strain gauge cables.
2
3.2 I nstru mentation
The measurements, listed below, all demanded instrumentation work prior to the installation of the
pipe:-
(a)
(b)
(c)
Strain in the pipe wall
Deflection of the pipe
Soil pressure around the pipe.
(a) After removal of the bituminous sheathing in 300 mm wide strips, resistance foil strain gauges
were cemented circumferentially at 45 ° spacing around the inside and outside of the pipe. Heat
cured epoxy resin was used as an adhesive, and gauges were connected through a junction box
to 30 m lengths of multi-core cable for subsequent connection to data-logging equipment.
'Dummy' gauges were attached to small steel sections, cut from a spare length of pipe, individually
paired with the 'active' gauges to form one half of the Wheatstone bridge circuit for measuring
strain. Following attachment of the gauges, the protective bituminous sheath was replaced
externally. The interior protection was not replaced until after the dynamic tests described in
Section 3.5.
(b) Pipe deflections were studied by means of internal diameter measurements. Small stainless steel
studs were cemented to the pipe wall at 45 ° spacings adjacent to the strain gauge positions, and
diameters were checked with the gauge as shown in Fig. 2a. Dynamic deflections were monitored
with a similar device shown in Fig. 2b but fitted with an inductive displacement transducer, the
output of which was fed to a high speed galvanometer recorder.
(c) Soil pressures were measured with a small cell recently developed at the Laboratory, and shown
in Fig. 3. This cell is capable of resolving both static and dynamic pressures in the range e
0 -200 kN/m 2. Initial calibration was against a precision Bourdon type gauge; using applied
hydrostatic pressure. '~"
3.3 Tests during installation of pipe
After the pipe was installed in the trench and before backfilling, the strain gauges were connected to
I00-channel data logging equipment, all strains being then recorded automatically. Pipe diameter measure-
ments were taken manually with the pipe gauge. One pressure cell had been previously installed in the sand
below the pipe, and connected to the data logger. The remaining cells were installed and connected as back-
filling progressed. Readings of strain, deflection and pressure were all repeated at intervals during the back-
filling process and 3 days after completion of backfilling to road formation level.
- L
Concurrently with the above tests, soil density tests to BS 1377 : 1967 were carried out on the sand
backfill using the core-cutter method.
3.4 Static surcharge loading tests
Before reinstatement of the road, concrete blocks of total mass 20 Mg were placed on the backfill over
an area of 10.5m 2 to apply an average stress over the width of the trench of about 19 kN/m 2 at the surface.
The effects on strain in the pipe wall, deflection of the pipe and soil pressure were all observed. In an attempt
to increase pipe deflection, the same number of concrete blocks were stacked in one-half the area, to give an
average stress of 38 kN/m 2 over the reduced width, and the measurements repeated. 3
3.5 Vehicle loading tests
After a period of about 4 weeks and following reinstatement of the road surface, loading tests were
carried out with a stationary and moving vehicle. The reinstatement comprised a nominal 200 mm thick
layer of hard core, surfaced with 60 mm of single course tarmacadam. Further tests were carried out after
a period of 7 months, during which time the pipe had been filled with water and emptied. These tests are
referred to subsequently as first and second series respectively.
A two-axle lorry with a mass distribution of 10 Mg at the rear axle and 4 Mg at the front axle was used.
The tests involved standing the lorry at various distances from the centre line of the pipe, and obtaining
deflections and soil pressure readings for static conditions, followed by dynamic tests at vehicle speeds of
5 - 3 2 kin/h, both normal and oblique to the pipe. During each run the lorry was positioned so that the
back wheels passed directly over the rings of instrumentation around the pipe. To obtain a value for the
impact factor, a 50 mm thick plank 300 mm wide was placed over the pipe, normal to the direction of the
vehicle. Pipe deflections were recorded with two of the inductive displacement diameter gauges, installed
at right angles to each other across the horizontal and vertical diameter of the pipe. The output was fed to
a high speed galvanometer recorder along with that from the pressure cells, and the traces obtained .were
related to displacement and pressure.
3.6 Tests at Moulton Crossing
During the second series of loading tests (June, 1971), the opportunity was taken to observe pipe
deflections when the same vehicle and impact conditions were used at another road crossing at Moulton,
where the normally specified concrete surround and lean concrete backfill had been used (see Section 2).
At this site the pipe crossed the road at right angles. Two inductive transducers were installed inside the
pipe to measure vertical and horizontal deflections.
3.7 Measurements of the road pavement deflection
To compare the stiffness of the reinstated road above the pipe with the adjacent undisturbed construct-
ion, deflection beam measurements were made both at Kirtling and at Moulton. These are discussed in
Appendix 1.
4. RESULTS
4.1 Pipe deflections
4.1 .1 During backfill and surcharge loading. Figs. 4 and 5 show the pattern of static pipe deflection
throughout backfill and surcharge loading. After compaction of the sand sidefill, the vertical diameter of
the pipe increased by 4.0 mm, and the horizontal diameter decreased 3.3 mm. Following completion of
backfilling and surcharge loading, the pipe returned more closely to its circular shape, as illustrated in Fig.5.
The maximum vertical deflection was only about 0.2 per cent of the pipe diameter.
4.1.2 During vehicle loading (first series). The static pipe deflections measured with the rear wheels
of the test vehicle at various positions with respect to the pipe and after completion of the pavement were
very small, reaching maxima of only 0.14 mm and 0.10 mm respectively in the vertical and horizontal
direction, as shown in Fig. 6. Dynamic deflections with the vehicle running at both normal and oblique
angles to the pipe, and at an average speed of 9 kin/h, were of the same order as the static ones. The
4
lorry formed an oblique angle to the pipe, when travelling along the centre line of the road, due to the 52 °
angle subtended by the centre lines of pipe and road. Tests with the vehicle travelling oblique to the pipe
at an average speed of 30 km/h and passing over the 50 mm thick plank, gave a maximum vertical deflection
of 0.27 mm, corresponding to ari impact factor approximately 2.1 for the rear axle. Slower impact runs at
an average speed of 6 km/h gave a maximum vertical deflection of 0.22 mm, corresponding to an impact
factor of approximately 1.7. Tests with the vehicle normal to the pipe, and travelling at similar speeds, gave
a vertical deflection of only 0.14 mm corresponding to an impact factor of 1.3. Fig. 7 shows the results of
the dynamic pipe deflections tests. The impact tests are further discussed in Section 5.5.
4 .1 .3 During vehicle loading (second series). These tests were carried out after a period of 7 months,
and were a repeat of the first series. Results were very similar (Fig. 7) with static deflections ofO.16 mm
and 0.10 mm in the vertical and horizontal directions (0.14 and 0.10 respectively in December 1970).
Impact factors were 1.5 and 2.2 at the rear axle for the fast and slow runs oblique to the pipe, and 1.8 for
the slow run normal to the pipe (1.7, 2.1 and 1.3 respectively in December 1970).
4.1.4 Measurements at the Moul ton Crossing. Attempts to measure the horizontal and vertical
deflections in the pipe at Moulton, when the vehicle was driven over it showed that the pipe deflections were
too small to measure (less than 0.0001 mm). This was also the case when impact tests were made, as at Kirtling.
4.2 Strains in pipe wall -~
Strains measured during backfilling and following surcharge loading were very low for a steel pipe, and •
at no time exceeded 100 microstrain. The distribution and magnitude of the compressive and tensile strains
are shown in Fig. 8. The drift towards a tensile component at the conclusion of the surcharge tests and on
removal of load could be explained by a rise in temperature at the inside of the pipe of from 8 ° C in the
morning to 25 ° C at the conclusion of tests• This was mainly due to welding operations and to the application,~
of a hot bituminous coating to the joints. Strains recorded during the tests with the heavy vehicle were small
(generally less than 10 micro strain) and have therefore not been reported in detail.
4.3 Pressures around and above pipe
4.3.1 During backf i l l ing and surcharge loading. The distributions of radial and vertical pressures
during backfilling and surcharge loading are shown in Figs. 9 and 10. The radial pressures were highest around
the top half of the pipe initially, but tended to increase over the lower half with increasing load, and to
approach a state of nearly uniform compression under sustained surcharge. The negative pressure recorded
at the invert following compaction around the sides of the pipe is probably due to the tendency of the pipe
to be lifted off the bedding by compaction of the lower part of the side filling. The vertical pressures show
a markedly asymmetric distribution about the centre over one edge both initially and when repeated in
June 197 I. Th6 reason for this effect, which is repeated throughout the subsequent dynamic loading tests,
is not known and will be studied in more detail in later experiments.
Also shown on Fig. 10 are calculated vertical pressures acting on the horizontal plane containing the
pressure gauges above the pipe. For the conditions without surcharge it is assumed that the pressure exerted
by the overburden acts uniformly and the pressures are calculated directly from the wet weight of the over-
burden. For the surcharge condition the component added to the overburden pressure was calculated from
the Boussinesq equations for strip loading. The comparatively small increase in pressure for the larger
surcharge is explained by the method used to increase the surcharge; the width of surcharge was halved,
whilst the intensity was doubled. The calculated values neglect the presence of the pipe, which, as would be
expected, reduces the soil pressures over the crown and increases it towards the trench boundaries. A more
rigorous finite-element analysis taking the presence of the pipe into account is discussed in Appendix 2.
4.3.2 During vehicle loading (first series). Pressure changes recorded during the vehicle tests are shown
in Fig. 11 ; they are of a low order, being generally below 10 kN/m 2. The pressure changes recorded by
gauges 1 and 2 are greater than those for the other gauges leading to a similar asymmetry to that observed in
the static loading tests.
Fig. 11 also shows the calculated maximum vertical stress generated by the passage of the rear wheel of
the test vehicle. The assumptions made were (a) that the load was transmitted over a circular area calculated
from the nominal wheel load and tyre pressure; (b) that the pavement, soil and backfill constituted a material
uniform with depth and (c) no pipe was present. If the pavement had an elastic modulus 50 times that of
the soil (as was probably the case) the calculated vertical stress would be reduced to about one half the value
shown and consequently more in line with the values measured. As with the results discussed in relation to
Fig. 10, the presence of the pipe would materially affect pressures measured above it. Again a more rigorous
theoretical treatment is required.
The soil pressures measured with the vehicle moving obliquely to the pipe are consistently greater than
those observed when it passed normal to the pipe. The reason for this is not understood and it is a matter
which will need further investigation at other sites.
4.3.3 During vehicle loading (second series). Pressures recorded are also shown in Fig. 11, and it will
"be seen that vertical and radial pressures are all slightly lower than in the first series.
4.4 Results of soil tests to BS 1377 : 1967 on sand backfill and natural ground
A sieve analysis of the sand backfill is given in Table 1, and shows the material to be a uniformly graded
fine sand. A standard 'Proctor ' compaction test gave a maximum dry density of 1.71 Mg/m 3 at an optimum
moisture content of 7 per cent. The results of in-situ density tests carried out on the sand during backfill
operations are shown in Table 2. The variation was small, and ranged from 1.59 to 1.61 Mg/m 3 (93 - 95 per
cent of Proctor compaction). CBR tests carried out on remoulded samples of the sand backfill, gave an
approximate value of 6 corresponding to the average field density of 1.60 Mg/m3; the results are given in
Table 3.
In-situ density tests carried out on the natural ground, gave an average dry density of 1.63 Mg/m 3 at
a moisture content of 20.9 per cent.
4.5 Deflection studies on road pavement
The elastic deflection of the road pavement at Kirtling was rather smaller over the pipe than on the
adjacent undisturbed pavement which is Weak, and exhibits some crazing. This would be due to the relatively
high stiffness of the reinstatement and confirms that pipe deflection is small in comparison with the elastic
deflection of the pavement materials and the supporting subgrade. At Moulton the use of the lean concrete
surround and backfill reduced the measured deflections by about 80 per cent.
6
5. DISCUSSION OF RESULTS
5.1 Loadings applied to the pipe
The static vertical soil pressures across the pipe crown produced by the backfill and by the application
of surcharge shown in Fig. 10, and the recorded dynamic soil pressures across the pipe crown produced by
the test vehicle shown in Fig. 11, indicate a minimum immediately above the pipe crown.
In Fig. 10, the calculated pressures corresponding to the applied loads have been indicafed, and are
shown to be in fairly good agreement with the average pressures measured across the pipe crown, except in
the case of the 38 kN/m 2 surcharge load. This can probably be explained by the fact that when the concrete
blocks were piled up over the pipe to double the applied pressure compared with that used in the previous
test, (19 kN/m 2) the width of loading was reduced.
The recorded dynamic pressures across the pipe crown for the rear axle-load of the test vehicle (Fig. 11)
are much lower than the value predicted by a Boussinesq analysis. This is to be expected, as the calculated
pressure at the pipe crown does not take account of the load-spreading effect of the road construction.
5.2 Horizontal soil pressure, and modulus of soil reaction
In Fig. 12, the measured horizontal pressure is shown plotted against horizontal deflection of the pipe
when the trench was loaded by the rear axle of the test Vehicle (10 Mg), both for the vehicle stationary, and
when driven over a 50 mm 'bump'. From the results, a mean value of the modulus of the soil reaction E' of
55,000 kN/m 2 has been calculated.
It has not been possible to produce a similar calculation for the modulus of soil reaction from the static
loading tests, since the pipe deflection produced by back-filling and by the surcharge loading were measured • :
only to + 0.25 mm, which was of the same order as the deflections produced by the loading. (A more accurate
deflection gauge had been used for the dynamic work).
5.3 Comparison of horizontal and vertical pressures
Although it is realised that the Spangler equation 1 strictly applies to a wide-trench condition, it is
interesting to compare the horizontal and vertical pressures measured in the experiment with those predicted
by the equation.
The Spangler equation i s : -
DKWcR3
A X = 'El + 0.061 E'R 3 (i)
where AX =
D =
K =
W c =
- R =
E =
change in horizontal diameter
deflection lag factor
Bedding constant, depending on bedding angle
vertical load per unit length of pipe
mean radius of pipe
elastic modulus of pipe material
7
I
E' = modulus of soil reaction
I f it is assumed that
W c = 2RP v
and E' - 2RPh AX
where, Pv = vertical pressure at pipe crown
Ph = horizontal pressure at side of pipe
= Second moment of area per unit length of cross-section of pipe wall
(2)
(3)
Then ignoring the term El, which is small compared with 0.061E'R 3, and substituting equations (2) and (3)
in equation (1)
AX = DKP v A X
0.061P h
.'. 0.061P h = DKP v (4)
Since the tests were all short-term D = 1, and putting K = 0.1
Equation 4 reduces to
0.61P h = Pv (5)
Table 4 gives the values of horizontal and vertical soil pressures as measured for various static and dynamic
loading conditions. These are shown plottin in Fig. 13. The regression line calculated from these results
gives the relat ionship:-
Pv = 0"79Ph + 1.22 (6)
The difference between this relationship and that predicted using the Spangler equation may be explained
by the fact that the experimental pipe was buried at a shallow depth in relation to its diameter, and that
Spangler's assumption of a uniform verticalpressure acting across the diameter of the pipe was not in accord-
ance with the observed pressure distribution.
5.4 Comparison of calculated horizontal deflection with observed value
I f the value of E' = 4820 kN/m 2 as recommended by Spangler (1) for general use with compacted
material is substituted in his formula, the change in horizontal deflection can be predicted for the loading
produced by backfilling from stage 5 to stage 6 (see Fig. 4).
From Fig. 9 vertical pressure above the pipe is 26 kN/m 2 due to the backfill.
Taking equation (2) in Section 5.3 above
We= 2RP v
= 26 x 1.83 kN/m
8
Assuming D = 1, and K = 0.1 as before
Then n X = 0 . 1 x 2 6 x 1 .83xR 3
0.061 x 4820 x R 3
.'. A X = 16.5 mm
By comparison, the measured change in horizontal deflection for this backfilling as seen in Fig. 4 was : -
A X = 0.5 mm
The dynamic measurements Of the horizontal pipe deflection, and of soil pressure given in Fig. 12
Correspond to a value of E' of 55,000 kN/m 2. If this value is used in the equation, the pipe deflection
obtained i s : -
/ ~ = 1.4 mm
This is of the same order as the measured value, but the measurements of the static deflections were too coarse,
at these very low values, for a reliable comparison to be possible.
It should also be borne in mind that Spangler's recommended value for E' was based upon field
measurements made mainly upon culverts installed in embankment conditions. In trench conditions, as
at Kirtling, it is to be expected that the effective value "of E' would be higher.
5.5 Impact factors from test vehicle
The Impact Factors shown in Fig. 14 are derived from the horizontal and vertical deflections of the
pipe caused by the front and rear wheels of the test vehicle. The ratio between the recorded peak deflections
when the vehicle was driven over the 50 mm 'bump' and the deflections caused when the vehicle was driven
slowly over the corresponding position without the bump gave the value of the impact factor.
In Fig. 14 values obtained at 6 km/h and at 30 km/h, which represented the maximum speed obtainable
at the site, are shown compared with the predicted values. These latter values z're derived from earlier un-
published work at RRL, in which the same vehicle with nearly the same axle loads was driven over a dynamic
weighbridge on the surface of which were attached artificial 'bumps' up to 17.5 mm in height. These values
quoted in Fig. 14 represent an extrapolation of these results to a 'bump' of 50 mm height, and are therefore
only approximate. The higher impact factors for the front axle are as expected since the factor tends to be
greater for a lower load on a given wheel, at a given speed. The results, however, indicate that the trench and
pipe behaved elastically under dynamic loading, and that impact factors relating to 'flexible' pipes are unlikely
to be very different from those relating to rigid pipes 2.
5.6 Comparison of measured stresses and deflections with values calculated usinq the finite element method
A preliminary attempt is made in Appendix 2 to apply the finite element method to the calculation of
backfill stresses and pipe deflections. The results appear very promising.
9
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
6. CONCLUSIONS
The largest deflection measured in the pipe during installation, backfilling and subsequent loading
(4 mm) was produced by the compaction of the sidefdl material around the pipe in the trench. This
produced a measurable ovality of the pipe in the vertical direction, which was subsequently only partly
reduced by the backfilling of the trench.
The observed deflections of the pipe were consistent with a value of E' for the combinations of the sand
and the trench walls of 55,000 kN/m 2. This was derived from the relation between the horizontal soil
pressure and the horizontal pipe deflection. It should be noted that this value only applies to the con-
ditions of this experiment.
The deflection and strains measured in the pipe were less than one-tenth of the values calculated by the
Spangler equation, using the recommended value for E' of 4820 kN/m 2. When calculated on the basis
of the value of E' obtained experimentally, the pipe deflection obtained was of the same order as the
measured value.
Comparison of the horizontal and vertical soil pressures around the pipe gave a relationship somewhat
different from that predicted by the Spangler equation. This may, however, be due to the large diameter
of the pipe in relation to the depth of fill, and to the difference in pressure distribution across the pipe
from that assumed by Spangler.
Using a structural approach based on assumed elastic behaviour the finite element method indicated
soil stresses and pipe deflections reasonably consistent with the measured values (Appendix 2).
The strains and deflections measured when the test vehicle (10 Mg rear axle load) was driven over the
pipe, both with and without the 50 mm 'bump' on the road surface, were all extremely small, the
strains being in general too small for reliable measurement.
The measured impact factors obtained for a 50 mm 'bump' on the road surface and derived from com-
parison of the pipe deflections with and without the 'bump' were, in general, of the magnitude which
would be expected for the vehicle used. There was no evidence of any difference of behaviour between
the flexible steel pipe and that observed in the earlier work on rigid pipes 2.
Comparison tests carried out at a second road crossing, where the pipe had been encased in concrete
• and lean concrete backfill had been used, gave dynamic pipe deflections which were too small to record
(0.0001 mm) from the passage of the same test vehicle as was used at Kirtling.
Measurements of the road stiffness at Kirtling, using a deflection beam with a standard wheel load of
3.2 Mg, indicated that the stiffness immediately above the pipe was consistent with a road of this form
of construction. It was however appreciably higher than the original roadway, which visual observation
indicated was in rather a weak condition with some crazing.
The results in general indicate that the use of well-compacted sand as a bedding and backfill material
was a satisfactory substitute for concrete encasement at this road crossing.
10
7. ACKNOWLEDGEMENTS
The Laboratory gratefully acknowledges the cooperation in this experiment of Messrs. Binnie and Partners
and their Resident Engineer Mr. Lee and his Staff; also that of Messrs. Biggs Wall the main contractors, and
the Essex River Authority who agreed to the use of their pipeline for the experiment. The County Surveyor
for Cambridgeshire, Mr. R. Lacey, O.B.E., F,I.C.I., M.I.Mun.E., is thanked for his cooperation in allowing
the use of sand backfill, and for the construction of lay-bys.
The following members of the research team assisted with the exper iment : -
H.G. Longlands, J.B. Stevens Who carried out the road stiffness tests, and P.D. Hopes and MJ . Corney who
were responsible for the electronic instrumentation. Mr. P. Nath was responsible for the finite element
analysis.
8. REFERENCES
1. SPANGLER, M.G. 'Soil Engineering'. International Textbook Company, Scranton, Penn. 1960.
. PAGE, J. ' Impact Tests on Pipes Buried under Roads'. Ministry of Transport, RRL Report No.35,
Harmondsworth 1966 (Road Research Laboratory).
. LISTER, N.W. Deflection criteria for flexible pavements. Ministry of Transport, RRL Report No.375.
Crowthorne, 1971 (Road Research Laboratory).
9. APPENDIX 1
COMPARISON OF THE sTIFFNESS OF THE ORIGINAL ROAD STRUCTURE, AND THE REINSTATEMENT OVER THE PIPELINE
9.1 Description of test
The measurement of the elastic deflections of a road pavement when a moderate load is applied at the
surface provides a useful means of comparing the load-spreading properties of various pavements. A simple
instrument for the measurement of the transient deformation of road surfaces when subjected to a dual
wheel load at creep speeds is the 'deflection beam '3.
The beam is designed to pass between the dual rear wheels of a loaded lorry so that the lorry can be
driven slowly past the tip of the beam, which rests on the road surface. The beam is pivoted at a point one
third of the way along its 3.6 m length, and the movement of the tip is recorded on a dial gauge at the oppo-
site end of the beam.
9.2 Tests at Kirtling
A plan of the measuring points chosen for the deflection beam survey carried out at Kirtling is shown
in Fig. 15A. A standard 3.2 Mg wheel load was used. One transverse line of points was located over the
trench and the other some 10 m away on the undisturbed construction. Results are shown in Fig. 16.
11
9.3 Tests at Moulton
Measurements were made only over the trench at this site. The average deflection was very low, being
less than 110 x 10"3mm.
9.4 Discussion of results
At Kirtling significantly lower deflections were obtained on the pipe reinstatement than on the original
road structure indicating an increase in stiffness over the pipe. The value of 500-600 x l f f3mm measured
over the pipe is normal for this type of construction; the higher values observed on the undisturbed road
indicated that this is in a relatively weak condition. This conclusion is supported by the crazing observed.
The tests were carried out at a road temperature of 30* C (measured at 100 mm depth below the road
surface). No temperature correction has been made to the results because of lack of knowledge of the sus-
ceptibility to temperature changes of the original road structure, and the lack of a large thickness of temper-
ature-susceptible material in the reinstatement. The very low deflections at Moulton are consistent with a
road pavement utilising a lean concrete base and are consistent with the negligible deflections observed in
the pipe at the site (see section 9.3).
10. A P P E N D I X 2
APPLICATION OF FINITE ELEMENT ANALYSIS TO THE CALCULATION OF STRESSES AND DEFLECTIONS IN PIPELINES
10.1 I ntrodu ction
Buried pipelines embrace a wide range of variables such as pipe diameter and material, depth of instal-
lation, width of trench, nature of soil and backfdl, bedding and imposed loads. The effects of these variables
can be studied in broad terms by full-scale experiments carried out under controlled conditions. A theoretical
approach, once validated by experiment, would however be invaluable in generalising the conclusions from
field studies such as those described in this report.
Various modem methods of analysis are available, of which the most applicable to this problem is the
finite element method, now being used in the solution of a wide range of structural problems. A brief outline
of the method is given below.
1,0.2 The finite element method
The complete structure is divided into a finite number of sub-structures (elements) and the structural
characteristics of each of these elements are determined. The behaviour of the whole structure is then estab-
lished by combining the structural effects of all the elements. For plane structures, whe whole structure can
be divided into a network or mesh of triangular elements, each apex being referred to as a node. For the
sake o f simplicity the following assumptions are m a d e : -
(a) each triangular element is connected to its neighbours only at the nodes. Hence any element
experiences forces from other elements only through its nodes, and no forces are transmitted
through the sides of the elements. It follows that external forces are also applied at the nodes
only.
(b) Inside each element the stress (or strain) remains constant. 12
From these assumptions it follows that the sides of the triangles remain straight before and after defor-
mation, thus assuring a condition of comparability throughout the structure. The element of approximation introduced by the assumptions decreases with decreasing size of element.
Using these assumptions a relationship can be derived between the nodal forces IF]and the nodal dis- placements [:6 ] in the form:-
[F i] = [ki][6 i ] (1)
where
[k i] = / f f [ B i ] T [ D i ] [B i ] d× dy dt
For triangular element of unit thickness and plane area a i
[k i ] = [B i } T [ D i][Bi]/xi
The stiffness [k i ] for any element t will depend on the geometrical properties contained in the matrix [B i ]
and the elastic properties contained in the matrix [D i ].
• Having established [k i ] for all the elements one can build up the stiffness matrix for the whole structure
[K ] of which each [k i ] is a sub-matrix.
If [R ] is the applied load to the whole structure, then one can write
[R] = [K] [6] (2)
where [ 6 ] is the combination of all the sub-matrices [ 6 i ]
All that remains now is to apply the restraints in the form [6j ] where j = 1, 2, . . ~. . (total number of
restraint boundaries of the problem) and solve the system of equation (2) for [ 6 ] .
Having found [ 6 ] , the stresses and strains for any element 'i' follows from equation (1). :~
The advantage of the finite element method lies in the fact that the calculation of k i (equation (1) )
involves the same set of mathematical manipulations for all the elements, thus making the solution suitable
for computer programming. Moreover, the resolution of the stress pattern can be increased by simply using
smaller elements for those parts of the structure where stress concentrations occur.
10.3 Application to pipelines
Fig. 17 shows the cross-section of the most complicated case likely to arise with a buried pipeline, i.e.
the case where the pipe passes Under a road. The finite element method is capable of producing solutions for
the stresses and displacements in such a case, but the results will depend on how representative the values
chosen for the properties of the various materials are of the conditions in practice.
10.4 Application to the pipe-line at Kirtling
The method has been applied to the pipeline at Kirtling mainly to illustrate its potential value. Sufficient
data relating to the soil and the friction between the pipe and its backfill were not available to justify a complete analysis in this case.
13
The assumption has been made that the trench walls were rigid, i.e. stress conditions in the sand backfill
only have been examined. To test the implications of this assumption the effects of widening and deepening
the trench beyond the dimensions actually used have been explored.
The mesh used is shown in Fig. 18. The boundary ABC represents the half-width of the trench with
the pipe to scale. The other boundaries FDE and FGH represent the cases where the trench is deepened by
300 mm and widened by 300 or 900 mm. The sand backfill is represented by traingular elements and the
pipe is represented by 'line' elements, each having two nodes. They are assumed to be able to sustain only
axial forces (the bending strength of the pipe being ignored). These elements are assembled with the triangular
elements in the stiffness matrix [K ] in equation (2).
The force due to the self weight of the backfill is taken into account as follows. The total force on each
element is represented by equivalent forces at the nodes. When this has been done for all the elements, the
total resultant forces at each node are calculated. These nodal forces are treated as external loads and included
in the matrix [R] in equation (2).
Since each element has constant strain, the calculated stresses of two adjacent elements will in general
be different. These discontinuous jumps in stress values from one element to the next can be made less
obvious by using more, and smaller, elements. In the present application such smaller elements have been
used adjacent tO the pipe. It will in the future be probably desirable to use even smaller elements in some
areas, although care is necessary to keep the zomputations within the scope of the computer available. In
addition, stresses have been calculated for each node by taking the average of the stresses of all the elements
connected to that node. These nodal average stresses show more clearly the pattern of change in stress.
Of the various loading conditions investigated experimentally at Kirtling that involving a uniform sur-
charge of 19 kN/m 2 was chosen for this preliminary analysis. For the first case examined values of Young's
Modulus of 130 MN/m 2 and 21 x l04 MN/m 2 were taken for the sand backfill and the steel pipe respectively,
the value for the sand being based on measurements made on a material of similar grading. Fig. 19 shows the
displacement vectors for the nodes calculated for this case, and Figs. 20 and 21 give the vertical and horizontal
stress contours and the stresses in the pipe wall. The average stresses at the nodes are included in the diagrams.
The assumptions made relative to the bar elements and their associated triangular elements imply com-
plete friction between the pipe and the backfill. In practice a degree of slip must occur and this would
materially affect the stress pattern in the backf'dl. The degree of friction can be established by experiment
and included in the analysis. However the effect of reducing the friction in terms of backfill stress can be
examined with reasonable accuracy by reducing the elastic modulus value adopted for the pipe. Such a
reduction to a value less than that of the sand would correspond to a no-friction condition. Figs. 21 and 22
show respectively the nodal deflections and vertical stress contours when the elastic modulus of the pipe is
reduced to a value of 13 MN/m 2, i.e. one-tenth that of the backf'dl. The experimental results both for stresses
and pipe deflections are compared with the theoretical values in Figs. 23 and 24. The effect of increasing the
trench dimensions to the limits represented by the boundaries FDE and FGH shown in Fig. 18 on stresses and
deflections, is also shown in Figs. 23 and 24. Rigid boundaries are again assumed.
10.5 Conclusions from a comparison of experimental and theoretical results
Considering the coarseness of the finite element mesh and the assumptions made, the correlation
between computed and experimental stress and deflection values is sufficiently good to merit refinement of
the theoretical curves for full and zero friction between the pipe and the backfill. (By selecting an inter-
mediate friction condition closer agreement could be established). There is some evidence to suggest that
the friction may vary round the pipe circumference.
The distance between the pipe and the trench boundaries has a significant effort on the stress regime
in the backfdl. Replacing the rigid boundaries by an elastic soil is likely to have a bigger effect. This is being
investigated.
15
TABLE 1
Sieve analysis of sand backfill
B.S. sieve Percentage passing
3/8 in
3/16 in
No. 7
14
25
52
100
100
100
96
92
87
65
13.5
TABLE 2
In-situ density tests on sand backfill
Depth below Dry density Moisture content surface (mm) :(Mg/m 3) (per cent)
0
500
900
1200
1800
2300
2800
1.61
1.59
1.60
1.60
1.59
1.62
1.61
11.9
11.0
12.5
12.7
7.3
11.2
10.1
Average wet density (Unit weight) = 1.78 Mg/m 3
TABLE 3
CBR tests on remoulded sand backfdl
Average CBR
(per cent)
3.0"
5.0
10.0
6.5
Average dry
densit~ (Mg/m j)
1.36
1.62
1.72
1.67
Average moisture content
(per cent)
2.9
5.6
7.3
15.4
1 6
TABLE 4
Measured vertical andhorizontal soil pressures upon the pipe
Loading
Backfill to road base
Surcharge 19 kN/m 2
Surcharge, after 18h
Surcharge 38 kN/m 2
Surcharge removed
Stationary vehicle
Vertical pressure
(Pv) (kN/m2)
Vehicle moving normal to pipe at 9 km/h
Vehicle over bump normal to pipe at 6 km/h
Vehicle moving oblique to pipe at 9 km[h
Vehicle over bump oblique to pipe at 32 km/h
Vehicle over bump oblique to pipe at 6 km/h
Dec. 1970
25.0
25.5
22.I
14.5
-0.5
Jun. 1971
0.5
1.5
2.0
2.5
3.5
2.0
Horizontal pressure
(Pit) (kN/m2)
Dec. 1970
1.2
2.1
9.2
6.6
4.8
22.7
29.6
31.0
30.3
20.2
2.3
2.5
2 . 8
2.6 5.2
5.5
Jun. 1971
2.0
2.0
2.0
2.0
4.9
4.1
17
(a) Splays for vehicle manoeuvres during dynamic testing
(b) Hardstanding for mobile laboratory
//'I ¢ I
/ /
I !
(~)(~)Position of Jl (a) instrumented J I rings I
I (~ Strain gauge and ~
pressure ce,l,eads ~ ,~ are stored in \\ cable pit ~ t / S "
%% %
5 2 *
(a~ I ! I ! i ! i !
I- ~_ road
N
% ,% \
(b) ., ~ pipe
j j ~ ' . I .'<,/~/
~Y~.~vs~'~Air valve chamber ~ / ; " " (used for entry to pipe)
J s
~ lns t rumented pipe
Bedding angle of pipe
Fig. 1. LAYOUT OF EXPERIMENTAL PIPELINE SECTION
Stainless steel studs f i xed to crown and invert of pipe (adjacent t o st ra in gaug, s) ~
ac i n p u t / o u t p u t rec t i f ied to dc for record ing on data logger or ga lvanometer recorder
Calibrated scale w i t h 0 .5mm resolut ion
Plastic clamp holding LVDT to plunqer.
Spring loaded plunger
Linear var iable d i f f e r e n t i a l transformer. (LVDT) capable of 0-02 mm resolution
1"83m
30 ram O.D. aluminium tube
\ /
Fig. 20. G,~UGE FOR STATIC MEASUREMENT OF PiPE OEFLECTION
Fig. 2b GAUGE FOR OVNAMIC ~
MEASUREMENT OF PIPE OEFLECTION
..=I __I
T
Z) 0 f~ I l-
z 0 I--
W
__I - - I W
0
Z
- - I
>~ -o o
o - -
U
~ 0
>
U.~O.
C
E~ ~> ..~,,
o L
N
I -
~ ._.1 f ' - - _ _ ..~ -.~8~
JIZ JQ
m "-' ~: o "E .~ E u o O.J . --. f,_
L ~ -o=~ 200
.__..,=_ ,~ - - I "0 *- '
/
~~ .~._ O'ID
L L o-~,o _ ~ g ~ ,,-~ 6 _ . o o ~ U.,..~ 0 C C
°'o'
iu o "~g gg~ ¢'~ 6 ¢- c - I [ . E ~- o
E o ~ ,r~ .,.. U t'i
.,:(
IIIIIIII
I
I
._I _J I.I.I
I.I.I
ev-
-w
I.I-
u o ! I o e h l e P e E o T u e 3 J a d I !
6 6 8 j
I l • i " j ,~7~'-,b,:-I
t I J ' ' " /%~,~ ~I '~ ' . I / E I . • • I ' I ~ ~ \~ I .~-~,,,m~o.~E 4 ~ ' . , ~ - ~ ~ - ~ 1 I
~ . ~ I ' . " I \ . ~ ,,., / / . I o _ ~ano4 ~,~ Jo~o ~ , f ' ' ~.',~v'~-? ~ ' ~ i " l
l - " I I " ~ " "l"i" I F -- ~UJIN~IO'61, " ' ~ I"' '- "'" ~" "~ " ' "I
v~ _ ~ w / N ~ ~ . 6 " " " 4[ ~ ~
~N E~
in
O~ 0 u}
u 0
m
@
®
J @ ~ ) U J O ! ( ]
m m=-- ¢..}
. .J
5 U ! S O e J 3 a p J e ~ , a w o ! o
• )~- U') ~ ( '1 i'M , - 0 , - - • i ' l l ~ ~ " L¢) I I I I I
(Luw) s6u !J 8 puo V uo{T:~alJ.ap a60JaAV
ID
L
i_
if)
E
03
o z z
~ ' ~
rn
° , , J - - , ,
% Z
M
u
u o
II] gE E
m a
Z
0
Z
O- -
L~
Z
. - - J I J - -
C~ o - -
~3L
O
I
6
=
I I I
-4- ~-I-
>, I . . L
0 _1
+ , , +
< •
o'} .E "5
-4- m
'~ -t'- ¢-.
°~
~ " t -
'" -t-
u- I -
-t'- ' ~ - t -
--t-- < - t - I I
I .g_ * • ~ ~
E
° ~
~ , "10
O
f,.,.
. ~ ' ~
N
-1- :~ .~:
I , , .
u . _ o f ,_ 'o
Q.
~5'5
~=. °
o
(/~IUOVBU!~I)(LUUU) uo!l.~alJ=~p ed!cl
, ~ r- ¢.
E o . ~
~ ~ 0
~ ~ ~,
- ( . 9
- L I , I ~ t-,,
f .
- - ' a L
f,.. f , . O
- U O
c
-fi o m . °
E
<
0
Q~
W
!
I , . . -
0
0 m
~LJ
°~
3
0
m
0
~6 o
"6 o
E
_E ® 3 o-
o
o E L
o z
o F . ̀ ~1~
u c
c ~d o
m
t " t ' -
. U
0 "E q) @) 0
[L n" ~ SI
I I I I
I.i. n" ) - X
I
_-i t
_-I L
-4
:1
3 1
I I
_.-I"
X
. . J
f=AJ
z
X Q "-" ~ . ) - 7O
d) " " G) uJ
Q- z er)
.u_ ~ - r "
¢.=)
.=.J I 1 1.1.1
).- L~.
×® ) -
x®
P)
d 0 ( w w ) u o G ) a l ~ a p ed!d
~ m
O
O
0 " ) C
"1o
~ 7 o ,-~
. C , ~ ; U L '- I t/}
U .
C 0
"1o C o U
g
o
0 I
o I
_ O0
O3
0" )
-®
-®
-®
, , ,
I '
I I "<=: ' l i I
• ~ r
L.L
LL '<["
/ /
/
/ I
/ I(
\
" r l:O
%, %.
% '%
!
I I I
/ /
/ /
/ ' /
I \
( . ) b J P s "
/
f •
-/ /
/
(
3 J
,,, J
-@
-®
-® 0 0
0
uo!ss,=nJdUJO0
( UlDJ-lc~OJ31LU ) UlDJ~S • , . . . . , •
uo!suo.L
o ~
I /
I 0 0
D
.mr-
0 " 2
Z
, ~ J . - - J
z Q ~
Q -
Z
z
¢ 0
° ~ L ~
I I \ o l I \
i <"E . . . . I?
~> ,o, , .... ' ~ ~
m
>
<~ . ~ o / ~
o ~ . . . . . o ~ - - - ?
o I11 % ff % #
~ ...0 ~ " %. •
lJ II "~ .-0 " ~* > i..
'a , % J
'%. J
o ~o o
c-
O I--
U
t~
o,.
0
qi--
U
Ill
0
z e--J
l.i=l •
Q~
c#*i
z
i_i
.el
l.i.l
l,i.l
II.
._.I
0
°I l.i==
0 ¢-
U
E Z
o'3
s.O" S
0 ~"
03 f,- 0 ¢.
U (..
E Z
m
Ul 0
JO
'(3 0 0 I_
0
. _
U 13
r n
r,.
~o & o~ A t~
~ . I I
S ' ~ ~ , ~" J
• ~ . ,
0 J
J J
? I
/
i0,,,." /
_I
d ~J
o U
c- O
u
L
8' I
6
I I I I I
0 0 0 0 0 0 e~ 0 CO (D ~ cv
~LU/N~I o J n s S o J d I!OS
A
p
i
0
! ~Q,,1
n •
E f,,_ 0
tnD Q.
0
0 .Q o
E E
0
E
m
L . G.
8
¢-
0
1~.¢-.
® o t " ~ . 0 U q) D
ul .~ O
& . l .
Z W X I,.1=1
Z ~ z 0 0 _ _
o - Z
0 ~ 1.1=1
0
Z
I.,.,,-
° - - t,.I.,,
u ' ~ ° I
. I 13
~O O~ ~ ~ - ~ o
~-'~1 ~ 0 0 ~
I 0 0e)
pJO3~J O) ~ O l O O i ~Buoq3 ~ J n S S ~ J ~ -~='- -
°
I m m ~ I
~ I # ~
¢-
,-. , - e- e- e- e- x : ~
~,~._ I \ / hi \\.]..L/
:_~ s ~ l ~,, -I ~ 1 I I
uo- - - I ['~', 0 ~ I ~ ~--
, - , 1 5 6 ~ ,
I / , ' / / i I /I I
"f'" /~
I I I I I I I 0 0 0 0 0 0
(8UU/N~l) eBuoq~ eunsseud
¢I)
U C
e .O_
I - O.
- i f )
°411..
C
0
~ n u
. ~ L..
1.- ¢- i'~
I 0<31 I
I - -
I
z
z I
- - j
. - ~ ¢~
Q* *
¢~
t - - ,
. . . J qq [ .
I
L* . I
. I
0
o,I
E Z
• o 0 0
. I~
i - n "--"
o g ~ g 0 < 3 O 4
Q. E
0 0 1 . . , C C
-g E E ° ° E ~._~ L ( . . L t .
...1 o . J o
• I I
<] •
0'~ <)0
°i
c~
A
E E
H <3
o.O_ U
m
4) £3
O
(~UJ/N~l) ganssaad a^!sSOcl
0
z
I 1 - u L i J . _ J
. . . I l a ~
Z
N
0 C ~ L ~
~ X
~ r
~ H
~ ~ J
0
,.,,...J
G C
0
4 - "
8~
0 ~
03 @ - ~
4- o
X , .
, \
o 0 o
o
( ~ U J I N ~ ) ^ d a j n s s ~ J d I!OS IO3!~.J,~A
0 L (~1 o"
-r"
2
÷
" 0 0
==
L .J
W
,...4
f""4
.=.
.z.
==
5 .=..I w
i..=.
( - 0
U o
U o c l
E
4 0
3.0
2.0
1.0
0
Test veh ic le : - Loaded 'Mandator ' l o r ry Front axle load 4 mg Rear 10 mg
,p
f J ,r
f f
Front
f f
/ /
/ f /
4-
I IRear
_1 _o Dec 1970
0 Using ver t ica l deformat ion ~Obl ique z~ Using horizontal de fo rmat ion . / to pipe n Using ver t i ca l de fo rma t i on \ N o r m a l 0 Using horizontal deformat ion. / to pipe
June 1971 as above but points shaded
+ Pred ic ted values f rom ear l ie r tes ts w i t h the same vehicle and ax le load, using a dynamic we ighb r idge
0 10 20 30 Vehicle speed ( k i n / h )
Fig.IL,.IMPACT FACTORS OBTAINED FROM PIPE DEFLECTIONS WITH TEST VEHICLE PASSING OVER A 50tam'BUMP'
o. K I R T L I N G
l O m ,"-
\ \
Pipe C..
K i r t l i n g
~.Road
Q
b. M O U L T O N
M o u I t o n
~E
D C
B
IA
Pipe
Newmarket
Road
Fig.15. LOCATION OF ROAD OEFLECTION MEASURMENT POINTS
2 000
'0 X
E E
v
c- 0
u
0
1 750
1 500
1 250
1 000
750
500
250
O ~ 0
10m from pipe
0.~0 Over pipe
I Crazed
P° i i t
J ,
1 2 3 4 Distance from east side of road ( m )
5
Fig.16. OEFLECTIONS OF ROAD AND PIPELINE REINSTATEMENT, KIRTLING
~~ Wheel load
Pavement
• , . . . . . . . . . . . . ~ . . . . . , . . . . !
o o ~ ~%~o%o g. Oo~ ~,oO o gE 20°0°o oo°o~,o~%o'#c'~8°oo°c
' ~Base Sub-base
Backfi l l
Soil
~ P i p e
- ~ B e d d i n g
Fig.17. COMPONENTS OF" PIPELINE STRUCTURE
C £ H
Y
' ~ X
S c a l e :- I I I
o qso 300 m m
A
Fig.18. FINITE ELEMENT MESH
D G
L
I
Y
I
i I
I I I
I I
LOAD Body force
wy = -17-3 k N / m 3 Surface f o r ce
py = - 1 9 k N l m 2 MATERIALS Sand
y = 0"4 E = 0"13 x 106 k N I m 2 G = 4 6 - 4 x 10 3 k N / m 2
STEEL E = 2 0 6 ' 8 x 106 k N / m 2 As = 1 2 7 m m 2
- - - X
I I
/ J / / /
Sca le •
M e s h I I I I
0 150 300 4 5 0 m m
D i s p l a c e m e n t s I i t t 0 0"2 0-4 0 6 mm
Fig.19. DISPLACEMENT VECIORS (FULL FRICION CASE )
22 209 21 ~4 2 ~
. . . . . . _ _ . . . . . 2 . 5
127 • • • 2"9 2'7 2"66 2"8
" - - 3 0
3.15 e3"39 • 3.34 • 3.33 3-48
/ / 3-5
• . ~ ' - - - , . , . . ~ . ~ , , . _= , . . . . , ~ ' % . .
~ 4-0 " ~
~ 6 ' 6 . 3 ~ , , , , ~ 4 . 3 7 •4.37
Y 4"36
4o4 4"3
.-X
Units: kNI m2(x 10) Compr. + ve
i • 44 /
4.1 ~ . / 4 - ~ 1
/ / 4.71 4-56
4.52 . , . . . . ._
I 0 5-49, 5-26
~ . 5 "5 "-" ---. ~ 1 1 1
I %_5"0 / ~ I ~ 6 . 0 6 0 Z
~,-sl ~.51 -6.08 ~ .e9 ° 6 1 3
Fig.20. VERTICAL STRESSESANO STRESSES IN THE PIPE-WALL (FULL FRICTION CASE )
'1'11 0"96 0 .96 0 " 8 9 0 .14
1.5
1-70 1-66
1-65
%
• 1.52 1"81
2"0
~ ' 07 2 "18
2.23
2 . 5 2"42 ~ - - - - - - 2 • ' 5 3 ~
• - - ' ~ • 2 -54
2-4
2 . 0 5
2 "74
2-68
2.5.6
Y
=X
Unit" k N / m 2 ( x 10)
1"48
2"95 3"0 . . - --- -
2 ' 9 7 ~ ~ e /
f 3"41
/ 3-38 4.0
~ 4.27 f o 4"32
/ 4"5
', 5. 'q 5 . ~ \\g62 -, ~ 4'98'
3-97 4 . 5 ~ \
1-99 4.3, / / e4'O I
~ 3 - 5 4.o~ \ 3"30 ~ ~ 6 8 3.79 \ 4.11_ 4.15
Fig.21. HORIZONTAL STRESSES (FULL FRICTION CASE)
i i_ i i
.! i
1 X : X : X~
X
×
t,
I • Original node x Displaced node
- - -D isp laced outline
Scale.
1 I I
0 2 3 mm
Fig. 22, NODAL DISPLACEMENTS (NO FRICTION CASE)
2.11 2-~29 2.53 2-52 2-59 ~
\ \ \ \ \
- 1 . 6 4 ~ " 2. 2
\ \ \ \
1.26 1-78 /
( ) ' 6 3 / •2.28 I I
• 1-83
2.82
/
J
2.83 3.13 3.1
/
f O
/ 4-17 4.73 /
/ / z / /
4 ' 4 5 5 ' 9 2 /
/~/..0 735 J
f f e6.26
8.0 • 8.51
Uni t " kN I m 2 ( x l O )
. ~ 11"28 10. -0~ - . . .~
• 1055 . 10"97 \
\
/
e~.~12'17"
11"98 " " 12"0
1"14
0 '6
4-07 I
~ 11.58
~ % • 11.56- . ~,0~.0~ 11-35
I / \~ 8.17 I
\ \ / 3-75 \ ~ 110"6 11.83
Fig.23. VERTICAl STRESSES (NO FRICTION CASE)
h
- 80
-60 I
-40
_.ol. ",-%..x.,,,,-" J \ ~ ~#'t Vert icai stress
I ~, ~ " L 0
B
Scale :-
G e o m e t r y I i I mm O 150 3O0
Pressure I I kNIm 2 O 10 20
Displacement I I I mm 0 1 .2
z ~ ~ . !nitial posit ion
I 1!i No friction, trench FDE -----
• No fr ict ion, trench FGH -----
N O friction,-trenchABC --on
Full friction, trench .A B C
Exper iment, trench AISC
A
Pipe def lect ion
Fig.2/..VERIICAL SI"RESS ABOVE PIPE AgO PIPE OEFLEC/IONS
(962) Dd891996 3,.250 7/72 H PL t d . , So'ton G1915 PRINTED IN ENGLAND
- 4 0
- 3 0
- 2 0
-10
0 -
k N / m 2
o
Pipe wall
Y
R = 9 1 4 m m
TrenCh FoE No friction
Trench FOH No friction
Trench ABC Full friction No •friction Experiment
0 O
- 1 0
- 2 0
- 3 0
- 4 0
Fig. 25. RAOIAL PRESSURE OISTRIBUTION (OR A RAOIUS = d.,.150mm WHERE 2d=OlA OF PIPE)
ABSTRACT
Experimental work on large steel pipeline at Kirtling: J J TROTT and J GAUNT (Appendix 2 by P NATH): Department of the Environment, TRRL Report LR 472: Crowthorne, 1972 (Transport and Road Research Laboratory). The Underground Pipes Group at the Laboratory is carrying out work to determine the loads on buried pipelines, and their effects on the pipes concerned. As part of the programme a steel pipeline was instrumented where it passes under a minor road, and observations were made during the backfilling and sub- sequent loading tests in the period between October 1970 and June 1971. The pipes are 1.83 m in diameter, with a wall thickness of 12.7 mm. Over the test length sand was used for bedding the pipe and for backfilling the trench, the crown of the pipe being 1.60 mm below road level.
This report gives the results of soil pressure measurements around and above the pipe, changes in the internal diameter, and strain in the pipe wall around the circumference.
The measured deflections were small (no more than 4.0 millimetres at any stage), as were the strains in the pipe wall. Comparisons are made with calculated deflections by the Spangler formula, and by a finite element analysis.
ABSTRACT
Experimental work on large steel pipeline at Kirtling: J J TROTT and J GAUNT (Appendix 2 by P NATH): Department of the Environment, TRRL Report LR 472: Crowthorne, 1972 (Transport and Road Research Laboratory). The Underground Pipes Group at the Laboratory is carrying out work to determine the loads on buried pipelines, and their effects on the pipes concerned. As part of the programme a steel pipeline was instrumented where it passes under a minor road, and observations were made during the backfilling and sub- sequent loading tests in the period between October 1970 and June 1971. The pipes are 1.83 m in diameter, with a wall thickness of 12.7 mm. Over the test length sand was used for bedding the pipe and for backfilling the trench, the crown of the pipe being 1.60 m~a below road level.
This report gives the results of soil pressure measurements around and above the pipe, changes in the internal diameter, and strain in the pipe wall around the circumference.
The measured deflections were small (no more than 4.0 millimetres at any stage), as were the strains in the pipe wall. Comparisons are made with calculated deflections by the Spangler formula, and by a finite element analysis.