HOJA DE CALCULO
ESTACA DISTANCIA AREAS
CORTE0.00 0.00
20.00 20.00 0.0040.00 20.00 1.5342.70 2.70 3.9450.00 7.30 17.6951.59 1.59 20.7660.00 8.41 30.6360.48 0.48 30.9880.00 19.52 19.85
100.00 20.00 1.96103.69 3.69 4.42
PRESUPUESTO DEL METRADO
ITEMS1.001.011.021.03
HOJA DE CALCULO
AREAS VOLUMENESRELLENO CORTE RELLENO
10.5812.51 0.00 230.905.60 7.65 181.100.94 7.38 8.830.00 78.95 1.720.00 30.57 0.000.00 216.09 0.000.00 14.79 0.000.00 496.10 0.008.41 218.10 42.056.12 11.77 26.81
PRESUPUESTO DEL METRADO
PARTIDA UND METRADOMOVIMIENTO DE TIERRAS M3
CORTE DE MATERIAL PROPIO M3 1482.42RELLENO CON MATERIAL DE PRESTAMO M3 683.06ACARREO Y ELIMINACION DE MATERIAL M3 799.36
HOJA DE CALCULO
VOLUMEN CORREGIDO DIAGRAMA DE MASASMATERIAL CORTE RELLENO DIFERENCIA ORDENADA DISTANCIA
0.00 0.002.00 0.00 320.95 -320.95 -320.95 20.002.00 9.56 251.73 -242.17 -563.12 40.002.00 9.23 12.27 -3.04 -566.16 60.002.00 98.69 2.39 96.30 -469.86 80.002.00 38.21 0.00 38.21 -431.65 100.002.00 270.11 0.00 270.11 -161.54 120.002.00 18.49 0.00 18.49 -143.05 140.003.00 709.42 0.00 709.42 566.37 160.003.00 311.88 58.45 253.43 819.80 180.003.00 16.83 37.27 -20.44 799.36 200.00
VOL. TOTAL 1482.42 683.06
P.UNITARIO PARCIAL SUBTOTAL13219.75
4.80 7115.622.50 1707.655.50 4396.48
COSTO DIRECTO $ 13219.75GG . Y UTILIDAD 20 $ 2643.95SUB TOTAL $ 15863.70IGB 18 % $ 2855.47TOTAL $ 18719.17
FACTORES DE RELLENO Y CORTE
80 m FACT-CORTE FACT RELarena 1.11 1.17
matl suelto 1.25 1.39arcilla y rocso 1.43 1.39
roca fija 1.5 1.39
, ,, ,, ,