callide oxyfuel project development and progress oxyfuel project development and progress dr chris...

19
Callide Oxyfuel Project Development and Progress Dr Chris Spero Oxyfuel Capacity Building Course – Tokyo Institute of Technology 2 – 3 September 2012

Upload: voduong

Post on 10-Apr-2018

216 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Callide Oxyfuel Project Development and Progress Oxyfuel Project Development and Progress Dr Chris Spero Oxyfuel Capacity Building Course –Toky o Institute of Technology 2 –3 September

Callide Oxyfuel Project Development and Progress

Dr Chris Spero

Oxyfuel Capacity Building Course – Tokyo Institute of Technology

2 – 3 September 2012

Page 2: Callide Oxyfuel Project Development and Progress Oxyfuel Project Development and Progress Dr Chris Spero Oxyfuel Capacity Building Course –Toky o Institute of Technology 2 –3 September

Presentation Overview

Project history and structure

Process description and permitting

Oxyfuel boiler construction

Comparison of oxy‐firing with air‐firing

CO2 capture plant 

Future deployment of oxyfuel technology

Page 3: Callide Oxyfuel Project Development and Progress Oxyfuel Project Development and Progress Dr Chris Spero Oxyfuel Capacity Building Course –Toky o Institute of Technology 2 –3 September

Project history

Page 4: Callide Oxyfuel Project Development and Progress Oxyfuel Project Development and Progress Dr Chris Spero Oxyfuel Capacity Building Course –Toky o Institute of Technology 2 –3 September

Project structure

Page 5: Callide Oxyfuel Project Development and Progress Oxyfuel Project Development and Progress Dr Chris Spero Oxyfuel Capacity Building Course –Toky o Institute of Technology 2 –3 September

COP – Work flow

Page 6: Callide Oxyfuel Project Development and Progress Oxyfuel Project Development and Progress Dr Chris Spero Oxyfuel Capacity Building Course –Toky o Institute of Technology 2 –3 September

Pulverised Coal Consumption

5.5 kg/s20 tph

Quality HHV: 19 MJ/kg ar

Ash: 21% arMoisture: 14% ar

Sulfur: 0.3% dafAnglo Callide Coal mine

SteamFlow 37.7kg/s or 136 t/h Pressure 4.1MPa, Temperature 460oC

Oxygen (GOX)Purity: 98 vol% Oxygen

Pressure : 180kPa(a)Flow: 7.6kg/s

Size: 2 x nominal 330 TPD Air Liquide Sigma cryogenic ASUs

Recirculated Flue Gases

Flow: 30kg/sCO2: ~67% mass

Chimney Stack

Flow: 13.2kg/sHeight: 76m

CO2 Purification and CompressionCO2 Product: 75t/dayCO2 Purity: 99.9% molCO2 Temperature: -20oC CO2 Pressure: 1,600kPa

Road TransportB Double – 30tSingle Tanker – 20t

Boiler Exit Flue Gases350oC44.9kg/s

Feed Gas to CO2 PlantFlue Gas Processed Flow: 1.7kg/sTemp ~ 150oC

Callide A Demonstration –

Simplified

Page 7: Callide Oxyfuel Project Development and Progress Oxyfuel Project Development and Progress Dr Chris Spero Oxyfuel Capacity Building Course –Toky o Institute of Technology 2 –3 September

Stage 1 –

Callide A

Exempted from development approval under local 

Government Planning Scheme – not deemed to be a 

material change of use

Amendments proposed to existing Callide A 

environmental authority

Vented gas streams from CO2

CPU

Condensates from flue gas scrubber columns

Define additional release points and monitoring 

regime

Stage 2 – CO2

road transport

Carbon Dioxide (CO2

) is a Dangerous Good (Class 2.2) 

under the Queensland Transport Act

Stage 2 – CO2

storage

Greenhouse Gas Storage Act 2009 (QLD) 

Greenhouse Gas Storage Regulation 2010 (QLD)

Environmental Protection Act 1994 (QLD

Permitting

Page 8: Callide Oxyfuel Project Development and Progress Oxyfuel Project Development and Progress Dr Chris Spero Oxyfuel Capacity Building Course –Toky o Institute of Technology 2 –3 September

Callide A Unit 4 ‐

Original

8

Page 9: Callide Oxyfuel Project Development and Progress Oxyfuel Project Development and Progress Dr Chris Spero Oxyfuel Capacity Building Course –Toky o Institute of Technology 2 –3 September

Boiler Plant/Equipment Removed Ready for New Equipment

Walkway to Fabric Filter to Remain

U3 Multiclone to Remain

Cable Tray to Fabric Filters to Remain

9

Page 10: Callide Oxyfuel Project Development and Progress Oxyfuel Project Development and Progress Dr Chris Spero Oxyfuel Capacity Building Course –Toky o Institute of Technology 2 –3 September

Callide A Unit 4 ‐

After Oxfuel RetrofitOxygen

Flue Gas Before Air Heaters

Flue Gas After Air Heaters

Flue Gas (Clean after FF bags)

Recycled Gas

Rich CO2 Flue Gas to CPU

Secondary Recycled Gas

Cold Primary Recycled Gas to Mills

Hot Primary Recycled Gas to Mills

v

New Feedwater 

Heater

New 

Primary 

Gas Heater

TO CPU

FROM ASU

1 of 1440 

Fabric Filter 

(FF) Bags

Dust

FDF = Forced Draft Fan IDF = Induced Draft Fan

CPU = CO2 COMPRESSION & PURIFICATION UNIT

PRE SCRUBBER

H2O Remover

Pumps & Heat Exchangers

Stack

Fabric Filter

IDF(1x100%)

Air 

Intake

FDF

(1x100%)

10

Existing 

Air 

Heater

Page 11: Callide Oxyfuel Project Development and Progress Oxyfuel Project Development and Progress Dr Chris Spero Oxyfuel Capacity Building Course –Toky o Institute of Technology 2 –3 September

11

Callide A Unit 4 ‐

After Oxfuel Retrofit

11

Page 12: Callide Oxyfuel Project Development and Progress Oxyfuel Project Development and Progress Dr Chris Spero Oxyfuel Capacity Building Course –Toky o Institute of Technology 2 –3 September

Oxy‐firing schematic

FD fan

O2

Page 13: Callide Oxyfuel Project Development and Progress Oxyfuel Project Development and Progress Dr Chris Spero Oxyfuel Capacity Building Course –Toky o Institute of Technology 2 –3 September

Oxy‐firing mode changes

Flue Gas Composition Air‐Firing mode O2 Sequence RFG Mode Oxy‐mode

O2 vol %, dry 4.7 6.0 6.8 5.4

CO2 vol %, dry 15.0 16.2 59.9 68.3

CO ppm, dry 18 20 12 12

SO2 ppm, dry 220 230 800 890

NO ppm, dry 550 720 1195 965

NO2 ppm, dry 9 10 45 46

H2O vol % 8 8.5 20.5 21.6

NOx ppm, dry @ 7% O2 480 680 1220 910

NOx ppm, dry @ 12% CO2 445 540 250 180Flue Gas to 

Stack kg/s (wet basis) 54 59 15.4 14.0

NOx g/s 43 61 21 15

Air‐firing mode means normal air firing

O2 sequence means increased O2 to the boiler via O2 injection nozzles but no recirculation of flue gas

RFG mode means that the recirculated flue gas sequence has been completed

Oxy‐mode means that on completion of the RFG sequence the overall O2

is reduced to normal levels and full oxy‐mode is 

achieved

Page 14: Callide Oxyfuel Project Development and Progress Oxyfuel Project Development and Progress Dr Chris Spero Oxyfuel Capacity Building Course –Toky o Institute of Technology 2 –3 September

Flue gas mass balance

Parameter Unit CPU inlet CO2

product

Flow rate  kg/s 1.7 0.9

Composition % 65% (CO2) 99.9 (CO2)

Temperature C 145 ‐30

Pressure kPa (abs) 101 1,600

Blower

IDF

FDF

CPU: 1.7 kg/s

Stack:13 kg/s

To boiler:28 kg/s

From boiler:42 kg/s

Page 15: Callide Oxyfuel Project Development and Progress Oxyfuel Project Development and Progress Dr Chris Spero Oxyfuel Capacity Building Course –Toky o Institute of Technology 2 –3 September

Carbon dioxide capture plant

Courtesy of Air Liquide

LP ScrubberDriersHP Scrubber

Compressor

Cold box/inerts separators

Page 16: Callide Oxyfuel Project Development and Progress Oxyfuel Project Development and Progress Dr Chris Spero Oxyfuel Capacity Building Course –Toky o Institute of Technology 2 –3 September

Oxygen plant CO2

capture plant

COP – Site Works – Oxygen and CO2

Capture Plant

Page 17: Callide Oxyfuel Project Development and Progress Oxyfuel Project Development and Progress Dr Chris Spero Oxyfuel Capacity Building Course –Toky o Institute of Technology 2 –3 September

1 year NEDO Study led by IHI together with CS Energy and Air LiquideOption 1 –

1000 MWe Oxyfuel boilerOption 2 – 250 MWe oxyfuel boilerOption 3 – Hybrid Oxyfuel Power Plant (HOPP) concept 750 MW Ultra supercritical boiler + 

250 MW ultra supercritical boiler

Hybrid Oxyfuel Power Plant (HOPP) Concept

Page 18: Callide Oxyfuel Project Development and Progress Oxyfuel Project Development and Progress Dr Chris Spero Oxyfuel Capacity Building Course –Toky o Institute of Technology 2 –3 September

Concluding comments

1.

Callide Oxyfuel Project – ASU and Oxyfuel plant has been operating since  March 2012

2.

Over 300 hours of oxyfuel operation since 22 August 2012

3.

CO2 capture plant commissioning – in progress

4.

NEDO study on future CCS commenced in July 2012

5.

COP is still evaluation options for CO2 storage or sale of CO2 for industrial  applications

Page 19: Callide Oxyfuel Project Development and Progress Oxyfuel Project Development and Progress Dr Chris Spero Oxyfuel Capacity Building Course –Toky o Institute of Technology 2 –3 September

Thank you

for more information:  www.callideoxyfuel.com

Callide Oxyfuel Project –

Participants