Capital Budgeting. Arguing for your project. Arguing for your project. Capital budgeting CFO receives proposals from divisions Projects described by cash flows. Arguing means applying measures. Net present value is the right measure. Many smart people use the wrong ones. - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Capital Budgeting](https://reader033.vdocuments.net/reader033/viewer/2022051623/5681586a550346895dc5c9db/html5/thumbnails/1.jpg)
Capital Budgeting
Arguing for your project
![Page 2: Capital Budgeting](https://reader033.vdocuments.net/reader033/viewer/2022051623/5681586a550346895dc5c9db/html5/thumbnails/2.jpg)
Arguing for your project
Capital budgeting CFO receives proposals from divisions Projects described by cash flows
![Page 3: Capital Budgeting](https://reader033.vdocuments.net/reader033/viewer/2022051623/5681586a550346895dc5c9db/html5/thumbnails/3.jpg)
Arguing means applying measures
Net present value is the right measure. Many smart people use the wrong
ones. Alternative ways to the same end.
![Page 4: Capital Budgeting](https://reader033.vdocuments.net/reader033/viewer/2022051623/5681586a550346895dc5c9db/html5/thumbnails/4.jpg)
Uses of measures
Project acceptance Mutually exclusive alternatives.
![Page 5: Capital Budgeting](https://reader033.vdocuments.net/reader033/viewer/2022051623/5681586a550346895dc5c9db/html5/thumbnails/5.jpg)
Capital Budgeting Techniques
Kim, Crick, and Kim, Management Accounting
Nov. 1986, p. 49-52
![Page 6: Capital Budgeting](https://reader033.vdocuments.net/reader033/viewer/2022051623/5681586a550346895dc5c9db/html5/thumbnails/6.jpg)
Survey of use of measures by corporations
Measure Primary Secondary
Internal rate of return 49% 15%Accounting rate of return 8% 19%Net present value 21% 24%Payback period 19% 35%Other 17% 7%
Total responses 587 469
![Page 7: Capital Budgeting](https://reader033.vdocuments.net/reader033/viewer/2022051623/5681586a550346895dc5c9db/html5/thumbnails/7.jpg)
Make no mistake
NPV is the right measure always. Others work sometimes. NPV measures value to owners, their
wealth.
![Page 8: Capital Budgeting](https://reader033.vdocuments.net/reader033/viewer/2022051623/5681586a550346895dc5c9db/html5/thumbnails/8.jpg)
Objectives of a good measure
Value cash flows. Respond to the market.
![Page 9: Capital Budgeting](https://reader033.vdocuments.net/reader033/viewer/2022051623/5681586a550346895dc5c9db/html5/thumbnails/9.jpg)
NPV’s merits
Values cash flows as the market does. Responsive because the discount rate
is the current market rate. Measures increase in shareholder
value.
![Page 10: Capital Budgeting](https://reader033.vdocuments.net/reader033/viewer/2022051623/5681586a550346895dc5c9db/html5/thumbnails/10.jpg)
Payback period is
The time required for undiscounted cash flows to add up to the initial investment.
e.g., build a Wendy’s if it “pays for itself” in two years or less.
![Page 11: Capital Budgeting](https://reader033.vdocuments.net/reader033/viewer/2022051623/5681586a550346895dc5c9db/html5/thumbnails/11.jpg)
Payback merits
Based on cash flows
![Page 12: Capital Budgeting](https://reader033.vdocuments.net/reader033/viewer/2022051623/5681586a550346895dc5c9db/html5/thumbnails/12.jpg)
Payback defects
No market response.When r is high, payback period should be shorter.
Subtracts time-t dollars from time-0 dollars, a cardinal sin.
Ignores cash flow after payback. Ignores timing during payback.
![Page 13: Capital Budgeting](https://reader033.vdocuments.net/reader033/viewer/2022051623/5681586a550346895dc5c9db/html5/thumbnails/13.jpg)
Defects are not necessarily fatal
Repeated, similar investments. Stable financial conditions.
![Page 14: Capital Budgeting](https://reader033.vdocuments.net/reader033/viewer/2022051623/5681586a550346895dc5c9db/html5/thumbnails/14.jpg)
The well-informed capital budgeter knows
When to accept payback period as a measure.
When it is likely to fail.
![Page 15: Capital Budgeting](https://reader033.vdocuments.net/reader033/viewer/2022051623/5681586a550346895dc5c9db/html5/thumbnails/15.jpg)
Accounting rate of return
Doesn’t value cash flows No market response Ignores market values Scaling problems: melons or malls
![Page 16: Capital Budgeting](https://reader033.vdocuments.net/reader033/viewer/2022051623/5681586a550346895dc5c9db/html5/thumbnails/16.jpg)
Merits of accounting r.o.r.
Easily understood. Sometimes okay in stable markets. Smart application can overcome
defects.
![Page 17: Capital Budgeting](https://reader033.vdocuments.net/reader033/viewer/2022051623/5681586a550346895dc5c9db/html5/thumbnails/17.jpg)
Internal rate of return
Definition: IRR is the discount rate that makes NPV = 0
CFCF
r
CF
r
CF
rTT0
1 221 1 1
0
( )
. . .( )
That is, IRR is the r such that
![Page 18: Capital Budgeting](https://reader033.vdocuments.net/reader033/viewer/2022051623/5681586a550346895dc5c9db/html5/thumbnails/18.jpg)
Internal rate of return
Definition: IRR is the discount rate that makes NPV(r) = 0.
NPV(r) is a function. RWJ Figures 6.4 and 6.5.
![Page 19: Capital Budgeting](https://reader033.vdocuments.net/reader033/viewer/2022051623/5681586a550346895dc5c9db/html5/thumbnails/19.jpg)
Project
Time 0 1 2 3Cash flow -200 100 100 100
![Page 20: Capital Budgeting](https://reader033.vdocuments.net/reader033/viewer/2022051623/5681586a550346895dc5c9db/html5/thumbnails/20.jpg)
Figure 6.4: NPV(r)=0 at r=23.37%
NPV
r
100
NPV(r)
NPV(.1) = 48.68520
.1
IRR =23.3748.685
![Page 21: Capital Budgeting](https://reader033.vdocuments.net/reader033/viewer/2022051623/5681586a550346895dc5c9db/html5/thumbnails/21.jpg)
Figure 6.4
NPV (r) = 0 at r = 23.37%
![Page 22: Capital Budgeting](https://reader033.vdocuments.net/reader033/viewer/2022051623/5681586a550346895dc5c9db/html5/thumbnails/22.jpg)
Applications of IRR measure
Hurdle rate = market rate Project acceptance: Accept a project if
IRR > hurdle rate. Mutually exclusive projects: Take the
one with the highest IRR (> hurdle rate)????? Don’t rely on it.
![Page 23: Capital Budgeting](https://reader033.vdocuments.net/reader033/viewer/2022051623/5681586a550346895dc5c9db/html5/thumbnails/23.jpg)
Project acceptance:
NPV and IRR give the same conclusion when ...
Cash flows have one sign change. In the example: IRR = 23.37% > hurdle
= 10% for an investment project. IRR = 23.37% < hurdle rate = 30% for a
financing or “borrowing from nature” project.
![Page 24: Capital Budgeting](https://reader033.vdocuments.net/reader033/viewer/2022051623/5681586a550346895dc5c9db/html5/thumbnails/24.jpg)
Merits
Uses cash flows. Responds to the market when the
hurdle rate changes
![Page 25: Capital Budgeting](https://reader033.vdocuments.net/reader033/viewer/2022051623/5681586a550346895dc5c9db/html5/thumbnails/25.jpg)
Objective
Learn to recognize the times when NPV and IRR are the same.
and also the problems with IRR
![Page 26: Capital Budgeting](https://reader033.vdocuments.net/reader033/viewer/2022051623/5681586a550346895dc5c9db/html5/thumbnails/26.jpg)
Defects of IRR -- project acceptance
Lending to nature or borrowing from her?
Multiple IRR's may occur.
![Page 27: Capital Budgeting](https://reader033.vdocuments.net/reader033/viewer/2022051623/5681586a550346895dc5c9db/html5/thumbnails/27.jpg)
Financing (borrowing from nature)
Seek IRR < hurdle rate Same as NPV > 0
![Page 28: Capital Budgeting](https://reader033.vdocuments.net/reader033/viewer/2022051623/5681586a550346895dc5c9db/html5/thumbnails/28.jpg)
Multiple IRR's
Time in decades 0 1 2Cash flows -1 5 -6
![Page 29: Capital Budgeting](https://reader033.vdocuments.net/reader033/viewer/2022051623/5681586a550346895dc5c9db/html5/thumbnails/29.jpg)
IRR’s at r = 1 and r = 2
100% per decade = 7.17735% per year. 200% per decade = 11.61232% per
year.
![Page 30: Capital Budgeting](https://reader033.vdocuments.net/reader033/viewer/2022051623/5681586a550346895dc5c9db/html5/thumbnails/30.jpg)
IRR’s at r=1 and r=2.
NPV
r
100% 200%
![Page 31: Capital Budgeting](https://reader033.vdocuments.net/reader033/viewer/2022051623/5681586a550346895dc5c9db/html5/thumbnails/31.jpg)
Descartes’ Rule
The number of internal rates of return is no more than the number of sign changes.
![Page 32: Capital Budgeting](https://reader033.vdocuments.net/reader033/viewer/2022051623/5681586a550346895dc5c9db/html5/thumbnails/32.jpg)
Defects of IRR -- mutually exclusive projects
Ignores market values. Scale problems -- melons or malls.
![Page 33: Capital Budgeting](https://reader033.vdocuments.net/reader033/viewer/2022051623/5681586a550346895dc5c9db/html5/thumbnails/33.jpg)
Typical hour exam question
What is the scale problem in using IRR to choose between mutually exclusive projects?
![Page 34: Capital Budgeting](https://reader033.vdocuments.net/reader033/viewer/2022051623/5681586a550346895dc5c9db/html5/thumbnails/34.jpg)
Scale problem in IRR
Time 0 1 IRR NPV(r=.1)Little dam -100 200 1 81.8181…Big dam -1000 1500 0.5 363.6363…
One canyon, one dam.
![Page 35: Capital Budgeting](https://reader033.vdocuments.net/reader033/viewer/2022051623/5681586a550346895dc5c9db/html5/thumbnails/35.jpg)
Sketch of answer
The smaller dam has the higher IRR. The big dam has higher value. The big dam extends consumption
possibility of owners more than the little dam does.
It is wrong to take the higher IRR in this case.
![Page 36: Capital Budgeting](https://reader033.vdocuments.net/reader033/viewer/2022051623/5681586a550346895dc5c9db/html5/thumbnails/36.jpg)
Scale problems in IRR
Time 0 1 IRR NPV(r=.1)
Littledam
-100 200 1 81.8181...
Bigdam
-1000 1500 .5 363.63...
![Page 37: Capital Budgeting](https://reader033.vdocuments.net/reader033/viewer/2022051623/5681586a550346895dc5c9db/html5/thumbnails/37.jpg)
More answer
Consider the project of replacing the little dam by the big dam.
Cash flows are -900, +1300. IRR of the project is 4/9 = .4444 > .1 NPV is 281.8181… So replace the little dam. Capital budgeting jiu jitsu.
![Page 38: Capital Budgeting](https://reader033.vdocuments.net/reader033/viewer/2022051623/5681586a550346895dc5c9db/html5/thumbnails/38.jpg)
r
NPV
50% 100%
100
500
Big dam
Little dam
IRR IRR
![Page 39: Capital Budgeting](https://reader033.vdocuments.net/reader033/viewer/2022051623/5681586a550346895dc5c9db/html5/thumbnails/39.jpg)
Big dam, little dam
NPV
NPV of the big dam
NPV of the small dam
500
100
.51
r
r*
For hurdle rates below r*,the big dam is preferred.
r* = .4444...
![Page 40: Capital Budgeting](https://reader033.vdocuments.net/reader033/viewer/2022051623/5681586a550346895dc5c9db/html5/thumbnails/40.jpg)