capital budgeting with leverage. introduction discuss three approaches to valuing a risky project...

41
CAPITAL BUDGETING WITH LEVERAGE

Upload: kari-douthat

Post on 16-Dec-2015

218 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: CAPITAL BUDGETING WITH LEVERAGE. Introduction  Discuss three approaches to valuing a risky project that uses debt and equity financing.  Initial Assumptions

CAPITAL BUDGETING WITH LEVERAGE

Page 2: CAPITAL BUDGETING WITH LEVERAGE. Introduction  Discuss three approaches to valuing a risky project that uses debt and equity financing.  Initial Assumptions

Introduction

Discuss three approaches to valuing a risky project that uses debt and equity financing.

Initial Assumptions The project has average risk.

For convenience the betas or costs of capital used will be for the existing firm rather than being project specific.

The firm’s debt-equity ratio is constant. This simplifies the application in that we don’t need to worry

about changing costs of capital and fixes the adjustment of our risk measure for leverage.

Corporate taxes are the only imperfection. No agency, bankruptcy or issuance costs to quantify.

Page 3: CAPITAL BUDGETING WITH LEVERAGE. Introduction  Discuss three approaches to valuing a risky project that uses debt and equity financing.  Initial Assumptions

The Weighted Average Cost of Capital Method

Because the WACC incorporates the tax savings from debt, we can compute the levered value (V for enterprise value, L for leverage) of an investment, by discounting its future expected free cash flow using the WACC.

(1 ) wacc E D c

E Dr r r

E D E D

31 20 2 3

1 (1 ) (1 )

L

wacc wacc wacc

FCFFCF FCFV

r r r

Page 4: CAPITAL BUDGETING WITH LEVERAGE. Introduction  Discuss three approaches to valuing a risky project that uses debt and equity financing.  Initial Assumptions

Valuing a Project with WACC

Ralph Inc. is considering introducing a new type of chew toy for dogs. Ralph expects the toys to become obsolete

after five years when it will be discovered that chew toys only encourage dogs to eat shoes. However, the marketing group expects annual sales of $40 million for the first year, increasing by $10 million per year for the following four years.

Manufacturing costs and operating expenses (excluding depreciation) are expected to be 40% of sales and $7 million, respectively, each year.

Page 5: CAPITAL BUDGETING WITH LEVERAGE. Introduction  Discuss three approaches to valuing a risky project that uses debt and equity financing.  Initial Assumptions

Valuing a Project with WACC

Developing the product will require upfront R&D and marketing expenses of $8 million. The fixed assets necessary to produce the product will require an additional investment of $20 million. The equipment will be obsolete once production

ceases and (for simplicity) will be depreciated via the straight-line method over the five year period.

Ralph expects no incremental net working capital requirements for the project.

Ralph has a target of 60% Equity financing.

Ralph pays a corporate tax rate of 35%.

Page 6: CAPITAL BUDGETING WITH LEVERAGE. Introduction  Discuss three approaches to valuing a risky project that uses debt and equity financing.  Initial Assumptions

Expected Future Free Cash Flow

"Income Statement:" Year 0 1 2 3 4 5Sales 40.00 50.00 60.00 70.00 80.00COGS 16.00 20.00 24.00 28.00 32.00Gross Profit 24.00 30.00 36.00 42.00 48.00Operating Expenses 8.00 7.00 7.00 7.00 7.00 7.00Depreciation Exp 4.00 4.00 4.00 4.00 4.00EBIT -8.00 13.00 19.00 25.00 31.00 37.00Tax (35%) -2.80 4.55 6.65 8.75 10.85 12.95Unlevered NI -5.20 8.45 12.35 16.25 20.15 24.05

Free Cash Flow:Unlevered NI -5.20 8.45 12.35 16.25 20.15 24.05Plus Deprecition Exp 0.00 4.00 4.00 4.00 4.00 4.00Less Net Cap Ex 20.00 0.00 0.00 0.00 0.00 0.00Less Changes in NWC 0.00 0.00 0.00 0.00 0.00 0.00Free Cash Flow -25.20 12.45 16.35 20.25 24.15 28.05

Page 7: CAPITAL BUDGETING WITH LEVERAGE. Introduction  Discuss three approaches to valuing a risky project that uses debt and equity financing.  Initial Assumptions

“Market Value” Balance Sheet

The firm is currently at its target leverage: Equity to Net Debt plus Equity ratio is:

$510.00/($510.00 + $390.00 - $50.00) = 60.0%

Excess Cash 50.00$ Debt 390.00$ Debt 5%Existing Assets 850.00$ Equity 510.00$ Equity 12%

Total Liabilities Risk Free 4%Total Assets 900.00$ and Equity 900.00$

Assets Liabilities Cost of Capital

Page 8: CAPITAL BUDGETING WITH LEVERAGE. Introduction  Discuss three approaches to valuing a risky project that uses debt and equity financing.  Initial Assumptions

Valuing a Project with WACC

Ralph intends to maintain a similar (net) debt-equity ratio for the foreseeable future, including any financing related to the project. Thus, Ralph’s WACC is:

(1 )

510 340 (12%) (5%)(1 0.35)850 850

8.5%

wacc E D c

E Dr r r

E D E D

Page 9: CAPITAL BUDGETING WITH LEVERAGE. Introduction  Discuss three approaches to valuing a risky project that uses debt and equity financing.  Initial Assumptions

Valuing a Project with WACC

The value of the project, including the tax shield from debt, is calculated as the present value of its future free cash flows discounted at the WACC.

The NPV (value added) of the project is $52.10 million

$77.30 million – $25.20 million = $52.10 million It is important to remember the difference between

value and value added.

0 2 3 4 5

12.45 16.35 20.25 24.15 28.05 +

1.085 1.085 1.085 1.085 1.085 $77.30 million

LV

Page 10: CAPITAL BUDGETING WITH LEVERAGE. Introduction  Discuss three approaches to valuing a risky project that uses debt and equity financing.  Initial Assumptions

Summary of the WACC Method1. Determine the free cash flow of the investment.

2. Compute the weighted average cost of capital.

3. Compute the value of the investment, including the tax benefit of leverage, by discounting the free cash flow of the investment using the WACC.

4. The WACC can be used throughout the firm as the companywide cost of capital for new investments that are of comparable risk to the rest of the firm and that will not alter the firm’s debt-equity ratio.

Page 11: CAPITAL BUDGETING WITH LEVERAGE. Introduction  Discuss three approaches to valuing a risky project that uses debt and equity financing.  Initial Assumptions

Implementing a Constant Debt-Equity Ratio

By undertaking the project, Ralph adds new assets to the firm with an initial market value $77.30 million. Therefore, to maintain the target debt-to-

value ratio, Ralph must add $30.92 million in new debt. 40% × $77.30 = $30.92 60% × $77.30 = $46.38 (compare to $52.10)

Page 12: CAPITAL BUDGETING WITH LEVERAGE. Introduction  Discuss three approaches to valuing a risky project that uses debt and equity financing.  Initial Assumptions

Implementing a Constant Debt-Equity Ratio

Ralph can add (net) debt in this amount either by reducing cash and/or by borrowing and increasing actual debt. Suppose Ralph decides to spend $25.20 million

(cover the negative FCF in year 0) in cash to initiate the project. This increases net debt by $25.20 million

Excess Cash 24.80$ Debt 390.00$ Debt 39.4%Existing Assets 850.00$ Equity 562.10$ Equity 60.6%New Project 77.30$

Total LiabilitiesTotal Assets 952.10$ and Equity 952.10$

Assets Liabilities % of Total Value

Page 13: CAPITAL BUDGETING WITH LEVERAGE. Introduction  Discuss three approaches to valuing a risky project that uses debt and equity financing.  Initial Assumptions

New Market Value Balance Sheet We need an increase in net debt of

$30.92. Spend $25.20 million on the project and

pay a $5.72 million dividend so $30.92 million in cash goes out (this further increases net debt and reduces equity by the required amount).Excess Cash 19.08$ Debt 390.00$ Debt 40.0%

Existing Assets 850.00$ Equity 556.38$ Equity 60.0%New Project 77.30$

Total LiabilitiesTotal Assets 946.38$ and Equity 946.38$

Assets Liabilities % of Total Value

Page 14: CAPITAL BUDGETING WITH LEVERAGE. Introduction  Discuss three approaches to valuing a risky project that uses debt and equity financing.  Initial Assumptions

Implementing a Constant Debt-Equity Ratio

The market value of Ralph’s equity increases by $46.38 million. $556.38 − $510.00 = $46.38 (60% of $77.30)

Adding the dividend of $5.72 million into the mix, the shareholders’ total gain is $52.10 million. $46.38 + 5.72 = $52.10 Which is exactly the NPV calculated for the project Alternatively: without the dividend the equity

increased by the project’s NPV of $52.10 = $562.10 - $510.00. This is too large an increase in equity, given the increase in debt of $25.20, if Ralph is to maintain 60% equity.

Page 15: CAPITAL BUDGETING WITH LEVERAGE. Introduction  Discuss three approaches to valuing a risky project that uses debt and equity financing.  Initial Assumptions

Implementing a Constant Debt-Equity Ratio

Debt Capacity The amount of debt at a particular date

that is required to maintain the firm’s target debt-to-value ratio

The debt capacity at date t is calculated as:

Where d is the firm’s target debt-to-value ratio and VL

t is the project’s levered continuation value on date t.

Lt tD d V

Page 16: CAPITAL BUDGETING WITH LEVERAGE. Introduction  Discuss three approaches to valuing a risky project that uses debt and equity financing.  Initial Assumptions

Implementing a Constant Debt-Equity Ratio

Debt Capacity VL

t calculated as:Value of in year 2 and beyond

1 1

1

FCF t

LL t tt

wacc

FCF VV

r

Page 17: CAPITAL BUDGETING WITH LEVERAGE. Introduction  Discuss three approaches to valuing a risky project that uses debt and equity financing.  Initial Assumptions

Debt Capacity

In order to maintain the target financing, the amount of new debt must fall over the life of the project.

This is true because the value of the project depends upon the future cash flow at each point in time. Since the project ends, value decreases. Since value decreases, debt must also decrease.

year 0 1 2 3 4 5Free Cash Flow (25.20)$ 12.45$ 16.35$ 20.25$ 24.15$ 28.05$ Levered Value 77.30$ 71.42$ 61.14$ 46.09$ 25.85$ -$ Debt Capacity d = 40% 30.92$ 28.57$ 24.46$ 18.43$ 10.34$ -$

Page 18: CAPITAL BUDGETING WITH LEVERAGE. Introduction  Discuss three approaches to valuing a risky project that uses debt and equity financing.  Initial Assumptions

The Adjusted Present Value Method

Adjusted Present Value (APV) A valuation method to determine the

levered value of an investment by first calculating its unlevered value and then adding the value of the interest tax shield and deducting any costs that arise from other market imperfections

(Interest Tax Shield)

(Financial Distress, Agency, and Issuance Costs)

L UV APV V PV

PV

Page 19: CAPITAL BUDGETING WITH LEVERAGE. Introduction  Discuss three approaches to valuing a risky project that uses debt and equity financing.  Initial Assumptions

The Unlevered Value of the Project The first step in the APV method is to

calculate the value of the free cash flows using the project’s cost of capital if it were financed without leverage.

Page 20: CAPITAL BUDGETING WITH LEVERAGE. Introduction  Discuss three approaches to valuing a risky project that uses debt and equity financing.  Initial Assumptions

The Unlevered Value of the Project

Unlevered Cost of Capital The cost of capital of a firm, were it unlevered:

for a firm that maintains a target leverage ratio, it can be estimated (recall the picture) as the weighted average cost of capital computed without taking into account taxes (pre-tax WACC).

This is, strictly speaking, only true for firms that adjust their debt to maintain a target leverage ratio.

Pretax WACC U E D

E Dr r r

E D E D

Page 21: CAPITAL BUDGETING WITH LEVERAGE. Introduction  Discuss three approaches to valuing a risky project that uses debt and equity financing.  Initial Assumptions

The Unlevered Value of the Project

For Ralph, the unlevered cost of capital is calculated as:

The project’s value without leverage is then calculated as:

0.60 12.0% 0.40 5.0%

9.2%Ur

2 3 4 5

12.45 16.35 20.25 24.15 28.05 +

1.092 1.092 1.092 1.092 1.092 $75.71 million

UV

Page 22: CAPITAL BUDGETING WITH LEVERAGE. Introduction  Discuss three approaches to valuing a risky project that uses debt and equity financing.  Initial Assumptions

Valuing the Interest Tax Shield The value of $75.71 million is the value

of the unlevered project and does not include the value of the tax shield provided by the interest payments on debt.

The interest tax shield is equal to the interest paid multiplied by the corporate tax rate.

1Interest paid in year D tt r D

Page 23: CAPITAL BUDGETING WITH LEVERAGE. Introduction  Discuss three approaches to valuing a risky project that uses debt and equity financing.  Initial Assumptions

Interest Tax Shield

From the debt capacity calculation we can find the interest associated with the project if the financing is kept at the target. year 0 1 2 3 4 5

Free Cash Flow (25.20)$ 12.45$ 16.35$ 20.25$ 24.15$ 28.05$ Levered Value 77.30$ 71.42$ 61.14$ 46.09$ 25.85$ -$ Debt Capacity d = 40% 30.92$ 28.57$ 24.46$ 18.43$ 10.34$ -$ Interest -$ 1.55$ 1.43$ 1.22$ 0.92$ 0.52$ Interest Tax Shield -$ 0.54$ 0.50$ 0.43$ 0.32$ 0.18$

Page 24: CAPITAL BUDGETING WITH LEVERAGE. Introduction  Discuss three approaches to valuing a risky project that uses debt and equity financing.  Initial Assumptions

Valuing the Interest Tax Shield

The next step is to find the present value of the interest tax shield. When the firm maintains a target leverage

ratio, its future interest tax shields have similar risk to the project’s cash flows, so they should be discounted at the project’s unlevered cost of capital.

2 3 4 5

0.54 0.50 0.43 0.32 0.18(interest tax shield) +

1.092 1.092 1.092 1.092 1.092 $1.59 million

PV

Page 25: CAPITAL BUDGETING WITH LEVERAGE. Introduction  Discuss three approaches to valuing a risky project that uses debt and equity financing.  Initial Assumptions

Valuing the Project with Leverage

The total value of the project with leverage is the sum of the value of the interest tax shield and the value of the unlevered project.

The NPV of the project is $52.10 million $77.30 million – $25.20 million = $52.10 million

This is exactly the same value found using the WACC approach.

(interest tax shield)

75.71 1.59 $77.30 million

L UV V PV

Page 26: CAPITAL BUDGETING WITH LEVERAGE. Introduction  Discuss three approaches to valuing a risky project that uses debt and equity financing.  Initial Assumptions

Summary of the APV Method1. Determine the investment’s value

without leverage.

2. Determine the present value of the interest

tax shield.a. Determine the expected interest tax shield.

b. Discount the interest tax shield.

3. Add the unlevered value to the present value of the interest tax shield to determine the value of the investment with leverage.

Page 27: CAPITAL BUDGETING WITH LEVERAGE. Introduction  Discuss three approaches to valuing a risky project that uses debt and equity financing.  Initial Assumptions

Summary of the APV Method

The APV method has some advantages. It can be easier to apply than the WACC

method when the firm does not maintain a constant debt-equity ratio.

The APV approach also explicitly values market imperfections and therefore allows managers to measure their contribution to value.

Page 28: CAPITAL BUDGETING WITH LEVERAGE. Introduction  Discuss three approaches to valuing a risky project that uses debt and equity financing.  Initial Assumptions

The Flow-to-Equity Method

Flow-to-Equity A valuation method that calculates the free

cash flow available to equity holders taking into account all payments to and from debt holders. Free Cash Flow to Equity (FCFE), the free cash

flow that remains after adjusting for interest payments, debt issuance and debt repayments

The cash flows to equity holders are then discounted using the equity cost of capital.

Page 29: CAPITAL BUDGETING WITH LEVERAGE. Introduction  Discuss three approaches to valuing a risky project that uses debt and equity financing.  Initial Assumptions

Free Cash Flow to Equity

Free Cash Flow to EquityYear 0 1 2 3 4 5

Unlevered NI (5.20)$ 8.45$ 12.35$ 16.25$ 20.15$ 24.05$ Less After Tax Interest -$ 1.00$ 0.93$ 0.79$ 0.60$ 0.34$ Plus Depr -$ 4.00$ 4.00$ 4.00$ 4.00$ 4.00$ Less Net Cap Ex 20.00$ -$ -$ -$ -$ -$ Less Change in NWC -$ -$ -$ -$ -$ -$ Plus Net Borrowing 30.92$ (2.35)$ (4.11)$ (6.02)$ (8.09)$ (10.34)$ Free Cash Flow to Equity 5.72$ 9.09$ 11.31$ 13.43$ 15.46$ 17.37$

Page 30: CAPITAL BUDGETING WITH LEVERAGE. Introduction  Discuss three approaches to valuing a risky project that uses debt and equity financing.  Initial Assumptions

Valuing the Equity Cash Flows Because the FCFE represent payments to equity

holders, they should be discounted at the project’s equity cost of capital. Given that the risk and leverage of the project are the

same as for Ralph Inc. overall, we can use Ralph’s equity cost of capital of 12.0% to discount the project’s FCFE.

The value of the project’s FCFE represents the gain to shareholders from the project and it is identical to the NPV computed using the WACC and APV methods. (The debt is sold at a fair price.)

2 3 4 5

9.09 11.31 13.43 15.46 17.37( ) 5.72 +

1.12 1.12 1.12 1.12 1.12 $52.10 million

NPV FCFE

Page 31: CAPITAL BUDGETING WITH LEVERAGE. Introduction  Discuss three approaches to valuing a risky project that uses debt and equity financing.  Initial Assumptions

Project-Based Costs of Capital

In the real world, a specific project may have different market risk than the average project for the firm.

In addition, different projects will may also vary in the amount of leverage they will support.

Page 32: CAPITAL BUDGETING WITH LEVERAGE. Introduction  Discuss three approaches to valuing a risky project that uses debt and equity financing.  Initial Assumptions

Estimating the Unlevered Cost of Capital

Suppose the project Ralph launches faces different market risks than its main business. The unlevered cost of capital for the new

project can be estimated by looking at publicly traded, pure play firms that have similar business risks.

Page 33: CAPITAL BUDGETING WITH LEVERAGE. Introduction  Discuss three approaches to valuing a risky project that uses debt and equity financing.  Initial Assumptions

Estimating the Unlevered Cost of Capital

Assume two firms are comparable to the chew toy project in terms of basic business risk and have the following observable characteristics:Firm Equity Beta Debt Beta Debt-to-

Value Ratio

Firm A 1.7 0.05 40%

Firm B 1.9 0.10 50%

Page 34: CAPITAL BUDGETING WITH LEVERAGE. Introduction  Discuss three approaches to valuing a risky project that uses debt and equity financing.  Initial Assumptions

Estimating the Unlevered Cost of Capital using Betas

We now find their unlevered or asset betas:

An average of these unlevered betas is 1.02.

Note, an unlevered beta of 1.02 gives an unlevered cost of equity capital of:

0.6 0.41.7 0.05 1.04

0.6 0.4 0.6 0.4

0.5 0.51.9 0.1 1.0

0.5 0.5 0.5 0.5

A AA A AU E DA A A A

B BB B BU E DB B B B

E D

E D E D

E D

E D E D

( ) 4% 1.02(6%) 10.12%U f Ur r RP

Page 35: CAPITAL BUDGETING WITH LEVERAGE. Introduction  Discuss three approaches to valuing a risky project that uses debt and equity financing.  Initial Assumptions

Project Leverage and the Equity Cost of Capital

Now assume that Ralph plans to maintain a 20% debt to value ratio for its chew toy project, and it expects its borrowing cost to be 4%.

We now “relever” the unlevered beta estimate of 1.02 and using the SML we find the cost of levered equity:

A cost of debt capital of 4% is consistent with the low leverage chosen and a debt beta of 0.

0.2( ) 1.02 (1.02 0.0) 1.275

0.8( ) 4% 1.275(6%) 11.65%

E U U D

E f E

D

Er r RP

Page 36: CAPITAL BUDGETING WITH LEVERAGE. Introduction  Discuss three approaches to valuing a risky project that uses debt and equity financing.  Initial Assumptions

Project Leverage and the Weighted Average Cost of Capital

With a 20% debt to value ratio, a cost of equity capital of 11.65%, and a cost of debt capital of 4% we can now estimate the WACC for the project.

0.8 0.211.65% 4%(1 0.35) 9.84

0.8 0.2 0.8 0.2WACCr

Page 37: CAPITAL BUDGETING WITH LEVERAGE. Introduction  Discuss three approaches to valuing a risky project that uses debt and equity financing.  Initial Assumptions

An Alternate Approach

From the observable (or measurable) data we can get estimates of the cost of equity capital and the cost of debt capital:

Firm A:

Firm B:

4% 1.7 6% 14.2%

4% 0.05 6% 4.3%E

D

r

r

4% 1.9 6% 15.4%

4% 0.1 6% 4.6%E

D

r

r

Page 38: CAPITAL BUDGETING WITH LEVERAGE. Introduction  Discuss three approaches to valuing a risky project that uses debt and equity financing.  Initial Assumptions

An Alternate Approach

Recall the relation between the levered cost of equity capital and the unlevered cost of equity capital:

Rearranging this we find:

In other words, the unlevered cost of equity capital equals the pre-tax WACC

( )E U U D

Dr r r r

E

pre-tax WACCU E D

E Dr r r

E D E D

Page 39: CAPITAL BUDGETING WITH LEVERAGE. Introduction  Discuss three approaches to valuing a risky project that uses debt and equity financing.  Initial Assumptions

Estimating the Unlevered Cost of Capital

Assuming that both firms maintain a target leverage ratio, the unlevered cost of capital for each competitor can be estimated by calculating their pretax WACC.

Based on these comparable firms, we estimate an unlevered cost of capital for the project that is approximately 10.12%.

Firm A: 0.60 14.2% 0.40 4.3% 10.24%

Firm B: 0.50 15.4% 0.50 4.6% 10.0%U

U

r

r

Page 40: CAPITAL BUDGETING WITH LEVERAGE. Introduction  Discuss three approaches to valuing a risky project that uses debt and equity financing.  Initial Assumptions

Project Leverage and the Equity Cost of Capital

Ralph plans to maintain a 20% debt to value ratio for its chew toy project, and it expects its borrowing cost to be 4%. Given the unlevered cost of capital

estimate of 10.12%, the chew toy division’s equity cost of capital is estimated to be:

0.20 10.12% (10.12% 4%)

0.80 11.65%

Er

Page 41: CAPITAL BUDGETING WITH LEVERAGE. Introduction  Discuss three approaches to valuing a risky project that uses debt and equity financing.  Initial Assumptions

Project Leverage and the Weighted Average Cost of Capital

The division’s WACC can now be estimated to be:

An alternative method for calculating the chew toy division’s WACC is:

0.80 11.65% 0.20 4.0% (1 0.35)

9.84%WACCr

10.12% 0.20 0.35 4%

9.84%

WACC U c Dr r d r