CAPITAL BUDGETING & INVESTMENT APPRAISAL METHODS
PRESENTATION BY
PROF. V.RAMACHANDRAN SIESCOMS, NERUL, NAVI MUMBAI
2
AGENDA
Concept of Capital Budgeting Capital Expenditure Budget Importance of Capital Budgeting Rational of Capital Expenditure Kinds of Capital Investment Proposals Factors affecting Investment Decision Investment Appraisal Methods Capital Rationing
3
Concept of Capital Budgeting
Finance Manager is concerned with Planning and Financing investment decisions.
Financing Decisions relate to determination of amount of long term finance and decision on sources for financing the same.
Investment decisions also termed as “Capital Budgeting Decisions” involve cost - benefit analysis.
Investment decisions are based on careful consideration of factors like profitability, safety, liquidity, solvency etc.
4
Why Capital Budgeting
Capital investment means investments in projects which by nature involve huge expenditure and results of the same are known only after a long time.
Why Capital investment is necessary For investments in New Projects Replacement of worn out/ out dated assets. Expansion of existing capacity – To meet high demand or
inadequate production capacity. Diversification – to reduce risk Research and Development – Ensuring updated
technology. Miscellaneous – Installation of Pollution Control equipment,
other legal requirements.
5
Capital Budgeting The term Capital Budgeting refers to long term planning
for proposed capital outlays and their financing It involves raising of long term funds and their
utilization. In other words, It is the formal process for acquisition
and investment of capital. Capital Budgeting is a many-sided activity. It is a process of:
searching for new and more profitable investment options
by taking into account the consequences of accepting an investment proposal
by making a detailed economic analysis of the profit making potential of each investment proposal.
6
Capital Budgeting Essential features based on which decisions are
taken Profit potential Degree of risk Gestation period i.e time lag from the
period of initial investment to anticipated returns.
7
Capital Expenditure Budget
It is the formal plan of Capital expenditure on new projects/ purchase of fixed assets.
Provides for the capital outlay available for procurement of capital assets during the Budget period.
It is prepared by taking into consideration Future demand projections/growth of industry the available production capacities, allocation of existing resources and likely improvement in production
techniques.
8
Capital Expenditure Budget-objectives
Determines the When the work on capital projects can be commenced
Estimates the expenditure that would be incurred on the projects approved by the management and the sources from which finance will be obtained
Restricts capital expenditure on projects within the authorized limits
9
Importance of Capital Budgeting
One of most crucial and critical business decisions Involvement of heavy funds- Improper and ill-advised
investment and incorrect decisions can jeopardize the survival of even Biggest firm
Long – term implications- Impact of capital decisions are known after a long period. A wrong decision can prove disastrous for the long term survival of the firm
Irreversible decisions Most difficult decisions to make – Capital Budgeting
decisions require assessment of future events which are uncertain. Further assessing future costs and benefits accurately in quantitative terms is not easy. E.g KCC and Taloja
In view of the above the capital expenditure decisions are best reserved for consideration of the highest level of management
10
Kinds of Capital Investment Proposals
Independent proposals- Don’t compete with any other proposal. They are
cases of “accept or reject” proposals on the minimum return on investment cut off criteria basis.
Contingent or dependent Proposals :- Proposals whose acceptance depends on the
acceptance one or more proposals.-Substantial Expansion of plan, other capital requirement. Like township etc
Mutually exclusive proposals;- e.g Temperature control Systems, Agitator, Valves
Etc
11
Factors affecting Capital investment decisions The amount of investment-
where no funds constraints are there proposals giving higher rate of return than the minimum cut off rate may be accepted
However where fund constraints are there, then Capital Rationing has to be resorted to.
Projects should be arranged in ascending order of capital investment and giving due consideration of priority
12
Investment Appraisal Methods
In view of the importance of Capital Budgeting decisions, it is essential that the Capital Investment appraisal method adopted must be sound.
A good appraisal method should have the features. Clear Basis for distinguishing between acceptable
and non acceptable projects Ranking the projects on the basis of desirability Choosing among several alternatives A criterion applicable to any conceivable project Recognizing bigger benefit projects are preferable
to smaller ones and early benefit projects are preferable to later ones
13
Investment Appraisal Methods
In all the appraisal methods emphasis is on the return.
The basic approach to compare the investment in the project with benefits derived there from.
Following are the main methods generally used;-
1. Pay –back period method
2. Discounted Cash flow methoda) The Net present value method
b) Present value index method
c) IRR Method
3. Accounting Rate of return Method
14
Pay –back period method
The term Pay –back Period refers to the period in which the project will generate the necessary cash to recoup the initial investment
For e.g- if a project requires Rs.20000 as initial investment and it will generate an annual cash flow of Rs.5000 for ten years, the pay-back period will be 4 years, calculated as follows
Pay –back period =
The Annual cash flow is calculated on the basis of Net income before depreciation but after considering the tax. (PAT+Depreciation)
Initial investment Annual cash Flow
15
Pay –back period method
The income expressed as %of initial investment is termed as Unadjusted rate of return
Unadjusted Return = x100
= x100 =25%
Uneven cash flow:- If a project requires an initial investment of Rs.20000 and annual cash inflows for 5 years are Rs.6000,Rs.8000,Rs.5000,Rs.4000 and Rs.4000 respectively ,the pay –back period will be calculated as follows
Annual return Initial Investment
5000 20000
16
Pay –back period method
Year Cash Inflows
Cumulative cash inflows
1 6000 6000
2 8000 14000
3 5000 19000
4 4000 23000
5 4000 27000
Rs.19000 is recovered in 3years and Rs.1000 is left out of initial investment. The cash inflow in 4th year is Rs.4000 which indicates that pay-back period is in between 3rd and 4th year.i.e.3+(1000/4000) = 3.25 years
17
Pay –back period method
Criterion of accept or reject: Reciprocal of cost of capital (COC).
for e.g If COC is 20% the maximum acceptable Pay-back period would be 5 years (i.e.100/20)which can also be termed as cut off point.
May be a predetermined Criteria by management i.e.say Reciprocal of COC -Safety Margin.
5 years -1= 4 Refer to illustration 5.4 and 5.5
18
Pay –back period method
Merits Useful for evaluation of projects with high
uncertainty, political instability, obsolescence of Technology etc
Method based on the assumption that no profit arises till initial capital is recovered. Suitable of new companies
Simple to understand and to workout Reduces the possibility of loss due to
obsolescence as the investment is made only on short term projects
19
Pay –back period method
Demerits Ignores the returns after its pay –back
period Projects with long gestation period will
never be taken up though they yield better returns
The method ignores the time value of money
Pay –back period method
Suitability Hazy long term outlook- Political or other conditions are hazy this
method is suitable Firms suffering from liquidity crises Firms dependent on short term performances
20
21
Discounted Cash Flow (DCF)
DCF Technique is an improvement on payback period method.
It takes into account Time Value of money i.e interest factor as well as the returns after the payback period.
The method involves 3 stages Calculation of cash flows (both inflow and
outflow preferably after tax for full life of the project).
Discounting cash flows by applying a discount factor.
Aggregation of discounted cash flows and ascertainment of net cash flow.
22
NPV Method
The cash inflows and cash outflows associated with the project are worked out.
The present value of these cash flows is calculated at a rate of return acceptable to the management ( Cost of capital suitably adjusted for risk element)
The net present value (NPV) i.e. difference between total present value of cash inflow and total present value of cash outflow is ascertained.
23
NPV Method
Accept or reject criterion Where NPV > Zero Accept the proposal. Where NPV < Zero Reject the proposal. Refer illustration 5.6 , 5.7 and 5.8.
24
Excess present value index
This is a refinement of NPV method. Instead of working out the NPV a present
value index is worked out by comparing total present value of future cash inflows and total present value of future cash outflows.
Refer illustration 5.10.
25
Internal rate of return (IRR)
IRR is that rate of return at which the sum of discounted cash inflows equals the sum of cash outflows.
In other words it is the rate which discounts the cash flows to zero.
It can be stated in the form of formula as under.
=1
Cash inflows Cash outflows
26
Internal rate of return (IRR)
Accept / Reject Criterion: IRR is the maximum rate of interest which
an organization can afford to pay on capital invested in a project.
A Project would qualify only if IRR exceeds the cut-off rate.
A project giving higher IRR than cut-off rate would be preferred.
Refer e.g. 5.12 & 5.13.
27
Accounting Rate of return (ARR)
Under this method proposals are judged on the basis of relative profitability.
It is calculated on the following basis. (Annual Average net earnings / original
investments)*100 Annual Average net earnings is the average
net earnings after depreciations and tax for the entire life of the project.
Refer illustration 5.16.
28