INSTALLED COST ESTIMATE METHODS
FOR TYPE 1 OR 2 FEASIBILITY ESTIMATE USE PURCHASED EQUIPMENT COSTS AND
FACTORS SIMPLEST IS SIMPLY 4.0 FACTOR FOR PLANT TYPE ADJUSTMENT SEE TABLE 6-10.
RANGES ARE FROM 4.7 -6.0.7 USE M&S INDICES FOR INFLATION COST SCALE-
UP FOR INDIVIDUAL EQUIPMENT, USE FACTORS
FROM CHEMICAL ENGINEERING PLANT COST INDEX (ALSO IN CHEMICAL ENGINEERING MAGAZINE)
SPECIFIC PLANTS THE TEXT HAS SOME PLANT DATA IN
TABLE 6-11 DATA IS SCALED UP FROM 1970 DATA SO
IS IN QUESTION MOST ESTIMATES ARE BASED ON
EQUIPMENT COSTS THAT EQUIPMENT COSTS CARRY AN
ACCURACY LIMIT AS WELL - +25% IS TYPICAL FOR PEP PROJECTS
AT SRI
FOR TYPE 3 FUNDING ESTIMATE
USE PROJECT DATA - DESIGN CRITERIA, DESIGN BASES, INITIAL SITE DATA
NEED STRUCTURAL DATA NEED SHOP VS. FIELD FABRICATION DATA NEED LABOR VALUES
USE VENDOR QUOTES FOR EQUIPMENT PLUS SHIPPING TO GET DELIVERED COSTS
FOR CONTROL BUDGET
NEED FINAL DRAWINGS NEED QUOTATIONS FROM
CONSTRUCTION SUBCONTRACTORS WHERE AVAILABLE
NEED SPECIFIC COSTS FOR EQUIPMENT, MATERIALS, LABOR AND ERECTION EQUIPMENT
NEED DEFINITION OF SHOP VS. FIELD RESOURCES
CAPITAL ESTIMATE COMPONENTS
DIRECT FIXED CAPITAL INCLUDES COMPONENTS AS PER TABLE
6-3 DEFINITION SUMMARY (TABLE 6-9)
TOTAL PLANT CAPITAL (TPC) = TOTAL PLANT DIRECT CAPITAL (TPDC) + TOTAL PLANT INDIRECT COSTS (TPIC) + WORKING CAPITAL (WC) TPC = TPDC + TPIC+ WC
FEASIBILITY ESTIMATE DEVELOP PEC AND USE PEC
FACTORS METHOD TYPICAL FACTORS FOR ESTIMATE
COMPONENTS ARE IN TABLE 6-3 & 6-17
INSTALLATION COSTS DEPENDS ON AMOUNT OF PIPING VS.
SOLIDS HANDLING (NON-SLURRY) INCLUDES FOUNDATION AND
STRUCTURAL BUT NO INTERCONNECTING SYSTEMS
IF ESTIMATED ON AN EQUIPMENT ITEM BASIS, SEE TABLE 6-5 FOR TYPICAL VALUES
PROCESS PIPING FACTOR RANGES OVER PLANT TYPE FROM SOLIDS
ONLY TO FLUIDS ONLY SEE TABLE 6-6 FOR FACTORS
INSTRUMENTATION FACTORS
RANGE FROM MANUAL TO TOTAL COMPUTER CONTROL, 10% - 50% OF PEC
MOST PLANTS USE THE 35% LEVEL WITH DISTRIBUTED CONTROL SYSTEMS
BATCH OR INTERMITTENT OPERATION THROUGH PROGRAMMABLE CONTROLLERS
FOR A DISCUSSION OF THE USE OF WIRELESS INSTRUMENTATION :
http://www.automationworld.com/view-1936
OTHER FACTORS INSULATION FACTORS
USED FOR CONTROL OF HEAT LOSS, HEAT GAIN AND PERSONNEL PROTECTION
TOTALS RUN AROUND 8% OF PEC ELECTRICAL FACILITIES FACTOR
DOES NOT INCLUDE CONTROL, BUT DOES INCLUDE POWER SUPPLIES.
ASSUMES POWER FROM SOURCE OUTSIDE OF BATTERY LIMITS
AMOUNTS TO ABOUT 15% OF PEC SEE COMPONENTS IN TABLE 6-8
OTHER FACTORS BUILDINGS FACTOR
DEPENDS ON CRITERIA
FOR JOB FOR EXISTING PLANTS, TYPICAL VALUES ARE SHOWN IN TABLE 6-9
YARD IMPROVEMENT INCLUDES ALL THE CIVIL ASPECTS OF THE
PROJECT INITIAL GRADING UNDERGROUND UTILITY SYSTEMS TRANSPORTATION COMPONENTS AND FINISH OUTSIDE OF PROCESS AREAS
OTHER DIRECT COSTS
AUXILIARY SYSTEMS THE UTILITY COMPONENTS FROM
OUTSIDE THE BATTERY LIMITS REQUIRED FOR OPERATION
MAY INCLUDE UPGRADE OF EXISTING UNITS.
INDIRECT COMPONENT FACTORS
ENGINEERING COSTS INCLUDE COSTS FOR DESIGN THROUGHOUT
THE PROJECT. TEND TO INCLUDE ASPECTS OF CONSTRUCTION.
VALUES ARE SHOWN AS TOTAL IN TABLE 6-9
CONSTRUCTION INCLUDES ADMINISTRATION OF ALL
ASPECTS OF PROJECT DEPENDS ON MANY FACTORS AS INDICATED
IN TABLE 6-9
INDIRECT COMPONENT FACTORS
CONTRACTORS FEE PROFIT AND OVERHEAD COMPONENT FOR
ENGINEERING AND CONSTRUCTION FIRMS RANGES AROUND 4-6% OF TOTAL FIXED
CAPITAL INVESTMENT
CONTINGENCY - ANTICIPATED COSTS FOR CHANGES THAT WILL OCCUR DURING THE PROJECT
FOR THIS PROJECT USE THE VALUES IN TABLE 6.17 AND EXPLAIN BASIS OF CHOICE