capstone ceen-cpst-0 11 ohio power plant foundation
TRANSCRIPT
CAPSTONE
CEEn-CPST-0
Ohio Power Plant Foundation
April 9, 2021 1
11
US/Guam Alliance
Austin KennedyChloe GogueWill Berger
Taylor Emmertson
CAPSTONE
Introduction
April 9, 2021 2
We will be justifying how we arrived at the specified foundation/ground improvement technique combination of each building.
CAPSTONE
Project Tasks and Deliverables
April 9, 2021 3
▪ We were tasked with researching foundation options and ground improvement techniques to ensure that the power plant would not settle more than 1 in.
▪ Each building was assessed and options were chosen based on economic feasibility and bearing capacity/settlement requirements
▪ The project was completed on time and in full, to the best of our ability considering our status as students and our low level of expertise.
CAPSTONE
Design and Analysis
April 9, 2021 4
Analysis of the power plant was done in separate sections, where we focused on one building at a time as they each of had unique soil profiles and collected data. This information was then used in our settlement calculations and helped in assigning proposed foundation types and ground improvement techniques.
CAPSTONE
Design and Analysis Cont’d
April 9, 2021 5
Below is a list of the soil conditions and anticipated settlement for each area.
Structure Soil Conditions Anticipated Settlement
Water Treatment Building - Sandy clay- High water table due to entrapped water
⅝ in.
Tank Farm - Sandy gravel- Entrapped water
⅝ in.
Cooling Tower - Sandy gravel- Half lies on entrapped water
½ in.
Admin Building - Clayey silty sand ½ in.
GSU/UAT - Gravelly sand- Must excavate top portion of clay so that deep dynamic compaction reaches intended soil
layers
⅝ in.
Turbine Building - Mostly well-graded gravel, with a patch of clay in the middle ⅝ in.
AUX BRL Building - Gravelly sand with a top layer of clay- Entrapped water
⅝ in.
HRSG - Well graded gravel with thin layer of lean clay with fine gravel ⅞ in.
Electrical/Ammonia Building - First two feet are clay and need to be excavated- The soil underneath is gravelly sand
½ in.
CAPSTONE
Discussion of Results
April 9, 2021 6
Challenges:▪ Limited knowledge on the subject ▪ Little outside verification from mentor▪ Hard to determine if we accounted for everything when determining our
recommendations▪ Unable to know if our list of options was exhaustive
Results:▪ The results were based on our limited interpretations of the data that was
given to us▪ We did our best to establish a soil profile of each building and determine
which recommendation options would be the best
CAPSTONE
Discussion of Results Cont’d
April 9, 2021 7
Possible foundation systems include:
Foundation System Application Advantages Drawbacks
Spread footing with slab - Wall loads present- Shallow
- Cost-effective- Non-skilled labor- Simple construction
- Higher settlement- Requires higher soil bearing capacity- May cause irregularity in future structure
Pier and Beam - Shallow- Steel buildings- Swelling soils
- Applicable in a variety of site locations
- Allows room for crawl space/ basement
- More expensive shallow option
Pile - Deep- Large Structures- Areas with unsuitable shallow soil- Areas with high groundwater table
- Bypasses shallow soil- High load capacity- Corrosion-
resistant
- Possible pile damage during construction- Located below ground level- Custom pile lengths common (increased
cost)
Matte foundation - Large distributed loads- Areas with weak soil- Buildings with basements
- Resists differential settlement- Very strong- Low cost when doubled as floor slab
- Swelling soils cause uplift- May need heavy reinforcement- Experienced labor needed
CAPSTONE
Discussion of Results Cont’d
April 9, 2021 8
Possible ground improvement techniques include:
Technique Application Advantage Drawback
Grouting - Filling pores in soil or rock - Decreased permeability- Higher shear strength
- Quality assurance is unknown- Difficult in shallow depths
Deep Dynamic Compaction - Densifies soil by dropping heavy steel/concrete weight with crane
- Increased density- Increased strength- Decreased settlement- Lower liquefaction potential- Higher bearing capacity
- Non-applicable in areas with soft cohesive soils
- Non-applicable within 100ft of existing building
Vibro-compaction/ Vibro- Replacement - Course aggregate added to existing hole and compacted using vibration
- Increased density- Reduced differential/total settlement- Higher bearing capacity
- Granular soil contains more than 12-15% silt or more
Rammed Aggregate Piers - Aggregate/grout columns added below slab
- No dewatering- Short construction time- Increased soil stiffness
- Limited Bearing capacity per pier- Increased cost per additional pier
Wick Drains - Drainage path for excess pore water in soft/compressible soil
- Reduced long term settlement - High equipment cost- Only viable in shallow depths
CAPSTONE
Conclusions
April 9, 2021 9
Lessons Learned:▪ Communication is key, especially if you are inexperienced and need
Zoom to get anything done▪ We got to learn lessons in reading test pit tables, cone penetration
tests, and boring logs to draw conclusions on soil conditions▪ Most of our recommendations will become more reasonable with
practice