capture-ready principles and design for pulverised coal plants mathieu lucquiaud, hannah chalmers,...
TRANSCRIPT
Capture-ready principles and design for pulverised coal plants
Mathieu Lucquiaud, Hannah Chalmers, Jia Li and Jon Gibbins
Energy Technology for Sustainable Development Group,
Department of Mechanical Engineering, Imperial
Xi Liang and David Reiner, Judge Business School, Cambridge
UKCCSC project meeting, 20th March 2008
Why do CCS? – cumulative global CO2 emissions
‘Unconventional oil’ includes oil sands and oil shales but not CTL. ‘Unconventional gas’
includes coal bed methane, deep geopressured gas etc. but not gas from coal and a possible
12,000 GtC from gas hydrates.
CARBON IN
FOSSIL FUELS
CARBON THAT CAN BE
EMITTED TO ATMOSPHERE
From 3rd Assessment Report, http://www.ipcc.ch/
Why do capture-ready? – time needed to learn (1)
Gibbins and Chalmers (2008), Energy Policy
FIRST TRANCHE
Demonstration
SECOND TRANCHE
Commercial &Regulatory Drivers
Overall effortalso important
to maintain continuity
GLOBALCCS
ROLLOUTBig prize is getting two learning cycles
from two tranches of CCS projects before
global rollout
EUCCS
ROLLOUT
PLANTSCOMINGINTO SERVICE
12 plants by 2015 in EU
CCS build-up plus all plants built capture-ready
CCS retrofit on capture-ready plants
2015DEMO
PROJECTSIN PLACE
2020CCS
STANDARDIN EU
2025GLOBAL
CCSROLLOUT
Critical path for IGCC and oxyfuel demo and deployment?…Critical path for IGCC and oxyfuel demo and deployment?…
Why do capture-ready? – time needed to learn (2)Critical path for post-combustion capture demo and deployment?…Critical path for post-combustion capture demo and deployment?…
Gibbins and Chalmers (2008), Energy Policy
Second tranche plants overlap with first tranche since many lessons can be learned without needing a
new plant (e.g. solvent development and some aspects of absorber
design, including packing)
PLANTSCOMINGINTO SERVICE
2015 2020 2025
First tranche plants earlier (especially if
retrofits)
Big prize is having technology suitable for
global deployment available up to 5 years earlier (and well suited to retrofit too)
Construction of second tranche plants can start
earlier since capture plant design fixed later in
the process Shorter timescales for building new capture
plant (since don’t need new power plant) mean that more learning is available from
earlier tranches for rollout
• Owner – needs to protect the investment value– needs to get plant permitted
• Society – doesn’t need to protect investment value, but– does need someone to be able to operate the
plant in the future with CCS (if the original owner goes broke)
• Regulator(s) – needs to keep the lights on, get new plant built,
provide continuity, minimise costs etc.
Also, some risk-based perspectives…
Must:• Have access to suitable geological storage• Have space and access for capture equipment• Have reasonable confidence it will work (feasibility study)
Also consider:
• Up-front expenditure with savings later, e.g.
Bigger/better equipment?
Move near cheaper/better CO2 storage?
• Flexibility – initial retrofit and later technology upgrades
But only pre-investments with very good returns justified
See IEA GHG report on capture-ready
Basic principles for capture-ready design
Mustbut different
interests?
Must:• Have access to geological storage• Have space and access for capture equipment• Have reasonable confidence it will work
Also consider:• Up-front expenditure with savings later, e.g.
Bigger, better equipment?
Cheaper/better CO2 storage?
• Flexibility – initial retrofit and later technology upgrades
SocietyReasonably-justified plan for the future
Owner
& auditors,bank’s
engineers etc.Detailed studies
for immediate action, protect investment value
Regulator
e.g. Have to re-permit for CO2 after ten years?
Whys map on to hows
IGCC• Hard to integrate before and after capture• Oversize components (Parsons study)• Shift before capture (Jacobs GEM)• Simpler option - build a second unit alongside when capture is added and size to integrate?• Many designs possible (e.g. 4 entrained flow gasifiers)
OXYFUEL• Boiler manufacturers developing designs
• Can also make post-combustion capture ready
IGCC and oxyfuel capture-ready designs
• Post-com capture credibility - must be demonstrated• Many future developments likely• Should not lock in to known technology• Likely common requirements, can be met at low cost:
• Space – large volumes of gas to handle, building work• Clean and probably cool flue gas• Pressure drop• Provision for extra instrumentation and control, other services• Extra cooling (efficiency penalty)• Some electricity for capture/compression plant• Some steam for temperature swing solvents
Post-combustion capture-ready designs
• Limited experience of offshore CO2 pipelines
• More experience with onshore pipelines, but often in places with little/no population
• It seems likely that regulators will need to play a role here
• One key issue is then what a UK/North Sea network might look like (hub and spokes model?)…
Some key issues to consider for pipeline (and storage) planning
• CCS is needed since danger of excess cumulative emissions from fossil fuel use
• Various options for capture, transport and storage• Main actions now are getting ready for CCS
– Serious demonstration projects and deployment strategy required (local, regional and global)
– Also want new-build plants to be capture-ready
• Challenging, but we know enough to get started
Overview so far…
• Clutched LP turbine
added for capture
unclutched for capture or removed and LP rotor replaced by lay shaft
IPHP LP
LP
reboiler
DSH
3.6 bar
• Floating IP/LP crossover pressure
IPHP LP
LP
added for capturereboiler
DSH
6.7 bar => 3.6 bar
• Throttled LP turbine
IPHP LP
LP
added for capturereboiler
DSH
3.6 bar
Steam turbine design for capture-readiness
PC plant without
CCS
PC plant with CCS
Clutched LP turbine retrofit
Throttled LP turbine retrofit
Floating IP/LP
crossover pressure
Efficiency without CCS
45.3% 45.3% 45.3% 45.3%
Efficiency with CCS
35.9% 35.9% 35.0% 35.5%
Flexible design for 2nd and 3rd generation of
solvents
NO YES YES
Additional capital costs
High Negligible Negligible
Operation without capture
Reclutched LP turbine
Easy Easy
•IEA GHG Report – 2007/4 CO2 capture-ready power plants
•Report commissioned in response to G8 Gleneagles communiqué
•It will be presented at the G8 summit in Japan this summer
Inputs to policy process include…
•Capture-ready makes sense in the context of cumulative emissions and new-build of coal-fired power plants (globally)
•Capture-ready principles for post-combustion capture at coal-fired power plants are clear
•Additional costs close to zero
•Steam turbine manufacturers and power utilities have taken the message on board
Key conclusions
Capture-ready photo montage(some details omitted)
Richard Hotchkiss, RWE npower - Recent Developments in Carbon Capture and Storage (CCS) – Coal Research Forum - http://www.coalresearchforum.org/pastmeetings.html
Tilbury 2x 800 MWTilbury 2x 800 MW
Capture-ready photo montage(some details omitted)
Richard Hotchkiss, RWE npower - Recent Developments in Carbon Capture and Storage (CCS) – Coal Research Forum - http://www.coalresearchforum.org/pastmeetings.html
PROJECT TITLE: PROJECT TITLE: CHINESE ADVANCED POWER PLANT CHINESE ADVANCED POWER PLANT CARBON CAPTURE OPTIONS (CAPPCCO)CARBON CAPTURE OPTIONS (CAPPCCO)TECHNICAL SUMMARY OF PROJECTTECHNICAL SUMMARY OF PROJECT
• Carbon capture characteristics database for existing & Carbon capture characteristics database for existing & planned plantsplanned plants
• Develop and assess capture options for planned new Develop and assess capture options for planned new pulverised coal (PC) plantspulverised coal (PC) plants
• Develop and assess capture options for existing PC plantsDevelop and assess capture options for existing PC plants
• Special issues for adding carbon capture to Chinese power Special issues for adding carbon capture to Chinese power plants e.g. water requirements, cooling requirements, coal plants e.g. water requirements, cooling requirements, coal properties, capture performance under variable Chinese climatic properties, capture performance under variable Chinese climatic conditions including likely performance of next-generation conditions including likely performance of next-generation pollutant control technologiespollutant control technologies
• Financing capture ready and capture retrofitFinancing capture ready and capture retrofit
19
Capture Option – Financing Capture Ready
Capture Option
Issuing a Tradable Capture Option help financing Capture Ready
A Capture Option has plenty of potential benefits
The value of a Capture Option is significant
The feasibility of Capture Ready depends on the additional capital
outlay for Capture Ready. (For example, in this model, Capture
Ready is economic at all discount rate, if required additional total
capital is less than 2%. )
Financing Capture Ready: Issuing a Tradable Capture Option
20
Capture Option
Capture Site
Storage Site
Transportation
Storage Site
(IPCC CCS Special Report, 2005)
Reiner D, Liang X, Gibbins J, Li J
0
500
1000
1500
2000
2500
3000
mill
ion
CNY
Scenar i o HO_nCR 1625 627 153 22
Scenar i o HO_CR 2451 1255 471 97
Scenar i o LO_nCR 3 1 1 0
Scenar i o LO_CR 7 2 1 0
Scenar i o HP_nCR 10 2 2 0
Scenar i o HP_CR 25 7 5 2
Scenar i o LP_nCR 609 113 16 0
Scenar i o LP_CR 1326 439 99 11
6% 8% 10% 12%
21
Closure Possibilities
Capture Option
0. 00%
10. 00%
20. 00%
30. 00%
40. 00%
50. 00%
60. 00%
70. 00%
80. 00%
90. 00%
100. 00%
6% 8% 10% 12%
Di scount Rate
Clos
ure
Poss
ibil
ity
LP_nOpt i onLP_nCRLP_CR
22
Capture Option
Value of Capture Ready in a 600MW SCPC in China
831
630
311
711
713
327
758 3
1
816 3 2 100
100
200
300
400
500
600
700
800
900
6% 8% 10% 12%
CNY
mill
ion
Scenari o HO
Scenari o LO
Scenari o HP
Scenari o LP