carlsbad springs solar project - invenergy panels... · • the ieso is procuring 140 mw of solar...

21
Carlsbad Springs Solar Project Invenergy LLC Public Community Meeting August 6, 2015

Upload: dangnguyet

Post on 06-Sep-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

Carlsbad Springs Solar Project Invenergy LLC

Public Community Meeting August 6, 2015

Invenergy LLC is a Qualified Applicant • Invenergy LLC qualified to participate in the IESO

Large Renewable Procurement - Request for Proposals (LRP I RFP) in 2015.

• The IESO is procuring 140 MW of solar in this RFP. • Invenergy is preparing to submit a proposal for

the Carlsbad Springs Solar Project. • The proposal submission deadline is September

1, 2015 and the IESO’s proposal evaluation process will run until November – December 2015.

What is Ontario’s Large Renewable Procurement Program? • In recent years, the Feed-in Tariff (FIT) Program was the vehicle that enabled large

renewable energy development in Ontario. • In June 2013, the Ontario Minister of Energy directed the Independent Electricity

Systems Operator (IESO, formerly the Ontario Power Authority, or OPA) to cancel the FIT Program for larger renewable energy projects and develop a new competitive procurement process.

• In December 2013, the Minister of Energy released Ontario’s new Long-Term Energy Plan (LTEP), Achieving Balance. Visit www.energy.gov.on.ca/en/ltep to learn more about this plan.

• Consequently, the IESO developed a Large Renewable Procurement (LRP) program in response to this new plan to include a two-phase procurement process:

– An initial Request for Qualifications (RFQ) process to qualify applicants who wish to participate in the LRP

– A Request for Proposal (RFP) process to evaluate the projects proposed by qualified applicants

Carlsbad Springs Solar Project • This Public Community Meeting is for the Carlsbad Springs Solar Project • Located at 5281 Piperville Road, Ottawa, Ontario • Estimated maximum name plate capacity of approximately 25 megawatts (MW) • Proposed Connection Point would be the existing 44 kilovolt circuit on Hawthorne

Road at Louiseize Road

Preliminary Site Layout

Preliminary Site Layout Carlsbad Springs Solar Project, MRC Ottawa, Ontario, Canada

Invenergy LLC • Invenergy LLC headquartered in Chicago with regional

offices in Toronto, Denver, Warsaw, Mexico City and Tokyo

• Invenergy Canada based in Toronto • North America’s 6th largest renewable energy generation

company (largest independent) • Developed 9,000 MW+ in North America & Europe,

including 980+MW in Canada • Invenergy is committed to working with communities to

develop projects that are successful for everyone involved

Invenergy Canada • Invenergy has developed the following

projects in Canada: Raleigh Wind (78 MW) Le Plateau I and II Wind (138.6 MW and 21.15

MW) Des Moulins I and II Wind (135.7 MW and 21.1

MW) St. Clair Gas (584 MW) Sandringham Solar (10 MW) Woodville Solar (10 MW)

Solar Energy • Capturing the sun’s rays may be one of the oldest ways to harness

energy. • The Project will use solar photovoltaic (PV) technology. • PV cells convert light into electricity. • The more cells, the more electricity produced. • All electricity generated by the Project will be fed directly into the

provincial electricity grid. • Solar PV is used primarily for grid-connected electricity to operate

residential appliances, commercial equipment, lighting and air conditioning for all types of buildings.

• Solar PV panels can be ground mounted, installed on building rooftops or designed into building materials at the point of manufacturing.

Benefits of Solar Energy PEAK ENERGY NEEDS • Solar generation provides energy

during the day, when demand is highest, making solar a fuel-free source of peak power.

CLEAN, GREEN ENERGY • Solar energy is infinitely renewable:

– Emits no climate changing greenhouse gases;

– Creates no air or water pollution; and – Has little impact on land, wildlife or

ecosystems, and leaves no hazardous waste.

ECONOMIC COMPETITIVENESS • Solar, other renewable energy,

and energy conservation are strong drivers that will bolster Canada’s economic competitiveness, ensure a reliable supply of energy and enhance our global reputation as an energy superpower.

JOB CREATION • Solar energy creates more

jobs per megawatt output, and per dollar invested than any other energy source.

How Solar Energy Works: Part 1 Molten silicon is used to make...

wafers which are put together to create...

cells that when put together make...

a module that is mounted on a rack.

How Solar Energy Works: Part 2 • When light shines on a

cell, it frees electrons from the semiconductor wafers creating electricity

• Very low maintenance required

Equipment • The solar modules will be poly or monocrystalline

producing 200-300 watts of direct current (DC) energy

• DC wiring will connect the modules through the racks and to the inverter

• Inverters will be 250 to 500 kilowatts (kW) each converting DC to AC (alternating current)

• AC wiring will connect the inverter to the substations

Solar Modules and Inverters

Solar Module Installation

Inverters are required to convert DC module electrical output to AC electricity.

Inverter Control Cabinet

Construction Activities include: • Site clearing and grading • Installation of site fencing

and erosion control measures • Underground cable

installation • Rack foundation, module and

wiring installation • Inverter installation • Substation construction

Construction will be completed according to industry best practices. Any potential impacts will be minimized through the implementation of mitigation measures.

Visual Screening Mitigation

Community Engagement Approach

Phase I: Pre-Contract Award Community, Municipal, and Aboriginal Engagement

•Establish a Project website www.invenergyllc.com/carlsbadsprings •Request to meet with the City of Ottawa • Identify and engage interested Aboriginal

communities •Post Notice of Public Community Meeting in local

newspaper and Project website •Host a Public Community Meeting •Post a summary of the Public Community Meeting

on Project website •Provide a central email address [email protected] • Incorporate feedback from community engagement

activities into Project plan and LRP I RFP submission

Phase II: Post Contract Award Renewable Energy Approval (REA) Process – Community, Municipal, and Aboriginal Consultation

•Maintain a Project website www.invenergyllc.com/carlsbadsprings

•Respond to a central email address [email protected]

•Ensure local municipality is informed about project activities and milestone dates

•Continue to provide updates to interested Aboriginal communities

•Post results of REA studies and other REA reports to the Project website

•Host at least two public meetings in Project community •Listen to community concerns and propose reasonable

solutions •Share a summary of community concerns and

mitigation plans to address feedback on the Project website

Contract Award

Invenergy endeavors to keep members of the Project community informed throughout the Project’s development process by adhering to the community engagement guidelines set by the IESO.

Community Benefits • If the Project is awarded a power contract, Invenergy would establish a community

benefit fund to be administered by local volunteers for community projects and other local good works

• There would be an annual contribution to the fund for the duration of the power contract • A steady flow of funds can have many positive impacts on a community • The photos below highlight examples from the 78 MW energy centre south of Chatham,

Ontario which has distributed over $150,000 locally since 2011

Merlin splash pad, summer 2013 $20,000 contribution from CBF

24 Ipads for Merlin Public School $5,000 contribution from CBF

Environment and Health • It has been demonstrated that when Solar power plants are constructed using best

management practices, they can provide a positive benefit to biodiversity • Solar energy is often viewed as having very minimal waste because there is none

produced during operation • Currently, many solar companies meet or exceed national and international

standards for handling and mitigating hazardous materials • Evidence has been published that large-scale Solar plants use less land than some

traditional energy sources, such as coal, when land used for mining (for the energy source )is taken into consideration (Fthenakis and Kim, 2009)

• Solar parks can increase the number of species in a given area (German Renewable Energy Agency, 2010). When solar parks are managed responsibly, they can create new habitats for endangered animals and plants and make positive use of marginal and remediated lands

• Recommended best practices include avoidance of pesticides and fertilizers, use of sheep for grazing to reduce site maintenance activities, and risk assessments

Source: Assessment of the Environmental Performance of Solar Photovoltaic Technologies - Environment Canada, in partnership with Natural Resources Canada’s CanmetENERGY

Property Values The following are based on research done on properties in North Carolina • Concluded that there is no impact in sale price for residential, agricultural or vacant residential land that

adjoins existing or proposed solar farms • Larger solar farms using fixed panels are a passive use of the land that is considered in keeping with a

rural/residential area • Comparing a solar farm to a larger greenhouse as shown below is a very reasonable comparison given that

a greenhouse is essentially another method for collecting passive solar energy. The greenhouse use is well received in residential/rural areas and has a similar visual impact as a solar farm

Source: Appraisal Consult on Pit 64 solar proposal - Richard C. Kirkland, Jr., MAI State Certified General Appraiser

Next Steps • The next step in the process is to prepare a meeting summary report (MSR)

for IESO and post it on the project website. The report will be provided to the municipal Clerk (or other designate). The report will document your questions and comments as well as discuss how your input has impacted the project.

• The proponent will include the report in its Large Renewable Project (LRP) proposal submission to IESO in the Fall of 2015 (target). Once the complete proposal is received, IESO will evaluate all proponent proposals and notify selected proponents by the end of 2015 (target). It is expected that successful LRP proponents will commence the Renewable Energy Approval (REA) process that includes additional consultation in 2016.

Feedback Welcome Thank You For Attending! • Your attendance at today’s meeting is appreciated. We

encourage you to write down your comments or questions and either place them in our comment box, or provide them to a company representative

• We welcome your feedback and thank you for attending this public community meeting

• Additional comments following this meeting can be sent to [email protected]

• Visit www.invenergyllc.com/carlsbadsprings for Project updates