case study 36” carbon steel “sump pile” sap & kaps...

2
1018/SKPS/CAS/20 Case Study Sap & Kaps Petroleum Services l.l.c Page 1/2 [email protected] ® 36” Carbon Steel “Sump Pile” Leak Repair using Clock Spring Contour Wrap

Upload: others

Post on 12-Aug-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Case Study 36” Carbon Steel “Sump Pile” Sap & Kaps ...skps.com/wp-content/uploads/2021/04/1018-SKPS-CAS-20...SKPS designed a repair in accordance to ISO 24817 to apply a “Clock

1018/SKPS/CAS/20

Case Study

Sap & Kaps Petroleum Services l.l.c

Page 1/[email protected]

®

36” Carbon Steel “Sump Pile”Leak Repair using Clock Spring

Contour Wrap

Page 2: Case Study 36” Carbon Steel “Sump Pile” Sap & Kaps ...skps.com/wp-content/uploads/2021/04/1018-SKPS-CAS-20...SKPS designed a repair in accordance to ISO 24817 to apply a “Clock

:

:

:

:

:

:

Operating Pressure

Operating Temperature

Defect Type

Size

Material

Defect Analysis

5 psi

62º C

Through wall metal loss.

36”

Carbon Steel

Pin hole leak and it has been arrested using patch plate with steel putty.

Engineers onsite had requested SKPS to design a Clock Spring Contour repair to ensure the safe operation of the “Sump Pile” without the need for any shutdown due to “hot work”. The leak was temporarily sealed using a patch and leak sealing putty.

2

During a routine inspection, it was noticed that a leak (that eventually ended up being approximately 1” in diameter) had started on the “Sump Pile” as a result of internal corrosion.

Surface Preparation1

Design Criteria 4

®

®

Patch Plate & Putty Application

Clock Spring Contour ApplicationSKPS designed a repair in accordance to ISO 24817 to apply a “Clock Spring Contour” repair. The photo of the “Sump Pile” after the “Clock Spring Contour reinforcement”.

3

1018/SKPS/CAS/20 [email protected] Page 2/2

36” Carbon Steel “Sump Pile” Leak Repair using Clock Spring Contour Wrap®

®

®