case study on ied baseline report

15
CASE STUDY ON IED BASELINE REPORT BREAKOUT SESSION ON NICOLE SPRING WORKSHOP IN BERLIN, 2014, MAI 16TH, HORST HERZOG, INFRASERV

Upload: others

Post on 25-Apr-2022

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CASE STUDY ON IED BASELINE REPORT

CASE STUDY ONIED BASELINE REPORT

BREAKOUT SESSION ON NICOLE SPRING WORKSHOP IN BERLIN,

2014, MAI 16TH, HORST HERZOG, INFRASERV

Page 2: CASE STUDY ON IED BASELINE REPORT

CASE STUDY ON BASELINE REPORT IED

TASKS FOR CASE STUDY

21.05.2014 Infraserv Frankfurt/Main, Horst Herzog, Waste and Remediation Management

1. Design an approach for a Baseline Report

2. Please devide into 2x3 groups and focus on following 3 items:

• Team 1: What should be the contet of the Baseline Report? How many exploration pointsare necessary and where shoud they be placed? Are soil and / or groundwater analysisnecessary? If Yes – How many samples and which substances should be analyzed?

• Team 2: Which monitoring of the operation should be implemented? Which substances areof interest? Consider the historical pollution unter the site and the hydraulic barrier. Keep in mindthe possibility of a substance to be used as a indicator for pollution in 20 years! Can organizational standards of the crew or certifications be considered?

• Team 3: Use of Baseline Report at site closure? How to integrate IED requirements and usual remediation practices based on risk management? Is there a conflict between implementing a risk assessment and the direct comparison of concentrations / pollutant charges? How to consider monitoring information? Take into account the relevance of notifications of local authorities, agreements under public law or constructional characteristics.

Time: Team work: 09:30 – 10:15 Collect findings in groups: 10:15 – 10:30Presentation of resuts in plenum: 10:30 – 11:00

2

Page 3: CASE STUDY ON IED BASELINE REPORT

CASE STUDY ON BASELINE REPORT IED

PLANT IS LOCATED ON A HUGE CHEMICAL INDUSTRIALSITE, 1.100 ACRES (4,6 KM²)

21.05.2014 Infraserv Frankfurt/Main, Horst Herzog, Waste and Remediation Management 3

Page 4: CASE STUDY ON IED BASELINE REPORT

CASE STUDY ON BASELINE REPORT IED

UNTIL 1960 FLOODING PROTECTION AND SITE LEVELING WAS ACHIEVED BYFILLING-UP THE SITE WITH WASTE – FROM BUILDING DEMOLITION ANDCHEMICAL PRODUCTION

21.05.2014 Infraserv Frankfurt/Main, Horst Herzog, Waste and Remediation Management 4

Page 5: CASE STUDY ON IED BASELINE REPORT

CASE STUDY ON BASELINE REPORT IED

NORTH SITE, AREA 575 ACRES, INDUSTRIAL USE SINCE 1868

21.05.2014 Infraserv Frankfurt/Main, Horst Herzog, Waste and Remediation Management 5

• complete landfill, increasing height from the north rim towards the river from 1 to 12 m, average height 4,5 m; totally 21 Mio. t landfill

• partly heavy contamination of the soil below the filling down to 35 m depth

• heavy contamination by mainly

• several thousand t heavy metals, e.g. chromium and lead

• 1-2 thousand t arsenic

• about 5 thousand t of chlorinated hydrocarbons, aromates, aniline derivates etc.

• other production residues (lime pits, building demolation etc.)

• heterogeneous distribution of all contaminants

• Heavy historical groundwater contamination with increasing concentration toward the river Main

• 1st groundwater level 6-12 m below ground level

• 2nd groundwater level 14-20 m below ground level

• 3rd groundwater level 26-32 m below ground level

Page 6: CASE STUDY ON IED BASELINE REPORT

CASE STUDY ON BASELINE REPORT IED

CORE ELEMENT OF THE SITE REMEDIATION CONCEPT: THE GROUNDWATER IS CAPTURED BY REMEDIATION WELLS(2.5 MILL. M³/YR)

Southern site(10 wells)

Northern site(24 wells)

Infraserv Frankfurt/Main, Horst Herzog, Waste and Remediation Management21.05.2014 6

Page 7: CASE STUDY ON IED BASELINE REPORT

CASE STUDY ON BASELINE REPORT IED

HISTORICAL POLLUTION OF GROUNDWATER AND SOILUNTER THE PLANT

21.05.2014 Infraserv Frankfurt/Main, Horst Herzog, Waste and Remediation Management 7

Exemplaric concentrations in soil (original sustance and leachate)

Page 8: CASE STUDY ON IED BASELINE REPORT

CASE STUDY ON BASELINE REPORT IED

HISTORICAL POLLUTION OF GROUNDWATER AND SOILUNTER THE PLANT

21.05.2014 Infraserv Frankfurt/Main, Horst Herzog, Waste and Remediation Management 8

Exemplaricconcentrations in groundwater

Page 9: CASE STUDY ON IED BASELINE REPORT

CASE STUDY ON BASELINE REPORT IED

FRAME: ONGOING REMEDIATION ON INDUSTRIAL SITE

• Complete capture of the groundwater by hydraulic barrier (remediation wells)

• Reduction of contaminations by removal of hot spots if commensurate

• Recycling of former production areas for new building areas (total soil exchange as exception)

• Investigational program for soil, soil-air and groundwater

• All this is based on three General frame directives by order of local authorities, giving Investors certainty (not to have to start additional local remediation activities)

• Each Investor / Lesee gets a description of the pollution situation (soil/groundwater) of hissite

Infraserv Frankfurt/Main, Horst Herzog, Waste and Remediation Management21.05.2014 9

Page 10: CASE STUDY ON IED BASELINE REPORT

CASE STUDY ON BASELINE REPORT IED

GROUNDWATER UNDER PLANT IS CAPTURED BY2 REMEDIATION WELLS (16N1 AND 17N1)

21.05.2014 Infraserv Frankfurt/Main, Horst Herzog, Waste and Remediation Management 10

Remediation wellsMonitoring wells

GW-capture areasArea of interest

Page 11: CASE STUDY ON IED BASELINE REPORT

CASE STUDY ON BASELINE REPORT IED

NEW PROJECT: PLANNED ENLARGEMENT OF AN EXISTING PLANT WHICH DETERMINS A NEW PERMIT

• Construction of new storage tanks for acetic acid and vinyl acetate in enlargement of an existing plant

• Due to this, a complete Baseline Report is necessary – for both parts of the plant: newtanks ans old production plant

• Product called M* in Presentation is solid, a basic product for plastics / synthetic materials

• 10 additional Substances are listed in the application for production permit

• Plant is surrounded by pipeline bridges

• Area:

• Existing Plant 11.000 m²

• New Tanks: 4.000 m²

• Planned foundation: Excavation ´till 3,5 m under ground level and piling

• Special constructional protection devices(German VAwS)? Yes – see Plan on next pages

21.05.2014 Infraserv Frankfurt/Main, Horst Herzog, Waste and Remediation Management 11

Page 12: CASE STUDY ON IED BASELINE REPORT

CASE STUDY ON BASELINE REPORT IED

OVERVIEW OF AREA OF INTEREST

21.05.2014 Infraserv Frankfurt/Main, Horst Herzog, Waste and Remediation Management 12

Production plant withmeasuring station and office

Silo handling area

Distillation Plant

Page 13: CASE STUDY ON IED BASELINE REPORT

CASE STUDY ON BASELINE REPORT IED

TASKS FOR CASE STUDY

21.05.2014 Infraserv Frankfurt/Main, Horst Herzog, Waste and Remediation Management

1. Design an approach for a Baseline Report

2. Please devide into 2x3 groups and focus on following 3 items:

• Team 1: What should be the contet of Baseline Report?. How many exploration points arenecessary and where shoud they be placed? Are soil and / or groundwater analysis necessary? If Yes – How many samples and which substances should be analyzed?

• Team 2: Which monitoring of the operation should be implemented? Which substances areof interest? Consider the historical pollution unter the site and the hydraulic barrier. Keep in mindthe possibility of a substance to be used as a indicator for pollution in 20 years! Can organizational standards of the crew or certifications be considered?

• Team 3: Use of Baseline Report at site closure? How to integrate IED requirements and usual remediation practices based on risk management? Is there a conflict between implementing a risk assessment and the direct comparison of concentrations / pollutant charges? How to consider monitoring information? Take into account the relevance of notifications of local authorities, agreements under public law or constructional characteristics.

Time: Team work: 09:30 – 10:15 Collect findings in groups: 10:15 – 10:30Presentation of resuts in plenum: 10:30 – 11:00

13

Page 14: CASE STUDY ON IED BASELINE REPORT

CASE STUDY ON BASELINE REPORT IED

SUMMARY OF CASE STUDY (1/2)

21.05.2014 Infraserv Frankfurt/Main, Horst Herzog, Waste and Remediation Management 14

Page 15: CASE STUDY ON IED BASELINE REPORT

CASE STUDY ON BASELINE REPORT IED

SUMMARY OF CASE STUDY (2/2)

21.05.2014 Infraserv Frankfurt/Main, Horst Herzog, Waste and Remediation Management 15