case summary report on environment · case summary report on environment draft this report is a...

73
CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback and update. The materials are prepared by consultants; hence, ADB does not guarantee the accuracy, reliability, or timeliness of these materials and therefore will not be liable in any capacity for any damages or losses that may result from the use of these materials. ADB, likewise, shall not be responsible for any errors, inadvertent omissions, or unauthorized alterations that may occur in the disclosure of content on this website.

Upload: others

Post on 18-Mar-2020

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

CASE SUMMARY REPORT ON ENVIRONMENT

DRAFT

This report is a work in progress, the purpose of which is to encourage an iterative process of feedback and update. The materials are prepared by consultants; hence, ADB does not guarantee the accuracy, reliability, or timeliness of these materials and therefore will not be liable in any capacity for any damages or losses that may result from the use of these materials. ADB, likewise, shall not be responsible for any errors, inadvertent omissions, or unauthorized alterations that may occur in the disclosure of content on this website.

Page 2: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

Under its Safeguard Policy Statement (2009), ADB may approve a borrower’s request to use Country Safeguard Systems (CSS) in ADB-financed projects if (i) the CSS are equivalent to the objectives, scope, triggers, and principles of the Safeguard Policy Statement; and (ii) the borrower has the necessary capacity and experience to implement its own CSS. CSS can be applied at the national, subnational, sector, or agency level. The use of CSS does not relieve ADB of its due diligence and loan supervision responsibilities; it does not alter the role of ADB’s Accountability Mechanism. ADB must review safeguard plans and supervise their implementation for all projects implemented under CSS. The key difference between the use of CSS and ADB’s standard approach is that CSS and any agreed actions to fill any gaps between the CSS and ADB’s SPS will be the benchmark and the primary focus of ADB’s due diligence and supervision instead of the SPS requirements. In order for the ADB to determine if the borrower has the necessary capacity and experience to implement its own CSS, the SPS requires ADB to conduct an “acceptability assessment”. The assessment is designed to determine whether the concerned agency has acceptable implementation practice, track record, and capacity and commitment to implement the applicable laws, regulations, rules and procedures. As part of this assessment, Indonesia’s State Electricity Company/Perusahaan Listrik Negara (PLN) selected 18 representative cases each for environment and involuntary resettlement. This document provides a summary of these cases, covering the following key areas: (i) institutional capacity (institutional structure, human and financial resources, technical resources); (ii) implementation practice and delivery mechanism (process and procedures for implementing safeguards; and (iii) performance (output and outcome) which includes quality of planning documents (AMDAL, EMP, etc.). The case summary was one of the inputs to the comprehensive assessment carried out by ADB as part of the acceptability assessment, which also included: (i) desk review of PLN corporate documentation, (ii) interviews with PLN officials at headquarters and regional offices, (iii) interviews and consultations with other local agencies, project-affected people, interest groups and development partners, and (iv) site visits to selected projects. The detailed assessments and findings can be obtained below:

• Draft Acceptability Assessment of Environmental Safeguards [https://www.adb.org/projects/documents/ino-47287-001-dpta-8]

Page 3: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

Case/Desk Studies of Projects Assessed

No Project Names Assessment Method

1 Kadipaten 150 kV Power Transmission Line and Sub-station,

West Java

Site visit

2 Tanah Lot 150 kV Power Transmission Line and Switchgear,

Bali

Site visit

3 PLTU 2 Central Java 500 kV Power Transmission Line and

Main Switchgear, Central Java

Site visit

4 Kutampi 6 x 2 MW Diesel-Fueled Power Plant Project, Bali Site visit

5 Bali – Nusa Lembongan 20 kV Subsea Interconnection

System, Bali

Site visit

6 Minahasa 150 MW Peaker Gas/Diesel-Fired Power Plant

Project, North Sulawesi

Site visit

7 Lontar Coal-Fired Power Plant 1 x 315 MW Extension Project,

Banten

Site visit

8 Lapai Minihydro Power Plant Unit I (2 x 2 MW) Project, South-

east Sulawesi

Desk study

9 Nonohonis – Kefamenanu 70 kV Power Transmission Lines

and Towers, East Nusa Tenggara Province

Desk study

10 Namlea 10 MW Gas/Fuel Fired Power Plant, Maluku Desk study

11 Saumlaki 10 MW Gas/Fuel Fired Power Plant, Maluku Desk study

12 Malingping-Bayah 150 kV Power Transmission Lines and

Tower Project, Banten

Desk study

13 Malifut Peaker 5 MW Gas/Fuel Fired Power Plant Project,

North Maluku

Desk study

14 Sofifi 10 MW Gas/Fuel-Fired Mobile Power Plant in Ternate

Regency, North Maluku

Desk study

15 Namrole 10 MW Gas/Fuel Fired Power Plant Project, Maluku Desk study

16 Ternate 30 MW Gas/Fuel-Fired Mobile Power Plant Project in

Ternate Regency, North Maluku Province

Desk study

17 Muara Karang 500 MW Peaker Gas/Coal-Fired Power Plant

Expansion (Peaker) Project, DKI Jakarta

Desk study

18 Tanjung Awar-Awar 2 x 150 MW (Unit 3) Coal Fired Power

Plant Project, East Java

Desk study

Page 4: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

1. Kadipaten 150 kV Incomer High Voltage Power Transmission Line and 150 kV Substation

Project

Project Name Kadipaten 150 kV Incomer High Voltage Power Transmission Line

and 150 kV Substation Project

Location Majalengka Regency, West Java

Indonesian Environmental

Permitting Category

UKL-UPL

ADB Project Category B

Implementing Agency

(Project proponent)

PLN (Persero) Unit Pembangunan Jawa Bagian Tengah (UIP JBT)

II

Compiler/Consultant Tim Teknis PLN (Persero) UIP XVI

Environmental Permit Ref. 660/17.SK/V/BPLH

No

Key Elements

(ADB SPS 2009, Pages 41 – 43, except Parts A

and B)

Findings on Compliance and Quality of Data and Analysis

A Institutional Capacity

1 Institutional Structure PLN (Persero) UIP Jawa Bagian Tengah II (UIP JBT II), based in Yogyakarta, is the project proponent. The environmental engineers involved in each stage of development are embedded in the Planning Unit, Construction/Operation Unit, and Project Implementation Unit.

2 Budget At the UIP level, PLN allocates funds for management and monitoring activities. The UIP prepares an annual detailed plan and budget, covering AMDAL and UKL-UPL preparation, approval of the Environmental Permit, and implementation of mitigation measures and monitoring requirements. Monitoring is conducted by UPK, which is a sub unit of UIP. Annual budget allocations depend on the volume and number of proposed activities.

The physical and financial progress of UIP activities are regularly monitored and reported.

3 Human Resources In the PLN organization structure, UIP environmental specialists supervise UPP environmental specialists. In case of the UIP JBT II, two environmental specialists supervise a total of four environmental specialists (one specialist in each of four UPP).

The UIP environmental specialists have academic backgrounds in civil engineering, chemical engineering, or chemistry. UIP and UPP staff receive environmental assessment training in courses covering AMDAL A (basic level training on AMDAL), AMDAL B (preparation of AMDAL documents), AMDAL C (advanced level training for AMDAL review), and preparation of UKL-UPL.

Within PLN, the actual preparation of AMDAL and UKL-UPL documents is commonly carried out by consultants under the supervision of the UIP and UPP environmental specialists. The UIP and UPP Environmental Planning Units have overall responsibility

Page 5: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

for administering spatial planning recommendations, reviewing consultant outputs, and securing the required environmental permit.

B Process and Procedures

1 Coherence Based on desk study, field visits, and interviews with UIP JBT II staff, it was concluded that preparation of the project UKL-UPL was generally in accordance with prescribed processes and procedures. Eligibility of the project and its compliance with the prevailing spatial planning was assessed from the initial stage of the project by securing the required recommendation from the responsible government agency. It is noted that the project UKL-UPL is also consistent with Regulation No. 03/2014 on Guidance for Preparation of Environmental Document issued by the Majalengka Regency. This guideline further elaborates the requirements and criteria for environmental assessment to satisfy local requirements and conditions.

2 Transparency The requirement to conduct public consultations is not explicitly stated in the MOE Regulation No. 16/2012 and consequently may not be done for UKL-UPL projects. Consultation was however carried out as part of the land acquisition process. Additionally consultations occurred during preparation of the UKL-UPL, encompassing a social survey, interviews with affected people and local communities. The consultations only included two female landowners.

3 Consistency Based on desk study, interviews with UIP JBT II staff, and discussion with the local environmental agency (BPLH) of Majalengka Regency, it was concluded that preparation of the UKL-UPL for this project was consistent with the prescribed processes and procedures.

4 Effectiveness Preparation of the UKL-UPL for this project is considered effective, as evidenced by timely delivery of the assessment and the relatively short period between UKL-UPL approval, environmental permit issuance, and commencement of construction.

C Output and Outcome

1 Screening and Categorization

MOE Regulation No. 5/2012 on Type of Business and/or Activity Requiring Environmental Impact Assessment provides that only a UKL-UPL is required since the project size is not greater than 150 kV.

2 Scoping Not applicable to UKL-UPL projects.

3 Project Description The UKL-UPL describes the project’s physical-chemical, biological, social-economic/culture, and public health components, covering:

A. Pre-construction phase - Permitting - Survey (determination of location/configuration of network,

recording of soil data, and plants affected by the alignment) - Land acquisition for tower bases and substation - Land compensation required for the transmission line right of

way B. Construction phase

- Recruitment of workers (priority to be given to local workers for unskilled/laborer and middle skilled positons)

- Mobilization and demobilization of equipment and materials

Page 6: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

(vehicles used should be in good condition and suitable for prevailing requirements and local conditions)

- Land clearing (cutting of vegetation/trees at tower bases and trimming of vegetation which enters free space along the proposed transmission line right of way

- Foundation work for switchyard - Construction work for control building - Construction for facility and infrastructure - Tower construction - Erection of towers - Stringing of cables - Commissioning

C. Operation phase - Electricity distribution - Maintenance (preventive, corrective, emergency, base

condition) - Patrolling (to avoid disturbance and maintain public security) - Inspection (checking of transmission corridor, tower, isolator,

and cables)

4 Policy, Legal, and Administrative Framework

Relevant national laws and regulations (including sector regulations) as well as local regulations applicable to the project are listed. In addition, specific PLN regulations/guidance for power/transmission development are also referred to.

5 Environmental Baseline The UKL-UPL provides baseline information on:

A. Physical-chemical components - Climate - Air quality - Noise - Water quality - Electromagnetic - Road condition and traffic

B. Biological components - Flora - Fauna

C. Socio-economic, cultural, and public health components - Demographics - Education - Economic (infrastructure and facilities) - Religion - Health infrastructure and facilities

6 Analysis of Alternatives Analysis of project alternatives was described in Project Feasibility Assessment (Ref. 18.03.02/2016.08/02), which considered two alternatives: the no project alternative involving expansion of the medium voltage network through sourcing from the existing substation or other substations, and development of a new substation with similar capacity. The second alternative was selected as the most feasible option.

7 Impact and Risk Assessment

The UKL-UPL describes potential environmental and social impacts, taking into consideration:

- Impact sources - Impact type - Magnitude of impacts

Particular attention is given in the UKL-UPL to the electrical safety of

Page 7: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

the transmission line and its potential human and public health impacts, responding to concerns expressed by people living along the transmission line and close to the substation.

8 Environmental Management and Monitoring Plan (EMP)

The UKL-UPL details:

- Mitigation measures, locations, and schedule - Monitoring methods, locations, and schedule - Institutional arrangement of agencies/parties involved in

implementing, supervising, and reporting

The requirement to specify budget allocations for environmental management and monitoring in a UKL-UPL is not explicitly stated in the MOE Regulation No. 16/2012 and consequently is generally not included. The common understanding is that such costs are part of the project proponent’s or contractor’s budget.

Specified mitigation and monitoring measures focus on avoiding or reducing potential environmental and social impacts during the pre-construction, construction, and post construction phases, including:

− Dissatisfaction among affected parties with land prices and right of way compensation

− Employement and business opportunities for local communities

− Degraded air quality and increased dust and noise

− Damage to local roads due to mobilization of heavy equipment and material

− Traffic disturbance and accidents

− Loss of flora and fauna due to land conversion

− Degraded groundwater and surface water quality

− Waste generation

− Electromagnetic field and corona effect

9 Information Disclosure Information disclosure to the public was conducted as part of the land acquisition process. PLN’s land acquisition team disseminated information on the project goals, objectives, and benefits during a public meeting and additionally made the information available online.

10 Consultation and Participation

Consultation with affected parties was undertaken during the information disclosure meeting, where PLN discussed the project and requested permission from the neighborhood/households located in close proximity to the transmission line and substation.

During preparation of the UKL-UPL, particularly during collection of primary and secondary data, additional consultations were undertaken with people affected by the project (owners of land needed for tower bases, owners of trees/plants and buildings affected by project), informal leader (community and religious leaders), and formal leader (head of village).

11 Grievance Redress Mechanism Development

A grievance mechanism is provided for in MOE Decree No. 09/2010 on Community Grievances and Handling of Grievances caused by environmental pollution and/or degradation. At the project level, complaints arising during the construction phase are handled by the UIP’s Public Relation/Communication department which verifies and forwards the complaint to the responsible unit with authority to respond. During the operational phase complaints are handled by the Transmission Unit. In addition, the government Environmental Agency will also be informed of any complaints related to PLN

Page 8: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

projects for subsequent follow up with the project proponents.

12 EMP Implementation Review of an implementation report for the period January to June 2017 indicated that required mitigation measures are being undertaken. The report covered: source of impact, type of impact, performance indicator, mitigation measures, location of mitigation, mitigation period, supervisory implementation, and recipient of report.

13 Monitoring and Reporting

Similarly, monitoring is described in detail, covering: type of monitoring, monitoring locations, monitoring methods, monitoring period, and monitoring results.

Monitoring results were compared to both baseline data, and trend analysis was undertaken to evaluate acceptability of current status for noise, air quality, water quality, waste generation, work related accident, fire, and occupational health. Additionally, analytical results were compared with applicable environmental quality standards. No negative trends or exceedances were identified.

Sample analysis was undertaken by an Indonesian National Accreditation Committee accredited laboratory and analytical reports were included in the UKL-UPL implementation report.

Page 9: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

2. Tanah Lot 150 kV Incomer High Voltage Power Transmission Line and 150 kV Gas Insulated

Switchgear Project

Project name Tanah Lot 150 kV Incomer High Voltage Power Transmission Line and 150 kV Gas Insulated Switchgear Project

Location Tabanan Regency, Bali

Indonesian Environmental Permitting Category

UKL-UPL

ADB Project Category B

Implementing Agency (Project Proponent)

PLN (Persero) – Unit Induk Pembangunan (UIP) Jawa Bagian Timur dan Bali I (JBTB I) based in Surabaya

Compiler Consultant Team (certified)

Environmental Permit No. 660.1/3736/PP.BLH (dated October 14, 2016) issued by the Environmental Agency (BLH) of Tabanan Regency

No

Key Elements

(ADB SPS 2009, Pages 41 – 43, except Parts A

and B)

Findings on Compliance and Quality of Data and Analysis

A Institutional Capacity

1 Institutional Structure The UIP JBTB I, based in Surabaya, is the project proponent. The organization structure of this PLN unit refers to the regulations of PLN’s Directors No. 0015.P/DIR/2016, No. 0225.P/DIR/2016, and Decree No. 0490/SDM.01.03/DIVORG/2016 on the UIP Organization and Implementing Units.

The UIP comprises several units, among which environmental safeguards responsibilities are as follows:

- Planning unit is responsible for preparing, implementing, and evaluating environmental assessments and environmental management related to project facilities and land issues

- Construction/operation unit is responsible for preparing, implementing, and evaluating safety, occupational health, security, and environment program

- Project implemention unit is responsible for preparing, managing, and evaluating safety, occupational health, security, and environment program; and preparing, managing, and evaluating corporate social responsibility activities as agreed on with the UIP office

2 Budget At the UIP level, PLN allocates funds for management and monitoring activities. The UIP prepares an annual detailed plan and budget, covering AMDAL and UKL-UPL preparation, approval of the Environmental Permit, and implementation of mitigation measures and monitoring requirements. Monitoring is conducted by UPK, which is a sub-unit of UIP. Annual budget allocations depend on the volume and number of proposed activities.

The physical and financial progress of UIP activities are regularly monitored and reported.

Page 10: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

3 Human Resources In the PLN organizational structure, one UIP environmental specialist supervises two UPP environmental specialists. UIP and UPP staff receive environmental assessment training in courses covering AMDAL A (basic level training on AMDAL), AMDAL B (preparation of AMDAL documents), AMDAL C (review of AMDAL documents), and preparation of UKL-UPL.

Within PLN, the actual preparation of AMDAL and UKL-UPL documents is commonly carried out by consultants under the supervision of the UIP and UPP environmental specialists. The UIP and UPP Environmental Planning Units have overall responsibility for administering spatial planning recommendations, reviewing consultant outputs, and securing the required environmental permit.

B Process and Procedures

1 Coherence Based on desk study, field visits, and interviews with UIP JBTB I staff, it was concluded that preparation of the project UKL-UPL was in accordance with prescribed processes and procedures.

2 Transparency The requirement to conduct public consultations is not explicitly stated in MOE Regulation No. 16/2012 and consequently may not done for UKL-UPL projects. Public consultations were however carried out during which information was disclosed on both general and technical aspects of the project, and project objectives and benefits. No record on women participation in the consultations.

3 Consistency Based on an interview with UIP JBTB I personnel it was concluded that preparation of the UKL-UPL for this project was consistent with prescribed processes and procedures, including ensuring adherence with the local spatial plan.

4 Effectiveness Preparation of the UKL-UPL for this project is considered effective, as evidenced by timely delivery of the assessment and the relatively short period between UKL-UPL approval and commencement of construction.

C Output and Outcome

1 Screening and Categorization

MOE Regulation No. 5/2012 on Type of Business and/or Activity Requiring Environmental Impact Assessment provides that only an UKL-UPL is required since the project size is not greater than 150 kV.

A recommendation letter No. 050/5613/Bappeda/2015 from the Badan Perencanaan Pembangunan Daerah/Badan Koordinasi Penataan Ruang Daerah (Local Planning/Spatial Plan Agency) of Tabanan Regency confirms that the area required for the project aligns with the local spatial plan.

2 Scoping Not applicable to UKL-UPL projects.

3 Project Description The project goal and objectives are clearly stated, combined with the details of UKL-UPL preparation, covering:

- Identity of proponent and UKL-UPL compiler - Proposed project (including site plan and location layout) - Project scale - Land, land status, and compliance with spatial plan - Overall project design - Development phases (pre-construction, construction, and

operation)

Page 11: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

- Maintenance (preventive and corrective, and emergency)

4 Policy, Legal and Administrative Framework

Relevant national laws and regulations (including sector regulations) as well as local regulation are listed.

5 Environmental Baseline The UKL-UPL provides baseline information on:

A. Physical-chemical components - Climate (type of climate, rainfall, temperature and relative

humidity, duration of solar exposure, wind direction and speed)

- Ambient air quality and noise (air quality, noise intensity) - Physiography - Geology - Soil - Hydrology (surface water and groundwater, utilization of

water resources) - Earthquake prone areas - Spatial plan and land use - Electromagnetic field

B. Biological components - Baseline information is incomplete (required information on

terrestrial and aquatic flora and fauna is not provided) C. Social, economic, and cultural components

- Socio-economic (number and sex-segregated data of population, composition of population based on occupation, migration, economic structure, sectors, and GDP)

- Cultural (community organizations, cultural heritage, and community perceptions and attitude (as collected by questionnaire)

6 Analysis of Alternatives Not applicable, as the project only considers one option.

7 Impact and Risk Assessment

The UKL-UPL describes potential environmental and social impacts that may occur during the pre-construction, construction, and operation phases, covering:

- Pre-construction (permitting process, field survey, and land acquisition)

- Construction (labor recruitment and mobilization, mobilization of equipment and materials, preparation of land and foundations for towers, tower erection, installation and cable stringing, land clearing and building construction, installation of equipment, and construction of supporting facilities)

- Operation and maintenance

It is evident that some potential impacts are not covered in the UKL-UPL. For example, potential spills of hazardous substances and their disposal from substations is not mentioned despite PLN’s Directive (SK Dir. No. 114 on GIS Operation and Maintenance) requiring its units to manage Sulfur Hexafluoride.

8 Environmental Management and Monitoring Plan (EMP)

The UKL-UPL provides information on mitigation measures and monitoring for all potential impacts, excluding issues such as hazardous substances that were not identified in the impact assessment. Environmental and social management measures are formulated in terms of mitigation measures, location, and period of environmental management. Similarly, monitoring measures are

Page 12: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

formulated in terms of implementation method (i.e., field observation and data analysis), location, and schedule.

Particular emphasis is given to positive and negative impacts relating to:

- Social upset due to dissatisfaction of people regarding land prices and right of way compensation

- Employement and business opportunities for local community

- Degraded air quality and increased dust and noise - Damaged local roads due to mobilization of heavy

equipment and material - Traffic disturbance and accidents - Loss of flora and fauna due to land use conversion,

including impacts to aquatic flora and fauna - Degraded surface water and groundwater quality - Waste generation (including hazardous waste despite this

issue not being covered in the impact assessment) - Electromagnetic field and corona effect

The project proponent’s commitment to implement the UKL-UPL is provided in the form of a Statement Letter, which is stamped and signed by the person in charge.

Institutional arrangements for UKL-UPL implementation are described, covering responsible parties, supervision, and reporting.

There is no indication of cost estimates to implement the UKL-UPL or monitor performance indicators.

9 Information Disclosure Information disclosure to the public was conducted as part of the land acquisition process. The list of disclosure meeting attendants (signed sheets), contents, and conclusion of the dissemination are summarized in the Minutes of Dissemination No. 0001/HKM.04.01/UPKJJB.10/2016.

10 Consultation and Participation

Consultation with affected parties was undertaken during the information disclosure meeting.

11 Grievance Redress Mechanism Development

Although there is not an explicit requirement for a grievance mechanism in MOE Regulation No. 16/2012, PLN through its project level office has procedures to receive and follow-up on community complaints.

12 EMP Implementation Project is at construction phase.

13 Monitoring and Reporting

Implementation reports for 2017 is available.

Page 13: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

3. PLTU 2 Central Java 500 kV Power Transmission Lines and Kesugihan 500 kV Main Switchgear Project

Project Name PLTU 2 Central Java 500 kV Power Transmission Lines and Kesugihan 500 kV Main Switchgear

Location Cilacap Regency, Central Java

Indonesian Environmental Permitting Category

AMDAL

ADB Project Category B

Implementing Agency (Project proponent)

Unit Pelaksana Konstruksi Jaringan Jawa – Bali 7 (UPK JJB 7) Semarang of UIP XVI Yogyakarta

Compiler/Consultant PT Prima Layanan Nasional Enjiring (Jakarta) in cooperation with Environmental Research Center of Universitas Jenderal Soedirman (Purwokerto)

Environmental Permit Ref. 660.1/99/29/2010 issued by BLH Kabupaten Cilacap

No

Key Elements

(ADB SPS 2009, Pages 41 – 43, except Parts A

and B)

Findings on Compliance and Quality of Data and Analysis

A Institutional Capacity

1 Institutional Structure PLN (Persero) UIP JBT II based in Yogyakarta is the project proponent. The environmental engineers involved in each stage of development are embedded in the Planning Unit, Construction Unit, and Project Implementation Unit.

2 Budget At the UIP level, PLN allocates funds for management and monitoring activities. The UIP prepares a detailed annual plan and budget, covering AMDAL and UKL-UPL preparation, approval of the Environmental Permit, and implementation of mitigation measures and monitoring requirements. Monitoring is conducted by UPK, which is a sub-unit of UIP. Annual budget allocations depend on the volume and number of proposed activities.

The physical progress and financial progress of UIP activities are regularly monitored and reported.

3 Human Resources In the PLN organizational structure, UIP environmental specialists supervise UPP environmental specialists. In the case of the Yogyakarta UIP, two environmental specialists supervise a total of four environmental specialists (one at each of four UPP).

The UIP environmental specialists have academic backgrounds in civil engineering, chemical engineering, or chemistry. UIP and UPP staff receive environmental assessment training in courses covering AMDAL A (basic level training on AMDAL), AMDAL B (preparation of AMDAL documents), AMDAL C (advanced level training for AMDAL review), and preparation of UKL-UPL.

Within PLN, the actual preparation of AMDAL and UKL-UPL documents is commonly carried out by consultants under the supervision of the UIP and UPP environmental specialists. The UIP and UPP Environmental Planning Units have overall responsibility

Page 14: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

for administering the spatial planning recommendations, reviewing consultant outputs, and securing the required environmental permit.

B Process andProcedures

1 Coherence Based on desk study, field visits, and interviews with UPK JJB 7 and local environmental agency staff, it was concluded that preparation of the project AMDAL was in accordance with prescribed processes and procedures.

2 Transparency The AMDAL was carried out in a transparent manner through announcement in local newspapers and on radio, and posting in designated public places. Affected persons and key stakeholders and/or their representations were invited to and involved in multiple public consultations. However, consultations did not involve women’s participation.

3 Consistency Based on desk study, field visits, and interviews it was concluded that the AMDAL was consistent with prescribed processes and procedures.

4 Effectiveness Preparation of the AMDAL for this project is considered effective, as evidenced by the timely delivery of the assessment and the relatively short period between AMDAL approval and commencement of construction.

C Output and Outcome

1 Screening and Categorization

The screening for the environmental permitting of the project was undertaken based on the requirements of the former Environmental Law No. 23/1997 and former Government Regulation No. 27/1999 on AMDAL.

2 Scoping A scoping process was carried out to determine the assessment scope and identify potential environmental and social impacts related to the project. Scoping included a public consultation, involving affected persons and other stakeholders. The scoping process covered all applicable regulatory requirements:

- Description of the study area - Identification of significant impacts and prediction of impact

characteristics and magnitude - Consideration of the project’s environmental and social

feasibility - Explanation of how impacts were to be managed and monitored

through a RKL-RPL - An assessment terms of reference (KA-ANDAL) - Apparent gaps in the AMDAL documents comprising KA-

ANDAL, ANDAL, and RKL-RPL are: the ANDAL methodology does not optimally consider all potential impacts; and the ANDAL does not address the issue of extra and ultra-high voltage risk, an issue of concern expressed during public consultations

3 Project Description The ANDAL project description covers:

A. Pre-construction phase - Information dissemination - Determination of alignment - Land acquisition

B. Construction phase

Page 15: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

- Information dissemination - Labor and personnel recruitment - Mobilization of heavy equipment and materials - Land clearing - Installation of tower foundations - Civil work on GITET 500 kV - Erection of towers - Installation of GITET 500 kV - Stringing of conductor cables - Commissioning

C. Operation phase - Information dissemination - Transmission of electric power - Maintenance

D. Post-operation phase: - Information dissemination - Demolition - Reclamation - Asset recovery - Increased capacity

4 Policy, Legal, and Administrative Framework

Relevant national laws and regulations (including sector regulations) as well as local regulations related to the project are listed.

5 Environmental Baseline The ANDAL provides baseline information on:

- Geo-physical chemical components (geology, soil, surface water, groundwater, air, noise)

- Biological components (flora, fauna, ecosystem type, presence of rare and/or endemic species and their habitat)

- Social-economic components (income, occupation, local culture, archeological sites)

- Community and occupational health and safety

6 Analysis of Alternatives Limited consideration of alternatives, although in oder to avoid environmental and social impacts the, the location of two transmission towers was relocated.

7 Impact and Risk Assessment

The ANDAL provides an adequate assessment of impacts and risks. A flowchart was used to identify the interaction between key project activities and corresponding potential environmental and social impacts, covering:

A. Physical-chemical component

− Noise

− Air quality

− Electric force and magnetic force

− Soil stability

− Land and spatial use

− Run-off flow

− Transportation

− Aesthetics

B. Biological component

− Plant population and distribution

− Bird migration

C. Socio-economic and culture component

Page 16: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

− Employment and business opportunities

− Community income

− Land and building prices

− Social process

− Community perceptions

D. Public health component

− Work safety

− Inconvenience

− Disease prevalence

The study area boundary for purposes of assessing impacts and risks was clearly described, supported with maps.

8 Environmental Management and Monitoring Plan (EMP)

A Statement Letter to Implement the RKL-RPL, signed by the General Manager of PLN (Persero) PIKITRING JBN, is included in the AMDAL as a legally binding document.

The RKL-RPL is well structured, covering:

- Effectiveness of mitigation measures in addressing actual impacts

- Trends in environmental and social impacts - Effectiveness of monitoring program in assessing impact in

comparison with baseline conditions and trends

At the time of review the RKL-RPL had already been implemented during construction and the project has commenced operations.

9 Information Disclosure Information disclosure to the public was undertaken through a project notification made at the offices of Kecamatan Kesugihan, Kecamatan Adipala, and local Environmental Agency of Cilacap and by broadcasting through Radio Bayu Sakti (for one month). Social survey questionnaires were also used to generate baseline data on social, economy, culture, and public health aspects.

10 Consultation and Participation

Consultation with affected parties was undertaken during the information disclosure process and is consistent with Decree of Bupati Cilacap No. 76/2004 on Involvement of Community and Information Disclosure in the AMDAL Process.

Consultation involved announcements in local newspapers and radio and posting in designated public places. Affected and/or their representatives and key stakeholders were invited to and involved in multiple public consultations. However, the consultation did not specifically involve women’s participation.

11 Grievance Redress Mechanism Development

A specific grievance mechanism was not developed for the project. However, PLN through its project level office has procedures to receive and follow-up community complaints.

12 EMP Implementation Review of an RKL-RPL implementation report for the period July to December 2012 indicates that the report comprehensively covers:

- Significant impacts - Source of impacts - Performance indicators - Mitigation measures - Location of mitigation measures - Period of mitigation measures

An identified gap in the implementation report was the lack of a matrix summarizing all aspects of the RKP-RPL, making it difficult

Page 17: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

to determine whether all mitigation measures were being implemented.

13 Monitoring and Reporting Review of the RKL-RPL implementation report showed that environmental monitoring being undertaken was not described systematically, as required. It is difficult therefore to discern trends of specific impacts such as noise, air quality, water quality, waste generation, work accidents, fire, occupational health, or to compare monitoring results with applicable evironmental quality standards.

Reporting monitoring results are supported by analytical reports from an accredited laboratory.

Page 18: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

4. Kutampi 6 x 2 MW Diesel-Fueled Power Plant Project

Project Name Kutampi 6 x 2 MW Diesel-Fueled Power Plant

Location Klungkung Regency, Bali

Indonesian Environmental Permitting Category

UKL-UPL

ADB Project Category B

Implementing Agency (Project proponent)

PLN (Persero) Distribusi Bali Area - Bali Timur

Compiler/Consultant Consultant Team (certified)

Environmental Permit No. 660.1/094/KLH issued by the Environmental Agency of Klungkung Regency (dated January 25, 2012)

No

Key Elements

(ADB SPS 2009, Pages 41 – 43, except Parts A

and B)

Findings on Compliance and Quality of Data and Analysis

A Institutional Capacity

1 Institutional Structure In the PLN structure, there are combined Safety, Occupational Health and Environment positions in each Wilayah, reporting to the PLN Wilayah General Manager. A Safety, Occupational Health and Environment Supervisor reports to a Deputy Manager for Operational Control of the Distribution System in PLN (Persero).

2 Budget The PLN Distribution prepares an annual detailed plan and budget, covering AMDAL and UKL-UPL preparation, and implementation of mitigation measures and monitoring requirements. Annual budget allocations depend on the volume and the number of proposed activities.

3 Human Resources At the regional level of PLN Distribution there is one environmental supervisor position, filled by a full time staff.

B Process and Procedures

1 Coherence

Not applicable, as this case study only evaluates a UKL-UPL implementation report.

2 Transparency

3 Consistency

4 Effectiveness

C Output and Outcome

1 Screening and Categorization

The Kutampi six x 2 MW Diesel-Fueled Power Plant only requires a UKL-UPL due to the small scale of the project.

2 Scoping Not applicable to UKL-UPL projects.

3 Project Description The UKL-UPL clearly states the project goals and objectives, and the objectives of UKL-UPL preparation. This project was intended to provide electric supply for households, industries, tourism, street lighting and other community needs in Kecamatan Nusa Penida,

Page 19: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

No

Key Elements

(ADB SPS 2009, Pages 41 – 43, except Parts A

and B)

Findings on Compliance and Quality of Data and Analysis

covering people in Nusa Gede, Nusa Caningan, and Nusa Lembongan.

The PLTD comprises six 2 MW power units, with the plant including the following infrastructure and facilities:

- An office building providing working areas and an equipment and spare parts warehouse

- A security guard house - A kitchen - An unused water treatment unit - A 212 liter diesel storage tank and six pouring tanks with total

capacity of 70 liters - A storage area for new lubricant, used lubricants, water gallon,

and used spare parts - Two daily tanks with a capacity of 16,000 liters for the six power

units - A temporary depot for segregated solid organic, inorganic and

hazardous waste storage - An oil catcher to contain liquid waste from washing and

replacement of machine coolant - Six transformers

4 Policy, Legal and Administrative Framework

Relevant national laws and regulations (including sector regulations) as well as local regulations applicable to the project are listed in the UKL-UPL.

5 Environmental Baseline The UKL-UPL provides baseline information on:

- Physical-chemical components - Biological components - Socio-economic and cultural components

6 Analysis of Alternatives Not applicable to an UKL-UPL type project. Alternative technologies and plant design was considered during the earlier project feasibility stage.

7 Impact and Risk Assessment

The UK-UPL identifies environmental and social impacts during project pre-construction, construction, and operations phases.

8 Environmental Management Plan (EMP)

The UKL-UPL summarizes potential impacts during the project pre-construction, construction, and operation phases and corresponding mitigated measures and monitoring requirements. A commitment to implement the UKL-UPL is provided in a Statement Letter signed by the PLN Person in Charge.

9 Information Disclosure Not possible to describe information disclosure for this case study as the UKL-UPL document was not available, hence the focus on the UKL-UPL implementation report.

10 Consultation and Participation

Not possible to describe information disclosure for this case study as the UKL-UPL document was not available, hence the focus on the UKL-UPL implementation report.

11 Grievance Redress Mechanism Development

Although there is not an explicit requirement for a grievance mechanism in MOE Regulation No. 16/2012, PLN through its

Page 20: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

No

Key Elements

(ADB SPS 2009, Pages 41 – 43, except Parts A

and B)

Findings on Compliance and Quality of Data and Analysis

project level office has procedures to receive and follow-up on community complaints.

12 EMP Implementation Review of the UKL-UPL implementation report for July to December 2016 indicates that the report comprehensive covers:

- Source of impacts - Management measures - Performance indicators - Location of mitigation measures - Period of mitigation measures

13 Monitoring and Reporting Review of the UKL-UPL implementation report showed that required monitoring was undertaken, supported by laboratory analytical results. Detailed monitoring data is provided for:

- Source of impacts - Effectiveness of monitoring in discerning impacts - Monitoring locations - Parameters monitored - Monitoring methods - Monitoring results

Results for the second half of 2016 were compared to results from the previous semi-annual monitoring period to identify impact trends for noise, air quality, water quality, waste generation, work accidents, fire, and occupational health. Additionally, monitoring results were compared to applicable environmental quality standards.

The UKL-UPL implementation report also contained supporting documentation to demonstrate adherence to permit requirements for hazardous waste collection and transport (Ref. 104/NUSRA/07/2016), including a hazardous waste manifest, hazardous waste management balance, and hazardous waste reporting sheets.

Page 21: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

5. Bali - Nusa Lembongan 20 kV Subsea Cable Interconnection System Project

Project Name Bali - Nusa Lembongan 20 kV Subsea Cable Interconnection System

Location Gianyar and Klungkung Regencies, Bali

Indonesian Environmental Permitting Category

UKL-UPL

ADB Project Category B

Implementing Agency (Project proponent)

PLN (Persero) Distribusi Bali

Compiler/Consultant Team of AMDAL Experts

Environmental Permit Recommendation of Bali Environmental Agency No. 82/2013 dated March 19, 2013

No

Key Elements

(ADB SPS 2009, Pages 41 – 43, except Parts A

and B)

Findings on Compliance and Quality of Data and Analysis

A Institutional Capacity

1 Institutional Structure PLN (Persero) Distribution Bali is responsible for safeguards. PLN Bali (Distribution) is led by one General Manager, six Sector Managers, eighteen Deputy Managers, two Procurement Officers, five Area Managers, and thirteen District Managers. A dedicated safeguards unit (i.e., Supervisor for Safety, Occupational Health and Environment) is under the Distribution Manager and Deputy Manager for Operation Control of Distribution System.

2 Budget PLN Distribution prepares an annual detailed plan and budget, covering AMDAL and UKL-UPL preparation and implementation of mitigation measures and monitoring requirements. Annual budget allocations depend on the volume and the number of proposed activities.

The physical and financial progress of activities are regularly monitored and reported.

3 Human Resources The PLN Wilayah / Distribution Bali has one full time environmental supervisor position.

B Process and Procedures

1 Coherence Based on document review, field visits and interviews with PLN Distribution Bali staff, it was concluded that preparation of the project UKL-UPL was generally in accordance with prescribed processes and procedures.

2 Transparency The requirement to conduct public consultations is not explicitly stated in the MOE Regulation No. 16/2012 and consequently may not be done for UKL-UPL projects. Consultation was however carried out through inviting community leaders (vice of customary village treasurer, Jungut Batu village head, and community leaders), vice of Bupati Klungkung, Camat of Nusa Penida, and the PLN team to an initial information dissemination meeting. An additional information dissemination session was attended bypeople from Krama Subak Segara Wilis, including the Head of Desa Pering,

Page 22: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

Customary Village Treasurer, the PLN team, and community members. No women participated in either meeting.

3 Consistency Based on desk study, interviews with PLN Distribution Bali staff, it was concluded that preparation of the project UKL-UPL was consistent with the prescribed processes and procedures, including consistency with the district spatial plan.

4 Effectiveness Preparation of the UKL-UPL for this project is considered effective, as evidenced by timely delivery of the assessment. However, due to technical considerations the project has not yet been implemented.

C Output and Outcome

1 Screening and Categorization

MOE Regulation No. 5/2012 on Type of Business and/or Activity Requiring Environmental Impact Assessment provides that only a UKL-UPL is required since the project size is not greater than 150 kV.

At the screening phase it was determined the proposed project was not consistent with the spatial plan. Appendix VII of the Bali Spatial Plan No. 16/2009 already included the development of submarine power cable network system from Nusa Lembongan to a substation in Kabupaten Klungkung. However, development of the cable network has not been specifically identified in the Bali Spatial Plan No. 16/2009. Similarly, Perda No. 26/2007 on Kabupaten Gianjar Spatial Plan did not include the SKTM 20 kV transmission line.

2 Scoping Not applicable to UKL-UPL projects.

3 Project Description The project description explains that the project is intended to supply increasing demand of power in the three Bali islands of Nusa Penida, Lembongan, and Ceningan. The project will cross over Badung Strait from a relay substation at Pering Coast, Kecamatan Blahbatuh, Kabupaten Gianyar to the relay tower at Tanjung Ental, Jungutbatu, Nusa Lembongan, Kecamatan Nusa Penida, Klungkung. The network comprises two cables, each 17.1 kilometers long.

The UKL-UPL describes:

- Land status - Proposed project activities - Permitting (principal permit issued by Bali’s Governor No.

671/2576/Bappeda and permit for two line of sea cables (No. BX.627/KL.303 issued by Directorate General of Sea Transportation)

- Scale of business and/or activities (specification, land requirement, substation, and relay substation)

- Compliance of the project location with the spatial plan - Overall project design (pre-construction, construction and

operation)

4 Policy, Legal and Administrative Framework

Relevant national laws and regulations (including sector regulations) as well as local regulations applicable to the project are listed. In addition, several provincial and district level regulations are referred to:

- Regulation of Bali Province No. 4/2005 on Control of Pollution and Environmental Deterioration

- Regulation of Bali Province No. 16/2009 on Regional Spatial Plan

Page 23: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

- Regulation of Bali’s Governor No. 08/2007 on Environmental Quality Standard and Criteria of Environmental Deterioration

- Regulation of Gianyar Regency No. 26/2007 on Kabupaten Gianyar Spatial Plan

5 Environmental Baseline The UKL-UPL provides baseline information on:

A. Geophysical-chemical component

− Climate (rainfall, climate, air temperature and humidity, wind direction and speed, duration of solar exposure)

− Land (including map of substations and proposed layout of sea cable alignment)

− Hydro-oceanography (wave, sea current, tides)

− Land (spatial plan, change of land use)

− Physiography (morphology, landform, geological structure, soil characteristics, and erosion)

B. Biological component

− Terrestrial flora and fauna

− Aquatic/marine biology (plankton, macrozoobenthic, fishes, coral reef)

Extensive baseline information on the biological component is provided, including a detailed assessment of species richness, abundance, biodiversity and value index, and dominance.

C. Socio-cultural component

− Demographics (population number and distribution, population composition)

− Cultural values

− Social institutions

− Cultural heritage

− Public perceptions and attitude

D. Socio-economic component (income, pattern of double income) E. Public health component

− Potential human risks

− Type and number of health facilities

− Condition of environmental sanitation (water supply, public behavior on disposal of domestic wastes, public behavior on disposal of rubbish)

− Nutrition status and food adequacy

F. Transportation (mobilization of equipment and material)

6 Analysis of Alternatives Not applicable, as the project only considers one alternative.

7 Impact and Risk Assessment

The UKL-UPL describes potential environmental and social impacts during the project pre-construction, construction, and operation phases. Project impacts are categorized as small to moderate:

- Pre-construction phase (negative community perceptions, permit violations, incorrect cable alignment, failure on land negotiations)

- Construction phase (disturbance to religious ceremonies, social upset, accidents, turbidity of sea water, disturbance to sea transport/traffic, damage to coral reefs, disturbance to fishermen and seagrass farmers, disturbance to marine tourism)

- Operation phase (electromagnetic field and corona effect,

Page 24: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

electricity blackouts, and negative community perceptions).

8 Environmental Management and Monitoring Plan (EMP)

The UKL-UKL details mitigation measures and monitoring corresponding to impacts identified for the pre-construction, construction, and operation phases.

PLN’s commitment to fully implement the UKL-UPL is expressed in a stamped and signed Statement Letter from the General Manager of PLN (Persero) Distribusi Bali.

9 Information Disclosure Information dissemination occurred during a consultation meeting attended by invited community leaders (vice of customary village treasurer, head of Desa Jungut Batu and community leaders), vice of Bupati Klungkung, Camat of Nusa Penida, and the PLN team. An additional public consultation was carried out with people from Krama Subak Segara Wilis, and was attended by the Head of Desa Pering, Customary Village Treasurer, the PLN team, and community members. No women participated in the information dissemination meetings.

10 Consultation and Participation

A public consultation was carried out to explain the project objectives and technical details, and potential environmental and social impacts of the project. An additional consultation was carried out to address community concerns relating to electromagnecic risk. To reassure the local community on the safety of the transmission line, PLN issued a guarantee statement on electric magnetic force safety. Guarantee Letter No. 013.SJ/102/DIST.BALI/2012, PLN (Persero) Distribution Bali explaining and guaranteeing that the landing point tower and the transmission line right of way do not pose a safety and human health hazard.

11 Grievance Redress Mechanism Development

Although there is not an explicit requirement for a grievance mechanism in MOE Regulation No. 16/2012, PLN through its project level office has procedures to receive and follow-up on community complaints.

12 EMP Implementation Project has been suspended.

13 Monitoring and Reporting Not applicable.

Page 25: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

6. Minahasa Peaker 150 MW Gas- and Fuel-Fired Power Plant Project

Project Name Minahasa Peaker 150 MW Gas- and Fuel-Fired Power Plant Project, known as Pembangkit Listrik Tenaga Mesin Gas or PLTMG

Location North Minahasa Regency, North Sulawesi Province

Indonesian Environmental Permitting Category

AMDAL

ADB Project Category A

Implementing Agency (Project proponent)

PLN (Persero) Unit Pembangunan Sulawesi Bagian Utara (UIP Sulbagut)

Compiler/Consultant Environmental Study Center of Sam Ratulangi University, Manada (PSLH UNSRAT), Certification Registration No. 0056/LPJ/AMDAL-1/LRK/KLH

Environmental Permit Not yet secured as the AMDAL is still being processed.

No

Key Elements

(ADB SPS 2009, Pages 41 – 43, except Parts A

and B)

Findings on Compliance and Quality of Data and Analysis

A Institutional Capacity

1 Institutional Structure PLN (Persero) UIP Sulbagut, based in Manado, is the project proponent.

2 Budget At the UIP level, PLN allocates funds for management and monitoring activities. The Southern Sulawesi UIP prepares a detailed annual plan and budget, covering AMDAL and UKL-UPL preparation, approval of the Environmental Permit, and implementation of mitigation measures and monitoring requirements. Annual budget allocations depend on the volume and number of proposed activities.

The physical progress and financial progress of UIP activities are regularly monitored and reported.

3 Human Resources In the PLN organizational structure, UIP environmental specialists supervise UPP environmental specialists. In the case of Sulbagut UIP, two environmental specialists supervise a total of four environmental specialists (one at each of four UPP). The UIP environmental specialists have academic backgrounds in civil engineering, chemical engineering or chemistry. UIP and UPP staff receive environmental assessment training in courses covering AMDAL A (basic level training on AMDAL), AMDAL B (preparation of AMDAL documents), AMDAL C (advanced level training for AMDAL review), and preparation of UKL-UPL.

B Process and Procedures

1 Coherence Based on desk study, field visits, and interviews with UIP Sulbagut staff, it was concluded that preparation of the project AMDAL was in accordance with prescribed processes and procedures.

2 Transparency Ongoing AMDAL preparation was carried out in a transparent manner through announcement in local newspapers and posting of the project notification in designated public places. Affected persons

Page 26: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

and/or their representatives and key stakeholders were invited to and attended multiple public consultations. While women were involved in the consultations only a limited number attended.

3 Consistency The scoping process of the AMDAL is considered consistent with prescribed processes and procedures.

4 Effectiveness The scoping process of the AMDAL study is considered less effective since the KA-ANDAL (terms of reference for the environmental assessment) had not yet been approved at the time of the field visit.

C Output and Outcome

1 Screening and Categorization

MOE Regulation No. 5/2012 on Type of Business and/or Activity Requiring Environmental Impact Assessment provides that an AMDAL is required since the project size if greater than 100 MW. A single AMDAL approach applies in this instance since there is only one type of activity in the project area.

Decree No. 08/2013 on Procedure for Review and Examination of Environmental Document and Issuance of Environmental Permit, Article 19 stipulates that if the AMDAL Commission in the regency or municipality is not licensed, the authority of AMDAL review must be escalated to the AMDAL Commission at the provincial level. The latter process applies to this project.

Additionally, the project proponent coordinated with local government agencies, particularly to ensure project compliance with the local spatial plan. A recommendation was made by the local government of Minahasa Utara in a letter from the Head of Dinas Penataan Ruang dan Pertamanan of Minahasa Utara Regency No. 025/DPRP/600/700/III/2014 (dated 4 April 2014).

2 Scoping A scoping process was carried out to determine the assessment scope and identify potential environmental and social impacts of the project. The terms of reference prepared as part of the scoping process covers:

A. Description of business and/or activity

− Status of the AMDAL study

− Compliance of project location with the local spatial plan

− Description of proposed business and/or activity

B. Baseline information, including existing activities around the proposed location of the project

C. Public consultation results D. Potential significant impacts

− Identification of potential impacts

− Evaluation of potential impacts

E. Study areas and timeline

− Project boundary, describing locations of all project activities

− Ecological boundary, describing the area where significant impacts may occur to terrestrial, aquatic and air components

− Social boundary, describing the area where social impacts may occur

Page 27: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

− Administrative boundary, describing the smallest administrative area

3 Project Description The project goal and objectives and scope of the AMDAL are clearly described, covering:

A. Pre-construction phase

− Permitting administration

− Land acquisition

− Public consultation

B. Construction phase

− Labor mobilization

− Mobilization/demobilization of equipment and materials

− Land consolidation

− Construction of main structure and supporting facilities

− Testing and commissioning

C. Operation phase

− Worker mobilization

− Power plant operation

− Power plant maintenance

− Waste management (including hazardous wastes)

D. Post-operation phase

− Demolition of main structures and supporting facilities

− Revegetation and reclamation

4 Policy, Legal and

Administrative Framework

This aspect is not described in the terms of reference, but will be included as part of the ANDAL.

5 Environmental Baseline Baseline information for the project includes:

A. Geophysical-chemical component

− Rainfall

− Ambient air quality

− Noise

− Vibration

− Geomorphology and geology

− Soil

B. Biological component

− Flora

− Fauna

C. Socio-economic, cultural, and health component

− Demography

− Regional infrastructure

− Transportation

− Social economic

− Public health In addition, existing business and/or activities identified within the project area are:

- Settlement of Wineru dan Likupang Kampung Ambong villages - Sea fishery activities - Protected mangrove - Marine tourism activities

Page 28: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

6 Analysis of Alternatives Based on an interview with PLN staff is was confirmed that selection of the project location had considered risks and vulnerability to natural disasters, including avoidance of river bank/floodplain and landslide prone areas. Shifting of the location of project activities to avoid or minimize impacts is possible.

7 Impact and Risk

Assessment At the current scoping stage of the assessment, potential significant impacts have already been formulated, involving impact identification and evaluation of potential impacts to determine significance.

Potential significant impacts were identified through field observation, and consultation with experts, competent agencies and concerned persons. Evaluation criteria are:

- Existing pressure on environmental and social components - Importance of components to the daily livelihood of the

surrounding community and ecological values - People’s concerns about potential environmental and social

impacts - Compliance with existing regulations or restrictions

8 Environmental

Management and

Monitoring Plan (EMP)

The RKL-RPL has not yet been prepared since the assessment is still at the scoping stage, awaiting approval of the terms of reference.

9 Information Disclosure Information disclosure and consultation occurred during the scoping stage of the assessment involving interviews with village heads and the local community from Wineru and Likupang Timur villages within are situated in close proximity to the project area.

10 Consultation and

Participation

Community consultation commenced with a public meeting attended by the Secretary of Camat Likupang Timur and staff, Head of Likupang Kampung Ambong and Wineru Villages, head of neighborhood, village secretary, religious leaders, women leaders, and youth leaders. The meeting was advertised in local newspapers to ensure good participation. Additionally, empowerment activities were carried at the village level involving women’s and youth groups.

Comments, suggestions, and responses from these consultation activities included::

- The project proponent was requested to conduct direct information dissemination and consultation with communities, especially relating to land acquisition

- The public consultation was considered to have been properly held and accepted by the local community

- Information provided and meeting participation (including women’s representation) was considered to be adequate

- Potential environmental and social impacts were satisfactorily explained

- No protected or endangered flora and fauna within the project area were identified

- In order to avoid traffic congestion, the project should build a separate access road

- The project should prioritize the recruitment of local people for workers/labors

Page 29: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

11 Grievance Redress

Mechanism Development

A specific grievance mechanism has not yet been developed for the project. However, conflicts and complaints are referred to the village heads who act a mediator to try to resolve problems at the local level. In cases where a problem cannot be resolved, the village head reports to higher level government for resolution.

12 EMP Implementation Project implementation has not yet commenced.

13 Monitoring and Reporting Project implementation has not yet commenced.

Page 30: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

7. Lontar Coal-Fired Power Plant 1 x 315 MW Extension Project

Project Name Lontar Coal-Fired Power Plant 1 x 315 MW Extension Project

Location Tangerang Regency, Banten Province, Java, Indonesia

Indonesian Environmental Permitting Category

ANDAL and RKL-RPL addendum

ADB Project Category A

Implementing Agency (Proponent)

PT Perusahaan Listrik Negara (Persero) Unit Pembangunan VIII - PLTU 3 Banten - Lontar

Compiler/Consultant Human Resources and Environmental Study Centre of University of Indonesia, Jakarta

Environmental Approval and Permit

Environmental approval and permits covering the extension project:

- Environmental Feasibility Approval (AMDAL approval) No. 668/Kep.8-Huk/2015 (dated 15 January 2015) granted by the Governor of Banten Province

- Environmental Permit No. 668/Kep.83-Huk/2015 (dated 16 February 2015) granted by the Governor of Banten Province

No

Key Elements

(ADB SPS 2009, Pages 41 – 43, except Parts A

and B)

Findings on Compliance and Quality of Data and Analysis

A Institutional Capacity

1 Institutional Structure PLTU Lontar is part of the wider organization of PLN, and is the project proponent.

2 Budget At the UIP level, PLN allocates funds for management and monitoring activities. The UIP prepares an annual detailed plan and budget, covering AMDAL and UKL-UPL preparation, and implementation of mitigation measures and monitoring requirements. Annual budget allocations depend on the volume and number of proposed activities.

The physical and financial progress of UIP activities are regularly monitored and reported.

3 Human Resources In the PLN organizational structure, UIP environmental specialists supervise UPP environmental specialists. The UIP environmental specialists have academic backgrounds in civil engineering, chemical engineering, or chemistry. UIP and UPP staff receive environmental assessment training in courses covering AMDAL A (basic level training on AMDAL), AMDAL B (preparation of AMDAL documents), AMDAL C (advanced level training for AMDAL review), and preparation of UKL-UPL.

Page 31: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

No

Key Elements

(ADB SPS 2009, Pages 41 – 43, except Parts A

and B)

Findings on Compliance and Quality of Data and Analysis

B Process and Procedures

1 Coherence Based on desk study, field visits and interviews with PLTU Lontar staff, it was concluded that preparation of the ANDAL and RKL-RPL was in accordance with the prescribed processes and procedures for an AMDAL extension project and adhered to the direction of the Regional Environmental Agency of Banten Province.

2 Transparency According to the government Regulation No. 27/2012 on Environmental Permitting, no public notification or consultation is required for ANDAL addendum projects. However, PLTU Lontar did inform local communities about the extension project during an information dissemination meeting and through informal communication. Community representatives and government stakeholders were additionally involved in the evaluation of the ANDAL and RKL-RPL for the extension project. The Regional Environmental Agency of Banten Province facilitated stakeholder involvement in this evaluation process.

3 Consistency Based on desk study and interviews with PLTU Lontar staff it was concluded that preparation of the ANDAL and RKL-RPL for this extension project was consistent with prescribed processes and procedures are set out in government Regulation No. 27/2012 on Environmental Permitting.

The ANDAL addendum focuses on the assessment of potentially significant environmental and social impacts of the extension project as identified during a scoping process. Based on the outcomes of the impact assessment, the RKL-RPL defines mitigation measures for significant impacts and corresponding monitoring requirements. Moreover, for those impacts that are considered insignificant but which could be of concern if not managed properly, mitigation measures and monitoring are also defined in the RKL-RPL.

4 Effectiveness The ANDAL addendum process undertaken for the extension project is considered effective with regards to focusing the assessment on potentially significant environmental and social impacts identified in the terms of reference. Furthermore, the engagement of community and government stakeholders through the ANDAL addendum process was useful to define effective mitigation measures and monitoring requirements to be included into the RKL-RPL.

Nevertheless, it should be noted that the ANDAL and RKL-RPL for the extension project were developed in 2015 when most of the land acquisition, land clearing and construction of the transmission tower had already been completed.

C Output and Outcome

1 Screening and Categorization

PLTU Lontar has completed the ANDAL and RKL-RPL addendum for the extension project in compliance with government Regulation

Page 32: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

No

Key Elements

(ADB SPS 2009, Pages 41 – 43, except Parts A

and B)

Findings on Compliance and Quality of Data and Analysis

No. 27/2012 on Environmental Permitting and following direction from the Regional Environmental Agency of Banten Province.

2 Scoping The scoping process, including conduct of a baseline survey, was completed in accordance with requirements set out in government Regulation No. 27/2012 on Environmental Permitting. Under this regulation a terms of reference is not required, with the process instead requiring an ANDAL and RKL-RPL.

3 Project Description The assessment describes both the existing operation and the project extension. The existing and new power plants will use low grade coal that has a calorific value of approximately 4,200 kcal and Sulphur content of 0.33-0.35% (weight based) supplied from Sumatera and/or Kalimantan islands. In addition, high speed diesel will be used as auxiliary fuel for start-up and stabilizing the power generation prior to switching to coal.

The main components of the existing facility are three 315 MW power plants, an emission stack, coal yard and handling facilities, water treatment and cooling water system, fly/bottom ash storage, and jetty.

The project extension involves:

- Construction of a fourth 315 MW power plant including installation of associated equipment and systems covering an area of approximately 16.5 hectares within the existing 117 hectares of PLN land

- Mobilization of up to 2,200 construction workforces during peak construction

- Jetty extension to a length of 280 meters to accommodate simultaneous coal unloading from two barges

- Upgrading of drainage, fuel, cooling water, and power transmission systems

- Anticipated additional employment of up to 120 personnel when the fourth power plant becomes operational

Figures, photos, and drawing are provided to support the information contained in the project description. Overall, the project description is clear and adequate for the impact assessment purpose, except for that for the post operation phase as described below.

Unlike the description of the construction and operation activities, that of the post-operation activities (i.e. post 30-years of operation) is limited, just stating that the facility would continue to be operated, converted to gas fuel, have its capacity increased or subject to decommissioning without further elaboration.

4 Policy, Legal and Administrative Framework

Relevant national laws and regulations are listed.

5 Environmental Baseline The ANDAL addendum includes adequate information of the existing environmental baseline conditions in the area required for the extension project and its proximity.

Page 33: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

No

Key Elements

(ADB SPS 2009, Pages 41 – 43, except Parts A

and B)

Findings on Compliance and Quality of Data and Analysis

However, the baseline information related to coastal water quality and marine biota potential as fishery resources for the local fishermen are deficient, and do not provide adequate insights into potential impacts of existing and expanded operations.

Similarly, the socio-economic and public health baseline data relies on secondary data published by the government instead of primary data acquired through a social survey. In the absence of primary data, project impacts on local communities cannot be accurately assessed. Additionally, information on cultural heritage within the study area is lacking.

6 Analysis of Alternatives The ANDAL addendum only considers the sole alternative of an additional power plant. Other than expansion project siting, no different technological options or construction methods were considered.

7 Impact and Risk Assessment

The ANDAL addendum provides a reasonable assessment of both environmental and social impacts and risks for the extension project. The assessment was undertaken using a semi-quantitative methodology which considered:

- Ambient air quality - Ambient noise level - Road and sea traffic - Coastal marine water quality - Coastal abrasion and sedimentation - Marine biota - Community perceptions - Employment and business opportunities - Public health

Review of the assessment findings suggests that impacts and risks to marine water quality, marine biota, employment and business opportunities, and public health may have been underestimated.

Risks associated with institutional capacity and commitment to managing impacts are not assessed as this undertaking is not mandatory in an ANDAL addendum.

8 Environmental Management and Monitoring Plan (EMP)

The RKL-RPL details mitigation measures and monitoring requirements to be undertaken by PLTU Lontar. Some of the mitigation measures are unclear or insufficient (e.g., mitigation and monitoring required to ensure that the drainage from the coal stockpiles does not discharge directly to the river and coastal areas).

Budget allocations to implement additional mitigation measures and monitoring are not explicitly provided for the extenson project.

9 Information Disclosure Although government Regulation No. 27/2012 on Environmental Permitting does not require information disclosure and public consultation for ANDAL and RKL-RPL addendum, PLPLTU Lontar organized an information dissemination meeting for three villages, and sub-district officials in the proximity of the extension project

Page 34: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

No

Key Elements

(ADB SPS 2009, Pages 41 – 43, except Parts A

and B)

Findings on Compliance and Quality of Data and Analysis

area. Sufficient details were provided on the project description, technology selected, the land area to be used, and employment. This dissemination was undertaken prior to the construction phase.

10 Consultation and Participation

As indicated for Information Disclosure village representatives and officials were invited to evaluate the ANDAL and RKL-RPL addendum documents. Women’s participation in the consultation process was confirmed.

11 Grievance Redress Mechanism Development

The ANDAL addendum does not indicate the existence of a grievance mechanism. However, public concerns, complaints, and grievances are received by UIP’s Public Relations/Communication department which verifies and forwards them to the responsible unit with authority to respond.

12 EMP Implementation Project is at pre-construction phase. Observations during the site visit indicated that PLTU Lontar adheres to the RKL-RPL addendum in implementing its environmental and social mitigation measures and monitoring.

13 Monitoring and Reporting Conduct and reporting of monitoring could not be assessed since no RKL-RPL implementation reports were provided by PLTU Lontar for review.

Page 35: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

8. Lapai Minihydro Power Plant Unit I (2 x 2 MW) Project

Project name Lapai Minihydro Electric Power Plant Unit I Project (2 x 2 MW)

known as pembangkit listrik tenaga minihidro (PLTM)

Location Koreiha dan Watumotaha Village in Ngapa Sub-district, Kolaka

Utara Regency, South-east Sulawesi Province

Indonesian Environmental

Permitting Category

AMDAL

ADB Project Category B

Implementing Agency

(Proponent)

PT. PLN (Persero) Unit Induk Pembangunan Sulawesi Bagian

Selatan

Compiler/Consultant PT Arthayu Rali Perdana (certified)

Environmental Permit Governor of South-east Sulawesi Province Decree No.

660/38/IV/2016 (Approval for KA-ANDAL)

No

Key Elements

(ADB SPS 2009, Pages 41 – 43, except Parts A

and B)

Findings on compliance and quality of data and analysis

A Institutional Capacity

1 Institutional Structure PT. PLN (Persero), based in Makassar city, is the project proponent. As typical of the PLN institutional structure, the UIP Southern Sulawesi has several units, which have duties related to safeguards distributed within the Planning, Construction, and Project Implementation units:

- Planning Unit is responsible for preparing, implementing, and evaluating impacts related to project facilities and land issues

- Construction Unit is responsible for preparing, implementing, and evaluating safety, occupational health, security, and environmental program

- Project Implementation Unit is responsible for preparing, managing, and evaluating safety, occupational health, security, and environment program; and preparing, managing, and evaluating corporate social responsibility activities as agreed on with the UIP office

2 Budget At the UIP level, PLN allocates funds for management and monitoring activities. The Southern Sulawesi UIP prepares an annual detailed plan and budget covering AMDAL and UKL-UPL preparation, and implementation of mitigation measures and monitoring requirements. Annual budget allocations depend on the volume and number of proposed activities.

The physical and financial progress of UIP activities are regularly monitored and reported.

3 Human Resources In the PLN organization structure, UIP environmental specialists supervise UPP environmental specialists, with each UIP specialist supervising two UPP specialists. UIP and UPP staff receive environmental assessment training in courses covering AMDAL A (basic level training on AMDAL), AMDAL B (preparation of AMDAL

Page 36: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

documents), AMDAL C (advanced level training for AMDAL review), and preparation of UKL-UPL.

B Process and Procedures

1 Coherence Based on desk study, it was concluded that preparation of the project AMDAL was in accordance with prescribed processes and procedures. Eligibility of the project and its compliance with spatial planning was assessed at the initial project phase through securing the required government agency recommendation.

2 Transparency During the AMDAL preparation, a social survey and interviews with the local community, affected people, and the general public in the project area were undertaken.

3 Consistency Based on desk conducted, it was concluded that preparation of the project AMDAL was consistent with prescribed processes and procedures.

4 Effectiveness No determination could be made regarding effectiveness based on the available information.

C Output and Outcome

1 Screening and Categorization

Although projects of this size (i.e., two x 2 MW) would normally be subject to UKL-UPL, the project appears to have been instead categorized as an AMDAL type project due the large number of persons directly affected, potential impacts to endangered bird species, and lesser extent impacts to protected forest, and water quality and aquatic biota due to erosion.

2 Scoping The scoping process involving identification of potential environmental and social impacts was undertaken by looking at the interaction between the project activities and environmental and social components that may be impacted. Potential impacts were then evaluated to identify issues that should be assessed in detail in the AMDAL study. The scoping report covered:

- Proposed activities - Planned environmental management - Environmental components affected - Scoping (potential impacts, evaluation of potential impacts) - Study area - Schedule for the AMDAL study

At the scoping stage, only limited information was available. The following criteria were therefore used to make a determination of impact significance:

- High pressure to an environmental component - Affected environmental component of importance to the daily

livelihood of surrounding community (social and economical values) and other environmental component (ecological values)

- Strong community concern about an environmental component - Applicable regulation or policy prohibiting impacts

3 Project Description The PLTM Lapai mini-hydro power plant is located in Koreiha and Watumotaha villages, Ngapa sub-district, Kolaka Utara Regency, South-east Sulawesi Province. The AMDAL provides details on the engineering aspects of the project.

4 Policy, Legal and Key laws and regulations are not listed in the project AMDAL study.

Page 37: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

Administrative Framework

5 Environmental Baseline The AMDAL provides baseline information on physical-chemical, biological, social economic, social cultural, and public health components. Details are provided of protected fauna in the project area (e.g., Haliastur indus, Elanus caeruleus, Falco moluccensis,

Tyto alba, Halcyon chloris, Macaca ochreata, Hydrosaurus

amboinensis, and Macrogalidia musschenbroekii), including several CITES vulnerable to extinct bird species.

6 Analysis of Alternatives Only one option was considered in the project AMDAL.

7 Impact and Risk Assessment

The AMDAL describes potentially significant environmental and social impacts using matrix. The impact and risk assessment considered:

- Number of people affected - Distribution of impacts - Impact duration and intensity - Number of environmental components affected - Cumulative impacts - Reversibility or irreversibility of impacts

Evaluation of impacts particularly focused on:

- Social, economic, cultural, and public health conditions of the community in Koreiha and Watumotaha villages

- Flora and fauna, and protected forest in the project area - Erosion and sedimentation around the project site - Hydrological conditions around the project site

8 Environmental Management Plan (EMP)

The UKL-UPL describes the management of impacts during the project pre-construction, construction, operation, and post-construction phases, covering:

1) Environmental impacts to be mitigated 2) Impact type and source 3) Performance indicator 4) Mitigation type (technological, social-economic, institutional) 5) Location of mitigation measures 6) Implementation period 7) Institutional arrangements (implementer, supervisor,

recipient of reports)

The UKL-UPL also describes monitoring requirements for each project phase, covering:

1) Impacts monitored (type of impact, indicator/parameter monitored, source of impact)

2) Form of monitoring (method of data collection and analysis, location of monitoring, time and frequency of monitoring)

3) Institutional arrangements for environmental monitoring (implementer, supervisor, recipient of reports)

9 Information Disclosure Information disclosure was undertaken by the project proponent through inviting relevant technical agencies at the regency level, local government of Ngapa sub-district, community leaders and affected people. In addition, a project notification was announced in the Kendari Pos daily newspaper.

10 Consultation and Participation

The AMDAL poorly documents the extent of community consultations undertaken. Although there is some indications that

Page 38: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

some consultations were completed prior to commencement of construction no records of such consultation are provided.

11 Grievance Redress Mechanism Development

At project level, environmental and social complaints during the construction phase are handled by the UIP’s Public Relation/Communication department, which verifies and forwards the complaint to the relevant unit with the authority to respond. During the operational phase complaints are handled by the Transmission Unit. In addition, the government Environmental Agency (known as Badan Lingkungan Hidup or Dinas Lingkungan Hidup) will also be informed of any complaints related to PLN projects for subsequent follow up with the project proponent.

12 EMP Implementation Project is at pre-construction phase.

13 Monitoring and Reporting Implementation reports are not yet available.

Page 39: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

9. Nonohonis – Kefamenanu 70 kV Power Transmission Lines and Towers Project

Project name Nonohonis – Kefamenanu 70 kV Power Transmission Lines and Towers Project

Location Timor Tengah Selatan Regency and Timor Tengah Utara Regency in Timor Island, East Nusa Tenggara Province

Indonesian Environmental Permitting Category

AMDAL (since the project area crosses over protection and production forest)

ADB Project Category B

Implementing Agency (Proponent)

PLN (Persero) – Unit Induk Pembangunan XI in Mataram city, Lombok Island

Compiler/Consultant PT. Arthayu Rali Perdana (certified)

Environmental Permit - Environmental feasibility approval (AMDAL approval) based on the Governor of East Nusa Tenggara Province Decree No. 281/KEP/K/2015 (dated 3 December 2015) which covers approval of the ANDAL and RKL-RPL

- Environmental Permit based on the Governor of East Nusa Tenggara Province Decree No. 282/KEP/K/2015 (dated 3 December 2015)

No

Key Elements

(ADB SPS 2009, Pages 41 – 43, except Parts A

and B)

Findings on compliance and quality of data and analysis

A Institutional Capacity

1 Institutional Structure PT. PLN (Persero) UIP XI, based in Mataram, is the project proponent. Typical of the PLN institutional structure, the UIP has several units, which have safeguard duties distributed within the Planning, Construction, and Project Implementation units:

- Planning Unit is responsible for preparing, implementing, and evaluating environmental assessments and environmental management related to project facilities and land issues

- Construction Unit is responsible for preparing, managing, and evaluating safety, occupational health, security, and environmental program

- Project Implementation Unit is responsible for preparing, managing, and evaluating safety, occupational health, security, and environment program; and preparing, managing, and evaluating corporate social responsibility activities as agreed on with the UIP office

The ANDAL provides additional data on the organization and profile of UIP XI.

2 Budget At the UIP level, PLN allocates funds for management and monitoring activities. The UIP XI prepares an annual detailed plan and budget, covering AMDAL and UKL-UPL preparation, and implementation of mitigation measures and monitoring requirements. Annual budget allocations depend on the volume and number of proposed activities.

The physical and financial progress of activities are regularly

Page 40: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

monitored and reported.

3 Human Resources In the PLN organizational structure, UIP environmental specialists supervise UPP environmental specialists. UIP and UPP staff receive environmental assessment training in courses covering AMDAL A (basic level training on AMDAL), AMDAL B (preparation of AMDAL documents), AMDAL C (review of AMDAL documents), and preparation of UKL-UPL.

B Process and Procedures

1 Coherence Based on desk study, it was concluded that preparation of the project AMDAL is in accordance with prescribed processes and procedures. Eligibility of the project and its compliance with spatial planning was assessed at the initial project stage by securing the required recommendation from relevant government agencies.

2 Transparency During the AMDAL study, a social survey and interviews with local communities, affected persons and general public around the project area were carried out.

3 Consistency Based on desk study, it was concluded that the AMDAL preparation is consistent with prescribed processes and procedures.

4 Effectiveness No determination could be made regarding effectiveness based on the available information.

C Output and Outcome

1 Screening and Categorization

The power transmission lines and towers will cross over 7,056 hectares of limited production forest and and 1,372 hectares of protection forest. Transmission towers 142 to 159 (18 towers), and 139 to 141 (3 towers) will be constructed in production forest and protection forest, respectively.

In accordance with MOE Regulation No. 5/2012 on Type of Business and/or Activity Requiring AMDAL, particularly Appendix II, the transmission line project is subject to AMDAL since it will impinge upon protection forest.

2 Scoping A scoping process was undertaken which examined the interaction between project activities and environmental and social components that may be impacted. Potential impacts were then evaluated to identify issues that should be addressed in detail in the AMDAL study. The scoping report covered:

- Proposed activities - Planned environmental management - Environmental components affected - Scoping (potential evaluation of potential impacts) - Study area - Schedule for the AMDAL study

3 Project Description The 44.73 kilometer long power transmission line will span from Kabupaten Timor Tengah to Kabupaten Timor Tengah Selatan. The construction involves erection of 159 transmission towers, which cross over seventeen villages and seven sub-districts. Initially, 162 towers were proposed to be built, but three towers were eliminated due to their unsuitable locations (two towers were located in a valley, and one tower was located in close proximity to a village). The transmission line will cross over protection forest (which

Page 41: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

provides a buffer system for water conservation, flood prevention, and erosion control, and maintaining soil fertility), and production forest.

The project proponent applied for a Forestry Borrow-to-Use permit (Izin Pinjam Pakai Kawasan Hutan or IPPKH) as stipulated in the Ministry of Forestry Regulation No. P.16/Menhut-II/2014 on Guidelines for Forest Area IPPKH. Subsequently, the Forestry Agency of East Nusa Tenggara Province issued a technical recommendations for the IPPKH based on the Letter No. Dk. 522.16/13/II/NTT-2015 (dated 16 April 2015).

4 Policy, Legal and Administrative Framework

Key laws and regulations are not listed in the project AMDAL study.

5 Environmental Baseline The AMDAL provides baseline information physical-chemical, biological (including biodiversity status), social economic, social culture, and public health components.

6 Analysis of Alternatives No analysis of project alternatives was undertaken in the project AMDAL. However, at the feasibility stage a decision was made to eliminate three towers for engineering (spanning a valley) and social (close proximity to a settlement) reasons.

Project planning was based on a field survey which considered technical, economical, social, and environmental aspects. The length of the power line between towers was designed to be as short as possible in order to reduce power loss, achieve cost saving, and increase ease of construction and maintenance. Other considerations in the project design were to reduce environmental impacts, protect natural sanctuaries, avoid community impacts and disputes, minimize visual impact to tourism, and protect cultural and historical heritage.

7 Impact and Risk Assessment

The AMDAL describes potential environmental and social impacts and identifies potentially significant impacts using a combination of mathematical calculation and professional judgment. The magnitude of impacts was scaled using an Environmental Quality Scale, which employs both qualitative and quantitative methods.

8 Environmental Management and Monitoring Plan (EMP)

The RKL-RPL describes the management of project impacts as follows:

A. Technology - Construct the transmission lines in accordance with

applicable Indonesian standards (i.e., SNI 04.6918-2002 on Requirements of SUTT and SUTET for Right of Way and Clearance)

- Undertake regular maintenance of vehicles used during construction (to reduce emissions)

- Periodically measure electromagnetic exposure as regulated in the applicable Indonesian standard (i.e., SNI 04-6950-2003 on Threshold Value of Electromagnetic Force)

- Erect notice boards during the construction work B. Socio-economic

- Forbid workers to hunt birds in the protection forest - Provide information to community on planned activities as

standard operating practice - Provide compensation to affected people whose lands are

acquired by the project

Page 42: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

- Provide compensation to people in case any damage occurs during stringing of conductor cables

C. Institutional - Apply for a Forest Borrow-To-Use permit prior to

constructing towers and installing the transmission lines in forest areas

- Inform the Bupati, Camat, and Head of Village about the schedule for information dissemination

- Inform local communities about project activities through newspapers and radio and through village channels

9 Information Disclosure Information dissemination was carried out by PLN (Persero) UIP XI to inform local communities about the project and planned project activities. Information dissemination took place during the field visits and the land acquisition consultation process in accordance with PLN’s standard operating procedure on Information Disclosure of Project Plan.

10 Consultation and Participation

Multiple public consultations were carried out during AMDAL preparation.

11 Grievance Redress Mechanism Development

At the project level, environmental and social complaints during the construction phase are handled by the UIP’s Public Relation/Communication department, which verifies and forwards a complaint to the relevant unit with the authority to respond. During the operational phase complaints are handled by the Transmission Unit. In addition, the government Environmental Agency (known as Badan Lingkungan Hidup or Dinas Lingkungan Hidup) will also be informed of any complaints related to PLN projects for subsequent follow up with the project proponent.

12 EMP Implementation Project is at pre-construction phase.

13 Monitoring and Reporting Implementation reports are not yet available.

Page 43: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

10. Namlea 10 MW Gas/Fuel Power Plant Project

Project name Namlea 10 MW Gas/Fuel Fired Power Plant (known as Pembangkit Listrik Tenaga Mesin Gas or PLTMG)

Location Buru Regency, Maluku Province

Indonesian Environmental Permitting Category

UKL-UPL

ADB Project Category B

Implementing Agency (Proponent)

PT. PLN (Persero) Unit Induk Pembangunan Maluku

Compiler/Consultant PT. PLN (Persero) Unit Induk Pembangunan Maluku

Environmental Permit The UKL-UPL has been approved and is awaiting permit issuance

No Key Elements

(ADB SPS 2009, Pages 41 – 43, except Parts A

and B)

Findings on Compliance and Quality of Data and Analysis

A Institutional Capacity

1 Institutional Structure PT. PLN (Persero) UIP Maluku, based in Ambon, is the project proponent. The UIP comprises several units, among which environmental safeguards responsibilities are as follows:

- Planning Unit is responsible for preparing, implementing, and evaluating environmental assessments and environmental management related to project facilities and land issues

- Construction Operation Unit is responsible for preparing, implementing, and evaluating safety, occupational health, security, and environment program

- Project Implemention Unit is responsible for preparing, managing, and evaluating safety, occupational health, security, and environment program; and preparing, managing, and evaluating corporate social responsibility activities as agreed on with the UIP office

2 Budget At the UIP level, PLN allocates funds for management and monitoring activities. The Maluka UIP prepares an annual detailed plan and budget, covering AMDAL and UKL-UPL preparation, approval of the Environmental Permit, and implementation of mitigation measures and monitoring requirements. Annual budget allocations depend on the volume and number of proposed activities.

The physical and financial progress of UIP activities are regularly monitored and reported.

3 Human Resources In the PLN organizational structure, one UIP environmental specialist supervises two UPP environmental specialists. UIP and UPP staff receive environmental assessment training in courses covering AMDAL A (basic level training on AMDAL), AMDAL B (preparation of AMDAL documents), AMDAL C (review of AMDAL documents), and preparation of UKL-UPL.

Page 44: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

B Process and Procedures

1 Coherence No determination could be made regarding coherence based on the available information.

2 Transparency No determination could be made regarding transparency based on the available information.

3 Consistency No determination could be made regarding consistency based on the available information.

4 Effectiveness No determination could be made regarding effectiveness based on the available information.

C Output and Outcome

1 Screening and Categorization

MOE Regulation No. 5/2012 on Type of Business and/or Activity Requiring Environmental Impact Assessment provides that only an UKL-UPL is required since the project size is less than 100 MW.

2 Scoping Not applicable to UKL-UPL projects. For UKL-UPL, potential impacts and mitigation measures are directly identified and formulated.

3 Project Description The project description details the components of the project during the pre-construction, construction, and operation phases, and explains the project’s alignment with spatial planning and the permitting process. While some technical specifications and illustrations are included, no information is provided on project activities that may cause adverse environmental and social impacts, including relating to solid waste generation, waste water discharges, and air emissions.

4 Policy, Legal and Administrative Framework

Relevant national laws and regulations are referred to in the UKL-UPL. Additionally, the project alignment with the local spatial plan, and permitting and land acquisition processes are described.

5 Environmental Baseline Although the environmental baseline is not described in the main report, primary and secondary data on climate, ambient air quality and noise, water quality, hydro-oceanography, geological and natural disaster, soil, transportation volume, terrestrial and aquatic biota, demographics, local economy, social cultural, community perception to the project, public health, and photo documentation of the project site is provided in an appendix.

There seems to be a limited connection between the baseline information provided and identification of potential impacts.

6 Analysis of Alternatives There is no discussion of project alternatives. For UKL-UPL projects alternatives are typically considered prior to preparation of the environmental assessment during technical and economic feasibility studies.

7 Impact and Risk Assessment

The UKL-UPL describes potential environmental and social impacts and corresponding mitigation measures and monitoring. The impact matrix covers:

- Pre-construction phase (site preparation and land acquisition) - Construction phase (worker recruitment, base camp construction

and operation, mobilization and demobilization of equipment and materials, land clearing and consolidation, construction of the main structure and supporting facilities)

Page 45: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

- Operation phase (recruitment of operational staff, fuel transportation, operation of power plant, and maintenance of the power plant)

8 Environmental Management and Monitoring Plan (EMP)

The UKL-UPL provides information on mitigation measures and monitoring for all potential impacts, covering:

Project impacts - Source of impact - Type of impact - Magnitude of impact

Mitigation plan - Mitigation measures - Location of mitigations - Period of mitigations

Monitoring plans - Monitoring measures - Monitoring locations - Period of monitoring

A. Institutional arrangements - Assigned mitigation and monitoring responsibilities

(implementer, supervisor, and reporting lines)

Mitigation measures and monitoring identified for the project encompassed: information disclosure and community consultation/coordination, transparent land acquisition payments, use of local workers, public health, surface water quality management, protection of aquatic biota, ambient air quality management, erosion and drainage control, solid waste and hazardous waste handling, workersafety, adequate wages, and worker insurance.

A legally binding statement letter signed by UIP’s Person in Charge (General Manager) reflecting the project proponent’s commitment to fully implement mitigation measures and monitoring is attached to the UKL-UPL.

9 Information Disclosure The UKL-UPL does not describe the information disclosure process but does mention that some information dissemination occurred during the project pre-construction phase.

10 Consultation and Participation

The requirement to conduct public consultations is not explicitly stated in MOE Regulation No. 16/2012 and consequently may not be done for UKL-UPL projects. No mention is made in the UKL-UPL of public consultations undertaken.

11 Grievance Redress Mechanism Development

Although there is not an explicit requirement for a grievance mechanism in MOE Regulation No. 16/2012, PLN through its project level office has procedures to receive and follow-up on community complaints.

12 EMP Implementation Project is at pre-construction phase.

13 Monitoring and Reporting Implementation reports are not yet available.

Page 46: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

11. Saumlaki 10 MW Gas/Fuel Power Plant Project

Project Name Saumlaki 10 MW Gas/Fuel Fired Power Plant (known as Pembangkit Listrik Tenaga Mesin Gas or PLTMG)

Location Lauran Village in Tanimbar Selatan Sub-district, Maluku Tenggara Barat Regency, Maluku Province

Indonesian Environmental Permitting Category

UKL-UPL

ADB Project Category B

Implementing Agency (Proponent)

PT. PLN (Persero) Unit Induk Pembangunan Maluku

Compiler/Consultant PT. PLN (Persero) Unit Induk Pembangunan Maluku

Environmental Permit No information has been provided by PLN regarding permit issuance status.

No Key Elements

(ADB SPS 2009, Pages 41 – 43, except Parts A

and B)

Findings on Compliance and Quality of Data and Analysis

A Institutional Capacity

1 Institutional Structure PT. PLN (Persero) UIP Maluku, based in Ambon, is the project proponent. The UIP comprises several units, among which environmental safeguards responsibilities are as follows:

- Planning Unit is responsible for preparing, implementing, and evaluating environmental assessments and environmental management related to project facilities and land issues

- Construction Operation Unit is responsible for preparing, implementing, and evaluating safety, occupational health, security, and environment program

- Project Implemention Unit is responsible for preparing, managing, and evaluating safety, occupational health, security, and environment program; and preparing, managing, and evaluating corporate social responsibility activities as agreed on with the UIP office

2 Budget At the UIP level, PLN allocates funds for management and monitoring activities. The Maluka UIP prepares an annual detailed plan and budget, covering AMDAL and UKL-UPL preparation, approval of the Environmental Permit, and implementation of implementation of mitigation measures and monitoring requirements. Annual budget allocations depend on the volume and number of proposed activities.

The physical and financial progress of UIP activities are regularly monitored and reported.

3 Human Resources In the PLN organizational structure, one UIP environmental specialist supervises two UPP environmental specialists. UIP and UPP staff receive environmental assessment training in courses covering AMDAL A (basic level training on AMDAL), AMDAL B (preparation of AMDAL documents), AMDAL C (review of AMDAL documents), and preparation of UKL-UPL.

Page 47: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

B Process and Procedures

1 Coherence No determination could be made regarding coherence based on the available information.

2 Transparency No determination could be made regarding transparency based on the available information.

3 Consistency No determination could be made regarding consistency based on the available information.

4 Effectiveness No determination could be made regarding effectiveness based on the available information.

C Output and Outcome

1 Screening and Categorization

MOE Regulation No. 5/2012 on Type of Business and/or Activity Requiring Environmental Impact Assessment provides that only an UKL-UPL is required since the project size is less than 100 MW.

The project is aligned with the local spatial plan based on the recommendation letter No. 670/1663/2015.

2 Scoping Not applicable to UKL-UPL projects. For UKL-UPL, potential impacts and mitigation measures are directly identified and formulated.

3 Project Description The project description details the project components during the pre-construction, construction, and operation phases, and explains the project’s alignment with spatial planning and the permitting process. While some technical specifications and illustrations are included, no information is provided on project activities that may cause adverse environmental and social impacts, including relating to solid waste generation, waste water discharges, and air emissions.

4 Policy, Legal and Administrative Framework

Relevant national laws and regulations are referred to in the UKL-UPL. Additionally, the project alignment with the local spatial plan, and permitting and land acquisition processes are described.

5 Environmental Baseline The requirement to include baseline information in a UPL-UKL is not explicitly stated in MOE Regulation No. 16/2012 and consequently may not be done for UKL-UPL projects. Baseline information is provided in an appendix of the UKL-UPL, supported by survey reports and laboratory results.

6 Analysis of Alternatives There is no discussion of project alternatives the UKL-UPL. The project is the only option considered.

7 Impact and Risk Assessment

The UKL-UPL describes potential environmental and social impacts and corresponding mitigation measures and monitoring for each project phase as follows:

- Pre-construction phase (field survey, land acquisition, and mobilization of workers)

- Construction phase (mobilization and demobilization of equipment and materials, land clearing and consolidation, construction of the main structure and supporting facilities)

- Operation phase (recruitment of operational staff, power plant operation and maintenance)

Page 48: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

8 Environmental Management and Monitoring Plan (EMP)

The UKL-UPL provides information organized in a matrix on mitigation measures and monitoring for potential impacts, covering:

- Impacts (sources, types, and magnitude) - Management plan (form, location, and period of mitigation

measures) - Monitoring plan (forms, location and period of monitoring

measures) - Institutional arrangements for management and monitoring

Mitigation measures and monitoring requirements to be implemented by the project include: ambient air quality and noise, surface water quality, hazardous wastes, fauna and aquatic biota; local employment, community concerns, and public health.

A legally binding statement letter signed by UIP’s Person in Charge (General Manager) reflecting the project proponent’s commitment to fully implement mitigation measures and monitoring is attached to the UKL-UPL.

Based on UKL-UPL, the project requires a permit for temporary storage of hazardous wastes and emissions.

9 Information Disclosure The UKL-UPL does not describe the information disclosure process, instead noting that information dissemination occurred during the project pre-construction phase.

10 Consultation and Participation

The requirement to conduct public consultations is not explicitly stated in MOE Regulation No. 16/2012 and consequently may not be done for UKL-UPL projects. No mention is made in the UKL-UPL of public consultations undertaken.

11 Grievance Redress Mechanism Development

Although there is not an explicit requirement for a grievance mechanism in MOE Regulation No. 16/2012, PLN through its project level office has procedures to receive and follow-up on community complaints.

12 EMP Implementation Project is at pre-construction phase.

13 Monitoring and Reporting Implementation reports are not yet available.

Page 49: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

12. Malingping-Bayah 150 kV Power Transmission Lines and Tower Project

Project name Malingping-Bayah 150 kV Power Transmission Lines and Tower

Location Malingping, Cihara, Panggarangan and Bayah Sub-districts, in Lebak Regency, Banten Province

Indonesian Environmental Permitting Category

UKL-UPL

ADB Project Category B

Implementing Agency (Proponent)

PT. PLN (Persero) Unit Induk Pembangunan Sumatra – Java Interconnection

Compiler/Consultant PLN (Persero) UIP ISJ with expert support from Lembaga Teknologi FTUI

Environmental Permit Head of BLH Decree No. 660/IL/048/BLH/XI/2016

No. Key Elements

(ADB SPS 2009, Pages 41 – 43, except Parts A and

B)

Findings on Compliance and Quality of Data and Analysis

A. Institutional Capacity

1 Institutional Structure PT. PLN (Persero) UIP Sumatra, based in Jakarta, is the project proponent. The UIP comprises several units, among which environmental safeguards responsibilities are as follows:

- Planning Unit is responsible for preparing, implementing, and evaluating environmental assessments and environmental management related to project facilities and land issues

- Construction Operation Unit is responsible for preparing, implementing, and evaluating safety, occupational health, security, and environment program

- Project Implemention Unit is responsible for preparing, managing, and evaluating safety, occupational health, security, and environment program; and preparing, managing, and evaluating corporate social responsibility activities as agreed on with the UIP office

2 Budget At the UIP level, PLN allocates funds for management and monitoring activities. The Maluka UIP prepares an annual detailed plan and budget, covering AMDAL and UKL-UPL preparation, approval of the Environmental Permit, and implementation of mitigation measures and monitoring requirements. Annual budget allocations depend on the volume and number of proposed activities.

The physical and financial progress of UIP activities are regularly monitored and reported.

3 Human Resources In the PLN organizational structure, one UIP environmental specialist supervises two UPP environmental specialists. UIP and UPP staff receive environmental assessment training in courses covering AMDAL A (basic level training on AMDAL), AMDAL B (preparation of AMDAL documents), AMDAL C (review of AMDAL documents), and preparation of UKL-UPL.

Page 50: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

B Process and Procedures

1 Coherence No determination could be made regarding coherence based on the available information.

2 Transparency No determination could be made regarding transparency based on the available information.

3 Consistency No determination could be made regarding consistency based on the available information.

4 Effectiveness No determination could be made regarding effectiveness based on the available information.

C Output and Outcome

1 Screening and Categorization

MOE Regulation No. 5/2012 on Type of Business and/or Activity Requiring Environmental Impact Assessment provides that only an UKL-UPL is required since the transmission line is less than 150 kV.

2 Scoping Not applicable to UKL-UPL projects. For UKL-UPL, potential impacts and mitigation measures are directly identified and formulated.

3 Project Description The project description covers alignment with the regional spatial plan, existing activities in the project area, and design parameters. Additionally, details are provided by project phase as follows:

- Pre-construction phase (permitting process, survey, land acquisition, and information dissemination)

- Construction phase (worker recruitment, mobilization and demobilization of equipment and materials, construction of high voltage transmission line, and commissioning)

- Operation phase (distribution of power and maintenance of SUTT)

A project schedule is also provided in the UKL-UPL to detail the project timeframe, and corresponding timing of management actions.

4 Policy, Legal and Administrative Framework

Relevant national laws and regulations are referred to in the UKL-UPL, including those stipulated by MEMR and PLN. Additionally, the spatial planning alignment and land acquisition process are described.

5 Environmental Baseline Although baseline conditions are not described in the main report, two appendices provide baseline information on:

- Climate, noise, road classification, ambient air quality (dust), geography, hydrology, and land use

- Biological component (flora and fauna) - Socio-economic and cultural components (demographics,

education, profile of respondents, community perceptions, and public health)

The baseline information is supported by laboratory results of environmental sampling by an accredited laboratory. Information on socieconomic-cultural aspects is supported by questionnaire results.

Page 51: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

6 Analysis of Alternatives There is no discussion of project alternatives. For UKL-UPL projects alternatives are typically considered prior to preparation of the environmental assessment during technical and economic feasibility studies.

7 Impact and Risk Assessment

The UKL-UPL describes potential environmental and social impacts and corresponding mitigation measures and monitoring. The impact assessment covers:

- Pre-construction phase (field survey, land acquisition, and mobilization of workers)

- Construction phase (mobilization and demobilization of equipment and materials, land clearing and consolidation, construction of themain structure and supporting facilities)

- Operation phase (recruitment of operational staff, operation of the transmission line, and maintenance of the transmission line)

8 Environmental Management and Monitoring Plan (EMP)

The UKL-UPL provides information on mitigation measures and monitoring for potential impacts, covering:

- Source of impact - Type of impact - Magnitude of impact - Mitigation measures, location, and period of mitigation - Environmental monitoring, location, and period of monitoring - Institutional arrangements for management and monitoring

The UKL-UPL contains a summary matrix to facilitate understanding of mitigation and monitoring plans.

9 Information Disclosure The requirement to conduct public consultations is not explicitly stated in MOE Regulation No. 16/2012 and consequently may not be done for UKL-UPL projects. Although no information is provided in the UKL-UPL, during the pre-construction phase, the project proponent carried out information dissemination to inform the local community that their lands could potentially be affected by the project, and to explain the mitigation measures to be undertaken.

10 Consultation and Participation

The requirement to conduct public consultations is not explicitly stated in MOE Regulation No. 16/2012 and consequently is generally not done for UKL-UPL projects. A public consultation was however carried out as part of UKL-UPL preparation. Some women attended the consultation meeting. Additionally, social surveys using a questionnaire were also undertaken to acquire information on the community profile and perceptions about the project.

11 Grievance Redress Mechanism Development

Although there is not an explicit requirement for a grievance mechanism in MOE Regulation No. 16/2012, PLN through its project level office has procedures to receive and follow-up on community complaints.

12 EMP Implementation Project is at construction phase.

13 Monitoring and Reporting Implementation reports are not yet available.

Page 52: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

13. Malifut Peaker 5 MW Gas/Fuel Fired Power Plant Project

Project Name Malifut Peaker 5 MW Gas/Fuel Fired Power Plant

Location Halmahera Utara Regency, North Maluku Province

Indonesian Enviromental Permitting Category

UKL-UPL

ADB Project Category B

Implementing Agency (Proponent)

PLN (Persero) UIP Maluku, Kantor Induk

Compiler/Consultant Environmental and Disaster Mitigation Center (Kampus Akehuda, Jalan Bandara Babullah, Ternate)

Environmental Permit No information has been provided by PLN regarding permit issuance status.

No Key Elements

(ADB SPS 2009, Pages 41 – 43, except Parts A

and B)

Findings on Compliance and Quality of Data and Analysis

A Institutional Capacity

1 Institutional Structure PT. PLN (Persero) UIP Maluku, based in Ternate, is the project proponent. The UIP comprises several units, among which environmental safeguards responsibilities are as follows:

- Planning Unit is responsible for preparing, implementing, and evaluating environmental assessments and environmental management related to project facilities and land issues

- Construction Operation Unit is responsible for preparing, implementing, and evaluating safety, occupational health, security, and environment program

- Project Implemention Unit is responsible for preparing, managing, and evaluating safety, occupational health, security, and environment program; and preparing, managing, and evaluating corporate social responsibility activities as agreed on with the UIP office

2 Budget At the UIP level, PLN allocates funds for management and monitoring activities. The Maluka UIP prepares an annual detailed plan and budget, covering AMDAL and UKL-UPL preparation, approval of the Environmental Permit, and implementation of mitigation measures and monitoring requirements. Annual budget allocations depend on the volume and number of proposed activities.

The physical and financial progress of UIP activities are regularly monitored and reported.

3 Human Resources In the PLN organizational structure, one UIP environmental specialist supervises two UPP environmental specialists. UIP and UPP staff receive environmental assessment training in courses covering AMDAL A (basic level training on AMDAL), AMDAL B

Page 53: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

No Key Elements

(ADB SPS 2009, Pages 41 – 43, except Parts A

and B)

Findings on Compliance and Quality of Data and Analysis

(preparation of AMDAL documents), AMDAL C (review of AMDAL documents), and preparation of UKL-UPL.

B Process and Procedures

1 Coherence No determination could be made regarding coherence based on the available information.

2 Transparency No determination could be made regarding transparency based on the available information.

3 Consistency No determination could be made regarding consistency based on the available information.

4 Effectiveness No determination could be made regarding effectiveness based on the available information.

C Output and Outcome

1 Screening and Categorization

MOE Regulation No. 5/2012 on Type of Business and/or Activity Requiring Environmental Impact Assessment provides that only an UKL-UPL is required since the project size is less than 100 MW.

The project is aligned with the local spatial plan, as documented in Bappeda of Halmahera Utara Regency Letter No. 050/101/Bapp (dated 28 Dec 2015).

2 Scoping Not applicable to UKL-UPL projects.

3 Project Description The project description covers the project location, scale, size, and details the project components during the project phases as follows:

- Pre-construction (survey, information dissemination, and land acquisition)

- Construction (worker recruitment, land clearing, mobilization of materials, construction of project infrastructure)

- Operation (worker recruitment, power plant operation, air emission control, maintenance)

- Post-operation (worker demobilization, equipment dismantling, site remediation)

4 Policy, Legal and Administrative Framework

Relevant national laws and regulations are referred to in the UKL-UPL, including those stipulated by MEMR and PLN.

5 Environmental Baseline The requirement to include baseline information in a UPL-UKL is not explicitly stated in MOE Regulation No. 16/2012 and consequently may not be done for UKL-UPL projects. The UKL-UPL however provides information on the initial environmental setting in the main document, covering:

- Location and accessibility (administrative boundaries and accessibility)

- Physical-chemical component (climate, ambient air quality and noise, topography, hydrology, groundwater quality, geology and geomorphology, soil characteristics and nutrient status, and land use)

- Biological component (flora and fauna) supported with survey photographs

Page 54: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

No Key Elements

(ADB SPS 2009, Pages 41 – 43, except Parts A

and B)

Findings on Compliance and Quality of Data and Analysis

- Social, economic, and cultural component (demographics, occupation, income, education facilities, electricity utility, safety)

- Public health component (disease distribution, sanitation, waste disposal, and community perceptions)

The baseline information is supported by laboratory analysis.

While the baseline information is quite extensive, it does not appear to be fully used in the impact assessment.

6 Analysis of Alternatives There is no discussion on alternative analysis in the UKL-UPL.

7 Impact and Risk Assessment

The UKL-UPL describes potential environmental and social impacts and corresponding mitigation measures and monitoring for each project phase as follows:

- Pre-construction phase (field survey, land acquisition) - Construction phase (mobilization of equipment, land clearing

and consolidation, mobilization of materials, construction of infrastructure and supporting facilities, construction of the main structure, mobilization and release of workers)

- Operation phase (recruitment of operational staff, power plant operation, operation of air emission controls, and power plant maintenance)

- Post-operation phase (worker demobilization, dismantling infrastructure and supporting facilities, and revegetation)

8 Environmental Management and Monitoring Plan (EMP)

The UKL-UPL provides information organized in a matrix on mitigation measures and monitoring for potential impacts, covering:

- Type and source of impacts - Performance indicators - Management objectives - Proposed mitigation measures and monitoring - Monitoring parameters - Location and period of mitigations and monitoring - Institutional arrangements for management. (implementer,

supervisor, and recipient of reports)

Specifically for hazardous wastes, the UKL-UPL specifies the following:

- Permit for temporary storage of hazardous wastes - Permit for transport of hazardous wastes - Permit for utilization of hazardous wastes - Permit for treatment of hazardous wastes

The UKL-UPL covers mitigation measures and monitoring requirements to be implemented by the project, including: ambient air quality and noise, surface water quality, fauna and aquatic biota, hazardous wastes, local employment, community concerns, and public health.

A legally binding statement letter signed by UIP’s Person in Charge (General Manager) reflecting the project proponent’s commitment to fully implement mitigation measures and monitoring is attached to the UKL-UPL.

Page 55: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

No Key Elements

(ADB SPS 2009, Pages 41 – 43, except Parts A

and B)

Findings on Compliance and Quality of Data and Analysis

9 Information Disclosure The UKL-UPL does not describe the information disclosure process, instead noting that information dissemination occurred during the project pre-construction phase.

10 Consultation and Participation

The requirement to conduct public consultations is not explicitly stated in MOE Regulation No. 16/2012 and consequently may not be done for UKL-UPL projects. No mention is made in the UKL-UPL of public consultations undertaken.

11 Grievance Redress Mechanism Development

Although there is not an explicit requirement for a grievance mechanism in MOE Regulation No. 16/2012, PLN through its project level office has procedures to receive and follow-up on community complaints.

12 EMP Implementation Project is at pre-construction phase.

13 Monitoring and Reporting Implementation reports are not yet available.

Page 56: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

14. Sofifi 10 MW Gas/Fuel Fired Mobile Power Plant Project

Project Name Sofifi 10 MW Gas/Fuel Fired Mobile Power Plant

Location Tidore Kepulauan Municipality, North Maluku Province

Indonesian Environmental Permitting Category

UKL-UPL

ADB Project Category B

Implementing Agency (Proponent)

PT. PLN (Persero) Unit Induk Pembangunan (UIP) Maluku

Compiler/Consultant Environmental and Disaster Mitigation Center (Kampus Akehuda Jalan Bandara Babullah, Ternate)

Environmental Permit No information has been provided by PLN regarding permit issuance status.

No

Key Elements

(ADB SPS 2009, Pages 41 – 43, except Parts A

and B)

Findings on Compliance and Quality of Data and Analysis

A Institutional Capacity

1 Institutional Structure PT. PLN (Persero) UIP Maluku, based in Ternate, is the project proponent. The UIP comprises several units, among which environmental safeguards responsibilities are as follows:

- Planning Unit is responsible for preparing, implementing, and evaluating environmental assessments and environmental management related to project facilities and land issues

- Construction Operation Unit is responsible for preparing, implementing, and evaluating safety, occupational health, security, and environment program

- Project Implemention Unit is responsible for preparing, managing, and evaluating safety, occupational health, security, and environment program; and preparing, managing, and evaluating corporate social responsibility activities as agreed on with the UIP office

2 Budget At the UIP level, PLN allocates funds for management and monitoring activities. The Maluka UIP prepares an annual detailed plan and budget, covering AMDAL and UKL-UPL preparation, approval of the Environmental Permit, and implementation of mitigation measures and monitoring requirements. Annual budget allocations depend on the volume and number of proposed activities.

The physical and financial progress of UIP activities are regularly monitored and reported.

3 Human Resources In the PLN organizational structure, one UIP environmental specialist supervises two UPP environmental specialists. UIP and UPP staff receive environmental assessment training in courses covering AMDAL A (basic level training on AMDAL), AMDAL B (preparation of AMDAL documents), AMDAL C (review of AMDAL documents), and preparation of UKL-UPL.

Page 57: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

B Process and Procedures

1 Coherence No determination could be made regarding coherence based on the available information.

2 Transparency No determination could be made regarding transparency based on the available information.

3 Consistency No determination could be made regarding consistency based on the available information.

4 Effectiveness No determination could be made regarding effectiveness based on the available information.

C Output and Outcome

1 Screening and Categorization

MOE Regulation No. 5/2012 on Type of Business and/or Activity Requiring Environmental Impact Assessment provides that only an UKL-UPL is required since the project size is less than 100 MW.

The project is aligned with the local spatial plan as stipulated in Decree No. 050/149/17/2015 from Bappeda Kota Tidore Kepulauan.

2 Scoping Not applicable to UKL-UPL projects.

3 Project Description The project description covers the project location, scale, size, and details the project components during the project phases as follows:

- Pre-construction (survey, information dissemination, and land acquisition)

- Construction (worker recruitment, land clearing, mobilization of materials, construction of project infrastructure)

- Operation (worker recruitment, power plant operation, air emission control, power plant maintenance)

- Post-operation (worker demobilization, equipment dismantling, site remediation)

4 Policy, Legal and Administrative Framework

Relevant national laws and regulations are referred to in the UKL-UPL, including those stipulated by MEMR and PLN.

5 Environmental Baseline The requirement to include baseline information in a UPL-UKL is not explicitly stated in MOE Regulation No. 16/2012 and consequently may not be done for UKL-UPL projects. The UKL-UPL however provides information on:

- Location and accessibility (administrative boundaries and accessibility)

- Physical-chemical component (climate, ambient air quality and noise, topography, hydrology, groundwater quality, geology and geomorphology, soil characteristics and nutrient status, and land use)

- Biological component (flora and fauna) supported with survey photographs

- Social, economic, and cultural component (demographics, occupation, income, education facilities, electricity utility, safety)

- Public health component (disease distribution,sanitation, waste disposal, and community perceptions)

The baseline information is supported by laboratory analysis.

6 Analysis of Alternatives There is no discussion on alternative analysis in the UKL-UPL.

Page 58: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

7 Impact and Risk Assessment

The UKL-UPL describes potential environmental and social impacts and corresponding mitigation measures and monitoring for each project phase as follows:

- Pre-construction phase (field survey and land acquisition) - Construction phase (mobilization and demobilization of equipment

and materials, land clearing and consolidation, construction of the main structure and supporting facilities, and mobilization and release of workers)

- Operation phase (recruitment of operational staff, power plant operation, operation of air emission controls, and power plant maintenance)

- Post-operation phase (worker demobilization, dismantling infrastructure and supporting facilities, and revegetation)

8 Environmental Management and Monitoring Plan (EMP)

The UKL-UPL provides information organized in a matrix on mitigation measures and monitoring for potential impacts, covering:

- Type and source of impacts - Performance indicators - Management objectives - Proposed mitigation measures and monitoring - Monitoring parameters - Location and period of mitigations and monitoring - Institutional arrangements for management. (implementer,

supervisor, and recipient of reports)

The UKL-UPL covers mitigation measures and monitoring requirements to be implemented by the project, including: ambient air quality and noise, surface water quality, fauna and aquatic biota, hazardous wastes, local employment, community concerns, and public health.

A legally binding statement letter signed by UIP’s Person in Charge (General Manager) reflecting the project proponent’s commitment to fully implement mitigation measures and monitoring is attached to the UKL-UPL.

9 Information Disclosure Information dissemination was undertaken, targeting the surrounding community, government apparatus of Kecamatan (sub-district), Kelurahan/Desa (village) and community leaders who articulated the community aspirations and perceptions about the project. Feedback provided by participants was recorded and documented.

10 Consultation and Participation

The requirement to conduct public consultations is not explicitly stated in MOE Regulation No. 16/2012 and consequently may not be done for UKL-UPL projects. Public consultation appears to have been limited to discussions which occurred during information disclosure.

11 Grievance Redress Mechanism Development

Although there is not an explicit requirement for a grievance mechanism in MOE Regulation No. 16/2012, PLN through its project level office has procedures to receive and follow-up on community complaints.

12 EMP Implementation Project is at pre-construction phase.

13 Monitoring and Reporting

Implementation reports are not yet available.

Page 59: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

15. Namrole 10 MW Gas/Fuel Fired Power Plant Project

Project Name Namrole 10 MW Gas/Fuel Fired Power Plant

Location Buru Selatan Regency, Maluku Province

Indonesian Environmental Permitting Category

UKL-UPL

ADB Project Category B

Implementing Agency (Proponent)

PLN (Persero) UIP Maluku

Compiler/Consultant PT. Surveyor Indonesia, Makassar branch

Environmental Permit - UKL-UPL approval letter No. 66.1/97/DLH-KBS/VI/2017 (dated 13 June 2017) issued by the Environmental Agency of Buru Selatan Regency

- Environmental Permit No. 66.1/95/DLH-KBS/VI/2017 (dated 14 June 2017) issued by the Environmental Agency of Buru Selatan Regency

No

Key Elements

(ADB SPS 2009, Pages 41 – 43, except Parts A

and B)

Findings on Compliance and Quality of Data and Analysis

A Institutional Capacity

1 Institutional Structure PT. PLN (Persero) UIP Maluku, based in Ambon, is the project proponent. The UIP comprises several units, among which environmental safeguards responsibilities are as follows:

- Planning Unit is responsible for preparing, implementing, and evaluating environmental assessments and environmental management related to project facilities and land issues

- Construction Operation Unit is responsible for preparing, implementing, and evaluating safety, occupational health, security, and environment program

- Project Implemention Unit is responsible for preparing, managing, and evaluating safety, occupational health, security, and environment program; and preparing, managing, and evaluating corporate social responsibility activities as agreed on with the UIP office

2 Budget At the UIP level, PLN allocates funds for management and monitoring activities. The Maluka UIP prepares an annual detailed plan and budget, covering AMDAL and UKL-UPL preparation, approval of the Environmental Permit, and implementation of mitigation measures and monitoring requirements. Annual budget allocations depend on the volume and number of proposed activities.

The physical and financial progress of UIP activities are regularly monitored and reported.

3 Human Resources In the PLN organizational structure, one UIP environmental specialist supervises two UPP environmental specialists. UIP and UPP staff receive environmental assessment training in courses covering AMDAL A (basic level training on AMDAL), AMDAL B

Page 60: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

(preparation of AMDAL documents), AMDAL C (review of AMDAL documents), and preparation of UKL-UPL.

B Process and Procedures

1 Coherence No determination could be made regarding coherence based on the available information.

2 Transparency No determination could be made regarding transparency based on the available information.

3 Consistency No determination could be made regarding consistency based on the available information.

4 Effectiveness No determination could be made regarding effectiveness based on the available information.

C Output and Outcome

1 Screening and Categorization

MOE Regulation No. 5/2012 on Type of Business and/or Activity Requiring Environmental Impact Assessment provides that only an UKL-UPL is required since the project size is less than 100 MW.

The project is aligned with the spatial plan as confirmed in Statement Letter No. 670.11/597 on Recommendation on Compliance of Regional Spatial Plan (RTRW) Kabupaten Buru Selatan.

2 Scoping Not applicable to UKL-UPL projects.

3 Project Description The project description details the:

- Project location - Project scale - Project activities - Project components The project description also details capacity design, supporting systems, technical specifications, alignment with the spatial plan, and work distribution during the pre-construction, construction, and operation phases.

4 Policy, Legal and Administrative Framework

The requirement to include a summary of applicable laws and regulations in a UPL-UKL is not explicitly stated in MOE Regulation No. 16/2012 and consequently may not be done for UKL-UPL projects. This UKL-UPL provides no information on this topic.

5 Environmental Baseline The requirement to include baseline information in a UPL-UKL is not explicitly stated in MOE Regulation No. 16/2012 and consequently may not be done for UKL-UPL projects. Although some photo documentation of the existing site, and laboratory analytical results are provided in appendices, no information is included on environmental baseline conditions thereby complicating impact identification.

6 Analysis of Alternatives Although there is no discussion on alternative analysis in the UKL-UPL, reference is made to a Feasibility Study prepared in 2017 which considered technical alternatives.

7 Impact and Risk Assessment

The UKL-UPL describes potential environmental and social impacts and corresponding mitigation measures and monitoring for each project phase as follows:

- Pre-construction phase (field survey, land acquisition, and

Page 61: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

mobilization of workers) - Construction phase (mobilization and demobilization of

equipment and materials, land clearing and consolidation, construction of the main structure and supporting facilities)

- Operation phase (recruitment of operational staff, power plant operation, and power plant maintenance)

Each potential impact is discussed according to impact source, type of impact, magnitude, and the extent to which impacts can be avoided or minimized.

8 Environmental Management and Monitoring Plan (EMP)

The UKL-UPL provides information on mitigation measures and monitoring for potential impacts, covering:

a) Project impacts - Source of impact - Type of impact - Magnitude of impact

b) Mitigation measures - Type of mitigation measures - Location of mitigation measures - Period of mitigation measures

c) Monitoring plan - Type of of monitoring - Location of monitoring - Period of monitoring

d) Institutional arrangements for management and monitoring (implementer, supervisor, and recipient of reports)

Mitigation measures and monitoring requirements to be implemented by the project encompass: ambient air quality and noise, surface water quality, hazardous wastes, fauna and aquatic biota, local employment, community concerns, and public health. The UKL-UPL recommends that the project reduce fly ash and pollutant emissions by using a de-nitrogen oxide and electrostatic precipitator.

The UKL-UPL also describes required environmental protection and management permits that may apply to a project. It states that PLTMG Namrole only requires a permit for the temporary storage of hazardous wastes prior to being handed over to a third party for treatment.

A legally binding statement letter signed by UIP’s Person in Charge (General Manager) reflecting the project proponent’s commitment to fully implement mitigation measures and monitoring is attached to the UKL-UPL.

9 Information Disclosure The UKL-UPL does not describe the information disclosure process. No information is provided on this element for review.

10 Consultation and Participation

The requirement to conduct public consultations is not explicitly stated in MOE Regulation No. 16/2012 and consequently is generally not done for UKL-UPL projects. No mention is made in the UKL-UPL of public consultations undertaken.

11 Grievance Redress Mechanism Development

Although there is not an explicit requirement for a grievance mechanism in MOE Regulation No. 16/2012, PLN through its project level office has procedures to receive and follow-up on community complaints.

Page 62: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

12 EMP Implementation Project is at pre-construction phase.

13 Monitoring and Reporting Implementation reports are not yet available.

Page 63: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

16. Ternate 30 MW Gas/Fuel-Fired Mobile Power Plant Project

Project Name Ternate 30 MW Gas- and Fuel-Fired Mobile Power Plant

Location Ternate City, Maluku Utara Province

Indonesian Environmental Permitting Category

UKL-UPL

ADB Project Category B

Implementing Agency (Proponent)

PT. PLN (Persero) Unit Induk Pembangunan (UIP) Maluku

Compiler/Consultant Environmental and Disaster Mitigation Center of Kampus Akehuda, Khairun University, Ternate.

Environmental Permit No information has been provided by PLN regarding permit issuance status.

No

Key Elements

(ADB SPS 2009, Pages 41 – 43, except Parts A

and B)

Findings on Compliance and Quality of Data and Analysis

A Institutional Capacity

1 Institutional Structure PT. PLN (Persero) UIP Maluku, based in Ambon, is the project proponent. The UIP comprises several units, among which environmental safeguards responsibilities are as follows:

- Planning Unit is responsible for preparing, implementing, and evaluating environmental assessments and environmental management related to project facilities and land issues

- Construction Operation Unit is responsible for preparing, implementing, and evaluating safety, occupational health, security, and environment program

- Project Implemention Unit is responsible for preparing, managing, and evaluating safety, occupational health, security, and environment program; and preparing, managing, and evaluating corporate social responsibility activities as agreed on with the UIP office

2 Budget At the UIP level, PLN allocates funds for management and monitoring activities. The Maluka UIP prepares an annual detailed plan and budget, covering AMDAL and UKL-UPL preparation, approval of the Environmental Permit, and implementation of mitigation measures and monitoring requirements. Annual budget allocations depend on the volume and number of proposed activities.

The physical and financial progress of UIP activities are regularly monitored and reported.

3 Human Resources In the PLN organizational structure, one UIP environmental specialist supervises two UPP environmental specialists. UIP and UPP staff receive environmental assessment training in courses covering AMDAL A (basic level training on AMDAL), AMDAL B (preparation of AMDAL documents), AMDAL C (review of AMDAL documents), and preparation of UKL-UPL.

Page 64: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

B Process and Procedures

1 Coherence No determination could be made regarding coherence based on the available information.

2 Transparency No determination could be made regarding transparency based on the available information.

3 Consistency No determination could be made regarding consistency based on the available information.

4 Effectiveness No determination could be made regarding effectiveness based on the available information.

C Output and Outcome

1 Screening and Categorization

MOE Regulation No. 5/2012 on Type of Business and/or Activity Requiring Environmental Impact Assessment provides that only an UKL-UPL is required since the project size is less than 100 MW.

2 Scoping Not applicable to UKL-UPL projects.

3 Project Description The project description explains the project location, scale, size, and details the project phases as follows:

- Pre-construction phase (field survey, information dissemination, and land acquisition)

- Construction phase (mobilization of equipment, land clearing and consolidation, procurement of materials, construction of infrastructure and facilities and recruitment of workers)

- Operation phase (staff recruitment, power plant operation, air emission control, and power plant maintenance)

- Post-operation phase (demobilization of staff, demolition of infrastructure and facilities, maintenance, and revegetation)

4 Policy, Legal and Administrative Framework

Relevant national laws and regulations are referred to in the UKL-UPL, although some are obsolete.

5 Environmental Baseline Comprehensive baseline information is provided in the UKL-UPL, starting with a description of the administrative boundaries and then providing a detailed description of:

- Physical-chemical component (climate, air quality and noise, topography, hydrology, groundwater and marine water quality, geology and geomorphology, land type and nutrient status, and land use)

- Biological component (flora and fauna) supported by survey photographs

- Social, economic and cultural component (demographics, occupation, income level, education facilities, security)

- Public health component (disease distribution, sanitation, waste disposal, and community perceptions)

The baseline information is supported by laboratory analytical results and photo documentation.

6 Analysis of Alternatives There is no discussion on alternative analysis in the UKL-UPL.

7 Impact and Risk Assessment

The UKL-UPL describes potential environmental and social impacts and corresponding mitigation measures and monitoring for each project phase as follows:

- Pre-construction phase (field survey, land acquisition, and

Page 65: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

mobilization of workers) - Construction phase (mobilization and demobilization of

equipment and materials, land clearing and consolidation, construction of the main structure and supporting facilities)

- Operation phase (recruitment of operational staff, power plant operation and maintenance)

- Post-operation phase (worker demobilization, dismantling infrastructure and supporting facilities, and revegetation)

8 Environmental Management and Monitoring Plan (EMP)

The UKL-UPL provides information organized in a matrix on mitigation measures and monitoring for potential impacts, covering:

- Type and source of impacts - Performance indicators - Management objectives - Proposed mitigation measures and monitoring - Monitoring parameters - Location and period of mitigations and monitoring - Institutional arrangements for management (implementer,

supervisor, and recipient of reports)

The UKL-UPL comprehensively covers mitigation measures and monitoring as well as reporting requirements for the following:

- Ambient air quality and noise - Erosion and sedimentation - Coastal water quality - Flora and fauna - Coastal biota - Disturbance to road access - Community concerns and perceptions - Local employment and business opportunities - Potential for community conflict - Public health

The UKL-UPL recommends that the project reduce fly ash and pollutant emissions by using a de-nitrogen oxide and electrostatic precipitator.

A legally binding statement letter signed by UIP’s Person in Charge (General Manager) reflecting the project proponent’s commitment to fully implement mitigation measures and monitoring is attached to the UKL-UPL.

9 Information Disclosure The UKL-UPL does not describe the information disclosure process.

10 Consultation and Participation

The requirement to conduct public consultations is not explicitly stated in MOE Regulation No. 16/2012 and consequently may not be done for UKL-UPL projects. No mention is made in the UKL-UPL of public consultations undertaken.

11 Grievance Redress Mechanism Development

Although there is not an explicit requirement for a grievance mechanism in MOE Regulation No. 16/2012, PLN through its project level office has procedures to receive and follow-up on community complaints.

12 EMP Implementation Project is at construction phase.

13 Monitoring and Reporting Implementation reports are not yet available.

Page 66: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

17. Muara Karang 500 MW Gas/Coal-Fired Power Plant Expansion (Peaker) Project

Project Name Muara Karang 500 MW Gas//Coal-Fired Power Plant Expansion (Peaker), known as pembangkit listrik tenaga gas dan uap (PLTGU)

Location DKI Jakarta

Indonesian Environmental Permitting Category

ANDAL and RKL-RPL addendum

ADB Project Category A

Implementing Agency (Proponent)

PLN (Persero) UIP V

Compiler/Consultant PT. Surveyor Indonesia (Registration: 0040/LPJ/AMDAL-1/LRK/KLH)

Environmental Permit Ref. No. 92/7.1/31/-1.774.1/20160

No

Key Elements

(ADB SPS 2009, Pages 41 – 43, except Parts A

and B)

Findings on Compliance and Quality of Data and Analysis

A Institutional Capacity

1 Institutional Structure PLN (Persero) UIP V is the project proponent responsible for the construction phase of the project, whereas PT PJB UP Muara Karang will be responsible for its operation.

The UIP comprises several units, among which environmental safeguards responsibilities are as follows:

- Planning Unit is responsible for preparing, implementing, and evaluating environmental assessments and environmental management related to project facilities and land issues

- Construction Operation Unit is responsible for preparing, implementing, and evaluating safety, occupational health, security, and environment program

- Project Implemention Unit is responsible for preparing, managing, and evaluating safety, occupational health, security, and environment program; and preparing, managing, and evaluating corporate social responsibility activities

2 Budget At the UIP level, PLN allocates funds for management and monitoring activities. The Maluka UIP prepares an annual detailed plan and budget, covering AMDAL and UKL-UPL preparation, approval of the Environmental Permit, and implementation of mitigation measures and monitoring requirements. Annual budget allocations depend on the volume and number of proposed activities.

The physical and financial progress of UIP activities are regularly monitored and reported.

3 Human Resources In the PLN organizational structure, one UIP environmental specialist supervises two UPP environmental specialists. UIP and UPP staff receive environmental assessment training in courses covering AMDAL A (basic level training on AMDAL), AMDAL B (preparation of AMDAL documents), AMDAL C (review of AMDAL documents), and preparation of UKL-UPL.

Page 67: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

B Process and Procedures

1 Coherence Based on desk study, it was concluded that preparation of the ANDAL and RKL-RPL was in accordance with the prescribed processes and procedures for an AMDAL extension project and adhered to the direction of the Environmental Agency of DKI Jakarta Province (Ref: Letter No. 28/Andal/-1.774.151 dated 30 May 2011 on Recommendation for Updating of ANDAL and RKL-RPL of Power Plant Project of PT Pembangkitan Jawa Bali UP Muara Karang).

2 Transparency According to the government Regulation No. 27/2012 on Environmental Permitting, no public notification of consultation is required for ANDAL addendum projects. However, PLTGU Muara Karang did inform local communities about the extension project during an information dissemination meeting.

Community representatives and government stakeholders were additionally involved in the evaluation of the ANDAL and RKP-RKL.

3 Consistency Based on desk study, it was concluded that preparation of the ANDAL and RKL-RPL for this extension project was consistent with prescribed processes and procedures as set out in government Regulation No. 27/2012 on Environmental Permitting.

The ANDAL addendum focuses on the assessment of potentially significant environmental and social impacts of the extension project. Based on the outcomes of the impact assessment, the RKL-RPL defines mitigation measures for the significant impacts and corresponding monitoring requirements. Moreover, for those impacts that are considered insignificant but which could be of concern if not properly managed, mitigation measures and monitoring are also defined in the RKL-RPL.

4 Effectiveness The ANDAL addendum process undertaken for the extension project is considered effective with regards to focusing the assessment on potentially significant environmental and social impacts. Notwithstanding the limited engagement of community and government stakeholders, feedback provided was beneficial in identifying effective mitigating measures and monitoring requirements to be included in the RKL-RPL.

C Output and Outcome

1 Screening and Categorization

This AMDAL has already been subject to revision. The original AMDAL for the Muara Karang Power Plant was produced in 1993 and was subsequently updated in 2011 to accommodate changes in the design and increased capacity of the power plant.

The ANDAL and RKL-RPL addendum for the new extension project was completed in compliance with government Regulation No. 27/2012 on Environmental Permitting.

2 Scoping A limited scoping process, including conduct of a baseline survey, was completed according to requirements set out in government Regulation No. 27/2012 on Environmental Permitting.

Potential impacts were identified for each extension project phase as follows:

- Pre-construction phase (information dissemination, backfilling and land preparation)

Page 68: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

- Construction phase (worker recruitment, mobilization of equipment and materials, land preparation, construction of the power plant unit and utilities, and widening of the Muara Karang River intake canal)

- Operation phase (worker recruitment, and power plant operation and maintenance)

3 Project Description The assessment provides a comprehensive description of the project, covering:

- Existing plant operations - Evaluation of activities - Land clearing - Construction of the plant extension including equipment,

installation of piping system, and the operational plan (procurement of natural gas, combustion system and exhaust gas, cooling system, and power plant system)

- Construction of supporting facilities, including installation of the new gas pipeline and widening of the water intake canal

4 Policy, Legal and Administrative Framework

A detailed description of the legal framework, consisting of key laws and regulations is included in the addendum document.

5 Environmental Baseline The ANDAL addendum provides baseline information on:

a) Physical-chemical component - Climate type, rainfall, wind, humidity, solar exposure, and

air temperature - Air quality and noise - Land topography - Water level at intake canal - Bathymetry - Tides - Marine current

b) Biological component - Aquatic biota

c) Geography and demography

In addition, the addedum provides an evaluation of management and monitoring at the existing power plant for the following aspects:

- Ambient air quality - Noise generated from operation of equipment - Marine water quality due to increasing water temperature and

introduction of pollutants - Public perceptions

6 Analysis of Alternatives The ANDAL addendum only describes the already determined final design and configuration of the extension project.

7 Impact and Risk Assessment

The ANDAL addendum provides a comprehensive assessment of both environmental and social impacts and risks for the extension project. The assessment was undertaken using a combination of professional judgement, mathematical modelling, and a semi-quantitative analysis.

Consideration was given to:

- Comparison of environmental quality with and without the extension project

- Impacts to biodiversity were assessed by a special study and inventory in the surrounding areas carried out by the Faculty of

Page 69: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

Forestry, Bogor Agricultural University - Calculation of carbon dioxide sequestration in private

conservation areas of PT PJB UP Muara Karang

8 Environmental Management and Monitoring Plan (EMP)

The RKL-RPL details mitigation measures and monitoring requirements for the extension project, including:

- Technological approaches for pollution prevention (use of technology such as low nitrogen oxide burner to control/reduce emissions during operation, noise control using a building enclosure system with sound proof walls)

- Occupational Health and Safety Management System (integration of environmental management with occupational health and safety management by applying OHSAS 18001)

- Regular emission monitoring and reporting (quarterly monitoring and reporting of manual emission load, continuous emission monitoring system emission load, wastewater discharges)

The RKL-RPL states that some potential impacts are considered manageable, and can be managed effectively. A commitment to this effect is provided in a Statement Letter No. 0449.SPn/KLH.01/UIP V/2016, signed and completed with duty stamp by the General Manager dated 18 April 2016.

9 Information Disclosure Government Regulation No. 27/2012 on Environmental Permitting does not require information disclosure and public consultation for ANDAL and RKL-RPL addendum. The ANDAL addendum describes the limited information dissemination that was undertaken as part of community consultations.

10 Consultation and Participation.

A consultation meeting was held with community members, the head of the neighborhood, and community leaders. Of the fifty participants, less than ten were women.

11 Grievance Redress Mechanism Development

The RKL-RPL addendum does not indicate the existence of a grievance mechanism. However, PLN through its project level office has procedures to receive and follow-up on community complaints.

12 EMP Implementation Project is at construction phase.

13 Monitoring and Reporting Implementation reports are not yet available.

Page 70: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

18. Tanjung Awar-Awar 2 x 150 MW (Unit 3) Coal-Fired Power Plant Project

Project name Tanjung Awar-Awar 2 x 150 MW (Unit 3) Coal-Fired Power Plant Project

Location East Java

Indonesian Environmental Permitting Category

ANDAL and RKL-RPL addendum

ADB Project Category A

Implementing Agency (Proponent)

PT. PLN (Persero) UIP VIII

Compiler/Consultant PT. PLN (Persero) UIP VIII (as the UIP has LPJP /Service Provider for AMDAL preparation)

Environmental Permit Ref. No. 92/7.1/31/-1.774.1/2016

No

Key Elements

(ADB SPS 2009, Pages 41 – 43, except Parts A

and B)

Findings on Compliance and Quality of Data and Analysis

A Institutional Capacity

1 Institutional Structure PT. PLN (Persero) UIP VIII, based in Surabaya, is the project proponent. UIP VIII comprises several units, among which environmental safeguards responsibilities are as follows:

- Planning Unit is responsible for preparing, implementing, and evaluating environmental assessments and environmental management related to project facilities and land issues

- Construction Operation Unit is responsible for preparing, implementing, and evaluating safety, occupational health, security, and environment program

- Project Implemention Unit is responsible for preparing, managing, and evaluating safety, occupational health, security, and environment program; and preparing, managing, and evaluating corporate social responsibility activities as agreed on with the UIP offices

2 Budget At the UIP level, PLN allocates funds for management and monitoring activities. The Maluka UIP prepares an annual detailed plan and budget, covering AMDAL and UKL-UPL preparation, approval of the Environmental Permit, and implementation of mitigation measures and monitoring requirements. Annual budget allocations depend on the volume and number of proposed activities.

The physical and financial progress of UIP activities are regularly monitored and reported.

3 Human Resources In the PLN organizational structure, one UIP environmental specialist supervises two UPP environmental specialists. UIP and UPP staff receive environmental assessment training in courses covering AMDAL A (basic level training on AMDAL), AMDAL B (preparation of AMDAL documents), AMDAL C (review of AMDAL documents), and preparation of UKL-UPL.

Page 71: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

B Process and Procedures

1 Coherence Based on desk study, it was concluded that preparation of the ANDAL and RKL-RPL was in accordance with the prescribed processes and processes for an AMDAL extension project and adhered to the direction of the Regional Environmental Agency of East Java Province to PLTU 3 East Java.

2 Transparency According to the government Regulation No. 27/2012 on Environmental Permitting no public notification of consultation is required for ANDAL addendum projects. However, PLTU 3 East Java did inform local communities about the extension plan during an information dissemination meeting.

3 Consistency Based on desk study, it was concluded that preparation of the ANDAL and RKL-RPL for this extension project was consistent with prescribed processes and procedures as set out in government Regulation No. 27/2012 on Environmental Permitting.

The ANDAL addendum focuses on the assessment of potentially significant environmental and social impacts of the extension project. Based on the outcomes of the impact assessment, the RKL-RPL defines mitigation measures for the significant impacts and corresponding monitoring requirements. Moreover, for those impacts that are considered insignificant but which could be of concern if not properly managed, mitigation measures and monitoring are also defined in the RKL-RPL.

4 Effectiveness The ANDAL addendum process undertaken for the extension project is considered effective with regards to focusing the assessment on potentially significant environmental and social impacts. Notwithstanding the limited engagement of community and government stakeholders, feedback provided was beneficial in identifying effective mitigating measures and monitoring requirements to be included in the RKL-RPL.

C Output and Outcome

1 Screening and Categorization

This AMDAL has already been subject to revision. The original AMDAL for PLTU 3 Tanjung Awar-Awar was first approved in 2006, and was subsequently revised to reflect changes in the plant design and installed capacity.

The ANDAL and RKL-RPL addendum for the new extension project was completed in compliance with government Regulation No. 27/2012 on Environmental Permitting and is consistent with a letter issued by the Environmental Agency of East Java Province No. 660/9821/207.1/2012 (dated 19 October 2012).

2 Scoping No formal scoping process was undertaken as this is not required for an ANDAL and RKL-RPL addendum.

3 Project Description The assessment describes the project location, scale, area, and design and summarizes activities by project phase, including:

- Pre-construction phase (information dissemination, field survey, and land acquisition)

- Construction phase (mobilization of workers and equipment, land clearing and consolidation, procurement of materials, construction of infrastructure and facilities, recruitment and

Page 72: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

demobilization of construction workers) - Operation phase (recruitment of staff, power plant operation and

maintenance, and operation of air quality controls) - Post-operation phase (demobilization of staff, demolition of

infrastructure and facilities, maintenance, and site revegetation)

4 Policy, Legal and Administrative Framework

A comprehensive listing of laws and regulations is provided in the addendum document, although some of the referenced regulations are obsolete.

5 Environmental Baseline The ANDAL addendum provides detailed baseline information on:

- Physical-chemical components (climate, air quality and noise, topography, hydrology, groundwater and marine water quality, geology and geomorphology, land type and nutrient status, and land use)

- Biological components (flora and fauna) supported by survey photographs

- Social, economic, and cultural components (demographics, occupation, income level, education facilities, and security)

- Public health component (disease distribution, sanitation, waste disposal, and community perceptions)

Especially for the physical-chemical component, baseline information are supported with laboratory results from the Marine Productivity and Quality Laboratory of the Marine and Fishery Faculty at Hassanudin University.

6 Analysis of Alternatives The ANDAL addendum only describes the already determined final design and configuration of the extension project.

7 Impact and Risk Assessment

The ANDAL addendum provides a comprehensive assessment of both environmental and social impacts and risks for the extension project. The assessment was undertaken using a combination of professional judgement, mathematical modelling, and a semi-quantitative analysis.

Preparation of the ANDAL addendum was carried out by the project proponent themselves since they are a recognized Service Provider for AMDAL Preparation. This is consistent with government regulation No. 27/2012 Article 10, Clause 1 allowing that project proponents can prepare an AMDAL document by themselves or request assistance from other parties.

It is noted that this was an integrated AMDAL comprising the main structures and supporting facilities of jetty, power plant, and transmission line, covering an area of 80 hectares for the expansion and a twelve kilometer length power transmission line. In addition, the study also involves other related sectors/parties such as Sea Communication and the Navy.

8 Environmental Management and Monitoring Plan (EMP)

The RKL-RPL details mitigation measures and monitoring requirements for the extension project. It states that some potential impacts are considered manageable, and can be managed effectively. A commitment to this effect is explicitly written in a Statement Letter No. 225.SPn/013/UIP VIII/2013, signed and completed with duty stamp by the General Manage.

In addition, this addendum also presents good practices carried out by PLN (Persero) for the project, including:

- Management of hazardous wastes such as used lubricant, used

Page 73: CASE SUMMARY REPORT ON ENVIRONMENT · CASE SUMMARY REPORT ON ENVIRONMENT DRAFT This report is a work in progress, the purpose of which is to encourage an iterative process of feedback

gloves, dirty rags, used tungsten lamps, and used accumulators by establishing a temporary depot as required by regulation

- Application of technological approach to reduce air pollution by using electrostatic precipitator and a large capacity air filter which are able to separate more than 99% of fly ash

- Use of coal with low sulfur content (less than 0.4%) is another technological alternative applied (instead of flue gas desulphurization)

9 Information Disclosure Government Regulation No. 27/2012 on Environmental Permitting does not require information disclosure and public consultation for ANDAL and RKL-RPL addendum. No details of information dissemination are provided.

10 Consultation and Participation

A public consultation was carried out but no details of attendance, including women’s participation is provided.

11 Grievance Redress Mechanism Development

The RKL-RPL addendum does not indicate the existence of a grievance mechanism. However, PLN through its project level office has procedures to receive and follow-up on community complaints.

12 EMP Implementation Project is at construction phase.

13 Monitoring and Reporting Implementation reports are not yet available.