1 Cash Flow Analysis Cash Flow Analysis 29/09/2016 Emad Elbeltagi 2 Cash Flow Cash Flow Contract Cash Flow How much is the total cost? How to arrange for financing? Cash Flow = Cash In –Cash Out = Income – Expense = Revenue - Cost Contract Cash Flow How much is the total cost? How to arrange for financing? Cash Flow = Cash In –Cash Out = Income – Expense = Revenue - Cost

Upload: vannhi

Post on 10-Aug-2018

262 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: Cash Flow Analysis - Mansosp.mans.edu.eg/elbeltagi/CB517P Ch6.pdf · 1 Cash Flow Analysis 29/09/2016 Emad Elbeltagi 2 Cash Flow Contract Cash Flow How much is the total cost? How

1

Cash Flow AnalysisCash Flow Analysis

29/09/2016 Emad Elbeltagi 2

Cash FlowCash FlowContract Cash Flow

How much is the total cost?

How to arrange for financing?

Cash Flow = Cash In –Cash Out

= Income – Expense

= Revenue - Cost

Contract Cash Flow

How much is the total cost?

How to arrange for financing?

Cash Flow = Cash In –Cash Out

= Income – Expense

= Revenue - Cost

Page 2: Cash Flow Analysis - Mansosp.mans.edu.eg/elbeltagi/CB517P Ch6.pdf · 1 Cash Flow Analysis 29/09/2016 Emad Elbeltagi 2 Cash Flow Contract Cash Flow How much is the total cost? How

2

29/09/2016 Emad Elbeltagi 3

Cash FlowCash FlowProject Expenses

The project cost types:

Fixed cost (equipment,…)

Time-related cost (distributed over the duration of an activity, e.g.,

salaries, …)

Quantity (Production)-related costs (costs per unit of materials or

unit of resource usage)

When these costs are paid, it is named expenses

Project Expenses

The project cost types:

Fixed cost (equipment,…)

Time-related cost (distributed over the duration of an activity, e.g.,

salaries, …)

Quantity (Production)-related costs (costs per unit of materials or

unit of resource usage)

When these costs are paid, it is named expenses

29/09/2016 Emad Elbeltagi 4

Project Expenses (Smooth curve)Project Expenses (Smooth curve)

Cash FlowCash Flow

Cost

Expense

LE x1000

Time

Page 3: Cash Flow Analysis - Mansosp.mans.edu.eg/elbeltagi/CB517P Ch6.pdf · 1 Cash Flow Analysis 29/09/2016 Emad Elbeltagi 2 Cash Flow Contract Cash Flow How much is the total cost? How

3

29/09/2016 Emad Elbeltagi 5

Cash FlowCash FlowProject Expenses

The project S-Curve:Project Expenses

The project S-Curve:

Cost (LE)

Time

29/09/2016 Emad Elbeltagi 6

Cash FlowCash FlowProject Income

Project revenue is the summation of the activities prices

Represents the payment made by the owner to the contractor

Mostly, the contractor receive his payments after one month from

submitting his/her invoice

Retainage of 5 or 10 to ensure that no problems will arise during

construction

When the contractor receive his/her payments, it is called

Income

Project Income

Project revenue is the summation of the activities prices

Represents the payment made by the owner to the contractor

Mostly, the contractor receive his payments after one month from

submitting his/her invoice

Retainage of 5 or 10 to ensure that no problems will arise during

construction

When the contractor receive his/her payments, it is called

Income

Page 4: Cash Flow Analysis - Mansosp.mans.edu.eg/elbeltagi/CB517P Ch6.pdf · 1 Cash Flow Analysis 29/09/2016 Emad Elbeltagi 2 Cash Flow Contract Cash Flow How much is the total cost? How

4

29/09/2016 Emad Elbeltagi 7

Project Income (Stepped curve)Project Income (Stepped curve)

Cash FlowCash Flow

Time

IncomeRevenue

LE x1000

29/09/2016 Emad Elbeltagi 8

Cash FlowCash FlowExample

Consider the construction operation of a foundation activity

Activity duration 8 weeks

Labor cost of LE 1600 paid weekly

Equipment cost of LE 4000 paid weekly after 2-month credit facility

Material cost of LE 800 paid weekly after 3-month credit facility

Subcontractor cost of LE 2400 paid weekly after 1-month credit

facility

When each payment by the contractor is due and how much?

Example

Consider the construction operation of a foundation activity

Activity duration 8 weeks

Labor cost of LE 1600 paid weekly

Equipment cost of LE 4000 paid weekly after 2-month credit facility

Material cost of LE 800 paid weekly after 3-month credit facility

Subcontractor cost of LE 2400 paid weekly after 1-month credit

facility

When each payment by the contractor is due and how much?

Page 5: Cash Flow Analysis - Mansosp.mans.edu.eg/elbeltagi/CB517P Ch6.pdf · 1 Cash Flow Analysis 29/09/2016 Emad Elbeltagi 2 Cash Flow Contract Cash Flow How much is the total cost? How

5

29/09/2016 Emad Elbeltagi 9

Cash FlowCash Flow

Week 1 2 3 4 5 6 7 8

Payments 1100 1100 1100 1100 1100 1100 1100 1100

Total 1100 2200 3300 4400 5500 6600 7700 8800

Example Activity total cost = LE 8800

Example Activity total cost = LE 8800

29/09/2016 Emad Elbeltagi 10

ExpensesExpenses

Cash FlowCash Flow

wk 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

L

E

M

S

T

- 200 200 200 200 200 200 200 200

- - - - - - - - 500 500 500 500 500 500 500 500

- - - - - - - - - - - - 100 100 100 100 100 100 100 100

- - - - 300 300 300 300 300 300 300 300

- 200 200 200 500 500 500 500 1000 800 800 800 600 600 600 600 100 100 100 100

Page 6: Cash Flow Analysis - Mansosp.mans.edu.eg/elbeltagi/CB517P Ch6.pdf · 1 Cash Flow Analysis 29/09/2016 Emad Elbeltagi 2 Cash Flow Contract Cash Flow How much is the total cost? How

6

29/09/2016 Emad Elbeltagi 11

Contract Cash FlowContract Cash Flow

Cash FlowCash Flow

Cost (LE)

Expense

Profile

Month

Income Profile

Retainage

Cash out-of-flow

29/09/2016 Emad Elbeltagi 12

Contract Cash Flow - Admeasurements contractContract Cash Flow - Admeasurements contract

Cash FlowCash Flow

Cumulative cost (LE)

1 2 3 4 5 6 7 8Time

Income

Overdraft

Expense

Page 7: Cash Flow Analysis - Mansosp.mans.edu.eg/elbeltagi/CB517P Ch6.pdf · 1 Cash Flow Analysis 29/09/2016 Emad Elbeltagi 2 Cash Flow Contract Cash Flow How much is the total cost? How

7

29/09/2016 Emad Elbeltagi 13

Contract Cash Flow - Admeasurements contract with advanced payment

Contract Cash Flow - Admeasurements contract with advanced payment

Cash FlowCash Flow

Income

Cumulative Cost (LE)

0 1 2 3 4 5 6 7 8Time

Expense

Advanced payment

29/09/2016 Emad Elbeltagi 14

Contract Cash Flow – Lump sum contract with three

payments

Contract Cash Flow – Lump sum contract with three

payments

Cash FlowCash Flow

Cumulative Cost (LE)

0 1 2 3 4 5 6 7 8Time

Income

Expense

Page 8: Cash Flow Analysis - Mansosp.mans.edu.eg/elbeltagi/CB517P Ch6.pdf · 1 Cash Flow Analysis 29/09/2016 Emad Elbeltagi 2 Cash Flow Contract Cash Flow How much is the total cost? How

8

29/09/2016 Emad Elbeltagi 15

Cash FlowCash Flow

Variables needed to calculate cash flow

The project bar chart (project schedule)

Activities’ direct and indirect cost

Contractor method of paying his/her expenses

Contractor’s markup

Retention amount and its payback time

Time of payment delay by owner

Advanced or mobilization payment

Variables needed to calculate cash flow

The project bar chart (project schedule)

Activities’ direct and indirect cost

Contractor method of paying his/her expenses

Contractor’s markup

Retention amount and its payback time

Time of payment delay by owner

Advanced or mobilization payment

Contract Cash FlowContract Cash Flow

29/09/2016 Emad Elbeltagi 16

Cash FlowCash Flow

Procedure to calculate cash flow

The project bar chart (project schedule)

Perform project schedule

Draw bar chart based on early or late timings

Calculate the cost per time period

Calculate the cumulative cost

Adjust the cost to produce the expenses

Calculate cumulative revenue: revenue = cost x (1 + markup)

Adjust the revenue to produce the income

Calculate the cash flow (cash flow = income – expense).

Procedure to calculate cash flow

The project bar chart (project schedule)

Perform project schedule

Draw bar chart based on early or late timings

Calculate the cost per time period

Calculate the cumulative cost

Adjust the cost to produce the expenses

Calculate cumulative revenue: revenue = cost x (1 + markup)

Adjust the revenue to produce the income

Calculate the cash flow (cash flow = income – expense).

Contract Cash FlowContract Cash Flow

Page 9: Cash Flow Analysis - Mansosp.mans.edu.eg/elbeltagi/CB517P Ch6.pdf · 1 Cash Flow Analysis 29/09/2016 Emad Elbeltagi 2 Cash Flow Contract Cash Flow How much is the total cost? How

9

29/09/2016 Emad Elbeltagi 17

Cash FlowCash FlowExampleExample

0 0

6

1

2

4

3

65

7 8

9

A(4)

B(6)

C(2)

D(8)

F(10)

G(16)

J(6)

E(4)

H(8)

K(10)

I(6)

4

6

2 22

16

12

24 32 3226

22

22

18

16

14

29/09/2016 Emad Elbeltagi 18

Cash FlowCash Flow

Example data: Mark up = 5%Example data: Mark up = 5%ExampleExample

Activity Duration (day)

Total Cost (LE x 1000)

Total Revenue (LE x 1000)

ABCDEFGHIJK

46284101686610

04.0012.0004.0016.0020.0020.0016.0024.0012.0012.0010.00

04.2012.6004.2016.8021.0021.0016.8025.2012.6012.6010.50

Page 10: Cash Flow Analysis - Mansosp.mans.edu.eg/elbeltagi/CB517P Ch6.pdf · 1 Cash Flow Analysis 29/09/2016 Emad Elbeltagi 2 Cash Flow Contract Cash Flow How much is the total cost? How

10

29/09/2016 Emad Elbeltagi 19

Cash FlowCash Flow

Example data:

Contractor expenses will be paid immediately

Retention = 10% will be paid with the last payment

Calculations made every 8 days

Owner payment will be delayed one period

First invoice after at the end of the period

No advanced payment

Example data:

Contractor expenses will be paid immediately

Retention = 10% will be paid with the last payment

Calculations made every 8 days

Owner payment will be delayed one period

First invoice after at the end of the period

No advanced payment

ExampleExample

29/09/2016 Emad Elbeltagi 20

Cash FlowCash FlowExampleExample

Time (days)

1000/day

2000/day000/day

2000/day

2000/day

5000/day

2000/day

1000/day

3000/day

2000/day

2000/day

1000/day

Page 11: Cash Flow Analysis - Mansosp.mans.edu.eg/elbeltagi/CB517P Ch6.pdf · 1 Cash Flow Analysis 29/09/2016 Emad Elbeltagi 2 Cash Flow Contract Cash Flow How much is the total cost? How

11

29/09/2016 Emad Elbeltagi 21

Cash FlowCash FlowExampleExample

1. Cost/2 days x LE1000 10 10 12 14 10 10 16 16 8 8 8 8 6 6 6 2 - - - -

2. Cost each period x LE1000 46 52 32 20 -

3. Cumulative cost x LE1000 46 98 130 150 150

4. Cumulative Expense x 1000 46 98 130 150 150

5. Revenue = row 3 x 1.05 48.3 54.6 33.6 21 -

6. Revenue - retention = row 5 x 0.9 43.47 49.14 30.24 18.90 -

7. Retention x LE1000 - - - - 15.75

8. Cumulative revenue x LE1000 43.47 92.61 122.85 141.75 157.50

9. Cumulative income x LE1000 - 43.47 92.61 122.85 157.50

10. Cumulative cash flow x LE1000 = row 9 – row 4

-46 -98/-54.53 -86.53/-37.39 -57.39/-27.15 -27.15/+7.5

29/09/2016 Emad Elbeltagi 22

Cash FlowCash FlowExampleExample

Area = LE 10,000x 1 period (8-days)

Page 12: Cash Flow Analysis - Mansosp.mans.edu.eg/elbeltagi/CB517P Ch6.pdf · 1 Cash Flow Analysis 29/09/2016 Emad Elbeltagi 2 Cash Flow Contract Cash Flow How much is the total cost? How

12

29/09/2016 Emad Elbeltagi 23

Cash FlowCash FlowExampleExample

29/09/2016 Emad Elbeltagi 24

Cash FlowCash Flow

Loading of rates

Adjustment of work schedule to late start timing

Reduction of delays in receiving revenues

Asking for advanced or mobilization payment

Increasing the mark up and reducing the retention

Adjust the timing of delivery of large material orders

Delay in paying labor wages, equipment, material

Loading of rates

Adjustment of work schedule to late start timing

Reduction of delays in receiving revenues

Asking for advanced or mobilization payment

Increasing the mark up and reducing the retention

Adjust the timing of delivery of large material orders

Delay in paying labor wages, equipment, material

Minimizing Contract Negative Cash FlowMinimizing Contract Negative Cash Flow

Page 13: Cash Flow Analysis - Mansosp.mans.edu.eg/elbeltagi/CB517P Ch6.pdf · 1 Cash Flow Analysis 29/09/2016 Emad Elbeltagi 2 Cash Flow Contract Cash Flow How much is the total cost? How

13

29/09/2016 Emad Elbeltagi 25

Cash FlowCash Flow

24 unit areas, interest rate 1% per period Cost = 24 x 10000 x 0.01 = LE 2400 24 unit areas, interest rate 1% per period Cost = 24 x 10000 x 0.01 = LE 2400

Cost of BorrowingCost of Borrowing

Area = LE 10,000x 1 period (8-

days)

29/09/2016 Emad Elbeltagi 26

Cash FlowCash Flow

Time scale is much longer spans the whole life of a project

Feasibility studies

Execution

Operation

Time scale is much longer spans the whole life of a project

Feasibility studies

Execution

Operation

Project Cash FlowProject Cash Flow

Profitability indicators

Payback period

Maximum capital – maximum negative cash

Profit

Profitability indicators

Payback period

Maximum capital – maximum negative cash

Profit

Page 14: Cash Flow Analysis - Mansosp.mans.edu.eg/elbeltagi/CB517P Ch6.pdf · 1 Cash Flow Analysis 29/09/2016 Emad Elbeltagi 2 Cash Flow Contract Cash Flow How much is the total cost? How

14

29/09/2016 Emad Elbeltagi 27

Cash FlowCash FlowProject Cash FlowProject Cash Flow

Payback period

Maximum capital

Profit

Cumulative cash flow

Project duration

29/09/2016 Emad Elbeltagi 28

Cash FlowCash Flow

Year 1 2 3 4 5 6 7 8

Project A (LE x 1000)Project B (LE x1000)

-10-30

-50-110

-80-80

-60-30

0-20

200

3540

6580

Project Cash Flow: ExampleProject Cash Flow: Example Project net cash flow Project net cash flow

Project cumulative cash flow Project cumulative cash flow

Year 1 2 3 4 5 6 7 8

Project A (LE x 1000)Project B (LE x 1000)

-10-30

-40-80

-3030

2050

6010

2020

1540

3040

Page 15: Cash Flow Analysis - Mansosp.mans.edu.eg/elbeltagi/CB517P Ch6.pdf · 1 Cash Flow Analysis 29/09/2016 Emad Elbeltagi 2 Cash Flow Contract Cash Flow How much is the total cost? How

15

29/09/2016 Emad Elbeltagi 29

Cash FlowCash FlowProject Cash Flow: ExampleProject Cash Flow: Example

Project AProject A

Project BProject B