cc302-ch 4[1] (highway)
DESCRIPTION
noteTRANSCRIPT
Ch.4.1.1: FLEXIBLE
PAVEMENT
Pavement is the structure which separates
the tires of vehicles from the underlying
foundation material.
The flexible pavement usually consists of
three main layers, the bituminous surfacing
(wearing & binder course), the base or road
base and the sub base,
For the rigid pavement consists of two
layers, concrete slab and the subbase.
Flexible & Rigid Pavement
ELEMENT OF FLEXIBLE PAVEMENT
The principal element of flexible
pavement include ;
Wearing course
Binder course
Base course
Subbase couse
subgrade
Subgrade
Sub-base
Base
Binder Course
Wearing Course Surface
Formation layer
STRUCTURAL LAYER
ROAD SURFACE
It should be capable of
withstanding high tire pressure,
resisting the abrasive force due
to traffic.
Providing a skid-resistance
driving surface and preventing
the penetration of surface
water depending on the
expected traffic on the
pavement.
7
Top layer with the main function to
the safety of the road users.
The other functions of wearing
course:
Provides smooth & dense riding
surface
Takes up wear & tear due to traffic
Provides water tight
Provides hard surface Drainage system – provide water prove layer
and drain surface run-off to the side drain.
WEARING COURSE
This layer is used to spread
the force from the surface and
provide the flat surface to
construct the wearing course.
The maximum size of aggregate
used is ACB 14 or ACB 20 and
percentage of bitumen ranging
from 4 – 6 %. (Jabatan Kerja
Raya 1986).
BINDER COURSE
BASE COURSE
This layer is used to absorb force
from surface and spread the
force to the thickest layer
Base course shall apply selected
materials such as crushed stones
and sand, or a combination of
these materials. It may stabilized
with cement bitumen or lime.
According AASHTO T 96-97 (1982)
Grading A Table 1 of the size
aggregate to be used is 40 mm
Sub-base material consist of sand
gravel and laterite
Functions of sub-base: I. Support road base & spreads force
to the sub-grade
II. Prepares the drainage using rough
materials
III. Prepare cover at any layer that is
constructed
IV. Bears the pressure from heavy
vehicles
V. Prevent the sub-grade from traffic
flow
SUB-BASE COURSE
Sub-grade is the part of embankment or
natural soil / filled soil
The surface of sub-grade is identified as
a formation level.
The formation level is the soil surface
after the earthwork, consolidation,
compaction and stabilization works were
completed.
Sub-grade is used as a layer which
sustain load from the top surfaces. [email protected] 11
SUBGRADE COURSE
SUMMARY OF MATERIALS USED IN FP
PAVEMENT
LAYERS
MATERIAL TYPES
Sub-Grade Natural soil / filled soil
Sub-Base Sand gravel /
Laterite /
Selected soil
Base Crusher run (aggregate size 40
mm)
Surface Pre-mix bitumen
Pre-mix concrete asphalt (ACB 14
or ACB 20)
ANNOUNCEMENT
• LECTURE 28 SEPT 2012
• CHANGE TO 2:30 – 4:00 PM
CH.4.1.2. – 4.1.3. :
PREPARATION MATERIALS IN
SUB-BASE (SUB-TAPAK) AND
BASE (TAPAK) FOR FLEXIBLE
PAVEMENT C3010 – HIGHWAY
ENGINEERING
PREPARATION MATERIALS FOR
SUB-BASE (KETAPAK)
Introduction
• Materials used in sub-base layer must
consist of hard stone, high durability
and clean
• Consists of crusher run, gravel, laterite
(batu merah) or sand
• These materials must be freed from
organic content, lump of clay and any
materials that easily spoil
• Below is the BS standard Passing Weight % for crusher run, gravel or laterite materials.
• Other materials can be used but must achieve the CBR value (not less than 20 % after immersed and compacted to 95 % maximum dry density.)
• Materials also must be freed from leaf mass, soft particles or lump of clay.
Table 1.0: Passing Weight % for
Crusher Run, Gravel or Laterite
BS sieve Passing Weight
% (A)
Passing Weight
% (B)
40 mm (1 ½ in) 100 -
28 mm (1.0 in) 75 – 100 100
20 mm (3/4 in) 60 – 90 70 -100
10 mm (3/8 in) 45 – 75 58 – 75
5 mm (3/16 in) 30 – 60 35 – 65
2.4 mm (No. 7) 20 – 50 25 – 50
2.4 mm (No. 36) 10 – 30 15 – 30
75 m (No. 200) 0 – 2 0 - 2
CRUSHER RUN
• Crusher run road base is commonly used
by JKR (PWD)
• Its consist of one type of stone either
limestone or dolomite, and sometimes
granite and were crushed in two stages to
gain good grade and stabilization.
• Below the crusher run grade according to
BS 1377
Table 1.1: B.S. 1377 CRUSHER
RUN GRADE LIMIT
SIEVE B.S PASSING WEIGHT
%
50 mm
40 mm
20 mm
10 mm
5 mm
No. 7
No. 25
No. 200 (non-plasticity
quarry dust)
100
95 – 100
60 – 80
40 – 60
25 – 40
15 – 30
8 – 22
0 - 8
ADVANTAGES &
DISADVANTAGES OF CRUSHER
RUN
ADVANTAGES DISADVANTAGES
Materials easily laid and
leveled
Difficult to separate
between fine and coarse
aggregates
The desire density
(kepadatan) can be
obtained quickly
Materials cost is cheap
SAND
• Two types of sand used for
FP:-
–Dry sand mix (adunan pasir
kering)
–Wet sand mix (adunan pasir
basah)
SAND
• Dry sand mix:
–aggregates & selected sand
(clean sand) – don’t have 5%
clay and not more than 25%
gravel
SAND
• Wet sand mix:
–Sand that consist of 5% moisture
and selected clean sand – more
than 25% gravel and < 2% clay
Table 1.2: Passing Weight % for
Sand
B.S. SIEVE PASSING WEIGHT %
10 mm 100
5 mm 75 – 100
No. 14 45 – 80
No. 52 10 – 30
No. 100 2 - 10
LATERITE
• Late rite for sub-grade layer
• Compacted leveled and be cut to camber as in plan
• Unsuitable soil to be changed with suitable material
• Formation layer thickness is range from 50 – 75mm sand layer or quarry dust and be compacted with 8 – 10 tones compactors
• This job must be done to prevent clay from absorbing into stone layer of sub-base and reduce the shear strength of pavement
PREPARATION MATERIALS FOR
BASE LAYER
Introduction
• Material: crusher run / hard aggregates
• Properties of materials: high durability, clean, no lump of clay particles or organic content
• Achieve the testing requirement in B.S. 1377 for CBR test and Flakiness Index test in B.S. 812.
Method for materials base
construction of base
• 5 types of method used in preparation of materials at Base layer are:-
a. Crusher run road base
b. Dry bound macadam road base
c. Wet bound macadam road base
d. Bituminous bound road base
e. Stabilized soil road base
Dry-bound Macadam Road base
(Macadam Serikat Kering) • Dry bound macadam use two types materials
which were bring separately to site:-
i. Coarse aggregate: 37.5 – 100 mm
ii. Fine aggregate/fine dust: < 5mm
• Coarse aggregate was laid and compacted at the prepared location.
• Any empty gap between aggregates than will be filled with fine aggregate (quarry dust)
• Final layer, fine aggregate will be applied on the surface.
Figure: Roller
Compactor (Large)
Figure: Vibrator
Compactor
Wet bound macadam road base
(Macadam Serikat Basah)
• Method similar as dry bound
macadam but only added spraying
water after laying/compacting the
coarse aggregate
• Two reasons for spraying water:-
– Act as lubricants
– Moisture make dust to be bound
together
Figure: Bitumen Macadam Plant
Bituminous Bound Road Base
(Tapak Bercampuran Pengikat)
• Graded aggregates were mixed
with tar or bitumen
• Mixture is made at the mixer
before lay
• This method of construction is
costly, but the strength is
higher
Stabilized Soil Road Base
(Tapak Tanah Stabil)
• Soil be stabilized by mechanically
or with stabilize agent
• Mechanical stabilizer: using
compactor machine
• Stabilize agent: using cement,
lime or lime cement
CONSTRUCTION OF SUB-BASE,
BASE, SURFACE LAYER
a. Construction of SUB-BASE
• Sub-base constructed in 2 layers
(if the thickness is more then 150
mm)
• Every layer must be compacted
carefully with compactor
machine
• Compactors with rubber roller can
compact 120 mm layer in 12
times
a. Construction of SUB-BASE
• Compacting should start from the side
of the road then slowly towards the
middle of the road in horizontal way
• In super-elevated (sendeng) bends,
compaction machine will start at the
lowest part and slowly towards the
higher level.
• Finished part not be more than 20 mm
from the plan
b. Construction of BASE-
COURSE • Base material constructed with crusher run.
• Before road base is constructed, sub-grade
& sub-base surface MUST BE FORMED
PERFECTLY and COMPACTED enough
• Base must be constructed in 2 layers of
same thickness.
• Each layer should not exceed 150 mm
c. Construction of ROAD
SURFACE • Road surface constructed with bitumen
materials
• Materials: Concrete Asphalt, macadam
bitumen and tar
• Construction should free from dust and
waterproof
• Prime coat is poured onto road base
surface as a binder between road base and
base course (binder layer)
c. Construction of ROAD
SURFACE • Base course is built on one layer only
with paver’s machine, and later will be
compacted.
• Compacting must be done immediately
• Compacted should be started from the
side towards to the middle of the road
• Compacted at super elevated, from
lower to higher part
Paver Machine
CH.4.1.10:
Test to be carried out to
ensure the quality of the sub-
base & sub-road layer
SUB-GRADE
LAYER OF
PAVEMENT
TYPE OF TESTING TO BE
CARRIED OUT
Embankment,
fill / backfill &
select
fill/backfill
•Determination of ATTERBERG LIMITS
(Had alterberg), SWELLING or
SHRINKAGE CHARACTERISTIC (ciri-ciri
pengembangan atau pengecutan)
•Determination of PLASTICITY INDEX
(Indek keplastikan)
•GRADATION ANAYSIS of material
(Analisis Pengredan Bahan)
LOWER SUB-BASE & TOP 300
MM SUB-GRADE
LAYER OF
PAVEMENT
TYPE OF TESTING TO BE
CARRIED OUT
Lower Sub-
base and top
300 mm of
sub-grade
•ATTERBERG LIMITS
•PLASTICITY INDEX
•GRADATION ANALYSIS
•B.S. 1377 COMPACTION TEST (4.5 kg
rammer method)
•CBR test (4 day soak with surcharge and
swell measurement)
Earth
Shoulders
•Same as lower sub-base
SUB-BASE & ROAD BASE
LAYER OF
PAVEMENT
TYPE OF TESTING TO BE CARRIED
OUT
Sub-base and
Road base
(gravel
shoulders, gravel
surfacing,
crushed
aggregate)
•ATTERBERG LIMITS
•PLASTICITY INDX
•GRADATION ANALYSIS
•B.S. 1377 COMPACTION TEST (4.5 kg
rammer method)
•CBR test (4 day soak with surcharge and
swell measurement)
•Determination of FLAKINESS INDEX
•Determination of % PARTICLES with a
fractured face
SUB-BASE & ROAD BASE
LAYER OF
PAVEMENT
TYPE OF TESTING TO BE CARRIED
OUT
Sub-base &
Road base
(Quality
materials)
Same as above
Additional
Sodium sulphate soundness test
Aggregate crushing value test
Sub-base &
Road base
(cement or lime
stabilization of
soils or
aggregates)
Same as above
CBR test (as specified)
Compressive strength test (soil cement)
Wetting and drying test (soil cement)
BITUMINOUS SURFACE LAYER OF
PAVEMENT
TYPE OF TESTING TO BE CARRIED
OUT
Bituminous surface
(Aggregates and
penetration
Macadam)
•GRADATION ANALYSIS
•FLAKINESS INDEX, % of elongated
particles
•Determination of % PARTICLES with a
fractured face
Additional tests:
•SPECIFIC GRAVITY and
ABSORPTION test
•Sodium sulphate SOUNDNESS TEST
•AGGREGATE CRUSHING VALUE
TEST
•POLISHED STONE VALUE TEST
•BITUMEN STRIPPING TEST
BITUMINOUS SURFACE
LAYER OF
PAVEMENT
TYPE OF TESTING TO BE
CARRIED OUT
Bituminous Surface
(Aggregates for
Bituminous
Macadam and
Bituminous
Macadam Mixtures)
•Same as above
Additional tests:
•COMPREHENSIVE MARSHALL
Method test
Bituminous Surface
((Aggregates for
Asphaltic concrete
and Asphaltic
Concrete Mixture)
•Sodium sulphate SOUNDNESS TEST
•AGGREGATE CRUSHING VALUE TEST
•POLISHED STONE VALUE TEST
•BITUMEN STRIPPING TEST
Priming Work (Penyebuan)
Priming Work (Penyebuan)
• Priming (Penyebuan)
– Definition: The application of primer
pavement (salut turapan)
• Two types of priming work are:-
– Primer-binder (salut jelujur)
– Primer-sealing (salut perdana)
PRIMER BINDER (SALUT
JELUJUR) • Definition:
– A field or refinery cutback bitumen used, with a cover of aggregate, to provide surface penetration (preferably from 2 mm to 5 mm) and a trafficable wearing surface.
• Materials used: Asphalt cutback types RC -70, PK-3 or AK-3
• Application method: using spray
• Amount spray : 0.2 – 0.5 liter/m2
• Method spraying: spray bit by bit and uniform so as not to produce semi-thick coating of asphalt will cause problems asphalt surface layer