ccg meeting angaston 6 th may 2009
DESCRIPTION
CCG Meeting Angaston 6 th May 2009. Mine Operation Update. Eastern area Shaping and topsoil addition continuing Preparation for planting of trees and grass Continuing to crush on western side of eastern mound Western MPL Topsoil removal continuing will be completed by mid May - PowerPoint PPT PresentationTRANSCRIPT
1
CCG MeetingAngaston 6th May 2009
Mine Operation Update
Eastern area
Shaping and topsoil addition continuing
Preparation for planting of trees and grass
Continuing to crush on western side of eastern mound
Western MPL
Topsoil removal continuing will be completed by mid May
The accessible topsoil mound has been sown with sterile rye grass onto
Topsoil sample submitted for testing and results received for future comparison, sampling continuing
Overburden being placed and shaped first stage of levelling
Surface water retention basin in place, directional irrigation to silt traps
Other
Quarterly Compliance Report submitted to PIRSA
Draft overburden report submitted to PIRSA
Chasing NRM Board approval of Jaeckeli Ck Management Plan
Later loading time of train loading has commenced
Dust mitigation plan continuing
Investigating Mine closure concept plans (subject to hydrology outcome)
April 2009 Complaints Register
Refer corrected handout with full list for January to March 2009 in the Quarterly Compliance Report
4
Dust Emission Reduction Initiatives
No Plant Item Target Completion Date
Impact Action
1 Front entrance Road watering, only water to gate 1/4/09 Reduce water/drag out to Penrice Rd Completed
2 Penrice Road Change to Envirosweep street sweeper
6-04- 09 Improve sweeping of drag out Completion 27/4/09
3 Truck wash Upgrade water recycle system 31/07/09 Improve washing efficiency Quote being organised
4 Osborne train loader
Commence water sprays to Osborne stone ½ hour prior to loading
2/04/09 Reduce emissions at return circuit Commencing water sprays 1/4hour prior to loading (mud problem with ½ hour) Moving to automatic PLC
5 Osborne train loader
Maintain chute water sprays with polocitrus
Serviced quarterly
Comments from residents this is working
6 Osborne plant Apply water sprays on tertiary plant & Q10 at all times
1/04/09 Reduce dust at these handling points Aligned to No11- Completed 1/5/09
7 PC1 Crusher Auto water spray on trucks entering to unload
31/07/09 Negates manual activation by operator Receiving quotes for Automation using PLC
8 PC1 Crusher Shroud unload bin in shade cloth 31/07/09 Improve effectiveness of water sprays Barossa engineering quoting on this
9 ABC Stockpiles Shroud perimeter 30/04/09 Reduce dust emission through wind erosion
Two options- permanent cyclone fence with shade cloth or cement bollards
10 ABC Stockpile Spray completed pads with green covering
30/04/09 Reduce dust emission from stockpiles Paid for product waiting delivery
5
Dust Emission Reduction Initiatives
11 Fine Mill Plant Close down from 1/5/09 1/5/09 Customers to be notified Completed
12 Top Soil Stockpile
Spray stockpile with green covering 30/04/09 Reduce possible dust emission from wind & rain?
Seeded sterile Rye grass, finish when accessible
13 Aggregate PlantComplete auto water sprays of working area around plant
30/08/09 Reduce dust from vehicle movements Requires PLC being quoted
14 Aggregate plant feed stock piles
Erect a overhead water spray system for all trucks to pass under before unloading to stockpiles
30/9/09 Reduce dust in crushing plants Designs being considered
15 Aggregate PlantIncrease water application during start up/shut down and when empty with automatic sprays
30/04/09 Check if possible Looking at PLC installation for this watering control
16 Aggregate Plant Bins
Automate sprays to be on all day 15/04/09 Reduce dust in strong wind conditions Completed
17 Aggregate PlantImprove water sprays at sand output end
30/06/09 Reduce dust in string winds Options being investigated
18 OI Glass Plant Assemble foam spray applicators 30/09/09 Reduce dust emission in strong winds Investigating foam options
19 Aggregate PlantReview use of shade cloth in this area to reduce wind impact
31/07/09 Reduce dust emission in strong winds Under review along with No 9
20 Osborne train Review ability to stop return <50mm stone
30/6/09 Reduce dust emissions at return bins Trial scheduled for May
21 Front entrance Seal roads from entrance to weigh bridge
30/10/09 Reduce drag out to Penrice Rd Maunsells are doing design work for resurfacing
No Plant Item Target Completion Date
Impact Action
6
TSP & PM10 Dust results April
TSP Limits: 120 µg/m3
Date TSP (µg/m3)High wind Sp
(km/h) Wind direction
1/4/09 106.4 49.9 SSW
4/4/09 60.8 33.8 NW
7/4/09 84.4 53.1 SSW
10/4/09 26.5 41.8 SSW
13/4/09 72.5 43.5 NW
16/4/09 52.2 56.3 NNW
19/4/09 21.2 49.9 SSW
22/4/09 58.4 45.1 ESE
PM10 Limits: 50 µg/m3
Date PM10 (µg/m3) High wind Sp (km/h) Wind direction
1/4/09 41.1 49.9 SSW
4/4/09 16.7 33.8 NW
7/4/09 17.2 53.1 SSW
10/4/09 7.6 41.8 SSW
13/4/09 19.6 43.5 NW
16/4/09 18.9 56.3 NNW
19/4/09 5 49.9 SSW
22/4/09 20.6 45.1 ESE
PM10 1/4/09 potential source Western MPL topsoil
Noise Abatement Initiatives
Noise monitoring program at Penrice Rd residents complete, Penrice to meet with residents and discuss
Trial delayed start Train loading – 0730am start Monday to Friday – 0800hrs start Saturday and Sunday
Two trains on Thursday 9th and Friday 17th for Easter and Vintage Festival
Site Noise Monitoring by Bassett Acoustics will be undertaken in June and reported in July.
8
Hydrology
Have now commissioned Aquaterra to undertaken mine closure Hydrology Study
To be completed in approximately 4 weeks