ccps an aiche technology alliance · 2020. 10. 20. · an aiche technology alliance risk analysis...

55
C CPS Center for Chemical Process Safety An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration April 12, 2019 Slide - 1 Overview of the Risk Analysis Screening Tool C CPS Center for Chemical Process Safety An AIChE Technology Alliance

Upload: others

Post on 01-Feb-2021

9 views

Category:

Documents


1 download

TRANSCRIPT

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    April 12, 2019 Slide - 1

    Overview of the Risk Analysis Screening Tool

    CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    Risk Analysis Screening Tool (RAST)

    Overview and Demonstration

    ✓ What is RAST?

    ✓ Identifying and Screening of Chemical and Operational

    Hazards

    ✓ Developing Hazard Scenarios

    ✓ Consequence Analysis

    ✓ Frequency Evaluation

    ✓ Risk Analysis/Layers of Protection Analysis (LOPA)

    CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance

    April 12, 2019 Slide - 2

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    Risk Analysis Screening Tool (RAST)

    April 12, 2019 Slide - 3

    Disclaimer:It is sincerely hoped that the information presented in this document will lead to an even better safety

    record for the entire industry; however, neither the American Institute of Chemical Engineers, the

    European Process Safety Centre, its consultants, CCPS Technical Steering Committee and Subcommittee

    members, EPSC members board, their employers, their employers officers and directors, nor The Dow

    Chemical Company, and its employees warrant or represent, expressly or by implication, the correctness

    or accuracy of the content of the information presented in this document. As between (1) American

    Institute of Chemical Engineers, its consultants, CCPS Technical Steering Committee and Subcommittee

    members, their employers, their employers officers and directors, and The Dow Chemical Company, and

    its employees, and (2) the user of this document, the user accepts any legal liability or responsibility

    whatsoever for the consequence of its use or misuse.

    RASTRisk Analysis Screening Tools

    Version 2

    Welcome to RAST (Risk Analaysis Screening Tool).

    The RAST software and its associated CHEF documentation were developed through the collaborative

    efforts of volunteers from member companies of the Center for Chemical Process Safety (CCPS) and the

    European Process Safety Centre (EPSC). Special appreciation is extended to the Dow Chemical Company

    for donating RAST/CHEF for global use and for providing the resources to help modify the software and

    documentation such that companies can tailor the RAST software to meet their company-specific risk

    tolerance levels. It is sincerely hoped that companies using RAST and CHEF during their hazard

    identification and risks analysis studies will be able to improve their process safety performance.

    Latest Revision Date 3/02/19

    Go To Main Menu >>

    CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance

    Go To Instructions >>RAST (Risk Analysis Screening Tool) and

    CHEF (Chemical Hazard Engineering

    Fundamentals) were made available

    through a donation from the Dow

    Chemical Company to the Center for

    Chemical Process Safety (CCPS) and the

    European Process Safety Council (EPSC).

    The intent is to make this information

    easily available to the chemical industry

    to support “cost-effective elimination of

    process safety incidents”.

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    April 12, 2019 Slide - 4

    RAST is a collection of “Screening Level” Process Safety

    Tools to assist in performing a Hazard Identification and Risk

    Analysis study that draws upon basic input information.

    What is RAST?

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    April 12, 2019 Slide - 5

    Screening is the evaluation or investigation of something as part of a

    methodical survey, to assess suitability for a particular role or purpose.

    “Screening Level” Tool

    - Oxford Dictionary

    RAST is intended to bridge the gap between qualitative and detailed quantitative risk

    evaluation. It utilizes many simplifying assumptions, engineering approximations,

    and simplified methods to generate “order of magnitude” estimates of consequence,

    likelihood, and risk.

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    ❑ RAST contains a data table of chemical properties (for 250 chemicals as of the date of this

    manual) that are used for quantifying hazards and in source models to determine leak rate.

    Users may enter properties for additional chemicals as needed in the HIRA study.

    ❑ RAST generates a list of suggested scenarios for consideration by the study team. The

    suggested list of scenarios is not intended to represent all scenarios needed for an effective

    HIRA study, but a starting point that the evaluation team may build upon.

    ❑ RAST is intended as a productivity tool to aid evaluation teams in performing Hazard

    Identification and Risk Analysis (HIRA) studies to provide consistency among analysis teams

    while reinforcing company protocol and criteria. It utilizes simplified and often empirical

    methods in quantifying hazards, consequence and risk.

    What is RAST?

    April 12, 2019 Slide - 6

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    ❑ RAST and the accompanying Chemical Hazards Engineering Fundamentals (CHEF)

    materials are based on performing Hazard Identification and Risk Analysis (HIRA) tasks in

    a specific order. The order of task execution is based on an overall work flow such that

    results of a specific estimate (such as a source model) being available as input for the

    subsequent task (such as vapor dispersion). RAST is set up to use minimal information to

    get started with the addition of more information over time to improve the analysis and

    generate additional reports.

    ❑ RAST bridges the gap between qualitative and detailed quantitative risk evaluation

    allowing application of greater rigor and detail for high risk scenarios. In some cases, other

    software or rigorous evaluation methods may be needed beyond the capability of RAST to

    meet a company’s risk analysis requirements. For these cases, RAST accommodates the

    entry of results from other software or methods (including qualitative estimates) in the

    overall study. In other cases, the study team may merely enter qualitative results.

    What is RAST?

    April 12, 2019 Slide - 7

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    Hazard Identification and

    Risk Analysis (HIRA) Study

    Hazard Identification and Risk Analysis (HIRA) is a collective

    term that encompasses all activities involved in identifying

    hazards and evaluating risk at facilities, throughout their life

    cycle, to make certain that risks to employees, the public, or the

    environment are consistently controlled within the organization's

    risk tolerance.-Center for Chemical Process Safety

    April 12, 2019 Slide - 8

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    The information flow in RAST follows this Overall Work Process

    April 12, 2019 Slide - 9

    Overall Work Process Steps for Hazard

    Identification and Risk Analysis

    What are the Hazards?

    What can go Wrong?

    How Bad could it Be?

    How Oftenmight it

    Happen?

    Is the Risk Tolerable?

    Identify Chemical

    and ProcessHazards

    Estimate Frequency

    Analyze Consequences

    AnalyzeRisk

    IdentifyAdditional Safeguards as Needed

    DevelopScenarios

    Identify Equipment

    or Activity to be Analyzed

    Manage Barriers

    for Life Cycle of Facility

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    Hazard Identification and Risk Analysis are the processes whereby hazards are evaluated by answering basic questions:

    ▪What are the Hazards?

    ▪What can go wrong?

    ▪What are the potential consequences?

    ▪How likely is it to happen?

    ▪ Is the Risk Tolerable?

    Hazard Identification and

    Risk Analysis (HIRA) Study

    April 12, 2019 Slide - 10

    Hazard Identification and Risk Analysis is one of the key elements of CCPS Risk-Based

    Process Safety

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    April 12, 2019 Slide - 11

    Incr

    easi

    ng

    Pro

    cess

    Ris

    k

    and

    Det

    ail o

    f An

    alys

    is

    Hazard and Operability Study

    Layers of Protection Analysis

    Barrier Analysis

    RAST / CHEF

    Fault Tree Analysis

    Detailed Dispersion Modeling

    Detailed Explosion Modeling

    Human Vulnerability Analysis

    Process Risk Analysis – Level of Detail

    Detailed Quantitative Risk

    Method

    Simplified Quantitative Risk

    Method

    Qualitative Risk Method

    Hazard and/or Risk Screening Criteria

    QRA Criteria

    Process Safety Review

    Checklist Analysis

    Safeguard Recommendations

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    Screening Tool is a simplified model with limited capabilities, suitable for

    screening-level studies.

    RAST as a “Screening Level” Tool

    April 12, 2019 Slide - 12

    -Center for Chemical Process Safety

    Screening Criteria: A predetermined measure, standard, or rule (typically

    based upon company or regulatory requirements), on which a judgment or

    decision can be based.

    RAST contains screening criteria, that a company may modify, for process

    equipment (or scenarios associated with specific process equipment) when

    hazards or risk are not sufficient to warrant beyond a qualitative risk analysis.CCPS does not endorse any specific criteria but provides initial values needed for the

    program to run and for the company to consider.

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    April 12, 2019 Slide - 13

    Example Checklist Analysis

    Example HAZOP DocumentationScenario

    Identification

    Initiating Event

    + Enabling Conditions

    Lo

    ss E

    ven

    t

    Incident Outcome with

    Undesired Consequence

    Failure of Independent Protective

    Layers

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    April 12, 2019 Slide - 14

    Scenario Development within RAST

    -Center for Chemical Process Safety

    Scenario: A detailed description of an unplanned event or incident sequence that results in a

    loss event and its associated impacts, including the success or failure of safeguards involved

    in the incident sequence.

    Initiating Cause (or Initiating Event): The operational error, mechanical failure, or external

    event or agency that is the first event in an incident sequence and marks the transition from a

    normal situation to an abnormal situation.

    Loss Event: Point in time in an abnormal situation when an irreversible physical event occurs

    that has the potential for loss and harm impacts. Examples include release of a hazardous

    material, ignition of flammable vapors or ignitable dust cloud, and over-pressurization rupture

    of a tank or vessel.

    Incident Outcome: The physical manifestation of the incident: for toxic materials, the incident

    outcome is a toxic release, while for flammable materials; the incident outcome could be a

    boiling liquid expanding vapor explosion (BLEVE), flash fire, vapor cloud explosion (VCE), etc.

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    April 12, 2019 Slide - 15

    Scenario Development within RAST

    In addition to Cause (or Initiating Event) and Consequence (or Incident Outcome),

    a RAST scenario contains one unique Loss Event. Details of the Loss Event help

    clarify the event sequence for the analysis team. In addition, the Loss Event is

    linked to a specific Source Term that allows RAST to perform a simple

    Consequence Analysis.

    Standardized lists of Initiating Events, Loss Events, and Incident Outcome are

    used to develop scenarios in RAST. Common parameter deviations for the type of

    equipment being analyzed is used to link some Loss Events with Initiating Events

    consistent with a Hazard and Operability Study (HAZOP) approach.

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    April 12, 2019 Slide - 16

    HAZOP Node: HAZOP Design IntentPlant Section =

    Equipment Type = Vessel/Tank

    Equipment Tag = V-101

    LOPA Menu Filters:

    Scenario Type Scenario CommentsParameters and

    DeviationInitiating Event (Cause) Initiating Event Description Loss Event Outcome

    Off-

    Site

    Tox

    ic R

    elea

    se

    On-

    Site

    Tox

    ic R

    elea

    se

    Indo

    or T

    oxic

    Rel

    ease

    Toxi

    c In

    filtr

    atio

    n

    Che

    mic

    al E

    xpos

    ure

    Flas

    h Fi

    re o

    r Fi

    reba

    ll

    Vap

    or C

    loud

    Exp

    losi

    on

    Bui

    ldin

    g E

    xplo

    sion

    Equ

    ipm

    ent E

    xplo

    sion

    Pro

    pert

    y D

    amag

    e or

    Bus

    ines

    s Lo

    ss

    Env

    iron

    men

    tal D

    amag

    e

    Drain or Vent Valve Open

    Drain or Vent Valve left open following

    infrequent maintenance, purging or

    cleaning

    Flow-Loss of

    Containment

    Human Failure Action once per

    quarter or less

    Operator leaves Drain or Vent Open

    following infrequent maintenanceDrain or Vent Leak

    Off-Site Toxic Release, On-Site

    Toxic Release, Toxic Infiltration,

    Chemical Exposure, Flash Fire

    or Fireball

    5 4 4 3 4

    Vapor Relief Vent - FireOff-Site Toxic Release, On-Site

    Toxic Release, Toxic Infiltration6 5 5

    Equipment Rupture at Fire Conditions

    Off-Site Toxic Release, On-Site

    Toxic Release, Toxic Infiltration,

    Chemical Exposure, Flash Fire

    or Fireball, Equipment Explosion

    6 5 5 4 4 3

    Ignitable Headspace

    Chemical is Flammable or

    Combustible: Maximum Operating,

    Mechanical Energy or Heating Media

    Temperature exceeds Flash Point

    less 5 C

    Composition-Wrong

    ConcentrationBPCS Instrument Loop Failure

    Failure of Pressure or NonCombustible

    Atmosphere ControlEquipment Rupture - Deflagration

    Off-Site Toxic Release, On-Site

    Toxic Release, Toxic Infiltration,

    Chemical Exposure, Flash Fire

    or Fireball, Equipment Explosion

    6 5 5 3 4 3

    Mechanical Integrity Failure -

    Extremely Large

    Largest Pipe or Nozzle Size less than

    Extremely Large Hole Size

    Flow-Loss of

    Containment

    IEF=4 as determined by Process

    SafetyFailure from corrosion, fatigue, etc. Extremely Large Hole Size Leak

    Off-Site Toxic Release, On-Site

    Toxic Release, Toxic Infiltration,

    Chemical Exposure, Flash Fire

    or Fireball, Vapor Cloud

    Explosion

    6 5 5 3 4 5

    Mechanical Integrity Failure -

    Medium

    Mechanical Integrity Loss of

    Containment for Medium Hole Size

    Flow-Loss of

    Containment

    IEF=4 as determined by Process

    SafetyFailure from corrosion, fatigue, etc. Medium Hole Size Leak

    Off-Site Toxic Release, On-Site

    Toxic Release, Toxic Infiltration,

    Chemical Exposure, Flash Fire

    or Fireball

    6 5 5 3 4

    Mechanical Integrity Failure - Very

    Large

    Mechanical Integrity Loss of

    Containment for Very Large Hole Size

    Flow-Loss of

    Containment

    IEF=4 as determined by Process

    SafetyFailure from corrosion, fatigue, etc. Very Large Hole Size Leak

    Off-Site Toxic Release, On-Site

    Toxic Release, Toxic Infiltration,

    Chemical Exposure, Flash Fire

    or Fireball, Vapor Cloud

    Explosion

    6 5 5 3 4 5

    Mechanical Integrity Failure - Very

    Small

    Mechanical Integrity Loss of

    Containment for Very Small Hole Size

    Flow-Loss of

    Containment

    IEF=3 as determined by Process

    SafetyFailure from corrosion, fatigue, etc. Very Small Hole Size Leak

    On-Site Toxic Release, Flash

    Fire or Fireball3 4

    Overfill Release

    Off-Site Toxic Release, On-Site

    Toxic Release, Toxic Infiltration,

    Flash Fire or Fireball

    6 5 5 4

    Equipment Rupture at Operating

    Temperature

    Off-Site Toxic Release, On-Site

    Toxic Release, Toxic Infiltration,

    Chemical Exposure, Flash Fire

    or Fireball, Vapor Cloud

    Explosion

    6 5 5 3 5 5

    Vacuum DamageRating for Full lVacuum Not Entered

    for Low Design Pressure EquipmentPressure-Low BPCS Instrument Loop Failure Failure of Pressure Control

    Full Bore Hole Size Leak above

    Liquid Level

    On-Site Toxic Release, Flash

    Fire or Fireball3 4

    Excessive Heat Input - Heat

    Transfer

    No Heating Media Temperature was

    notedPressure-High BPCS Instrument Loop Failure Failure of Flow Control

    Criteria for Triggering Incidents Not

    Met

    Excessive Heat Input -

    Mechanical

    Vapor Pressure plus pad gas

    exceeds Maximum Allowable

    Working Pressure or Relief Set

    Pressure at Maximum Temperature

    from Mechanical Energy Input

    Pressure-HighHuman Failure Action once per

    quarter or less

    Agitation or Pump Recirculation left running

    for extended time allowing slow temperature

    increase

    Vapor Relief Vent - Mechanical

    Energy

    Consequence Does Not Exceed

    Threshold Criteria for Continuing

    with LOPA

    Excessive Pad Gas Pressure

    Maximum Pad Gas Pressure Does

    Not Exceed the Maximum Allowable

    Working Pressure or Relief Set

    Pressure

    Flow-High Regulator FailureRegulator Fails causing high flow or

    pressure

    Criteria for Triggering Incidents Not

    Met

    Excessive Heat Input - Pool Fire

    Exposure

    Overfill, Overflow, or Backflow

    IEF=3 as determined by Process

    Safety

    BPCS Instrument Loop Failure

    Leak of Flammable Material or Material

    above its Flash Point which may ignite

    Failure of Level Indication with continued

    addition of material

    Vapor Pressure exceeds Relief Set

    or Burst Pressure from Pool Fire

    Exposure

    Maximum Feed Pressure or

    Downstream Equipment Pressure is

    not sufficient to active Relief Device

    resulting in Overfill

    Pressure-High

    Level-High or Flow-

    Backflow

    Potential Outcome / Tolerable Frequency Factors

    Suggested Scenarios from the RAST Library

    Scenarios in gray were

    considered but are excluded for

    reason noted

    Scenarios with NO IPL's Required will NOT be reported.

    V-101 is a Vessel/Tank containing Acrylonitrile that operates at 25 C and 0.01 bar.

    The volume is 100 cu m with a maximum allowable working pressure of 0.2 bar.

    The maximum feed or flow rate is 400 kg/min.

    Off-

    Site

    Tox

    ic R

    elea

    se

    On-

    Site

    Tox

    ic R

    elea

    se

    Indo

    or T

    oxic

    Rel

    ease

    Toxi

    cIn

    filtr

    atio

    n

    Che

    mic

    alE

    xpos

    ure

    Flas

    hFi

    re o

    r Fir

    ebal

    l

    Vap

    or C

    loud

    Exp

    losi

    on

    Bui

    ldin

    g E

    xplo

    sion

    Equ

    ipm

    ent E

    xplo

    sion

    Pro

    pert

    y D

    amag

    e or

    Bus

    ines

    s Lo

    ss

    Env

    iron

    men

    tal D

    amag

    e

    Update Go To Scenario Results >

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    April 12, 2019 Slide - 17

    Consequence: The undesirable result of a loss event, usually measured in

    health and safety effects, environmental impacts, loss of property, and

    business interruption costs.

    Consequence Analysis: The analysis of the expected effects of incident

    outcome cases, independent of frequency or probability.

    Consequence Analysis with RAST

    -Center for Chemical Process Safety

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    Containment Dike

    Liquid Feed Rate

    Liquid Flash and

    Aerosol Evaporation

    Pool

    Evaporation

    Vent

    Release

    Liquid

    Release

    Vessel or Equipment

    Rupture

    Inert Feed Rate

    Relief Release

    Containment Dike

    Liquid Feed Rate

    Liquid Flash and

    Aerosol Evaporation

    Pool

    Evaporation

    Vent

    Release

    Liquid

    Release

    Vessel or Equipment

    Rupture

    Inert Feed Rate

    Relief Release

    Illustration of Source Models for

    Release of Vapor and LiquidRAST uses various source and effect models

    from CCPS and other literature sources. Loss

    events are categorized as related to hole size

    (vapor, liquid, or two-phase), material balance

    (such as overfill), heat balance (such as

    vaporization resulting from fire exposure), rupture

    (instantaneous release) or equipment damage. If

    the release is liquid or two-phase, vapor rate is

    estimated from simple flashing, aerosol

    evaporation and pool evaporation models.

    For more information on methods used within

    RAST, refer to Chemical Hazard Engineering

    Fundamentals (CHEF) documentation.

    Consequence Modeling in RAST

    April 12, 2019 Slide - 18

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    April 12, 2019 Slide - 19

    Consequence Analysis with RASTRAST Version 1.2

    Release Location Outdoors

    Airborne Quantity Summary:

    Release Temperature, C 25.0 Factor Probability

    Release Pressure, barg 0.010

    Physical State at Release Conditions Liquid

    Heat Input, Kcal/min

    Equivalent Hole Size, cm 1.000

    Release Rate, Kg/sec 0.45

    Release Duration, min 60.00

    Spray Distance, m 5.8

    Flash + Aerosol Evaporation Fraction 0.003

    Estimated Aerosol Droplet Diameter, micron 1225

    Pool Area, sq m 159.3

    Estimated Pool Temperature, C 8.2

    Maximum Pool Evaporation Rate, kg/sec 0.2457

    Total Airborne Rate, kg/sec 0.24

    Total Airborne Quantity, Kg 447.6

    Airborne Quantity Composition:

    Mole Fraction Acrylonitrile 1.000

    Mole Fraction Pad Gas (at Mw = 29)

    ERPG-2 for Vapor Composition, ppm by volume 56.6

    ERPG-3 for Vapor Composition, ppm by volume 121.3

    LFL for Vapor Composition, % by volume 3.00

    CONSEQUENCE SUMMARY Date:

    Gasket FailureLoss Event for: Vessel/Tank; V-101 Containing

    Acrylonitrile :

    with Personnel Not in Immediate Area

    Prob of Exposure (proximity based)

    Fence Line

    Concentration

    Exceeds ERPG-2

    On-Site Toxic POE

    Flash Fire POE

    Physical Explosion POE

    Chemical Exposure POE

    Ground or Work Area

    Exceeds Multiple of

    LFL or Time-Scaled

    ERPG-3

    RAST Version 1.2

    Dispersion Summary:

    Max Distance to Time-Scaled ERPG-2, m 180.4

    Max Distance to Time-Scaled ERPG-3, m 123.2

    Max Distance to 1% Lethality for 1.5 F weather, m 350.7

    Max Distance to Severe Toxic Impact, m 55.4

    Max Distance to 0.5 LFL, m 15.5

    Maximum Ground Elevation Concentration, ppm 1000000.0

    Concentration at Distance to Fence Line, ppm 56.8

    Concentration at Distance to Unrestricted Work Area, ppm 1000000.0

    Concentration at Distance to Occupied Bldg 1, ppm 374.9

    Concentration at Distance to Occupied Bldg 2, ppm

    Concentration within Enclosed Process Area, ppm

    Conc within Enclosed Process Area w/Ventilation, ppm

    Explosion Summary:

    VCE or Building Explosion Distance to 1 psi Overpressure, m 2

    Overpressure at Distance to Occupied Building, psi

    Overpressure at Center of Occupied Building, psi

    Distance to Severe Thermal Radiation Impact, m

    Distance to Direct Blast Impact (10 psi), m

    Maximum Fragment Range, m 2

    Rupture Distance to 1 psi Overpressure, m

    Rupture Overpressure at Distance to Occupied Building, psi

    Ruture Overpressure at Center of Occupied Building, psi

    CONSEQUENCE SUMMARY Date:

    Gasket FailureLoss Event for: Vessel/Tank; V-101 Containing

    Acrylonitrile :

    Probability of Ignition (POI)

    Probability of Explosion (POX)

    Potential Toxic Impact

    to Occupied Building

    (Conc > ERPG-3)

    A Consequence Analysis report is provided for any Loss Event. Each analysis includes a summary of the source model, dispersion model and explosion model if applicable.

    Either results of the Consequence Analysis or a Qualitative Consequence Severity may be used for Risk Analysis within RAST

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    April 12, 2019 Slide - 20

    Frequency Evaluation with RASTScenario Frequency in RAST is order-of-magnitude and based on independence of

    initiating events, enabling conditions/conditional modifiers and protective layers. Tables

    of initiating event frequencies, enabling condition or conditional modifier probabilities

    (such as probability of ignition), and probability of failure upon demand (PFD) for

    independent protective layers (IPL) are stored as administrative parameters.

    Residual failures (those leaks represented by chronic issues such as wear or fatigue

    rather than a process upset) are labeled Mechanical Integrity scenarios in RAST with

    frequency based on correlation on published leak frequency data. The User may either

    include or exclude residual failures in Risk Analysis.

    These tables and correlation coefficients may be updated to reflect a company’s specific

    frequency values for use in risk analysis. The scenario frequency is simply the product of

    the initiating event frequency times the enabling condition or conditional modifierprobability times the failure probability for each IPL appropriate for the scenario.

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    April 12, 2019 Slide - 21

    Risk - A measure of human injury, environmental damage, or economic loss

    in terms of both the incident likelihood and the magnitude of the loss or injury.

    Risk Analysis - The estimation of scenario, process, facility and/or

    organizational risk by identifying potential incident scenarios, then evaluating

    and combining the expected frequency and impact of each scenario having a

    consequence of concern, then summing the scenario risks, if necessary, to

    obtain the total risk estimate for the level at which the risk analysis is being

    performed.

    Risk and Risk Analysis

    -Center for Chemical Process Safety

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    Risk Analysis within RAST involves converting the Consequence Severity and

    Scenario Frequency to graduated scales representing order-of-magnitude levels.

    A tabular Risk Matrix is used to summarize results with each cell in the matrix (at

    intersecting values of Consequence Severity and Scenario Frequency)

    representing a specific value of scenario risk.

    Tolerable Risk may also be summarized in the same tabular Risk Matrix and

    compared to scenario risk in determining if further risk reduction is needed.

    The values of tolerable frequency for the various Consequence Severity levels are

    administrative parameters that should be updated to reflect a specific company’s

    risk tolerance criteria. The default parameters provided in RAST should be

    considered “examples” as CCPS does not endorse any specific risk criteria.

    RAST Analysis within RAST

    April 12, 2019 Slide - 22

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    Example Risk Matrix within RAST

    April 12, 2019 Slide - 23

    2 3 4 5 6 7

    Description Human Harm Environment Business Loss 10^-2/year 10^-3/year 10^-4/year 10^-5/year 10^-6/year 10^-7/year

    Reportable Incident to Environmental Agency OR

    < 10 kg Very Toxic to Waterway OR < 100 kg NFPA-H4 to Soil

    < 100 kg Toxic to Waterway OR < 1000 kg NFPA-H3 to Soil

    < 1000 kg Harmful to Waterway OR < 10000 kg NFPA-H2 to Soil

    Environmental Contamination Confined to Site OR

    < 100 kg Very Toxic to Waterway OR < 1000 kg NFPA-H4 to Soil

    < 1000 kg Toxic to Waterway OR < 10000 kg NFPA-H3 to Soil

    < 10000 kg Harmful to Waterway OR < 100000 kg NFPA-H2 to Soil

    Environmental Contamination of Local Groundwater OR

    < 1000 kg Very Toxic to Waterway OR < 10000 kg NFPA-H4 to Soil

    < 10000 kg Toxic to Waterway OR < 100000 kg NFPA-H3 to Soil

    < 100000 kg Harmful to Waterway OR < 1000000 kg NFPA-H2 to Soil

    Incident Requiring Significant Off-Site Remediation OR

    < 10000 kg Very Toxic to Waterway OR < 100000 kg NFPA-H4 to Soil

    < 100000 kg Toxic to Waterway OR < 1000000 kg NFPA-H3 to Soil

    > 100000 kg Harmful to Waterway OR > 100000 kg NFPA-H2 to Soil

    Incident with Significant National Media Attention OR

    < 100000 kg Very Toxic to Waterway OR < 1000000 kg NFPA-H4 to Soil

    > 100000 kg Toxic to Waterway OR > 1000000 kg NFPA-H3 to Soil

    Acceptable

    Tolerable - Offsite

    Tolerable - Onsite

    Unacceptable

    Low

    Con

    sequ

    ence

    Hig

    h

    Con

    sequ

    ence

    Low

    Frequency

    High

    Frequency

    Consequence Severity Description Frequency

    Severity Level-1

    Minor Injury On-site

    (or < 0.01 Person Severely Impacted On-site)

    Potential for Adverse Local Publicity

    Property Damage and

    Business Loss < $50M2 Orange Yellow

    Green

    Green

    Yellow> 10 People Severely Impacted On-site

    > 1 Person Severely Impacted Off-site

    Property Damage and

    Business Loss > $50 MM6 Red

    Red Red Orange Yellow GreenSeverity Level-41 to 10 People Severely Impacted On-site

    0.1 to 1 People Severely Impacted Off-site

    Property Damage and

    Business Loss $5 MM to

    $50 MM

    Legend

    6

    Yellow Green GreenSeverity Level-2

    Major Injury On-site

    (or 0.01 to 0.1 Person Severely Impacted On-site)

    Public Required to Shelter Indoors

    (or Minor Injury Off-site)

    Property Damage and

    Business Loss $50 M to

    $500 M

    3 Red

    Red Orange Yellow GreenSeverity Level-3

    Potential Fatality On-site

    (or 0.1 to 1 Person Severely Impacted On-site)

    or Potential Major Injury Off-site

    Property Damage and

    Business Loss $5 MM to

    $50 MM

    4 Red

    Severity Level-5

    6

    Red Orange

    5 Red

    Risk Matrix: Risk = Consequence Severity times Frequency

    Red Red

    Green Green Green Green

    Orange

    Each company determines the acceptable, unacceptable and tolerable

    frequencies for the consequence severity of a single scenario

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    Example Risk Analysis within RAST

    April 12, 2019 Slide - 24

    A Layers of Protection Analysis (LOPA) workbook within RAST is used to

    summarize the risk associated with each scenario to be analyzed. Scenarios are

    selected from a list of potential scenarios for risk analysis by the analysis team.

    Scenarios of relatively low risk may be screened out from LOPA consideration

    based on a company’s risk screening criteria which may be entered as

    administrative parameters.

    Those scenarios representing “worst cases” are noted (those requiring the greatest

    number of protective layers to meet a company’s risk tolerance criteria) to aid the

    analysis team in selecting which scenarios to include in the analysis.

    During LOPA, the study team adds additional cost effective IPLs until each scenario

    is at or below the tolerable risk criteria.

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    Example LOPA Worksheet within RAST

    April 12, 2019 Slide - 25

    Study Team updates Initiating Event

    Description and assigns Frequency Factor

    Study Team enters or updates any Enabling

    Condition or Conditional Modifier Probability

    Study Team reviews Scenario Description and Updates Consequence Severity

    Tolerable Frequency Factor

    Study Team enters Description and PFD for all Protective Layers to

    be Utilized

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    April 12, 2019 Slide - 26

    Documentation within RASTRAST maintains datasets of new chemicals, suggested scenarios,

    consequence analysis results, and layers of protection analysis results for

    each equipment item evaluated. These datasets are compatible with and

    may be imported into newer versions of the RAST tools to effectively

    manage the data and documentation associated with the study. Future

    HIRA studies for the facility are easily updated by importing previous

    studies into the latest version of RAST, review and update of inputs, and

    generation of updated reports.

    Key reports include: Summary of Hazards, List of Suggested Scenarios,

    Consequence Analysis for Loss Events, and a Layers of ProtectionAnalysis worksheet.

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    April 12, 2019 Slide - 27

    Desired Roles within a HIRA Study using RAST❑ Study Leader – Organizes and facilitates study team meetings. Is

    experienced in HIRA studies and ensures study objectives are being met.

    ❑ Scribe or Note Taker –Documents meeting progress and action items for the

    study team.

    ❑ Participant – Brings knowledge of facility design and/or operation to the study

    ❑ RAST User – Ensures appropriate inputs are entered into RAST to meet

    study objectives. Presents reports and results to the team to address

    questions and support decisions.

    ❑ RAST Technical Administrator – Ensures administrative parameters for

    RAST are consistent with company protocol and criteria. (May not necessarily

    participate in HIRA studies.)

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    April 12, 2019 Slide - 28

    Chemical Hazard Engineering Fundamentals (CHEF) is intended for newer engineers or

    as a refresher for experienced personnel. It describes methodology for performing a

    Hazard Identification and Risk Analysis (HIRA) study. There are many simplifying

    assumptions used that may not be suitable for every situation. A RAST User should be

    familiar with CHEF materials to recognize when a simplifying assumption may not be

    appropriate within a specific HIRA study.

    Risk Analysis Screening Tools (RAST Users) focuses on how to utilize the software in

    helping HIRA study teams to improve productivity, consistency, and quality of the studies.

    Various inputs and reports are described in detail with examples.

    RAST Technical Administrator is intended to show experienced Process Safety

    personnel how to incorporate a company’s specific risk matrix and other screening criteria

    into the RAST tools. It is intended for those filling a RAST Technical Administrator role

    rather than a RAST User.

    RAST Related Training Available

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    April 12, 2019 Slide - 29

    Risk Analysis Screening Tool (RAST)Links to RAST Materials from CCPS Web Site

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    CAI and Arnel Confined

    Space Explosion

    DPC Enterprises

    Chorine ReleaseT2 Laboratories Runaway

    Reaction and Explosion

    BP Refinery

    Explosion and Fire

    April 12, 2019 Slide - 30

    Risk Analysis Screening Tool (RAST)Case Studies on the CCPS Web Site

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    April 12, 2019 Slide - 31

    Risk Analysis Screening Tools (RAST)

    Case Study – CAI and Arnel

    CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance

    CONFINED SPACE EXPLOSION

    Danvers, Massachusetts

    November 22, 2006

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    April 12, 2019 Slide - 32

    Case Study – CAI and ArnelHazard Identification and Risk Analysis (HIRA) Study

    What are the Hazards?

    What can go Wrong?

    How Bad could it Be?

    How Oftenmight it

    Happen?

    Is the Risk Tolerable?

    Identify Chemical

    and ProcessHazards

    Estimate Frequency

    Analyze Consequences

    AnalyzeRisk

    IdentifyAdditional Safeguards as Needed

    DevelopScenarios

    Identify Equipment

    or Activity to be Analyzed

    Manage Barriers

    for Life Cycle of Facility

    We begin the study by Identifying the Equipment or Activity for which we intend to perform

    an analysis. RAST uses the operation of a specific equipment item containing a specific

    chemical or chemical mixture to define the activity. For example, the operation of a storage

    tank, a reactor, a piping network, etc. Inputs are chemical data, equipment designinformation, operating conditions, and plant layout.

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    April 12, 2019 Slide - 33

    Case Study – CAI and Arnel

    Process DescriptionThe Danversport , MA plant is a 12000 ft2 ink and paint manufacturing facility jointly owned by CAI and

    Arnel Companies. This facility began operations in the early 1960s within a minimally populated

    peninsula. Over several years, a large marina and many single family and duplex homes have located

    adjacent to the manufacturing plant, some homes as close as 150 ft. away.

    The CAI production manager and five employees manufactured solvent-based inks in the Danvers

    facility. At the end of each day, they loaded the day’s production of ink products onto a truck and

    delivered it to the Georgetown warehouse. CAI stored alcohols, heptane, other solvents, and pigments

    and resins in the building and in three 3000-gallon underground storage tanks (USTs).

    Nine Arnel employees worked in the Danvers facility, which was the company’s only business location.

    Arnel manufactured solvent- and water-based stains, lacquers, coatings, and paints, as well as

    polyurethane coatings and adhesives. They stored alcohols and other solvents, pigments, paint resins,

    and industrial grade nitrocellulose at the facility.

    This is an illustrative example and does not reflect a thorough or complete study.

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    April 12, 2019 Slide - 34

    Case Study – CAI and Arnel

    Process DescriptionCAI and Arnel mixed solvents,

    pigments, resins and nitrocellulose

    to produce inks and paints in 1000

    to 3000 gallon vessels. Vessels

    contained top mounted agitators

    and a steam heating jacket. Mix

    tanks 1 and 2 were fully open on

    top while mix tanks 3 and 4 were

    equipment with a 12 inch diameter

    access hatch to keep debris from

    falling into the tank but allowed

    vapor or air to pass through the

    opening.

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    April 12, 2019 Slide - 35

    The initial mixture of more than 2000 gal. of

    heptane and propyl alcohol is added to the tank

    from 500 gal. totes. Resin is hand loaded from

    fiber drums to the top of the tank. This mixture is

    then heated to between 90 and 120oF to dissolve

    the resin. Temperature control is achieved by

    manually opening a ¼ inch steam valve leading to

    the steam heating jacket. Following a quality

    control check, the liquid is pumped out the bottom

    of the mix tank to smaller pigment mixers, as

    needed. Unused resin-solvent mixture would

    remain in the mix tank until it was all utilized in

    specific ink products.

    Case Study – CAI and Arnel

    Process Description

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    April 12, 2019 Slide - 36

    Risk Analysis Screening Tools (RAST)

    Case Study – CAI and Arnel

    We will start by entering information for the Formulation Mixing Tank. At some point, we may

    decide to include other equipment in the study.

    One the Main Menu, enter the equipment identification as the Formulation Mixing Tank,

    equipment type as Stirred Reactor/Crystallizer and location as Indoors.

    Chemical Data – RAST requires a chemical or chemical mixture that is representative of the

    hazards. RAST does not perform time-dependent or location-dependent composition

    changes (such as within a reactor or distillation column). Where hazards may be

    significantly different between reactor feed and products, or distillation overheads versus

    bottoms; evaluation of the equipment may be repeated using different composition (such as

    Reactor A with feed composition and Reactor B with products composition).

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    Import from Previous Study

    Merge Data from Another Study into this Study

    Update Previously Saved Information

    Access LOPA Workbook from Scenario Results

    Update Notes and Comments for Entire Workbook

    Select Default Units: Study File: Case Study - CAI and Arnel Example.pptx.xlsm

    Session Date: Participants:

    Equipment Identification =

    Equipment Type =

    Equipment Location =

    Data Entry Status or Notes:

    Plant Section or Sub-Area:

    P&ID Number:

    Min

    Complete

    RAST

    Input Data Sufficient to Proceed with Analysis

    Input Information

    Stirred Reactor/Crystallizer

    Indoors

    Formulation Mixing Tank

    Evaluations and Reports

    Risk Analysis Screening Tools (V 2)Latest Revision Date 3/02/19

    Import from RAST File

    Equipment Parameter Input

    Chemical Data Input

    Reaction Input and Evaluation

    Fire & Explosion Index / Chemical Exposure Index

    English Units SI Units

    Relief Effluent Screening

    Scenario Identification

    Check Inputs

    Save Inputs toEquipment Table

    Go to Equipment Table >

    Process Conditions Input

    Plant Layout Input

    Hazards & Consequences

    LOPA Menu >

    Clear Input

    Update Scenarios for Equipment Loaded

    Input Guidance Information

    CLEAR EVERYTHING IN WORKBOOK

    Pool Fire Evaluation

    Merge Data from Another File

    Go to Workbook Notes >

    Go to Revision Log >

    Go To Scenario Results >

    Go To Instructions >>

    April 12, 2019 Slide - 37

    Enter Equipment Identification,

    Equipment Type and Location

    Risk Analysis Screening Tools (RAST)

    Case Study – CAI and Arnel

    Begin by entering

    information on the Main

    Menu worksheet. Start

    with the Formulation

    Mixing Tank

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    Chemical Data Input

    Equipment Identification: 40 C

    Equipment Type: 0.01 bar

    Location: 100.8 C

    Key Chemical: Reference:

    Chemical Comments:

    Reg. Agency Considers Toxic?

    Heptane 0.450 0.659 1.9374 100.2 800 4900 1.1

    Propanol, 1- 0.450 0.340 1.0000 60.07 250 4000 2.0

    Dissolved Solids 0.100 0.001 0.0082 100

    Sum = 1.00 Vapor Mixture Properties: 81.6 396.7 4440.3 1.4

    Mixture azeotrope? No

    Melting Point = -126 deg C

    Flash Point = -4 deg C

    Est Mixture Flash Point = 9.1 deg C

    1 Not “Sustained Burning”?

    AutoIgnition Temperature = deg C

    Ease of Ignition = Normal

    Fuel Reactivity = Medium

    Dermal Toxicity =

    Aquatic Toxicity =

    Model as a single Pseudo-Chemical? Mixture NFPA Flammability = 3

    Mixture NFPA Health = 1

    Reactivity Category =

    Mixture NFPA Reactivity = 0

    Estimated Boiling Point = 100.5 C Liquid Conductivity = Non-Conductive

    Vapor Pressure at Operating Temp = 0.081 atm

    Liquid Density at Operating Temp = 0.75 gm/ml

    Liq Heat Capacity at Op Temp = 0.59

    Liq Heat Capacity at Boiling Point = 0.69 micron

    Heat of Vaporization at Op Temp = 118 micron

    Heat of Vaporization at Boiling Point = 105 mJoule

    Boiling Point at Relief Set or MAWP = 103.3 C

    Boiling Point at Burst Pressure = 104.6 C

    From the above vapor composition: Estimated 1 hour LC 1 8880.5 ppm Estimated 1 hour LC 50 22201.3 ppm

    State Mol Weight ERPG-2 (ppm) ERPG-3 (ppm) LFL (vol %) Flash Pt (C )

    Pad Gas Properties Vapor 29

    Heat Transfer Fluid Vapor 18

    High Viscous Material (for F&EI)?

    Mixture Properties

    Wt Fraction

    Feed

    Molecular

    Weight

    Second Liq

    Phase

    Relative

    Volatility

    Wt Fraction

    Vapor

    User ValuesMixture

    Estimates

    ERPG-3 (ppm)ERPG-2 (ppm) LFL (vol %)

    Liquid

    Operating Temperature =

    Heptane

    Formulation Mixing Tank

    Indoors

    Stirred Reactor/Crystallizer

    Second Liq

    Phase

    Chemicals (the first chemical listed is the 'key' chemical)

    Wt Fraction

    Feed

    Saturation Temperature =

    Physical State =

    Operating Pressure (gauge) =

    Solids Mean Particle Size =

    cal/gmDust Min Ignition Energy =

    Name

    Water

    Dust-flammable hybrid?

    Particle Size at 10% Fraction =

    Solids Bulk Density >160 g/liter (>10 lb/ft3)?

    Summary of Chemical Properties

    cal/gm C

    Standard Mixture (the key chemical has been defined as a mixture)

    Dust CharacteristicsDust/Solids Hazard Class =

    Go To Process Conditions >Save All Input to Equipment TableEnter New Chemical Clear Input

    Show Chemical Details Hide Chemical Details

    Go To Equipment Input >

    April 12, 2019 Slide - 38

    Case Study – CAI and Arnel

    Chemical Data

    Saturation temperature is

    estimated as the boiling point

    at the operating pressure.

    The physical state is “liquid”

    Fortunately, all the chemicals needed

    in this evaluation are already in the

    Chemical Data Table internal to RAST.

    The solvent mixture concentration is

    assumed equal fractions of heptane

    and 1-propanol with a small amount of

    dissolved solids to represent the

    nitrocellulose resin is used as

    representative of the hazards.

    The operating pressure is essentially

    atmospheric such that 0.01 bar gauge

    is entered.

    RAST allows up to 5

    components.

    Chemical details may

    be shown or hidden

    The operating temperature of 40

    C represents a mixture at 90 to

    120 F. The operating pressure

    entered as 0.01 bar gauge

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    Equipment Input

    Equipment Identification:

    Equipment Type:

    Location:

    3000 gal Pipe Length = m

    0.1 bar Piping Vulnerable to Damage?

    Apply Screwed Connection Penalty?

    C

    C

    3 in Pump Type =

    Seal or Containment Type =

    Remote Start Pump?

    354 kg Pump Automated Suction or Discharge?

    kg Estimated User EntryPump Volume (including piping to block valves), liter 7.1

    Pump Surface (including piping to block valves), m2 0.43

    5 HP

    Equipment or Piping Connection =

    23 sq m

    sq m Replacement Cost & Business Loss

    m Drum Oven Volume = cu m

    mm High Speed Rotating Equipment?

    Bellows or Expansion Joint Used?

    Sight Glass Used?

    Relief Device Identification

    Relief Type =

    Relief Discharges to:

    Relief Set Pressure (gauge) = bar

    50 sq ft Relief Size (equiv. diameter) = mm

    100 BTU/hr sq ft F Relief Design Actual Flow Rate = kg/min

    120 C Release Pipe Diameter = mm

    0.5 bar Release Elevation m

    Closest Distance From Relief to Elevated Work Area = m

    Heat Transfer Fluid Name = Furthest Distance from Relief to Elevated Work Area = m

    Vapor Elevation of Nearest Work Area = m

    Enter Distances from Relief Location ONLY if Different from Equipment Location

    mm Relief Distance to Property Limit or Fence Line = m

    Relief Distance to Occupied Bldg 1 or Area = m

    sq m Relief Distance to Center of Occ Bldg 1 = m

    Kwatt /sq m C Occ Bldg 2 in Same Wind Direction for Relief?

    C Relief Distance to Occupied Bldg 2 = m

    Relief Distance to Center of Occ Bldg 2 = m

    Piping Parameters

    Pump / Agitator Parameters

    MAWP (gauge) =

    Equipment Description

    Formulation Mixing Tanks are 8 ft diameter by 10 ft tall.

    Equipment Volume =

    Stirred Reactor/Crystallizer

    Equipment Parameters

    Full Vacuum Rated?

    Estimated High Temperature Failure =

    Estimated Embrittlement Temperature =

    Equipment Elevation to Surface =

    Drain Valve Size

    Formulation Mixing Tank

    Indoors

    Susceptible to Vibration Fatigue?

    Motor Power =

    User Equipment Max. Wetted Area =

    Heat Transfer Fluid State =

    Vessel/Tank Parameters

    Material of Construction

    Internal Corrosive or Stress Cracking Potential?

    Equipment Mass =

    Number of Flanges or Nozzles =

    Nozzle or Pipe Size =

    Estimated Equip Mass based on C. Steel

    Other Equipment Parameters

    Transportation Equipment or Piping Parameters

    Tube Failure Release to Atmosphere?

    Insulation

    Estimated Equipment Max Wetted Area =

    Heating Fluid Temperature =

    Heating Transfer Area =

    Indoors

    Tracing ?

    Vessel/Tank Geometry?

    Insulation Heat Reduction Factor =

    Warning: Operating Pressure Greater than Relief Set Pressure

    Low Pressure Tank with Weak Seam Roof?

    Coolant Temperature =

    Conductive Dip Pipe or Bottom Fill?

    Cooling Transfer Area =

    Tube (or Leak) Diameter =

    Quantity Hot Oil Handled (for F&E) =

    Cooling Overall U =

    Number of Tubes =

    Relief Device Parameters

    Heat Transfer Parameters

    Heating Overall U =

    Water

    Heat Transfer Fluid Pressure (gauge) =

    Vessel/Tank Considered as "Storage"?

    Clear InputSave Input to Equipment Table< Go To Chemical Data

    Go To Plant Layout >

    Go To Reaction Input >

    April 12, 2019 Slide - 39

    Case Study – CAI and Arnel

    Equipment InputThe relief device is essentially

    the 12 inch access hatch on

    the top of the vessel and

    vented “Indoors” which is not

    typical.

    The vessel jacket/bottom

    head is roughly 50 ft2 and

    heated by low pressure

    steam.

    Only minimal data will be

    entered at this time.

    The equipment volume

    and maximum allowable

    working pressure

    A largest “working” nozzle

    of 3 inches is entered

    representing the bottom

    liquid outlet.

    The relief device is

    considered the 12 in hatch

    which vents indoors.

    Heat transfer

    information is entered.

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    April 12, 2019 Slide - 40

    Case Study – CAI and Arnel

    Process Conditions

    Ambient temperature of 25 C

    has been assumed (input left

    blank such that the default value

    is used).

    The maximum flowrate to the

    tank is approximately 50

    gal/min. from 500 gallon totes.

    The maximum liquid height in

    the vessel is 8 ft.

    Process Conditions Input

    Equipment Identification:

    Equipment Type:

    Location:

    Ambient Temperature = Operating Temperature = 40 C

    Inventory Limit (blank is unlimited) = kg Operating Pressure (gauge) = 0.01 bar

    Liquid Head within Equipment, Dh = 8 ft Physical State =

    Limiting Maximum Fill Fraction = Saturation Temperature = 100.8 C

    Limiting Minimum Fill Fraction = Contained Mass = 6856 kg

    Maximum Feed Press (gauge) = bar Maximum Contained Mass = 8569 kg

    Maximum Feed or Flow Rate = 50 gal/min Inventory for Reference = 17139 kg

    Maximum Feed Temperature = C

    Type of Feed (Batch or Continuous)

    Non-Ignitable Atmosphere Maintained?

    Potential for Aerosol or Mist?

    Pad Gas Name = Percent of Time in Operation =

    Max Pad Gas Pressure (gauge)= bar

    Maximum Pad Gas Rate = kg/min

    Downstream Pressure (gauge) = bar

    Maximum Back Flow Rate = kg/min

    Equipment Vents to .. =

    Use Time-based Release for Equipment Rupture? sec

    Formulation Mixing Tank

    Stirred Reactor/Crystallizer

    Process Description

    Process/Operating Conditions

    Indoors

    Summary for Heptane

    Frequent Turnaround or Cleanout?

    Operating Procedures

    Liquid

    Review Date:

    Review of Operating Procedures for

    Selected Equipment Item by:

    Centralized Ventilation Shut-Off Bldg 1?

    Centralized Ventilation Shut-Off Bldg 2?

    Clear InputSave Input to Equipment Table< Go To Chemical Data

    Go To Plant Layout >

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    April 12, 2019 Slide - 41Approximately 100 ft

    Case Study – CAI and Arnel

    Site Layout

    The enclosed production

    area (denoted as C, D, and

    E) is approximately 10,000

    ft3. Areas denoted A and B

    contained offices and a

    laboratory. Fiber drums of

    nitrocellulose were stored in

    trailers east of the building.

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    April 12, 2019 Slide - 42Approximately 500 ft

    Case Study – CAI and Arnel

    Site Layout

    A marina is adjacent to the

    site, approximately 150 ft

    east of the manufacturing

    area. A residential

    community is approximately

    100 ft north with the nearest

    houses 150 ft away.

    The CAI and Arnel facility is

    circled in the photograph.

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    April 12, 2019 Slide - 43

    Case Study – CAI and Arnel

    Site LayoutThere is a total of 15 employees

    between CAI and Arnel. For now, it is

    assumed that during normal work hours,

    2 people might be in the production area

    and 5 in the offices and laboratory.

    There has been assumed to be 10

    people located at the marina between

    customers, maintenance and sales staff.

    The enclosed process area is estimated

    to be 200,000 ft3. There are two 6,000

    cfm exhaust fans allowing roughly 3.6

    air changes per hour when running.

    Plant Layout Input

    Equipment Identification:

    Equipment Type:

    Location:

    Distance to Property Limit or Fence Line = 100 ft Occupied Building 1 Name =

    Furthest Distance to Fence Line ( > 30.48 m ) = m Distance to Occupied Bldg 1 or Area = 50 ft

    Max. Onsite Outdoor Population Density people/m2 Elevation of Occ Bldg 1 Ventilation Inlet = m

    Personnel Routinely in Immediate Area? Distance to Center of Occupied Bldg 1 = m

    Distance to end of Offsite Zone 1 m Occupied Bldg Type =

    Offsite Population Density within Zone 1 people/m2 Occupied Bldg Ventilation Rate = changes/hr

    Offsite Population Density Beyond Zone 1 people/m2 Number of Building Occupants = 5

    Effective Egress from Work Area? Occ Bldg 2 in Same Wind Direction? No

    Access for Emergency Services? Occupied Building 2 Name =

    Degree of Equipment Congestion in Area? Distance to Occupied Bldg 2 150 ft

    Containment or Dike Surface Area = sq m Elevation of Occ Bldg 2 Ventilation Inlet = m

    Consider Dike or Bund Failure for Vessel Rupture? Distance to Center of Occ Bldg2 = m

    Credit Fire Heat Adsorption for Drainage/Indirect? Occupied Bldg 2 Type =

    Distance to Nearest Fired Equipment = Occupied Bldg 2 Ventilation Rate = changes/hr

    Quantity of "Other" Flammables in Immediate Area kg Number of Occupants Bldg 2 = 10

    Quantity of Flammables in Adjacent Area kg

    Adjacent Containment or Dike Surface Area = sq m

    Automated EBVs to limit spill quantity?

    Spills to Soil Require Remediation?

    Potential for Water Contamination?

    Enclosed Process Volume = 200000 cu ft High Population Downstream of Facility?

    Enclosed Process Ventilation = 3.6 changes/hr

    No. Enclosed Area Personnel = 2

    Note that Environmental Scenarios are Excluded

    Enclosed Process Area Data

    Occupied Building DataLocation Information

    Environmental Inputs

    Marina

    Plant Offices and Laboratory

    Formulation Mixing Tank

    Stirred Reactor/Crystallizer

    Indoors

    Layout Description

    Process Areas C, E, and F are approximately 10,000 ft2 by maybe 20 ft

    height. Office area B roughly 50 ft from mixing tanks

    Clear InputSave Input to Equipment Table< Go To Process Conditions

    Go To Reaction Input >

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    Indoor Chemical Processing often intensifies hazards as dilution of

    airborne chemicals is minimized. Release quantities to reach

    flammable or toxic concentrations may be very small.

    An enclosed manufacturing volume of 1000 m3 only requires approximately 40 kg

    flammable vapor (such as 38 kg propane) for the entire volume to reach the

    lower flammable limit. A chemical with ERPG-3 of 150 ppm would only require

    0.15 m3 of toxic vapor (such as 0.23 kg HCl) to reach a potentially toxic

    concentration within the enclosed process area.

    Chemical Processing Indoors

    April 12, 2019 Slide - 44

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    April 12, 2019 Slide - 45

    Risk Analysis Screening Tools (RAST)

    Case Study – CAI and Arnel

    Input Data for an Equipment Item

    stored in one row by Equipment Tag

    Retrieve Information for an Equipment

    Item by selecting any cell in the desired

    row and entering Load Selected

    Select Save Inputs to Equipment Table (blue macro button). All Input Information

    will be stored in the Equipment Table in a single row identified by a unique Equipment

    Identification or Tag.

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    Risk Analysis Screening Tools (RAST)

    Risk Matrix

    April 12, 2019 Slide - 46

    To understand the Consequence

    Severity and Tolerable Frequency, the

    values for key Study Parameters and a

    Risk Matrix may be viewed on the

    Workbook Notes worksheet. These

    values may be updated on hidden

    worksheets and should reflect the

    company’s specific risk criteria.

    For this case study, the Risk Matrix

    (right) has been used. The Human

    Harm criteria is based on an estimated

    number of people severely impacted

    (severe injury including fatality).

    2 3 4 5 6 7

    Description Human Harm Environment Business Loss 10^-2/year 10^-3/year 10^-4/year 10^-5/year 10^-6/year 10^-7/year

    Reportable Incident to Environmental Agency OR

    < 10 kg Very Toxic to Waterway OR < 100 kg NFPA-H4 to Soil

    < 100 kg Toxic to Waterway OR < 1000 kg NFPA-H3 to Soil

    < 1000 kg Harmful to Waterway OR < 10000 kg NFPA-H2 to Soil

    Environmental Contamination Confined to Site OR

    < 100 kg Very Toxic to Waterway OR < 1000 kg NFPA-H4 to Soil

    < 1000 kg Toxic to Waterway OR < 10000 kg NFPA-H3 to Soil

    < 10000 kg Harmful to Waterway OR < 100000 kg NFPA-H2 to Soil

    Environmental Contamination of Local Groundwater OR

    < 1000 kg Very Toxic to Waterway OR < 10000 kg NFPA-H4 to Soil

    < 10000 kg Toxic to Waterway OR < 100000 kg NFPA-H3 to Soil

    < 100000 kg Harmful to Waterway OR < 1000000 kg NFPA-H2 to Soil

    Incident Requiring Significant Off-Site Remediation OR

    < 10000 kg Very Toxic to Waterway OR < 100000 kg NFPA-H4 to Soil

    < 100000 kg Toxic to Waterway OR < 1000000 kg NFPA-H3 to Soil

    > 100000 kg Harmful to Waterway OR > 100000 kg NFPA-H2 to Soil

    Incident with Significant National Media Attention OR

    < 100000 kg Very Toxic to Waterway OR < 1000000 kg NFPA-H4 to Soil

    > 100000 kg Toxic to Waterway OR > 1000000 kg NFPA-H3 to Soil

    Acceptable

    Tolerable - Offsite

    Tolerable - Onsite

    Unacceptable

    Low

    Con

    sequ

    ence

    Hig

    h

    Con

    sequ

    ence

    Low

    Frequency

    High

    Frequency

    Consequence Severity Description Frequency

    Severity Level-1

    Minor Injury On-site

    (or < 0.01 Person Severely Impacted On-site)

    Potential for Adverse Local Publicity

    Property Damage and

    Business Loss < $50M2 Orange Yellow

    Green

    Green

    Yellow> 10 People Severely Impacted On-site

    > 1 Person Severely Impacted Off-site

    Property Damage and

    Business Loss > $50 MM6 Red

    Red Red Orange Yellow GreenSeverity Level-41 to 10 People Severely Impacted On-site

    0.1 to 1 People Severely Impacted Off-site

    Property Damage and

    Business Loss $5 MM to

    $50 MM

    Legend

    6

    Yellow Green GreenSeverity Level-2

    Major Injury On-site

    (or 0.01 to 0.1 Person Severely Impacted On-site)

    Public Required to Shelter Indoors

    (or Minor Injury Off-site)

    Property Damage and

    Business Loss $50 M to

    $500 M

    3 Red

    Red Orange Yellow GreenSeverity Level-3

    Potential Fatality On-site

    (or 0.1 to 1 Person Severely Impacted On-site)

    or Potential Major Injury Off-site

    Property Damage and

    Business Loss $5 MM to

    $50 MM

    4 Red

    Severity Level-5

    6

    Red Orange

    5 Red

    Risk Matrix: Risk = Consequence Severity times Frequency

    Red Red

    Green Green Green Green

    Orange

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    HAZOP Node: HAZOP Design IntentPlant Section =

    Equipment Type = Stirred

    Reactor/Crystallizer

    Equipment Tag = Formulation Mixing

    Tank

    LOPA Menu Filters:

    Scenario Type Scenario CommentsParameters and

    DeviationInitiating Event (Cause) Initiating Event Description Loss Event Outcome

    Off

    -Sit

    e T

    oxi

    c R

    elea

    se

    On

    -Sit

    e T

    oxi

    c R

    elea

    se

    Ind

    oo

    r T

    oxi

    c R

    elea

    se

    To

    xic

    Infi

    ltra

    tio

    n

    Ch

    emic

    al E

    xpo

    sure

    Fla

    sh F

    ire

    or

    Fir

    ebal

    l

    Vap

    or

    Clo

    ud

    Exp

    losi

    on

    Bu

    ild

    ing

    Exp

    losi

    on

    Eq

    uip

    men

    t E

    xplo

    sio

    n

    Pro

    per

    ty D

    amag

    e o

    r B

    usi

    nes

    s L

    oss

    En

    viro

    nm

    enta

    l D

    amag

    e

    Drain or Vent Valve Open

    Drain or Vent Valve left open following

    infrequent maintenance, purging or

    cleaning

    Flow-Loss of

    Containment

    Human Failure Action once per

    quarter or less

    Operator leaves Drain or Vent Open

    following infrequent maintenanceDrain or Vent Leak Flash Fire or Fireball 4

    Vapor Relief Vent - Heat TransferFlash Fire or Fireball, Building

    Explosion5 6

    Equipment Rupture at Saturation

    Temperature

    Flash Fire or Fireball, Building

    Explosion5 6

    Vapor Relief Vent - FireIndoor Toxic Release, Flash Fire

    or Fireball, Building Explosion5 5 6

    Equipment Rupture at Fire Conditions Flash Fire or Fireball 3

    Ignitable Headspace

    Chemical is Flammable or

    Combustible: Maximum Operating,

    Mechanical Energy or Heating Media

    Temperature exceeds Flash Point

    less 5 C

    Composition-Wrong

    ConcentrationBPCS Instrument Loop Failure

    Failure of Pressure or NonCombustible

    Atmosphere ControlEquipment Rupture - Deflagration Flash Fire or Fireball 3

    Overfill Release Flash Fire or Fireball 5

    Equipment Rupture at Operating

    Temperature

    Flash Fire or Fireball, Building

    Explosion5 6

    Excessive Heat Input -

    Mechanical

    Vapor Pressure plus pad gas Does

    Not exceed Maximum Allowable

    Working Pressure or Relief Set

    Pressure at Maximum Temperature

    from Mechanical Energy Input

    Pressure-HighHuman Failure Action once per

    quarter or less

    Agitation or Pump Recirculation left running

    for extended time allowing slow temperature

    increase

    Criteria for Triggering Incidents Not

    Met

    Excessive Pad Gas Pressure

    Maximum Pad Gas Pressure Does

    Not Exceed the Maximum Allowable

    Working Pressure or Relief Set

    Pressure

    Flow-High Regulator FailureRegulator Fails causing high flow or

    pressure

    Criteria for Triggering Incidents Not

    Met

    High Temperature Failure

    Maximum Feed Temperature Does

    Not Exceed Temperature limits of

    Equipment

    Temperature-High BPCS Instrument Loop Failure Failure of Temperature ControlCriteria for Triggering Incidents Not

    Met

    Pad Gas Compression

    Maximum Feed or Downstream

    Pressure does not exceed the

    Maximum Allowable Working

    Pressure or Relief Set Pressure

    Pressure-High BPCS Instrument Loop Failure Failure of Pressure ControlCriteria for Triggering Incidents Not

    Met

    Piping or Equipment Leak - SmallAssessment Excludes Mechanical

    Integrity Scenarios

    Flow-Loss of

    ContainmentMechanical Failure

    Loss of Alignment or Equipment Support

    causing Vibration or Excessive Movement

    Criteria for Triggering Incidents Not

    Met

    Rotating Equipment DamageMotor Power below Rotating

    Equipment Vibration or Damage Limit

    Composition-

    ContaminantsMechanical Failure

    Breakage of rotating blade or internal parts

    due to alignment, wear,or fatigue

    Criteria for Triggering Incidents Not

    Met

    Seal Leak No Agitator Seal indicatedFlow-Loss of

    ContainmentSingle Mechanical Seal Failure

    Failure from corrosion, alignment, low flow,

    etc.

    Mechanical Seal Failure above Liquid

    Level

    Consequence Does Not Exceed

    Threshold Criteria for Continuing

    with LOPA

    Vacuum DamageRating for Full lVacuum Not Entered

    for Low Design Pressure EquipmentPressure-Low BPCS Instrument Loop Failure Failure of Pressure Control

    Full Bore Hole Size Leak above

    Liquid Level

    Consequence Does Not Exceed

    Threshold Criteria for Continuing

    with LOPA

    Excessive Heat Input - Heat

    Transfer

    Excessive Heat Input - Pool Fire

    Exposure

    Overfill or Backflow of liquid with spill

    rate equal to the feed rate to a

    maximum quantity of the available

    Level-High or Flow-

    BackflowOverfill, Overflow, or Backflow

    BPCS Instrument Loop Failure

    IEF=2 as determined by Process

    Safety

    Failure of Flow Control

    Leak of Flammable Material or Material

    above its Flash Point which may ignite

    BPCS Instrument Loop FailureFailure of Level Indication with continued

    addition of material

    Vapor Pressure plus pad gas

    exceeds Maximum Allowable

    Working Pressure or Relief Set

    Pressure at Ambient or Heating Media

    Vapor Pressure exceeds Relief Set

    or Burst Pressure from Pool Fire

    Exposure

    Pressure-High

    Pressure-High

    Potential Outcome / Tolerable Frequency Factors

    Suggested Scenarios from the RAST Library

    Scenarios in gray were

    considered but are excluded for

    reason noted

    Scenarios with NO IPL's Required will NOT be reported.Mechanical Integrity Scenarios will NOT be reported

    Formulation Mixing Tank is a Stirred Reactor/Crystallizer containing Heptane Mix

    that operates at 40 C and 0.01 bar. The volume is 3000 gal with a maximum

    allowable working pressure of 0.1 bar. The maximum feed or flow rate is 50

    gal/min.

    Off

    -Sit

    e T

    oxi

    c R

    elea

    se

    On

    -Sit

    e T

    oxi

    c R

    elea

    se

    Ind

    oo

    r T

    oxi

    c R

    elea

    se

    To

    xic

    Infi

    ltra

    tio

    n

    Ch

    emic

    alE

    xpo

    sure

    Fla

    shF

    ire

    or

    Fir

    ebal

    l

    Vap

    or

    Clo

    ud

    Exp

    losi

    on

    Bu

    ild

    ing

    Exp

    losi

    on

    Eq

    uip

    men

    t Exp

    losi

    on

    Pro

    per

    ty D

    amag

    e o

    r B

    usi

    nes

    s L

    oss

    En

    viro

    nm

    enta

    l D

    amag

    e

    Update Go To Scenario Results >

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    April 12, 2019 Slide - 48

    Case Study – CAI and Arnel

    Suggested Scenarios for Formulation Mixing Tank

    ❑ Review the suggested list of scenarios. Do these represent what you

    would expect for an indoor mix tank?

    ❑ Are there scenarios that have been “screened out” (shown in gray) that

    should be considered?

    ❑ Are there scenarios missing? (Possibly similar scenarios with different

    Initiating Events)

    ❑ Do you agree with the “worst” Consequence (Tolerable Frequency

    Factor) for the scenario listed?

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    RAST Version 2

    Release Location Indoors

    Airborne Quantity Summary:

    Release Temperature, C 103.3 Factor Probability

    Release Pressure, barg 0.100

    Physical State at Release Conditions Vapor

    Heat Input, Kcal/min 10.54

    Equivalent Hole Size, cm

    Release Rate, Kg/sec 0.09

    Release Duration, min 60.00

    Spray Distance, m 0.0

    Flash + Aerosol Evaporation Fraction

    Estimated Aerosol Droplet Diameter, micron

    Pool Area, sq m 0.0

    Estimated Pool Temperature, C

    Maximum Pool Evaporation Rate, kg/sec

    Total Airborne Rate, kg/sec 0.09

    Total Airborne Quantity, Kg 306.9

    Airborne Quantity Composition:

    Mole Fraction Heptane 0.356

    Mole Fraction Propanol, 1- 0.644

    Mole Fraction Dissolved Solids 0.000

    Mole Fraction Pad Gas (at Mw = 29)

    ERPG-2 for Vapor Composition, ppm by volume 331.0

    ERPG-3 for Vapor Composition, ppm by volume 4280.9

    LC-50 Concentration, ppm by volume 52430.0

    One-hour ERPG-3 for Vapor Composition, ppm by volume 4280.9

    One-hour LC-1 Concentration, ppm by volume 8561.8

    LFL for Vapor Composition, % by volume 1.55

    Dispersion Summary (Atmospheric Stability Class D with 3 m/sec wind except as noted):

    Max Distance to Time-Scaled ERPG-2, m 36.2

    Max Distance to Time-Scaled ERPG-3, m 3.8

    Max Distance to 1% Lethality for 1.5 F weather, m 0.1

    Max Distance to Estimated LC-50 Concentration, m 0.1

    Max Distance to Flash Fire Impact or 0.5 LFL, m 11.0

    Maximum Ground Elevation Concentration, ppm 1000000.0

    Concentration at Distance to Fence Line, ppm 455.1

    Concentration at Distance to Unrestricted Work Area, ppm

    Concentration within Occupied Bldg 1, ppm 677.1

    Concentration within Occupied Bldg 2, ppm 101.3

    Concentration within Enclosed Process Area, ppm 17817.8

    Conc within Enclosed Process Area w/Ventilation, ppm 4925.0

    Prob of Exposure (proximity based)

    Fence Line

    Concentration

    Exceeds ERPG-2

    On-Site Toxic POE

    Flash Fire POE

    Physical Explosion POE

    Chemical Exposure POE

    Enclosed Area

    Exceeds 0.5 LFL or

    ERPG-3

    CONSEQUENCE SUMMARY Date:

    Vapor Vent - Heat TransferLoss Event for: Stirred Reactor/Crystallizer; Formulation

    Mixing Tank Containing Heptane :

    Ground or Work Area

    Exceeds Multiple of

    LFL or Time-Scaled

    ERPG-3

    with Personnel Not in Immediate Area

    RAST Version 2

    Explosion Summary:

    VCE or Building Explosion Energy, kcal 4.8E+06 1

    VCE or Building Explosion Distance to 1 psi Overpressure, m 182.3

    Maximum Distance to LFL Concentration, m 7.7

    Blast Overpressure at Center of Occupied Building 1, psi 6.6

    Blast Overpressure at Center of Occupied Building 2, psi 4.3

    Distance to Severe Thermal Radiation Impact, m

    Rupture Explosion Energy, kcal

    Distance to Direct Blast Impact (10 psi), m 1

    Maximum Fragment Range, m

    Rupture Distance to 1 psi Overpressure, m

    Rupture Overpressure at Center of Occupied Building 1, psi 0.0

    Rupture Overpressure at Center of Occupied Building 2, psi 0.0

    Incident Outcome and Consequence Summary:

    NA

    Onsite Toxic Impact based on Indoor Concentration / LC-50 of 0.3 NA

    Time to ER-3 without Ventilation ~ 1751 sec; and Time to ER-3 with Ventilation ~ sec

    Onsite Flash Fire Impact based on Indoor / LFL Concentration of 1.1 5

    Chemical Exposure based on Dermal or Thermal Hazards and Spray Distance of 0 m NA

    Onsite Direct Blast Impact based on Distance to 10 psi of 0 m

    Onsite Thermal Radation Impact based on Distance from Fireball of 0 m

    Occupied Building Toxic Impact No NA

    Number of Potential Serious Impacts for Building 1: 0 people

    Number of Potential Serious Impacts for Building 2: 0 people

    Occupied Building Impact from Building Explosion Yes 6

    Number of Potential Serious Impacts for Building 1: 4.5 people

    Number of Potential Serious Impacts for Building 2: 7.9 people

    1 psi Blast Overpressure Distance exceeds the Fence Line, Consider additional Offsite Impacts

    Occupied Building Physical Explosion Impact No

    Number of Potential Serious Impacts for Building 1: 0 people

    Number of Potential Serious Impacts for Building 2: 0 people

    Environmental Impact:

    Estimated Number of

    People Impacted

    Probability of Ignition (POI)

    Potential Explosion

    Impact to Occupied

    Building

    Probability of Explosion (POX)

    LOPA Tolerable Frequency

    Factors Based On

    CONSEQUENCE SUMMARY Date:

    Vapor Vent - Heat TransferLoss Event for: Stirred Reactor/Crystallizer; Formulation

    Mixing Tank Containing Heptane :

    Impact Assessment with Personnel routinely in the immediate

    area

    Exceeds Threshold

    Criteria

    YesOffsite Toxic Impact based on Toxic Integration Method and 30.48 m to Fence Line

    April 12, 2019 Slide - 49

    Case Study – CAI and Arnel

    Consequence AnalysisFor the Raffinate Splitter, select

    Vapor Vent – Heat Transfer as

    the Loss Event. This represents

    a “worst” Consequence for filling

    the enclosed area with

    flammable vapor.

    Note under the Dispersion

    Summary that the enclosed

    area concentration is not

    estimated to reach the lower

    flammable limit if the ventilation

    system was running. 1 psi Blast Overpressure is estimated to 183 m (600 ft) and message notes this

    exceeds the distance to the fence line

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    April 12, 2019 Slide - 50

    Case Study – CAI and Arnel

    Consequence Analysis

    RAST estimated maximum 183 m

    (600 ft) to 1 psi blast overpressure

    from enclosed process area which

    is in excellent agreement with

    CSB modeling.

    REPORT NO. 2007-03-I-MA , US Chemical Safety Board,

    Figure 20. Aerial View showing estimated explosion overpressures

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    Scenario Definition

    Protection

    Gap

    Scenario /

    Cross Ref

    Description of Undesired ConsequenceLOPA Tolerable Frequency Factor

    (chemicals, quantity involved,

    and basis for calculations)

    Initiating Event Probability of Ignition Probability of Exposure

    (Presence Factor)

    Time at Risk or Other

    Enabling Factor

    New

    Instrumented

    Protection

    Credits

    Taken

    IPL Status? -->

    Safety

    AnalysisTolerable Frequency Factor 6 BPCS Instrument Loop Failure POI Probability Factor 1

    4 1 11 6 1 1 0

    Indoor Release of Flammable

    Material-POX

    6.01

    Failure of Flow Control

    Stirred Reactor/Crystallizer, Formulation Mixing Tank,

    is involved in an Excessive Heat Input - Heat Transfer

    event resulting in a Vapor Relief Vent - Heat Transfer

    with subsequent 307 kg airborne release of a Heptane

    Mixture at an airborne release rate of 11.3 Lb/min.

    Estimated time to relief set pressure is 11 min.

    This incident could result in a Building

    Explosion with Explosion Distance to 1 psi

    Overpressure of 598 ft including Explosion

    Overpressure at Typical Construction

    Occupied Bldg 1 (psi) of 6.6 psi. 1 psi

    Blast Overpresssure exceeds Distance to

    the Fence Line of 100 ft. Consider

    adjustment for Off-Site Impacts with the

    potential for Severity Level-5

    < Back to Scenario Results

    +

    Expand All Collapse All

    > Human Error ++ +> Possible IPLs

    Case Study – CAI and Arnel

    Risk Analysis / Layers of Protection Analysis (LOPA)

    April 12, 2019 Slide - 51

    The initial Initiating Event description notes BPCS

    flow control failure which should be updated to

    Human Error more than 1 per quarter to reflect

    that operator failed to close the steam valve.

    Select Loss Event of Vapor Relief

    Vent-Heat Transfer with Incident

    Outcome of Building Explosion

    for analysis in LOPA (“Yes”), then

    select LOPA Worksheet

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    Scenario Definition

    Protection

    Gap

    Scenario /

    Cross Ref

    Description of Undesired ConsequenceLOPA Tolerable Frequency Factor

    (chemicals, quantity involved,

    and basis for calculations)

    Initiating Event Probability of Ignition Probability of Exposure

    (Presence Factor)

    Time at Risk or Other

    Enabling Factor

    New

    Instrumented

    Protection

    Credits

    Taken

    IPL Status? -->

    Safety

    AnalysisTolerable Frequency Factor 6

    Human Failure Action more than

    once per quarterPOI Probability Factor 1

    4 1 11 6 1 1 0

    Indoor Release of Flammable

    Material-POX

    6.01

    Failure to close Steam Valve to

    vessel heater upon reaching

    desired temperature

    Stirred Reactor/Crystallizer, Formulation Mixing Tank,

    is involved in an Excessive Heat Input - Heat Transfer

    event resulting in a Vapor Relief Vent - Heat Transfer

    with subsequent 307 kg airborne release of a Heptane

    Mixture at an airborne release rate of 11.3 Lb/min.

    Estimated time to relief set pressure is 11 min.

    This incident could result in a Building

    Explosion with Explosion Distance to 1 psi

    Overpressure of 598 ft including Explosion

    Overpressure at Typical Construction

    Occupied Bldg 1 (psi) of 6.6 psi. 1 psi

    Blast Overpresssure exceeds Distance to

    the Fence Line of 100 ft. Consider

    adjustment for Off-Site Impacts with the

    potential for Severity Level-5

    < Back to Scenario Results

    +

    Expand All Collapse All

    > Human Error ++ +> Possible IPLs

    April 12, 2019 Slide - 52

    Case Study – CAI and Arnel

    Risk Analysis / Layers of Protection Analysis (LOPA)

    The probability of ignition in RAST is estimated at 0.1 for an indoor

    flammable release into a properly electrically classified area. This is an

    administrative parameter on a hidden worksheet that may be updated.

    RAST does not estimate offsite flammable

    impact directly but notes that the Consequence

    Severity may need to be adjusted.

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    BPCS Control or

    Human Response

    to Alarm

    BPCS Control or

    Human Response

    to Alarm

    SIS Function A SIS Function BPressure Relief Device SRPS 1 SRPS 2 SRPS 3

    BPCS Independent of

    Initiating Event

    1 - Other Safety related

    protection systems (PFD=0.1)

    1 1

    Building ventilation system

    capable of preventing

    concentration from reaching

    the lower flammable limit

    Notes / Comments

    High Temperature Closes

    Heating Media Valve

    Not Allowed

    + + + +

    April 12, 2019 Slide - 53

    Case Study – CAI and Arnel

    Risk Analysis / Layers of Protection Analysis (LOPA)

    The existing safeguards (even if there were a high temperature alarm which automatically

    closes the steam valve) were not sufficient to manage a scenario of this consequence severity.

    The scenario could have been managed

    by having a relief device set at a very

    low pressure or open line to vent

    outdoors and “sealing” the 12 inch solids

    loading hatch when not in use.

  • CCPSCenter for Chemical Process Safety

    An AIChE Technology Alliance Risk Analysis Screening Tools (RAST) Overview / Demonstration

    April 12, 2019 Slide - 54

    Risk Analysis Screening Tools (RAST)

    Case Study – CAI and ArnelRisk Analysis and Incident Investigation often use similar methods to better

    understand the scenario. Risk Analysis “anticipates” what could go wrong

    and what the potential consequences may be. For Incident Investigation, the

    Incident Outcome and Consequences are known in addition to the actual

    weather conditions, wind direction, time of day, and other factors.

    For the Formulation Mixing Tank, RAST did suggest column Excessive

    Heating as one of many scenarios to consider. RAST also recognized that a

    Building Explosion could be a feasible Incident Outcome. The estimate blast

    overpressure from RAST was in excellent agreement with CSB modeling.

    Fortunately, this incident occurred at night and resulti