cde-dpe-spot sept 2019 call · 2020-01-21 · • data clarifications: • most requested data is...

35
CDE-DPE-SPOT Sept 2019 Call Strategic Prioritization Office of Transportation (SPOT) NCDOT Division of Planning and Programming 9/20/2019

Upload: others

Post on 17-Jul-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CDE-DPE-SPOT Sept 2019 Call · 2020-01-21 · • Data clarifications: • Most requested data is *annual* values (existing and additional trips, revenue hours, system hours) •

CDE-DPE-SPOT Sept 2019 CallStrategic Prioritization Office of Transportation (SPOT)NCDOT Division of Planning and Programming

9/20/2019

Page 2: CDE-DPE-SPOT Sept 2019 Call · 2020-01-21 · • Data clarifications: • Most requested data is *annual* values (existing and additional trips, revenue hours, system hours) •

Today’s Roadmap

3

• Key Dates / Identified Needs Deadlines

• Skype / GoToMeeting Access

• Submittal Pointers

• Independent vs. Incidental Bike-Ped Projects

• Questions / Highway Testing Spreadsheet

Page 3: CDE-DPE-SPOT Sept 2019 Call · 2020-01-21 · • Data clarifications: • Most requested data is *annual* values (existing and additional trips, revenue hours, system hours) •

P6.0 Key Dates 2019

4

Completed:• June – Webinars with all partners to review P6.0 scoring changes• June 27th – BOT approval of P6.0 scoring components

Known Dates:• October – SPOT Online opens for project entry (testing with P6 data)• October – SPOT On!ine tutorials of submittal of all modes posted on

Prioritization Resources website

• November – SPOT On!ine regional workshops with all partners to assist with individual project entry and testing needs

Page 4: CDE-DPE-SPOT Sept 2019 Call · 2020-01-21 · • Data clarifications: • Most requested data is *annual* values (existing and additional trips, revenue hours, system hours) •

P6.0 Key Dates 2019/2020

5

Known Dates:• Dec 20, 2019 – Carryover deletions / modifications due

• May 1, 2020 – Submittal window closes • May 1, 2020 – Highway Mobility Area-Specific Weights due• May 1, 2020 – Highway Modernization Area-Specific Weights due• May 1, 2020 – Primary Route Requests due to Mobility & Safety

• October - November 2020 – Partner data review window

• March - May 2021 – Regional Impact Local Input assignment period

• August - Oct 2021 – Division Needs Local Input assignment period

Page 5: CDE-DPE-SPOT Sept 2019 Call · 2020-01-21 · • Data clarifications: • Most requested data is *annual* values (existing and additional trips, revenue hours, system hours) •

P6.0 Key Dates – Identified Needs

6

• Friday, June 19, 2020 – HIGHWAY projects must have a DRAFT Identified Needs report completed

• This means all questions answered in draft form, since some information could inform scoring or cost

• Friday, January 22, 2021 – ALL P6.0 Projects must have FINAL Identified Needs report completed

Page 6: CDE-DPE-SPOT Sept 2019 Call · 2020-01-21 · • Data clarifications: • Most requested data is *annual* values (existing and additional trips, revenue hours, system hours) •

Skype / GoToMeeting Access

Page 7: CDE-DPE-SPOT Sept 2019 Call · 2020-01-21 · • Data clarifications: • Most requested data is *annual* values (existing and additional trips, revenue hours, system hours) •

Submittal Pointers

Page 8: CDE-DPE-SPOT Sept 2019 Call · 2020-01-21 · • Data clarifications: • Most requested data is *annual* values (existing and additional trips, revenue hours, system hours) •

EXCITING NEWS!

9

Page 9: CDE-DPE-SPOT Sept 2019 Call · 2020-01-21 · • Data clarifications: • Most requested data is *annual* values (existing and additional trips, revenue hours, system hours) •

Submittal Checklist

10

1. Read Submittal Guidance Documentation per mode

2. Create/Enter project in SPOT On!ine “Submit” button after project entry Status = single green check

3. Complete Identified Needs form Pop-up Screen in SPOT On!ine Status = double blue check

4. Provide Complete Streets form (location TBD)

5. Provide cost estimate documentation (if applicable…)

Page 10: CDE-DPE-SPOT Sept 2019 Call · 2020-01-21 · • Data clarifications: • Most requested data is *annual* values (existing and additional trips, revenue hours, system hours) •

STI Law Eligibility DefinitionsMode Statewide Mobility

Highway

• Interstates (existing & future)• NHS routes (July 1, 2012)• STRAHNET• ADHS Routes• Uncompleted Intrastate

projects• Designated Toll Facilities

Aviation Large Commercial Service Airports ($500K cap)

Bicycle-Pedestrian N/A

Public Transportation N/A

Ferry N/A

Rail Freight Service on Class I Railroad Corridors

Regional Impact

Other US and NC Routes

Other Commercial Service Airports not in Statewide ($300K cap)

N/A

Service spanning two or more counties (10% cap)

Vessel or infrastructure expansion

Rail service spanning two or more counties not in Statewide

Division Needs

• All County (SR) Routes• Federal-Aid Eligible Local

Roads

All Airports without Commercial Service (General Aviation)($18.5M cap)

All projects ($0 state funds)

All other service, including terminals and stations

Replacement vessels

All other service, including terminals and stations (no short lines)

Page 11: CDE-DPE-SPOT Sept 2019 Call · 2020-01-21 · • Data clarifications: • Most requested data is *annual* values (existing and additional trips, revenue hours, system hours) •

Other Fund Contributions

12

Benefit/Cost and Funding Leverage Timing of other fund contributions

Other Fund contributions at the time of submittal get double impact:Lower “Cost to NCDOT” and Funding Leverage

Page 12: CDE-DPE-SPOT Sept 2019 Call · 2020-01-21 · • Data clarifications: • Most requested data is *annual* values (existing and additional trips, revenue hours, system hours) •

New General Data Fields

13

• Included in a Plan (and associated Name/Date)

• Original Submitter• Organization that submitted the original project• SPOT will provide historical cross reference for your use

on Carryover and Holding Tank projects (likely by early November 2019)

Page 13: CDE-DPE-SPOT Sept 2019 Call · 2020-01-21 · • Data clarifications: • Most requested data is *annual* values (existing and additional trips, revenue hours, system hours) •

Highway

14

Definitions – Facility Type & Access Control

Page 14: CDE-DPE-SPOT Sept 2019 Call · 2020-01-21 · • Data clarifications: • Most requested data is *annual* values (existing and additional trips, revenue hours, system hours) •

Highway

15

Logical termini

Easiest method is looking at NCDOT AADT web maphttp://ncdot.maps.arcgis.com/home/webmap/viewer.html?webmap=b7a26d6d8abd419f8c27f58a607b25a1

Any project types where logical termini does not matter? Modernization Access Management

What are not logical termini? County or jurisdictional boundaries Water crossings / Bridges Low volume intersections (in respect to the corridor)

Page 15: CDE-DPE-SPOT Sept 2019 Call · 2020-01-21 · • Data clarifications: • Most requested data is *annual* values (existing and additional trips, revenue hours, system hours) •

Highway

16

Identifying corridor intersections in SPOT On!ine

Extremely important for the cost estimation tool to give predictable results.

Page 16: CDE-DPE-SPOT Sept 2019 Call · 2020-01-21 · • Data clarifications: • Most requested data is *annual* values (existing and additional trips, revenue hours, system hours) •

Aviation

17

• Requesting component costs (ROW, Utilities, Construction)

• Requesting Source of Cost

• New Location and Airport Sponsor fields

• Work with your Airport Project Manager (APM) at the Division of Aviation

• Project pre-screening, FAA purpose• Correct SIT (expanded capital eligibility)• Inclusion in Airport Layout Plan• Partner Connect Project Request Number (PRN)• Cost

Page 17: CDE-DPE-SPOT Sept 2019 Call · 2020-01-21 · • Data clarifications: • Most requested data is *annual* values (existing and additional trips, revenue hours, system hours) •

New to P6.0

18

Remove P5.0 system plan goal requirement (for eligibility as a capital project) Expand eligibility to include projects that increase the

capacity of the airport and/or modernize the airport

Prescreening process – Division of Aviation to assist in screening and vetting projects prior to Prioritization submittal to ensure a better chance of meeting FAA approval of purpose and need

Page 18: CDE-DPE-SPOT Sept 2019 Call · 2020-01-21 · • Data clarifications: • Most requested data is *annual* values (existing and additional trips, revenue hours, system hours) •

P5.0 Specific Improvement Types

19

0500 - Runway Length/Width0535 - Runway Length: Taxiway Extension0540 - Runway Widening0605 - Pavement Strength - Runway0610 - Pavement Strength - Taxiway0615 - Pavement Strength - Apron1100 - Taxiway Requirements1200 - Aircraft Apron / Helipad Requirements1240 - Corporate and T-hangar Taxiway: Construction1305 - General Aviation Terminal Building: New Construction1315 - General Aviation Terminal Building: Construct Addition to Existing1320 - General Aviation Terminal Building: Construct Terminal Access Road1325 - General Aviation Terminal Building: Construct non-revenue terminal public parking1900 - Hangars2200 - Fuel Facilities3005 - Other: Not otherwise defined in system plan objectives

*Additional SITs for P6.0 – see next slide

Page 19: CDE-DPE-SPOT Sept 2019 Call · 2020-01-21 · • Data clarifications: • Most requested data is *annual* values (existing and additional trips, revenue hours, system hours) •

P6.0 Specific Improvement Types

20

105 - Runway Approach: Land 110 - Runway Approach: Obstruction 205 - Runway Safety Area: Land 210 - Runway Safety Area: Construction 305 - Runway Protection Zones: Land/Obstruction 505 - Runway Length: Benefit Cost Analysis 510 - Runway Length: Environmental Assessment 515 - Runway Length: Land 520 - Runway Length: Preliminary Engineering 525 - Runway Length: Design 528 - Road/Infrastructure Relocation 530 - Runway Length: Construction 535 - Runway Length: Taxiway Extension 540 - Runway Widening 605 - Pavement Strength: Runway 610 - Pavement Strength: Taxiway 615 - Pavement Strength: Apron 805 - Runway Edge Lighting: Install System 810 - Runway Edge Lighting: Electrical Vault 815 - Runway Edge Lighting: Pilot Control Lighting 825 - Runway Edge Lighting: Relocate 1005 - SIAP: Feasibility Study 1010 - SIAP: Land

1015 - SIAP: Clearing/Survey 1020 - SIAP: Site Development 1025 - ILS Localizer / Glideslope 1030 - Distance Measuring Equipment (DME) 1035 - Non-Directional Beacon (NDB) 1040 - SIAP: Install Approach Lighting 1105 - Taxiway: Environmental Assessment 1110 - Taxiway: Design 1115 - Taxiway: Land 1120 - Taxiway: Preliminary Engineering 1125 - Taxiway: Construction 1205 - Apron / Helipad: Environmental Assessment 1210 - Apron / Helipad: Design 1215 - Apron / Helipad: Land 1220 - Apron / Helipad: Preliminary Engineering 1225 - Apron / Helipad: Construction 1230 - Apron / Helipad: Security Lighting 1235 - Apron / Helipad: Security Fencing 1240 - Corporate And T-Hangar Taxiway: Construction 1305 - GA Terminal Bldg: New Construction 1310 - GA Terminal Bldg: Upgrade Existing 1315 - GA Terminal Bldg: Addition To Existing 1320 - GA Terminal Bldg: Terminal Access Road

1325 - GA Terminal Bldg: Non-Revenue Terminal Public Parking 1330 - GA Terminal Bldg: Water/Sewer Utilities Construction 1405 - Lighting: Install Taxiway Edge Lighting, Vault 1410 - Lighting: Install Apron Edge Lighting 1415 - Lighting: Relocate Taxiway Edge Lighting 1420 - Lighting: Relocate Apron Edge Lighting 1505 - Airfield Signage: Install 1510 - Airfield Signage: Install (Lighted) 1705 - Approach Lighting: Install MALS/MALSF/MALSR 1710 - Approach Lighting: Rehab/Replace MALS/MALSF/MALSR 1715 - Approach Lighting: Install ODALS 1805 - ARFF: Eligible Fire Suppression Equipment 1810 - ARFF: Personnel Fire Protection Turn Out Gear 1905 - Hangars: Construction 1920 - Hangars: Access Road 2105 - Perimeter Fencing: Construction 2205 - Fuel Facilities: Construction 3005 - Other: Not Defined In System Plan Objectives

Page 20: CDE-DPE-SPOT Sept 2019 Call · 2020-01-21 · • Data clarifications: • Most requested data is *annual* values (existing and additional trips, revenue hours, system hours) •

Bicycle/Pedestrian

21

• Requesting component costs• Preliminary Eng. / Design, ROW, Utilities, Construction

• Requesting Source of Cost• Bike/Ped Cost Estimation Tool

• Breakdown of how to calculate local match (to include PE/Design)

Page 21: CDE-DPE-SPOT Sept 2019 Call · 2020-01-21 · • Data clarifications: • Most requested data is *annual* values (existing and additional trips, revenue hours, system hours) •

Bicycle/Pedestrian

22

• New Project Sponsor field

• Big P6.0 changes to prepare for• Manual points of interest• Types of connections to other bike/ped infrastructure

(Existing, Committed, or Planned)• Bundling of multiple project types and/or across geographies

• Reminder that POs will be requested to process Carryover projects in SPOT On!ine

Page 22: CDE-DPE-SPOT Sept 2019 Call · 2020-01-21 · • Data clarifications: • Most requested data is *annual* values (existing and additional trips, revenue hours, system hours) •

Safety Benefit (based on new Facility Type)

23

Bicycle SIT Pedestrian SIT ScoreNew Bicycle/Pedestrian Bridge, New Bicycle/Pedestrian Tunnel, Rail-Trail, Shared-Use Path / Multi-Use Path

1, 2New Pedestrian Bridge, New Pedestrian Tunnel, Rail-Trail, Shared-Use Path / Multi-Use Path

6, 7 7

Buffered Bicycle Lane, Contra-Flow Bicycle Lanes, Separated Bike Lane, Sidepath 2 Sidepath, Sidewalk 7 6

Bicycle Lane 3 Sidewalk Widening, Trail Improvement 9 5

Paved Shoulder 4 Crossing Island, Curb Extensions, Streetscape / Corridor Improvements 8,9 4

Bicycle Detection / Actuation, Bicycle Signal, Curb Raddi Revisions, Hybrid Beacon, Intersection Markings / Signage, Lighting, Mid-Block Crossing

5

Accessible Pedestrian Signals, Curb Ramp, Lighting, Marked Crosswalk, Mid-Block Crossing, Pedestrian Hybrid Beacon, Pedestrian Signal, Rectangular Rapid Flashing Beacon

8 3

Shared Lane Marking ("Sharrow"), Signage 4 2

Bicycle Corral, Bicycle Parking, Bicycle Share / Micro-Mobility Share, Bicycle Wheel Channel, Wayfinding

5 Wayfinding 8 1

Page 23: CDE-DPE-SPOT Sept 2019 Call · 2020-01-21 · • Data clarifications: • Most requested data is *annual* values (existing and additional trips, revenue hours, system hours) •

Ferry

24

• Requesting component costs• ROW, Utilities, Construction

• Requesting Source of Cost

• New Location field

• Work with Cat Peele at the Ferry Division• Project needs to submit• Cost

Page 24: CDE-DPE-SPOT Sept 2019 Call · 2020-01-21 · • Data clarifications: • Most requested data is *annual* values (existing and additional trips, revenue hours, system hours) •

Public Transportation

25

• Requesting component costs• Preliminary Eng. / Design, ROW, Utilities, Construction

• Requesting Source of Cost

• Breakdown of how to calculate local match (to include PE/Design)

• New Location and Project Sponsor fields

Page 25: CDE-DPE-SPOT Sept 2019 Call · 2020-01-21 · • Data clarifications: • Most requested data is *annual* values (existing and additional trips, revenue hours, system hours) •

Public Transportation

26

• Data clarifications:• Most requested data is *annual* values (existing and

additional trips, revenue hours, system hours)• Additional values are projected for 10 years (2029)• Guidance provided on all calculations (additional trips,

service population around stops, facility data)

• Reminder that POs will be requested to process Carryover projects in SPOT On!ine

Page 26: CDE-DPE-SPOT Sept 2019 Call · 2020-01-21 · • Data clarifications: • Most requested data is *annual* values (existing and additional trips, revenue hours, system hours) •

Rail

27

• Requesting component costs (ROW, Utilities, Construction)

• Requesting Source of Cost

• New Location field

• Work with the Rail Division• Project needs to submit• Correct STI category• Cost

• New in P6.0 – ability to draw lines in SPOT On!ine for Freight and Passenger corridor projects

Page 27: CDE-DPE-SPOT Sept 2019 Call · 2020-01-21 · • Data clarifications: • Most requested data is *annual* values (existing and additional trips, revenue hours, system hours) •

Specific Improvement Types

28

1 - Freight rail infrastructure improvement or construction (line)2 - Freight rail infrastructure improvement or construction (point)3 - Highway-rail crossing improvement (point)4 - Passenger rail station improvement or construction (point)5 - Passenger rail service (line)6 - Other passenger rail improvements (point)

Page 28: CDE-DPE-SPOT Sept 2019 Call · 2020-01-21 · • Data clarifications: • Most requested data is *annual* values (existing and additional trips, revenue hours, system hours) •

Rail

29

Always choose to submit your Rail crossing project as a Rail SIT 3 (Highway-rail crossing improvement)

Rail SIT 3

HighwaySIT 23

Page 29: CDE-DPE-SPOT Sept 2019 Call · 2020-01-21 · • Data clarifications: • Most requested data is *annual* values (existing and additional trips, revenue hours, system hours) •

Tools on Prioritization Resources Site

30

https://connect.ncdot.gov/projects/planning/Pages/PrioritizationResources.aspx

• Project Database Guidance and Submittals by Organization• Local Input Points by Organization• P6.0 Highway Testing Spreadsheet• P5.0 Highway Projects for Area-Specific Weight Testing

Spreadsheet• Complete Streets Project Sheet• *NEW* Bike-Ped Cost Estimation Tool (spreadsheet)• Future spreadsheet and SPOT Online tutorial videos

Page 30: CDE-DPE-SPOT Sept 2019 Call · 2020-01-21 · • Data clarifications: • Most requested data is *annual* values (existing and additional trips, revenue hours, system hours) •

Independent vs. Incidental Bike-Ped Projects

Page 31: CDE-DPE-SPOT Sept 2019 Call · 2020-01-21 · • Data clarifications: • Most requested data is *annual* values (existing and additional trips, revenue hours, system hours) •

RPO Question

32

Has anyone heard the updated complete streets policy removes the local match for sidewalk/bike infrastructure as long as the bike/ped recommendations are in an adopted plan? I do not see that anywhere in the policy and I believe that change would have to go through the legislature as the match requirement is a part of the STI law.

Page 32: CDE-DPE-SPOT Sept 2019 Call · 2020-01-21 · • Data clarifications: • Most requested data is *annual* values (existing and additional trips, revenue hours, system hours) •

CDE-DPE Questions

Page 33: CDE-DPE-SPOT Sept 2019 Call · 2020-01-21 · • Data clarifications: • Most requested data is *annual* values (existing and additional trips, revenue hours, system hours) •

Questions Asked

34

• Submittal of Aviation project not currently in an ALP?

• One question that often comes up during express designs is what is the schedule…which really boils down to how late can we get the cost estimates in for P6.0?

• Will you briefly go over “how to” tips for using the existing testing spreadsheet?

• Will the P6.0 Highway testing spreadsheet be updated with P6.0 scaling? If so, when will it be available?

• Others?

Page 34: CDE-DPE-SPOT Sept 2019 Call · 2020-01-21 · • Data clarifications: • Most requested data is *annual* values (existing and additional trips, revenue hours, system hours) •

Questions to You from SPOT

35

• What additional tools can we provide for you to be successful?

• Any feedback or concerns being received from the POs about P6.0 scoring?

• Do you have a plan for project coordination with your POs to eliminate duplicate/similar project submissions?

• FYI – Public Input periods during project submittal

Page 35: CDE-DPE-SPOT Sept 2019 Call · 2020-01-21 · • Data clarifications: • Most requested data is *annual* values (existing and additional trips, revenue hours, system hours) •

Contact Information

36

https://www.ncdot.gov/[email protected] (Jason, Sarah, Austin, Justin)

Jason Schronce, P.E.SPOT ManagerPrioritization Office (SPOT)(919) [email protected]

Sarah E. LeePrioritization Office (SPOT)Non-Highway Modes(919) [email protected]

Austin ChamberlainPrioritization Office (SPOT)TOP3s / GIS Support(919) [email protected]

Justin Green, P.E.Prioritization Office (SPOT)Highway Mode(919) [email protected]