cedar party creek bridge replacement - mid-coast council

26
Cedar Party Creek Bridge Replacement Community Consultation Slides

Upload: others

Post on 22-Feb-2022

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Cedar Party Creek Bridge Replacement - Mid-Coast Council

Cedar Party Creek Bridge

Replacement Community Consultation Slides

Page 2: Cedar Party Creek Bridge Replacement - Mid-Coast Council

Midcoast Council have been successful in being awarded an Infrastructure NSW - Fixing Country Roads grant to progress options to replace Cedar Party Creek Bridge. Grant details:

• Grant value = $350K• Scope - to investigate options and complete design on

preferred option.• NO construction.• Complete detail design by end of 2017• A final design will allow Council to apply for a FCR grant

to fund construction.

Background

Page 3: Cedar Party Creek Bridge Replacement - Mid-Coast Council

Replacement of Cedar Party Creek Bridge has been considered for numerous years. Options were considered in 1986:

• Over 500 submissions received

• Preferred option – replace existing bridge

• Cost prohibitive (even to design)

• No funding source identified

• Option was not built

Background

Page 4: Cedar Party Creek Bridge Replacement - Mid-Coast Council

Current situation:• Timber bridge constructed in 1960s• Deck replaced with a Stress Laminated Timber deck in 1994• Replacement required in the next 10 years • Services over 10,000 vehicles/day (100+ heavy vehicles)• Weight limits could be imposed to maintain safety

Background

Page 5: Cedar Party Creek Bridge Replacement - Mid-Coast Council

Considerations of Cedar Party Creek Bridge:• On a Regional freight route• Currently impacted by flooding (1 in 5 year event)• Adjacent to a level rail crossing (boom gates)• Adjacent intersection is confusing – priority right turn to

accommodate heavy vehicles• Important access to Wingham• Community impact during

construction phase

Background

Page 6: Cedar Party Creek Bridge Replacement - Mid-Coast Council

Background

Chrissy Gollan Park

Swimming Pool Bowling Club

Schools

Wingham Town Centre

Page 7: Cedar Party Creek Bridge Replacement - Mid-Coast Council

Background

Funding considerations Refurbish existing bridge

Replace bridge

Improve flood access

Improve freight route

Potential to remove level crossing

Improve intersection

Improve an asset

Availability of grants

Page 8: Cedar Party Creek Bridge Replacement - Mid-Coast Council

Background

Funding considerations Refurbish existing bridge

Replace bridge

Improve flood access

Improve freight route

Potential to remove level crossing

Improve intersection

Improve an asset

Availability of grants

To be successful in achieving a grant to construct, options need to address

these considerations

Page 9: Cedar Party Creek Bridge Replacement - Mid-Coast Council

Council Engineers along with bridge & road design consultants considered many options, with 8 identified for further consideration. These 8 options have been developed with consideration of:

• Community impacts such as:- local economy- community functionality- noise/air impacts- gateway to Wingham

• Consultation with:- internal stakeholders- consulting specialists- RMS, ARTC, Infrastructure NSW

Strategic design and cost estimates have been determined for each option. Options have been scored and assessed using a weighted criteria analysis.

Options

Page 10: Cedar Party Creek Bridge Replacement - Mid-Coast Council

• With all options the old Cedar Party Creek bridge will be demolished. Cost and safety inhibit it being maintained for low volume vehicular or pedestrian use.

• ARTC will not support the relocation of the railway level crossing. If the rail crossing point needs to move a bridge over the tracks, high enough for double stack trains to pass underneath, would need to be included and ARTC would not contribute any funds toward this option.

Points of note

Page 11: Cedar Party Creek Bridge Replacement - Mid-Coast Council

A

B

C

D

EF

G

H

H

A. Around the BackB. Rowley StC. Ruth StD. North of the RailE. Existing AlignmentF. Eastern OffsetG. Pool RelocationH. Across the Floodplain

Note:• no particular order• each option has multiple

variations

Eight options considered

Page 12: Cedar Party Creek Bridge Replacement - Mid-Coast Council

The Roundabout

All options that include the current Wynter St / Combined St intersection have a common roundabout design. The roundabout requires a large volume of fill on the low side and a large cut on the high side. Significant retaining walls would be required on the south / west corner of the roundabout. It is a single lane roundabout with a mountable central island for trucks.

Page 13: Cedar Party Creek Bridge Replacement - Mid-Coast Council

Around the Back

Pro’s:• Can be constructed (mostly) offline• Minimal impact to Chrissy Gollan Park• Less visual/noise impact on existing residences• Will enable future subdivision development

Con’s:• Only an option if constructed with rail overpass

(significant cost) – road could be diverted back to existing rail crossing, but why go around the back then?

• Construction of roundabout complicated – high traffic impact, lengthy construction time

• Additional 1km of road construction ($)• Impact of roundabout on properties (acquisition)• Visual impact and costly retaining walls

Construction:• Timeframe = 11 months• Detours = local detours to

permit roundabout construction.

Page 14: Cedar Party Creek Bridge Replacement - Mid-Coast Council

Rowley Street

Pro’s:• Provides for a neat and visually aesthetic solution• Can be constructed offline

Con’s:• Diverts traffic past school (major safety concern)• Diverts traffic past numerous residents and

Wingham Brush (noise, environmental)• Long and expensive bridge structure (120m)• Requires upgrade to intersection of Rowley and

Combined St (further cost increase) • Cuts access to Chrissy Gollan Park

Construction:• Timeframe = 12 months• Detours = none. Traffic

control to permit tie ins at Wingham Rd and Rowley St.

Page 15: Cedar Party Creek Bridge Replacement - Mid-Coast Council

Ruth Street

Pro’s:• Can be constructed offline• Removes a turning manoeuvre for the majority of

traffic flow• Improved ease for heavy vehicles moving through town

Con’s:• Takes traffic immediately past Ruth Street residents

(great impact on noise and visual – new road height approx roof height)

• Complicated solution (bridge and road parallel to creek)• Long and expensive bridge structure (140m)• Requires full acquisition of the bowling club• Cuts access to Chrissy Gollan Park

Construction:• Timeframe = 12 months• Detours = none. Traffic

control to permit tie ins at Combined St / Wynter St and Wingham Rd.

Page 16: Cedar Party Creek Bridge Replacement - Mid-Coast Council

North of the Rail

Pro’s:• Decommission two existing level crossings• Only requires one small bridge

Con’s:• Unappealing entrance to Wingham (effectively

bypasses Wingham)• Diverts light vehicle traffic away from the CBD• Poor cost benefit ration - requires an upgrade to

Farquar Street to accommodate B Doubles and requires acquisition/demolition of numerous properties

• Cuts access to Chrissy Gollan Park

Construction:• Timeframe = 11 months• Detours = local detours to

permit construction on Price St.

Page 17: Cedar Party Creek Bridge Replacement - Mid-Coast Council

Existing Alignment

Pro’s:• Cost effective• Can be implemented

with or without a bridge over the rail line.

• Minimal change to the current approach to Wingham

Con’s:• Significant impact on traffic during construction• Temp bridge crossing connecting to Mortimer St for light vehicles (6 months+) • Detour for semi-trailers and B-doubles via Gloucester Road - 6 months +

(additional time and running costs, deterioration of detour route)• Construction of roundabout complicated – high traffic impact, lengthy

construction time• Impact of roundabout on properties (acquisition)• Visual impact and costly retaining walls• Significant impact to Chrissy Gollan Park

Construction:• Timeframe = 12 months• 4 month Detour = heavy vehicles via The Bucketts Way

and Gloucester Rd (additional 24km and 21 minutes). Light vehicles via temporary bridge to Mortimer St high flood susceptibility in which case detour via Tinonee if Bight Bridge is passable otherwise Burrell Creek).

Page 18: Cedar Party Creek Bridge Replacement - Mid-Coast Council

Eastern Offset

Pro’s:• Some of this project could be constructed offline• Gives priority to heavy vehicles moving through

town

Con’s:• Only an option if constructed with rail overpass

(significant cost)• Chrissy Gollan Park consumed• Major property impact - requires partial

acquisition of the bowling club and 3 other lots• Staging of roundabout complicated and costly

Construction:• Timeframe = 12 months• Detours = local detours to

permit roundabout construction.

Page 19: Cedar Party Creek Bridge Replacement - Mid-Coast Council

Pool RelocationPro’s:• Cost effective• Attractive entry to

Wingham• Removes a turning

manoeuvre for the majority of traffic flow

• Improved ease for heavy vehicles moving through town (improved safety and freight movement)

• Minimal land acquisition or retaining walls

• Constructed offline• Can be implemented

without a rail grade separation

Con’s:• Pool to be relocated

(funded in this project)• Some impact on Chrissy

Gollan Park• Bridge located on a

radius/extra width for turning lanes

Construction:• Timeframe = 10 months• Detours = traffic control

required to permit tie-ins at Wingham Rd and Combined St.

Page 20: Cedar Party Creek Bridge Replacement - Mid-Coast Council

Across the Floodplain

Pro’s:• Can be constructed offline

Con’s:• Diverts traffic past a school and residents• Additional 2km of greenfield road construction ($)• Requires massive amount of fill (or viaduct) to cross the

floodplain • Unstable ground• Flood prone / flooding issues

Construction:• Timeframe = 14 months• Detours = traffic control required to

permit Wingham Rd tie-in and construction along East Combined St.

Page 21: Cedar Party Creek Bridge Replacement - Mid-Coast Council

Weighted Criteria Score

Strategic Cost Estimate

No Rail Overpass Road Overpass

Around the Back 75 $20.4m $39.2m

Rowley St 59 n/a $28.9m

Ruth St 42 n/a $35.8m

North of Rail 38 n/a $25.6m

Existing Alignment 102 $18.4m $32.1m

Eastern Offset 96 n/a $33.0m

Pool Relocation 129 $19.1m $29.0m

Across the Floodplain Has not been priced or scored

Summary of Options

Page 22: Cedar Party Creek Bridge Replacement - Mid-Coast Council

Summary of Options

Page 23: Cedar Party Creek Bridge Replacement - Mid-Coast Council

Fixing Country Roads grant for construction will support the cost to relocate the swimming pool if this is the preferred option and the Benefit Cost Ratio (BCR) stacks up.

Swimming pool funding will not stretch beyond like for like replacement.

Existing pool is estimated at $1.5m to replace.

For $1.5m, you could get a new 6 lane 50m outdoor non heated swimming pool or a 6 lane 25m pool with a covered children’s wet play area.

Visitations per year (includes all) = 17,000 (93 per day)

Annual maintenance = $50k, Annual operating costs $140k

Significant upgrades required to prolong life

Swimming Pool

Page 24: Cedar Party Creek Bridge Replacement - Mid-Coast Council

Existing Alignment – more pictures

Page 25: Cedar Party Creek Bridge Replacement - Mid-Coast Council

Pool Relocation – more pics

Page 26: Cedar Party Creek Bridge Replacement - Mid-Coast Council

Community suggested option: Queen Street

Pro’s:• Existing Cedar Party Creek Bridge character remains• Heavy vehicles detour further away from CBD

Con’s:• Heavy vehicles diverted past 37 homes and a pre-

school (currently 28 homes)• Queen St is not flood free• Maintenance burden remains to keep Cedar Party

Creek Bridge and this bridge will still have a limited life even with light vehicles only

• Intersection at Combined / Wynter St can not be improved.

Construction:• Timeframe = 12 months• Detours = local detours to

permit construction of connections to Wingham Rd and Queen St.

Budget Estimate = $23m

Features:• Roundabout at intersection

of Youngs Rd / Wingham Rd• Roundabout at intersection

of new road and Queen Street

• Improvements required at roundabout at Dennes St / Farquar St roundabout

• Improvements of the Farquhar St bridge required