cedarvale & forest hill clc - construction update - oct 25, 2017

11
EGLINTON CROSSTOWN Cedarvale-Forest Hill Construction Liaison Committee October 25, 2017

Upload: crosstown-to

Post on 22-Jan-2018

1.602 views

Category:

Government & Nonprofit


0 download

TRANSCRIPT

Page 1: Cedarvale & Forest Hill CLC - Construction Update - Oct 25, 2017

EGLINTON CROSSTOWNCedarvale-Forest Hill Construction Liaison CommitteeOctober 25, 2017

Page 2: Cedarvale & Forest Hill CLC - Construction Update - Oct 25, 2017

2

Agenda

• Cedarvale Station Update

• Forest Hill Station Update

Page 3: Cedarvale & Forest Hill CLC - Construction Update - Oct 25, 2017

3

Cedarvale Station Updates – October 2017

Complete• Shoring for the east entrance (east of Allen Rd North, north of Eglinton Ave) • Everden Road utilities relocation works (sanitary sewer & water main) • 3/3 invert concrete pours in the launch shaft (east of the Allen)• Invert tunnel concrete pour • Utilities relocation works (Sanitary sewer & water main) across the Toronto Police

parking lot • Excavation for the east entrance• Utilities relocation works on Winnett Avenue• Roof slab concrete pour 1 of 3Ongoing• Waterproofing and formwork at the launch shaft• Noise and vibration monitoring• Shoring on the south side of Eglinton AveUpcoming• Roof slab concrete pour 2 and 3 • South Allen Road Diversion• Backfill of LS2 Crossover• Shoring on the north side of Eglinton Ave

Page 4: Cedarvale & Forest Hill CLC - Construction Update - Oct 25, 2017

4

Construction Progress Picture

First roof slab pour

Page 5: Cedarvale & Forest Hill CLC - Construction Update - Oct 25, 2017

5

Construction Progress Picture

Utility relocation under Eglinton Avenue at Winnett

Page 6: Cedarvale & Forest Hill CLC - Construction Update - Oct 25, 2017

6

Forest Hill Station Construction Update

Fall 2017

• Continue piling the south side of the station box

• Continue roof slab construction of the southwest side of the station box

• Continue piling at the Main Entrance

• Continue wet utilities relocation

Page 7: Cedarvale & Forest Hill CLC - Construction Update - Oct 25, 2017

7

Current Traffic Staging

Began September 2017 for approximately four (4) months

Page 8: Cedarvale & Forest Hill CLC - Construction Update - Oct 25, 2017

8

Forest Hill Station Concept Aerial View

Main Entrance

Secondary Entrance

*60% rendering

Page 9: Cedarvale & Forest Hill CLC - Construction Update - Oct 25, 2017

9

Forest Hill Station Construction Progress

9

DRILLING – MAIN ENTRANCE

Page 10: Cedarvale & Forest Hill CLC - Construction Update - Oct 25, 2017

10

Forest Hill Station Construction Progress

DRILLING – SOUTHWEST CORNER

Page 11: Cedarvale & Forest Hill CLC - Construction Update - Oct 25, 2017

11

Local Area Map