Solicitation Bid #V2114585P1 Construction Engineering & Inspection Services Transit Bus Stop Infrastructure
BROWARD COUNTY
YOUR CEI SOLUTION – YOUR PARTNERS
Calvin Giordano + Associates, Inc.
Cory Nichols, P.E Quality AssuranceQuality Control
Roderick Myrick, P.E. Principal In Charge
Christina Yero, P.E.Contract Support
Specialist
Erica Valencia Resident Compliance
Specialist
Ricardo Baraybar, P.E. Sr. Project Engineer
Chris Morris Sr. Construction
Inspector
Israel Cabrera Sr. Construction
Inspector
Alex BaaderSr. Construction
Inspector
Torrance ThomasConstruction Inspector
Keith Perry Construction Inspector
Expertise and Manpower
Calvin Giordano + Associates, Inc.
Expertise and Manpower
Expertise – Similar ExperienceRecent Projects:
• FDOT SR-A1A (Fort Lauderdale) 2017 FTBA Community Awareness Winner; Three roads from Mercedes River to Sunrise Blvd; FM 430601-1-52-01: Milling & resurfacing, widening, drainage including French drain, signalization improvements, sidewalk and curb ramp construction
• FDOT SR 441(Hallandale/Miami Gardens) New Construction with drainage, roadway widening, signalization, lighting, utility installations, sidewalk and curb, ADA ramps
• FDOT SR 441/US 700(Belle Glade/Pahokee) Major reconstruction/realignment to include de-muck and wick drain installations. Other improvements include drainage, base stabilization, geogrid and geosynthetic improvements.
• City of West Palm Beach; Clematis Street and Trolley Shelter Improvements; FDOT LAP Project FM 427652-1-58-01: Pedestrian, safety and landscape improvements including sidewalk construction and milling & resurfacing
• City of West Palm Beach; 15th Street Beautification Project; FDOT LAP Project FM 431652-1-58-01: Scope included signalization and drainage improvements, milling & resurfacing, and bike lane striping
• FDEP; Knights Key and Spanish Harbor Historical Bridge Project FM 422628-1-58-01: Replacement of missing bridge span sections via proprietary pre-fabricated truss and precast concrete beams, existing deck milling and resurfacing, joint/crack cleaning and resealing, aluminum safety railing, auger cast piles, navigational lighting, striping and signage. The project also included the addition of two recreational multi-use shelters
BCT AND FTA EXPERIENCE
BCT Bus Stop Improvements project.
Coral Springs, City of Oakland Park, Sunrise, Fort Lauderdale.
WO 44 –SR 870 Commercial Boulevard.
WO 158S B1 – Fort Lauderdale.
WO 268 – City of North Lauderdale Transit Shelter program. WO 237 ‐ North Perry Airport Park and Ride. Design included over 175 parking spaces, new asphalt pavement, and ADA improvements
I
II
III
IV
V
VI
Installation of Solar Powered Canopy Shelters throughout Broward County.
YOUR CEI SOLUTION – YOUR PARTNERS
SIDEWALK & ADA SAFETYEnsure contractor provide a safe permanent and temporary pedestrian sidewalks. This would include the addition of an ADA compliant TEMPORARY bus stop. We will maintain walkways free of hazards and ensure they are accessible to people with disabilities, including curb cuts, ramps, and railings where needed.
YOUR CEI SOLUTION – YOUR PARTNERS
MAINTENANCE OF TRAFFIC ( MOT)▪ Ensure proper MOT will be installed for the sidewalks and travel lanes being closed. This includes sign spacing, barricade spacing, per FDOT INDEX 600
▪ Experience with MOT on urban settings including driveways openings, business entrance, clear zone.
▪ Proper Public Information to ensure local businesses are aware of upcoming construction.
YOUR CEI SOLUTION – YOUR PARTNERS
INSPECTING AND DOCUMENTING▪ Daily Field Logs
▪ Measuring installation for Quantities & Compliance
▪ Construction Photos.
▪ FDOT/ ACI concrete testing
▪ Shop Drawing review and implementation
▪ Verify field utility locates
▪ Compliance with project specifications