cement performance · pdf fileinformation management mark mutter cement performance...
TRANSCRIPT
Contents of Presentation
• Scale and size development of cement plants
• History of process information (PI) capture and use
• Types of PI system available
• Responsibility for PI system
• Development of PI systems
• Off-line process information
• Conclusion
Scale and Size of Plants
• Capacity of plants has increased along with size of individualpieces of equipment
– Almost all raw grinding is now VSM
– Twin string precalciners are the standard
– Calciner design developments to increase throughput
– Cement milling is now moving to VSM technology
• Aim is to reduce unit cost of operations – fuel, power,maintenance, manpower
Size and Scale of Plants
• If plant is run under optimal performance then economies ofscale are lost – and ROI becomes more difficult
– 1000 tpd plant at 5% below capacity – 50 tpd/1500tpm/16,500 tpa
– 10,000 tpd plant at 5% below capacity – 500 tpd/15,000 tpm/165,000 tpa
• Fixed costs remain the same
• Impact on fuel and power consumption
• Cost and implications of importing clinker in sold out market
History of PI Capture
• Process information stored on log sheets, filled in by controlroom operatives
• Limited data was collected
• Information was for control and end of month reporting –generally a laboratory task
• Log sheets stored in laboratory
• Pulled out of storage and “dusted down” when plant problemsoccurred by Process Engineer
PI Capture Developments
• Control systems have developed to now allow all plant sensorsto be captured, recorded and manipulated
• Many systems available– Some designed as part of control system
– Some extract data onto separate server and download to software such asExcel
• Regardless of system, must be simple to use and accessible to all
• System should have a champion
PI System Champion
• Role of champion is to:– Develop the system to the users requirements
– Monitor the data such that performance of the plant is a focal point
– Be close to the process to monitor all of the inputs, and understand theinformation
– Act as an interface between all departments
– Understand when action is required
• Recommendation is that this role falls with the ProcessEngineering department
Basis PI System
• Primary level of analysis should be the major plant KPIs– Output
– Fuel Consumption
– Power consumption
– Alternative fuel usage
• All parameters can be in actual units or converted to financialterms
– Example: Cost of fuel when using alternative fuels
• Must include plant chemistry data
Basic PI System – Further uses
• Feedback to control room operators on actions– Optimisation of kiln and start-up actions
– Chemistry control
• Assessment of operator performance to identify training
• Troubleshooting of plant when efficiency is reduced– Comparison of parameters of good vs. poor performance
Advance PI System
• Use the data to optimise performance
• Examples:– Slowdown log
– Environmental emissions predictive systems
– Variability Reduction
• Flexibility of system is key as it can be adapted to almost anyplant issue
Advance PI System
• Slowdown Log– Daily comparison of the actual performance against the target
– Results in the identification of over and underperformance
– Champion to review daily the gap (positive and negative) and identifyand log any reasons
– Builds up a record of reasons for the gap which can then produce aPareto analysis
– Root Cause Analysis of major reasons for underperformance
– Can be converted into financial terms for capital investment purposes
Advance PI System
• Environmental Emissions Predictive Systems– Real time system to prevent emission limit exceedences
– Emissions limits are often for different time periods including one hourand 24 hour emissions targets are fixed by plant authorisation
– Each hour the average emission is calculated
– The system can then calculate what the level must be for the remainderof the 24 hour period to prevent an exceedence
– Assists operators in taking actions to reduce emissions below the limitand ensure compliance
Off-line Process Information
• Must not ignore or neglect other process parameters– Those that require human measurement
– Those that require calculation and human interpretation
• Many these are the process engineering tests– Mill inspections, measurements and material analysis
– Preheater audits, cooler heat balance, calciner combustion efficieny
– In-leaking air survey
– Separator efficiency audits
Off-line Process Information
• Must not be a one-off exercise when the plant is not performing
• Frequency must be correct– Too often and there will be very little change and the workload is too high
– Not enough and the performance will have deteriorated
• Need to build a database for comparative purposes
• All information must be passed on to the relevant departments, notkept within the process engineering department
• The solution is usually a combination of actions, not just a singleaction
Conclusion
• Cement plant operators cannot afford to not use all of theavailable process information available to them
• A centralised system should be put in place, with the processengineering team championing the system
• The tool should cover all areas of the process and also be used tobring together the different departments on the plant
• Basic process engineering tests should not be forgotten