CENTRAL LOOP BUS RAPID TRANSIT (BRT) September 2014 CDOT PROJECT NO.: B-1-633 I-4 GENERAL INFORMATION Shop Drawings for long lead items must be submitted within 3 weeks of Notice-to-Proceed. No additional compensation will be paid for delay in obtaining these items. The Contractor’s invoices will not be paid until the Schedule of Submittals has been approved by the Commissioner. Notification of Property Owners/Tenants The Contractor must notify the property owners/tenants in writing of the Work to be done at or adjacent to each property location a minimum of 2 weeks prior to beginning work. The Contractor shall provide a draft letter to the Commissioner which must be approved prior to distribution to property owners/tenants. Special Requirements The Contractor must adhere to all special requirements for Work in or adjacent to financial institutions. When directed by the Commissioner, the Contractor must accommodate special events during construction which may include but are not limited to (and are subject to change): Special events at Daley Plaza (50 W. Washington St.) including Farmer’s Markets Downtown holiday and celebratory parades Taste of Chicago Chicago Air and Water Show To accommodate special events, the Contractor shall: On the day before events: Complete clean the entire project area and move temporary drums, barriers, or barricades to optimize pedestrian access and safety. Trenches must be backfilled, covered with steel plates, or patched with temporary asphalt as directed by the Commissioner. Contractor equipment must be consolidated to a location specified by the Commissioner and protected with temporary fence. On the day of the event: Perform no Work except to be present to repair and maintain pedestrian safety and traffic control elements. Agency Permits The contractor must secure permits from IDOT before commencement of work on or adjacent to Jackson Boulevard, Adams Street, Washington Street west of Wacker Drive, and/or Randolph Street west of Canal Street. Samples of the following forms are provided in this book. Highway Permit (IDOT OPER 1045) Individual Highway Permit Bond (IDOT OPER 1046) Any cost incurred including coordination effort and the bond costs to acquire these permits shall be incidental to the contract. The anticipated bond amount is $100,000. For coordination, contact the IDOT Traffic Permit Coordinator, Thomas G. Gallenbach PE at (847) 705-4130. The contractor will also be required to secure a Temporary Permit to Enter Amtrak facilities to complete the work of installing traffic signal posts over the Amtrak facility on Canal Street. Coordination effort to secure permits from Amtrak shall be incidental to the contract.

Upload: dangnhi

Post on 20-Sep-2018

224 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CENTRAL LOOP BUS RAPID TRANSIT (BRT) September 2014 … · CENTRAL LOOP BUS RAPID TRANSIT (BRT) September 2014 CDOT PROJECT NO.: B-1-633 I-4 GENERAL INFORMATION Shop Drawings for

CENTRAL LOOP BUS RAPID TRANSIT (BRT) September 2014 CDOT PROJECT NO.: B-1-633

I-4 GENERAL INFORMATION

Shop Drawings for long lead items must be submitted within 3 weeks of Notice-to-Proceed. No additional compensation will be paid for delay in obtaining these items. The Contractor’s invoices will not be paid until the Schedule of Submittals has been approved by the Commissioner.

Notification of Property Owners/Tenants The Contractor must notify the property owners/tenants in writing of the Work to be done at or adjacent to each property location a minimum of 2 weeks prior to beginning work. The Contractor shall provide a draft letter to the Commissioner which must be approved prior to distribution to property owners/tenants.

Special Requirements The Contractor must adhere to all special requirements for Work in or adjacent to financial institutions.

When directed by the Commissioner, the Contractor must accommodate special events during construction which may include but are not limited to (and are subject to change):

Special events at Daley Plaza (50 W. Washington St.) including Farmer’s Markets

Downtown holiday and celebratory parades

Taste of Chicago

Chicago Air and Water Show

To accommodate special events, the Contractor shall:

On the day before events: Complete clean the entire project area and move temporary drums, barriers, or barricades to optimize pedestrian access and safety. Trenches must be backfilled, covered with steel plates, or patched with temporary asphalt as directed by the Commissioner. Contractor equipment must be consolidated to a location specified by the Commissioner and protected with temporary fence.

On the day of the event: Perform no Work except to be present to repair and maintain pedestrian safety and traffic control elements.

Agency Permits The contractor must secure permits from IDOT before commencement of work on or adjacent to Jackson Boulevard, Adams Street, Washington Street west of Wacker Drive, and/or Randolph Street west of Canal Street. Samples of the following forms are provided in this book.

Highway Permit (IDOT OPER 1045) Individual Highway Permit Bond (IDOT OPER 1046)

Any cost incurred including coordination effort and the bond costs to acquire these permits shall be incidental to the contract. The anticipated bond amount is $100,000. For coordination, contact the IDOT Traffic Permit Coordinator, Thomas G. Gallenbach PE at (847) 705-4130. The contractor will also be required to secure a Temporary Permit to Enter Amtrak facilities to complete the work of installing traffic signal posts over the Amtrak facility on Canal Street. Coordination effort to secure permits from Amtrak shall be incidental to the contract.

WangS
Text Box
As part of the contract, the Contractor must comply with the Storm Water Pollution Prevention Plan (SWPPP) included with these specifications and secure a National Pollutant Discharge Elimination System (NPDES) Permit No. ILR10 issued by the Illinois Environmental Protection Agency (IEPA) including all permit fees and coordination effort necessary.
WangS
Callout
CLARIFICATION NO. 1
Page 2: CENTRAL LOOP BUS RAPID TRANSIT (BRT) September 2014 … · CENTRAL LOOP BUS RAPID TRANSIT (BRT) September 2014 CDOT PROJECT NO.: B-1-633 I-4 GENERAL INFORMATION Shop Drawings for

DS - 86 CDOT Project B-1-633

CENTRAL LOOP BUS RAPID TRANSIT (BRT) September 2014 CDOT PROJECT NO.: B-1-633

spaced horizontally 24” o.c.. Cut and shape curbing where necessary to accommodate ramps and other items of Work. Dress arrises, edges, corners and welds on exposed surfaces to make flush, straight, smooth and free of surface blemishes for neat appearance. Hot-dip galvanize all components in accordance with ASTM A 123 requirements. Comply with ASTM A 384 and ASTM A 385 to prevent warpage and to provide high quality zinc coating on assemblies. Mark units on back for proper assembly and installation.

Verification of Conditions: Examine the areas to receive the Work and the conditions under which the Work would be performed. Contractor must remedy conditions detrimental to the proper and timely completion of the Work. Do not proceed until unsatisfactory conditions have been corrected.

Installation: Install steel plate curb accurately in location, alignment and elevation, plumb, level, true and free of rack, measured from established lines and levels. Fit adjoining sections together to form tight joints. .

Touch-Up Painting: Touch-up damaged and abraded areas of galvanized surfaces with specified zinc-rich primer paint. Thoroughly clean the surfaces and apply primer in accordance with paint manufacturer’s recommendations.

Method of Measurement: Steel Plate Edging will be measured in place in linear feet.

Basis of Payment: This Work will be paid for at the Contract Unit Price per linear feet for STEEL PLATE EDGING, which price includes all costs for completing the Work as specified.

WangS
Callout
CLARIFICATION NO. 1
WangS
Text Box
16"
Page 3: CENTRAL LOOP BUS RAPID TRANSIT (BRT) September 2014 … · CENTRAL LOOP BUS RAPID TRANSIT (BRT) September 2014 CDOT PROJECT NO.: B-1-633 I-4 GENERAL INFORMATION Shop Drawings for

DS - 198 CDOT Project B-1-633

CENTRAL LOOP BUS RAPID TRANSIT (BRT) September 2014 CDOT PROJECT NO.: B-1-633

ITEM 233 HIGH PERFORMANCE PAINT

Description. Work under this item shall be performed according to Section 506 and 1008 of the IDOT Standard Specifications for Road and Bridge Construction, except as herein modified.

This Work shall consist of cleaning and preparation of new steel and aluminum surfaces as indicated on plans; bus shelter structure and any miscellaneous metal items on platform, including but not limited to all metal used for bench support, metal plates around columns, advertizing panels, etc., furnishing, application, and protection of the paint coatings.

Materials. Thermoset Solution Fluoropolymer; color and gloss to be selected by owner. Acceptable manufactures and products: Ferrous Steel: a) Tnemec: Series 90-97 Tneme-Zinc Primer Fluoronar Series 1075 Endura Shield II Intermediate Coat Fluoronar Series 1072 Finish Coat b) PPG : Coraflon ADS 570 Zinc-Rich Epoxy Primer Coraflon ADS Epoxy Intermediate Cost Coraflon ADS Intermix Fluoropolymer Finish Coat c) Sherwin-Williams: S-W Zinc Clad IV Organic Zinc-Rich Epoxy Primer @ 3.0 - 5.0 mils dft. S-W Macropoxy 646 FF @ 5.0 - 8.0 mils DFT S-W Acrolon 218 HS @ 3.0 - 6.0 mils DFT (color selected by manufacturer) S-W FluoroKem HS @ 2.0 - 3.0 mils DFT Aluminum: a) Tnemec: Series 135 Chembuild primer Series 1071V Fluoronar finish coat b) PPG : Coraflon ADS 570 Zinc-Rich Epoxy Primer Coraflon ADS Epoxy Intermediate Cost Coraflon ADS Intermix Fluoropolymer Finish Coat c) Sherwin-Williams: S-W Macropoxy 646 FF @ 5.0 - 8.0 mils DFT (color selected by manufacturer) S-W FluoroKem HS @ 2.0 - 3.0 mils DFT (color selected by owner)

General Requirements.

All new steel and aluminum furnished under this Contract shall receive primer and coatings in the shop.

Surface preparation and product application: Follow manufacture’s recommendations.

WangS
Text Box
This Work shall consist of cleaning and preparation of ferrous metal and aluminum surfaces as indicated on plans; bus shelter structure, canopy drainage, conduit run and any miscellaneous metal items on platform, furnishing, application, and protection of the paint coatings. The top surface of canopy ribs directly in contact with glass canopy shall not be painted until coordination with the structural sealant manufacturer is done.
WangS
Callout
CLARIFICATION NO. 1
Page 4: CENTRAL LOOP BUS RAPID TRANSIT (BRT) September 2014 … · CENTRAL LOOP BUS RAPID TRANSIT (BRT) September 2014 CDOT PROJECT NO.: B-1-633 I-4 GENERAL INFORMATION Shop Drawings for

DS - 201 CDOT Project B-1-633

CENTRAL LOOP BUS RAPID TRANSIT (BRT) September 2014 CDOT PROJECT NO.: B-1-633

ITEM 234 MISCELLANEOUS METAL – METAL PLATE ASSEMBLY Description. Work under this item shall be performed according to Section 505 of the IDOT Standard Specifications for Road and Bridge Construction, except as herein modified. This Work shall consist of furnishing and installing items made primarily from plate, shapes, and other forms of metal, but which may include sheet metal components. Metal Plate: Stainless Steel plate at bus shelter bench and at column bases, digital/static ad and messaging panel housing and elsewhere as shown on plans.

Metal Shapes: Stainless Steel angles, channels used in the plate assembly, digital/static ad and messaging panel housing nd elsewhere, as shown on plans.

Anchors, fasteners, accessories and hardware used for connection to concrete base.

Materials.

(a) Stainless Steel Shapes:

(1) Shapes and Bars ASTM A276, Type 316 (2) Plate, Sheet and Strip ASTM A240, Type 316 (3) For Welding: AISI, Type 316L

(b) Hardware Components: T316 stainless steel. (c) Gaskets: As required to seal joints in formed metal and remain weathertight: as

recommended in writing by metal manufacturer (d) Sealant: Exterior: ASTM C 920; elastomeric; As recommended in writing by the metal

manufacturer. Sealants shall have a VOC content of not more than 250 g/L when calculated according to 40 CFR 59, Subpart D (EPA Method 24).

(e) Backing Paint: Protective Backing Paint: FS TT-C-494, Bituminous. (f) Grout: Non-shrink, non-ferrous minimum yield strength of 7,000 psi at 28 days. (g) Fasteners: Fabricated from same basic metal and alloy as fastened metal unless

otherwise indicated. Do not use metals that are incompatible with materials joined. (h) Anchors: Type best suited to application.

Finish.

All exposed stainless steel shall have matt, non-directional surface, EN 10088-2 2K, maximum surface roughness of .5 Microns Ra. Pickled and passivated process shall be used to remove all discoloration after fabrication for the entire pedestrian rail system, including but not limited to posts, attachments and anchor plate, per ASTM A380 and ASTM A967.

General Requirements. Work shall be in accordance to the details shown on the plans. Install components plumb and level, accurately fitted, free from distortion or defects.

Design metal items and connections under direct supervision of Professional Structural Engineer experienced in design of this Work and licensed in State of Illinois. Connections not fully detailed on the Drawings to resist the loads shown on the Contract Drawings or specified,

Build in straps, plates, and brackets as needed to support and anchor fabricated items to adjoining construction. Reinforce metal items as needed to attach and support other construction

WangS
Text Box
metal plate assembly
WangS
Callout
CLARIFICATION NO. 1
Page 5: CENTRAL LOOP BUS RAPID TRANSIT (BRT) September 2014 … · CENTRAL LOOP BUS RAPID TRANSIT (BRT) September 2014 CDOT PROJECT NO.: B-1-633 I-4 GENERAL INFORMATION Shop Drawings for

DS - 204 CDOT Project B-1-633

CENTRAL LOOP BUS RAPID TRANSIT (BRT) September 2014 CDOT PROJECT NO.: B-1-633

ITEM 235 MISCELLANEOUS METAL – CANOPY DRAINAGE AND CONDUIT RUN

Description. Work under this item shall be performed according to Section 505 and 506 of the IDOT Standard Specifications for Road and Bridge Construction except as herein modified.

This Work shall consist of furnishing and installing bus shelter canopy drainage system: metal flashings, gutters and downspouts, and conduit raceways.

Materials.

(a) Gutter: minimum 12 gauge extruded aluminum custom downspouts

(b) Downspout and conduit raceway: minimum 14 gauge extruded aluminum custom downspouts

(c) Flashing: minimum 16 gauge extruded aluminum custom downspouts Aluminum Shapes:

(1) Aluminum Sheet and Plate ASTM B209, Alloy 6061-T6 (2) Extruded Shapes ASTM B429, Alloy 6063-T6

(d) Solder: Class A, Grade I, half-and-half, pig lead and block tin, ASTM B32, Type 50-50, with rosin flux.

(e) Mastic: FS SS-S-153, Type 1, black plastic cement.

(f) Nails and Screws: Same metal as flashing/sheet metal, Stronghold type, with large flat heads and sharp points. Use lead or neoprene washers where indicated. Use sheet metal screws or self-tapping screws to fasten sheet metal to other metal. Match finish of exposed heads with finish of material being fastened.

(g) Lap Joint Sealer: Polyisobutylene non-hardening, non-skinning, non-drying, non-migrating sealant.

(h) Coating for Dissimilar Metals: bituminous paint.

(i) Epoxy Seam Sealer: Two-part non-corrosive metal seam cementing compound recommended by metal manufacturer for exterior/interior non-moving joints including riveted joints.

(j) Adhesives: Type recommended by flashing sheet manufacturer for waterproof/weatherproof seaming and adhesive application of flashing sheet.

(k) Metal Accessories: Sheet metal clips, straps, anchoring devices, and similar accessory units as required for installation of work, matching or compatible with material being installed, non-corrosive, size and gage as required for performance.

(l) Gutter and Conductor-Head Guards: Use materials compatible with gutters and downspouts. Connections butt welded and ground smooth.

Finish: All aluminum items: painted, per Special Provision: High Performance Paint. Paint aluminum in contact with concrete with protective bituminous backing paint to avoid dissimilar metal reaction.

WangS
Callout
gutter screen
WangS
Callout
CLARIFICATION NO. 1
WangS
Callout
(m) FRP drain pipe. 4” FRP drain pipe from top of concrete bench, as shown on drawings, to trench drain or storm sewer line
WangS
Callout
CLARIFICATION NO. 1
Page 6: CENTRAL LOOP BUS RAPID TRANSIT (BRT) September 2014 … · CENTRAL LOOP BUS RAPID TRANSIT (BRT) September 2014 CDOT PROJECT NO.: B-1-633 I-4 GENERAL INFORMATION Shop Drawings for

DS - 213 CDOT Project B-1-633

CENTRAL LOOP BUS RAPID TRANSIT (BRT) September 2014 CDOT PROJECT NO.: B-1-633

ITEM 238 BUS SHELTER BENCH SEAT

Description. This Work shall consist of furnishing, application, and installation of benches, as shown on plans and specified herein.

Materials.

Seat: Wood - Exterior use: lpe; FSC certified.

Mounting and connection hardware: Stainless Steel Grade 316

End caps, and seat dividers: Stainless Steel Grade 316

Finish.

Finish on wood – Unfinished

Finish on metal: All exposed stainless steel shall have matt, non-directional surface, EN 10088-2 2K, maximum surface roughness of 0.5 Microns Ra.

Pickled and passivated process shall be used to remove all discoloration after fabrication per ASTM A380 and ASTM A967.

General Requirements. Coordination: Coordinate with concrete platform,bench and curb manufacturer, shelter manufacturer, railing manufacturer, electrical and traffic surveillance requirements and any other trades.

Submittals: (a) Product Data: Submit manufacturer’s product data, storage and handling requirements and

recommendations, installation methods and available colors, styles, patterns and textures. (b) Shop Drawings: Submit manufacturer’s shop drawings, including plans and elevations,

indicating overall dimensions and details. (c) Samples: Submit samples of materials, finishes, and colors. (d) Submit min 24” long sample of the bench seat, including attachment to the concrete base

and seat dividers and adjacent metal plate. (e) Manufacturer’s Qualifications: Manufacturer regularly engaged in manufacture of site

furnishings since for min of 5 years

Construction Requirements. Bench seat shall be shop assembled in largest pieces possible. QC/QA Requirements. The Contractor shall provide material acceptance for all material that are not referred to in SSRBC. The Contractor shall provide a Manufacturer’s written certification that the material complies with these specifications for materials included in SSRBC. Warranty Products will be free from defects in material and/or workmanship for a period of three years.

WangS
Callout
CLARIFICATION NO. 1
WangS
Callout
AWS - Premium grade (criteria to meet requirements for Honduras Mahogany) Clear All Heart. Alternate wood species FSC garapa and FSC cumaru species can be used with Commissioner's approval of samples provided by the Contractor.
Page 7: CENTRAL LOOP BUS RAPID TRANSIT (BRT) September 2014 … · CENTRAL LOOP BUS RAPID TRANSIT (BRT) September 2014 CDOT PROJECT NO.: B-1-633 I-4 GENERAL INFORMATION Shop Drawings for

DS - 227 CDOT Project B-1-633

CENTRAL LOOP BUS RAPID TRANSIT (BRT) September 2014 CDOT PROJECT NO.: B-1-633

ITEM 244 BOLLARD BARRICADE SYSTEM

Description. This Work shall consist of furnishing all materials and equipment and all work necessary to construct the crash tested-crash certified – high security bollard barricade system, as indicated in the contract documents and specified herein. Material: Bollard: Steel Architectural Enhancement Outer Shells: Stainless Steel 316 Foundation:

Deep Foundation: Concrete Shallow Foundation: Steel members w/ steel reinforcing mesh welded in place.

Finish. Steel Structure. The foundation and underside of the Bollard shall be asphalt emulsion coated for corrosion protection. The roadway plates shall have a non-skid surface. The above grade portion of the Bollard shall be finished with an industrial enamel primer. Architectural Enhancement Outer Shells: Stainless Steel 316: matt, non-directional surface, EN 10088-2 2K, maximum surface roughness of 0.5Microns Ra., Wire mesh shall have surface finished as supplied by approved manufacturer. Pickled and passivated process shall be used to remove all discoloration after fabrication. Design: Based on DELTA SCIENTIFIC CORPORATION; Model Omni DSC800 General Requirements. System Configuration for crash rated Bollard Barricade System: (a) Bollard Height. Height of the Bollard shall be 30 inches (762 mm) as measured from the top of the foundation frame to the top of the Bollard assembly.

(b) Bollard Diameter, with Architectural Enhancement in place shall not be greater than 10” inches (260 mm) in diameter.

(c) Foundation is set into existing roadways or sidewalks.

(d) Spacing. Clear opening between Bollards shall be 43 inches (1.09 m) maximum.

(e) Stopping Capacity for BOLLARD BARRICADE SYSTEM:

The Bollard system shall be designed to stop a vehicle attacking from either direction.

(a) High Energy Attack. Bollard(s) shall have been shown by certified dynamic non linear analysis to be capable of stopping and immobilizing non-armored or non-tracked vehicles with weight and velocity characteristics as defined in next paragraph. The Bollard system shall be designed to destroy the front suspension system, steering linkage, engine crankcase and portions of the drive train.

(b) The Bollard shall be capable of stopping and destroying a vehicle(s) complying to DOS/DOD K4,L2 certification: 15,000 pounds at 30 mph (66,7 kN at 100 kph)

WangS
Callout
illuminated
WangS
Callout
CLARIFICATION NO. 1
Page 8: CENTRAL LOOP BUS RAPID TRANSIT (BRT) September 2014 … · CENTRAL LOOP BUS RAPID TRANSIT (BRT) September 2014 CDOT PROJECT NO.: B-1-633 I-4 GENERAL INFORMATION Shop Drawings for

DS - 239 CDOT Project B-1-633

CENTRAL LOOP BUS RAPID TRANSIT (BRT) September 2014 CDOT PROJECT NO.: B-1-633

ITEM 248 DIGITAL/STATIC AD AND MESSAGING PANEL HOUSING Description. Work under this item shall be performed according to applicable portions of Section 505 of the IDOT Standard Specifications for Road and Bridge Construction. This Work shall consist of furnishing and installing housing for the digital and static ad and messaging panels incorporating elements such as: JC Decaux static advertising poster, BUS TRACKER DIGITAL SIGNAGE, AUDIO ADA ANNUNCIATOR SYSTEM, LED UPLIGHT, electrical outlets, all electrical and Ethernet connections included under BUS SHELTER ELECTRICAL WORK required for the components to be housed.

Materials.

Metal Plate and Shapes: 316L stainless steel. (a) Comply with Special Provision: Bus Canopy Structural Steel. (b) Finish. As specified in Special Provisions -Item - MISCELLANEOUS METAL - METAL

PLATE ASSEMBLY

Hardware Components: T316 stainless steel. All exposed screws and hardware shall be tamper proof. Piano hinges: 316L stainless steel.

Sealant: As recommended by the manufacturer

Backing Paint: Protective Backing Paint: FS TT-C-494, Bituminous.

Grout: Non-shrink, non-ferrous minimum yield strength of 7,000 psi at 28 days.

Anchors: Type best suited to application.

Gasket: Neoprene

Louver: 316L stainless steel; 16 degree deflection, ¼” spacing between bars; weld-lock construction; mitered corners. Bases of design: AG40 Bar Grille by Architectural Grille. Approved Equal.

Pneumatic Strut: Hydraulically dampened gas spring for opening of lids; 2 per panel; Capacity: 500 LB.

Glazing: 3/8” Clear tempered and heat soaked monolithic. All edges will be ground flat with a frosted appearance. Comply with QC requirements listed for item: Poster Frame of Special Provision.

Finish. As specified in Special Provisions -Item - MISCELLANEOUS METAL - METAL PLATE ASSEMBLY

General Requirements. Work shall be in accordance to the details shown on the plans. Design metal plates, under direct supervision of Professional Structural Engineer experienced in design of this Work and licensed in State of Illinois.

WangS
Callout
Cladding
WangS
Callout
CLARIFICATION NO. 1
Page 9: CENTRAL LOOP BUS RAPID TRANSIT (BRT) September 2014 … · CENTRAL LOOP BUS RAPID TRANSIT (BRT) September 2014 CDOT PROJECT NO.: B-1-633 I-4 GENERAL INFORMATION Shop Drawings for

DS - 242 CDOT Project B-1-633

CENTRAL LOOP BUS RAPID TRANSIT (BRT) September 2014 CDOT PROJECT NO.: B-1-633

ITEM 249 BUS TRACKER DIGITAL SIGNAGE

Description. This item consists of furnishing and installing a combined digital display/ integrated PC into DIGITAL/STATIC AD AND MESSAGING PANEL HOUSINGs as detailed in the plans and all programming, system integration, and coordination work necessary for the digital display to show real-time Bus Tracker information from the Chicago Transit Authority (CTA) network.

Materials. Minimum Requirements: Digital Display:

38” diagonal display 7:2 aspect ratio 1920x520 LCD pixel resolution or higher 6mm hardened glass, optically boneded, anti-reflective/ant-glare coating or better LED backlight 1000 cd/m2 brightness, light sensor inward and outward facing LED 50,000 hour life or greater

Outdoor Environmentals: IP65 enclosure -5 degrees C to +40 degrees C operating temperature 90% relative humidity, non-condensing 44” W x 18” H x 10” D maximum 75 lbs maximum 110-240 VAC, 50-60 Hz, 300 Watts maximum 4 air flow temperature monitoring sensors ((1) internal display sensor, (1) internal

enclosure sensor, (2) air circulation sensors)

Integrated PC Intel Mobile Celeron 575 2.00GHz 1MB L2 Cache 667 MHz Socket-P processor or better 1 GB DDR SDRAM memory minimum 4 GB STAT DOM memory minimum 160 GB 2.5” SATA hard drive minimum 4 USB ports 1 D-sub RS-232 port 2 RJ-45 100Mbps/1000Mbps network ports Intel GM45/ICH9M chipset with GMA x 4500 graphics or better LVDS 24-bit 1920x1080 resolution or better

Remote Monitoring Screen activity Performance Internal temperature

WangS
Callout
CLARIFICATION NO. 1
WangS
Callout
Flexible intake and exhaust vent hoses sized per manufacturers recommendations attached to louver for venting of display panel