1 BROOKHAVEN SCIENCE ASSOCIATES

CF Coordination with Technical Divisions

Ove DylingConventional Facilities Advisory Committee Review

October 5-6, 2010

Page 2: CF Coordination with Technical Divisions

2 BROOKHAVEN SCIENCE ASSOCIATES

Outline• Interface Management Overview

• Implemented Changes

• Coordination with Technical Divisions

• Changes under Consideration

• Conclusion

Page 3: CF Coordination with Technical Divisions

3 BROOKHAVEN SCIENCE ASSOCIATES

Interface Management Overview

• Accelerator Group – Erik Johnson (Interface Manager)• Experimental Group – Andy Broadbent (Interface Manager)• Interface Mgr activities:

• Formal Weekly meetings• Additional meetings as required to resolve issues including Beneficial

Occupancy planning• Coordination meetings with Ring Building General Contractor• Use of Navisworks to coordinate in real time• Navisworks purchased by the Accelerator Group• Interface Mtg Minutes Documented on Share Point

Page 4: CF Coordination with Technical Divisions

4 BROOKHAVEN SCIENCE ASSOCIATES

Implemented Changes • Changes Implemented for Accelerator Group

• Beneficial Occupancy Coordination– Revised how magnets will be entering the Ring Tunnel

• RF Area Design Maturity– Revised roll-up door due to cryogenic equipment sizes– Revised RF Test Room Radiation Shielding Door

• Ring Tunnel Design Maturity– Revised Gaseous Nitrogen to Compressed Air

- Increased size of Cooling Tower Building • Injection Building Design Maturity – will discuss later

• Changes Implemented for Experimental Group– 100 Meter Long Beam Line (Hard X-ray Nanoprobe Satellite Building)

- Vibration Analysis- Integrated into both the Ring Building and LOB 3

Page 5: CF Coordination with Technical Divisions

5 BROOKHAVEN SCIENCE ASSOCIATES

Beneficial Occupancy Coordination

Temporary Entry DoorForklift area

Common Access Corridor Enlarged Opening

Page 6: CF Coordination with Technical Divisions

6 BROOKHAVEN SCIENCE ASSOCIATES

RF Area Design Maturity

Revised door height from 10’-0” to 14’-0”

Revised Radiation Shielding Door design in RF Test Area

Page 7: CF Coordination with Technical Divisions

7 BROOKHAVEN SCIENCE ASSOCIATES

Implemented Changes - MEP

• Labyrinth Coordination• Ductwork, Sprinkler Piping, and Electrical conduits coordinated with

Secondary DI water supply and return• Revised concrete penetration in Labyrinth wall

• Injection Building Coordination• Design Maturity of the Booster, Transport Line and Linac

• Revised sizing and location of the power supply.• Revised layout of the Electrical Systems• Coordination of ductwork layout• Located Secondary DI water locations• Revised concrete penetrations

Page 8: CF Coordination with Technical Divisions

8 BROOKHAVEN SCIENCE ASSOCIATES

Injection Building Plan

Page 9: CF Coordination with Technical Divisions

9 BROOKHAVEN SCIENCE ASSOCIATES

Injection Building Section

Page 10: CF Coordination with Technical Divisions

10 BROOKHAVEN SCIENCE ASSOCIATES

Coordination with Technical Divisions

• Coordination Processes• Shop Drawing Review

• Radiation Shielding Doors• RF Test Area Shielding Blocks• Location of Liquid and Gaseous Nitrogen drops• Integrated Power Cabinet (PAC) design and locations

• Regular Field Tours/Inspection of On-going Construction• Unistrut locations in Booster Tunnel

• Design documents indicated smooth arc• Construction methods resulting in 4’-6” segments

• Penetration omission in Booster Tunnel• Discovered mid August• Issued ECN 126 August 30, 2010

Page 11: CF Coordination with Technical Divisions

11 BROOKHAVEN SCIENCE ASSOCIATES

Changes under Consideration• Beneficial Occupancy Planning:

• Timing of Epoxy costing of experimental floor• Meetings conducted presently to identify optimal timing

• Accelerator System Scope:• Considering scope transfer for CF oversight of:

• Experimental Electrical Cable Tray• Lead Shielding in Ratchet Wall opening• Secondary DI water system inside Service Buildings & SR Tunnel

• Experimental Systems :• Additional Beam Lines during construction• Utility hook up to Hutches

Page 12: CF Coordination with Technical Divisions

12 BROOKHAVEN SCIENCE ASSOCIATES

Conclusions

• Technical Divisions and Conventional Facilities are confident that most changes have been discovered and incorporated into the design

• Planning for smooth integration of installation of Scientific equipment while construction is ongoing

• Technical Divisions and Conventional Facilities are well coordinated and are fully engaged in Conventional Facility Construction Progress