11/26/06 SJSU Bus. 286 - David Ben tley (Gray) 1 Copyright © 2008 by The McGraw-Hill Companies, Inc. All Rights Reserved. Chapter 13 - Progress and Performance Measurement and Evaluation Data collection and analysis; Project control process; Monitoring progress; Terminology; Baselines; Variances; Reporting

Upload: jawedsamsor

Post on 03-Apr-2015

215 views

Category:

Documents


7 download

TRANSCRIPT

Page 1: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

1Copyright © 2008 by The McGraw-Hill Companies, Inc. All

Rights Reserved.

Chapter 13 - Progress and Performance Measurementand Evaluation

Data collection and analysis; Project control process; Monitoring progress; Terminology; Baselines;

Variances; Reporting

Page 2: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

2

Course Structure

Page 3: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

3Copyright © 2008 by The McGraw-Hill Companies, Inc. All

Rights Reserved.

Project Monitoring System for Control

Page 4: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

4

Information System Structure

What data are collected? Collection and analysis questions Reports and reporting

(see following slides)

Page 5: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

5

What data are collected? Current status of project (schedule &

cost) Remaining cost to compete project Date that project will be complete Potential problems to be addressed now Out-of-control activities requiring

intervention Cost and/or schedule overruns and the

reasons for them Forecast of overruns at time of project

completion

Page 6: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

6

Collecting data and analysis

Who will collect project data? How will data be collected? When will the data be collected? Who will compile and analyze the

data?

Page 7: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

7

Reports and Reporting

Who will receive the reports? How will the reports be transmitted? When will the reports be distributed?

Page 8: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

8

Project Progress Report Format

Progress Since Last Report Current Status of Project

Schedule Cost Scope

Cumulative Trends Problems and Issues Since Last Report

Actions and resolution of earlier problems New variances and problems identified

Corrective Action Planned

Page 9: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

9Copyright © 2008 by The McGraw-Hill Companies, Inc. All

Rights Reserved.

The Project Control Process

Page 10: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

10

Definition of Control

The process of comparing actual performance against plan to identify deviations, evaluate courses of action, and take appropriate corrective action

Page 11: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

11

Project Control Steps Project Control Steps

1. Setting a baseline plan2. Measuring progress and performance3. Comparing plan against actual4. Taking actions

Page 12: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

12Copyright © 2008 by The McGraw-Hill Companies, Inc. All

Rights Reserved.

Monitoring Time Performance

Page 13: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

13

Tools for Variances and Status

Used to Catch Negative Variances from Plan and Communicate Project Schedule Status:

Tracking and baseline Gantt charts Show expected, actual, and trend data for

event duration performance Control charts

Plot the difference in scheduled time on the critical path with the actual point on the critical path

Page 14: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

14

Baseline and Tracking Gantt Charts

Page 15: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

15

Project Schedule Control Chart

Page 16: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

16Copyright © 2008 by The McGraw-Hill Companies, Inc. All

Rights Reserved.

Disparity Among Monitoring Systems

Page 17: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

17

Time-Phase Baseline Plan

Corrects the failure of most monitoring systems to connect a project’s actual performance to its schedule and forecast budget Systems that measure only cost

variances do not identify resource and project cost problems associated with falling behind or progressing ahead of schedule.

Page 18: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

18

Earned Value Cost/Schedule System

An integrated project management system based on the earned value concept that uses a time-phased budget baseline to compare actual and planned schedule and costs

Page 19: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

19Copyright © 2008 by The McGraw-Hill Companies, Inc. All

Rights Reserved.

Glossary of Terms

EV, PV, AC, CV, SV, BAC, EAC,ETC, VAC

Page 20: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

20

Earned Value (EV)

The percent complete times its original budget. The percent of the original budget that has been earned by actual work completed. The older acronym for this value was BCWP—budgeted cost of the work performed.

Page 21: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

21

Planned Value (PV)

The time-phased baseline of the value of the work scheduled. An approved cost estimate of the resources scheduled in a time-phased cumulative baseline (older acronym: BCWS—budgeted cost of the work scheduled).

Page 22: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

22

Actual Cost (AC)

The actual cost of the work completed. The sum of the costs incurred in accomplishing work. (older acronym: ACWP—actual cost of the work performed).

Page 23: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

23

Cost Variance (CV)

Cost variance is the difference between the earned value and the actual costs for the work completed to date where CV=EV-AC.

Page 24: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

24

Schedule Variance (SV)

Schedule variance (SV) is the difference between the earned value and the baseline line to date where SV=EV-PV.

Page 25: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

25

Budgeted Cost at Completion (BAC)

Budgeted cost at completion. The total budgeted cost of the baseline or project cost accounts.

Page 26: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

26

Estimated Cost at Completion (EAC)

Estimated costs at completion. Includes costs to-date plus revised estimated costs for the work remaining.

Page 27: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

27

Estimate to Complete (ETC)

Estimate to complete remaining work.

Page 28: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

28

Cost Variance at Completion (VAC)

Cost variance at completion (BAC-EAC), where EAC is derived by estimators in the field.

Or, alternatively, cost variance at completion (BAC-EACf), where EACf is derived from a formula using actual and earned value costs.

VAC indicates expected actual over-or underrun cost at completion.

Page 29: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

29Copyright © 2008 by The McGraw-Hill Companies, Inc. All

Rights Reserved.

Developing an Integrated Cost/Schedule System

1. Work Breakdown Structure (WBS)2. Work & Resource Schedules3. Time Phased Budget

Page 30: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

30

Define the Work Using a WBS

WBS contenta. Scopeb. Work packagesc. Deliverablesd. Organization unitse. Resourcesf. Budgets

Page 31: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

31

Develop Work and Resource Schedules

Work and resource schedulesa. Schedule resource to activitiesb. Time-phase work packages into a

network

Page 32: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

32

Develop a Time-phased Budget

Develop a time-phased budget using work packages included in an activity.

Accumulate budgets for all activities (PV)

Page 33: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

33

Collect Actual Costs

At the work package level, collect the actual costs for the work performed (AC).

Page 34: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

34

Determine Earned Value

Multiply percent complete times original budget (EV).

Page 35: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

35

Compute Variances

Schedule variance (SV = EV – PV) Cost variance (CV = EV – AV)

Page 36: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

36

Summary of Integrated Cost/Schedule System

1. Define the work using a WBS.

a. Scope

b. Work packages

c. Deliverables

d. Organization units

e. Resources

f. Budgets

2. Develop work and resource schedules.

a. Schedule resources to activities

b. Time-phase work packages into a network

3. Develop a time-phased budget using work packages included in an activity. Accumulate budgets (PV).

4. At the work package level, collect the actual costs for the work performed (AC).

5. Multiply percent complete times original budget (EV).

6. Compute the schedule variance (EV-PV) and the cost variance (EV-AC).

Page 37: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

37

Project Management System Overview

Page 38: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

38Copyright © 2008 by The McGraw-Hill Companies, Inc. All

Rights Reserved.

Developing Project Baselines

Page 39: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

39

Purposes of a Baseline (PV) An anchor point for measuring

performance A planned cost and expected schedule

against which actual cost and schedule are measured

A basis for cash flows and awarding progress payments

A summation of time-phased budgets (cost accounts as summed work packages) along a project timeline

Page 40: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

40

Costs Included in Baselines

Labor Equipment Materials Project direct overhead costs (DOC)

Page 41: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

41

Baseline Data Relationships

Page 42: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

42

Rules for Placing Costs in Baselines

Costs are placed exactly as they are expected to be “earned” in order to track them to their point of origin.

Percent Complete Rule Costs are periodically

assigned to a baseline as units of work are completed over the duration of a work package.

Page 43: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

43Copyright © 2008 by The McGraw-Hill Companies, Inc. All

Rights Reserved.

Methods of Variance Analysis

Comparing earned valueAssessing project status

Page 44: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

44

Comparing Earned Value

With the expected schedule value With the actual costs

Page 45: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

45

Assessing Status of a Project

Required data elements Data Budgeted cost of the work scheduled

(PV) Budgeted cost of the work completed (EV) Actual cost of the work completed (AC)

Calculate schedule and cost variances A positive variance indicates a desirable

condition, while a negative variance suggests problems or changes that have taken place.

Page 46: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

46

Variances

Cost Variance (CV) Indicates if the work accomplished using

labor and materials costs more or less than was planned at any point in the project

Schedule Variance (SV) Presents an overall assessment in dollar

terms of the progress of all work packages in the project scheduled to date

Page 47: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

47

Cost/Schedule Graph

Page 48: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

48

Earned Value Review Exercise

Page 49: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

49Copyright © 2008 by The McGraw-Hill Companies, Inc. All

Rights Reserved.

Developing A Status Report:A Hypothetical Example

Page 50: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

50

Assumptions Each cost account has only one work

package, and each cost account will be represented as an activity on the network.

The project network early start times will serve as the basis for assigning the baseline values.

Baseline value will be assigned linearly, unless stated differently.

From the moment work on an activity begins, some actual costs will be incurred each period until the activity is completed.

Page 51: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

51

Work Breakdown Structure and Cost Accounts

Page 52: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

52

Digital Camera Prototype Project Baseline Gantt Chart

Page 53: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

53

Digital Camera Prototype Project Baseline

Page 54: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

54

Digital Camera Prototype Status Reports: Periods 1–3

Page 55: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

55

Digital Camera Prototype Status Reports: Periods 4–6

Page 56: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

56

Digital Camera Prototype Status Reports: Period 7

Page 57: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

57

Digital Camera Prototype Summary Graph (000)

Page 58: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

58

Digital Camera Project Tracking Gantt Chart Showing Status—Through Period 7

Page 59: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

59

Digital Camera Project Rollup at End Period 7 (000)

Page 60: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

60Copyright © 2008 by The McGraw-Hill Companies, Inc. All

Rights Reserved.

Indexes to Monitor Progress

Page 61: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

61

Performance Indexes Cost Performance Index (CPI)

Measures the cost efficiency of work accomplished to date

CPI = EV/AC Scheduling Performance Index (SPI)

Measures scheduling efficiency SPI = EV/PV

Page 62: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

62

Percent Complete Indexes

Indicates how much of the work accomplished represents of the total budgeted (BAC) and actual (AC) dollars to date PCIB = EV/BAC (budget) PCIC = AC/EAC (actual)

Page 63: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

63

Interpretation of Indexes

TABLE 13.3

Page 64: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

64

Indexes Periods 1–7

FIGURE 13.13

Page 65: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

65

Typical Computer-Generated Status Reports

Schedule variance (EV-PV) by cost account and WBS and OBS

Cost variance (EV-AC) by cost account and WBS and OBS

Indexes—cost, schedule, total percent complete, and the to complete performance index

Cumulative actual total to date (AC) Expected costs at completion Paid and unpaid commitments

Page 66: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

66

Additional Earned Value Rules

Rules Applied to Short-Duration Activities and/or Small-Cost Activities 0/100 percent rule

Assumes 100 % of budget credit is earned at once and only when the work is completed

50/50 rule Allows for 50% of the value of the work

package budget to be earned when it is started and 50% to be earned when the package is completed

Page 67: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

67

Forecasting Final Project Cost

Methods Used to Revise Estimates of Future Project Costs: EACre

Allows experts in the field to change original baseline durations and costs because new information tells them the original estimates are not accurate

EACf Uses actual costs-to-date plus an efficiency index to

project final costs in large projects where the original budget is unreliable

Page 68: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

68

Forecasting Model: EACf

The equation for this forecasting model:

Page 69: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

69

To Complete Performance Index (TCPI)

BAC - EVTCPI= BAC – AC

TCPI = the amount of value each remaining dollar in the budget must earn to stay within budget

Page 70: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

70

Other Control Issues

Issues In Maintaining Control Of ProjectsIssues In Maintaining Control Of ProjectsIssues In Maintaining Control Of ProjectsIssues In Maintaining Control Of Projects

Baseline ChangesBaseline ChangesBaseline ChangesBaseline Changes

Contingency ReserveContingency ReserveContingency ReserveContingency Reserve

Costs and Problems of Data AcquisitionCosts and Problems of Data AcquisitionCosts and Problems of Data AcquisitionCosts and Problems of Data Acquisition

Scope CreepScope CreepScope CreepScope Creep

Managing the Portfolio of ProjectsManaging the Portfolio of ProjectsManaging the Portfolio of ProjectsManaging the Portfolio of Projects

Page 71: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

71

Scope Changes to a Baseline

FIGURE 13.14

Page 72: Ch 13 Progress and Performance

11/26/06 SJSU Bus. 286 - David Bentley (Gray)

72

Key Terms

Base line budget Schedule performance Control Chart index (SPI)Cost performance Schedule variance (SV)index (CPI) Scope creepCost variance (CV) To complete performanceEarned Value (EV) index (TCPI)Estimated cost at Tracking Gantt chartcompletion (EACre) Variance at completion (VAC)Percent complete index