Learning Objectives
1. Describe the master data associated with the productionprocess.
2. Identify the key steps in the production process and thedata, documents, and information associated with eachstep.
3. Effectively use SAP® ERP to execute the key steps in theproduction process.
4. Effectively use SAP ERP to extract meaningful informationabout the production process.
2 Magal and Word | Integrated Business Processes with ERP Systems | ©2011
-
8/9/2019 Ch06 the Production Process
3/75
Types of Manufacturing
Discrete vs. repetitive vs. process
Discrete and repetitive
Tangible products
Manufactured in individual units
Skateboards, bicycles
Repetitive manufacturing
Same or similar products are produced over a period of time
A specified quantity is produced over a period of time Discrete
Batches of different materials over time
Magal and Word | Integrated Business Processes with ERP Systems | ©2011
3
-
8/9/2019 Ch06 the Production Process
4/75
Types of manufacturing
Process manufacturing Not manufactured in individual units
Gallons, pints, liters
Paint, soft drinks
Magal and Word | Integrated Business Processes with ERP Systems | ©2011
4
-
8/9/2019 Ch06 the Production Process
5/75
A Basic Production Process
Magal and Word | Integrated Business Processes with ERP Systems | ©2011
5
-
8/9/2019 Ch06 the Production Process
6/75
Organizational Data
Client
Company code
Plant
Storage location
Magal and Word | Integrated Business Processes with ERP Systems | © 20116
-
8/9/2019 Ch06 the Production Process
7/75
Master Data
Bill of materials (BOM)
Work center
Product routing
Material master Production resource tools (PRT)
Magal and Word | Integrated Business Processes with ERP Systems | © 20117
-
8/9/2019 Ch06 the Production Process
8/75
Bill of Materials
Identifies the components needed to make the material
A component can have its own BOM to creates a multi-levelBOM
BOMs are used in
Material planning
Production
Procurement
Product costing
Magal and Word | Integrated Business Processes with ERP Systems | © 20118
-
8/9/2019 Ch06 the Production Process
9/75
Single-level and Multi-level BOMs
Magal and Word | Integrated Business Processes with ERP Systems | © 20119
-
8/9/2019 Ch06 the Production Process
10/75
Bill of Materials for Touring Bikes
Magal and Word | Integrated Business Processes with ERP Systems | © 201110
-
8/9/2019 Ch06 the Production Process
11/75
Bill of Materials for Off-road Bikes
Magal and Word | Integrated Business Processes with ERP Systems | © 201111
-
8/9/2019 Ch06 the Production Process
12/75
Bill of Materials - Header
Applies to the entire BOM
Status: active, inactive
Base quantity: materials specified are needed to make the base quantity (typically 1 unit).
Usage: production, engineering, costing, etc.
Plant: each plant can have a different BOM
Validity: date range
Magal and Word | Integrated Business Processes with ERP Systems | © 201112
-
8/9/2019 Ch06 the Production Process
13/75
Bill of Materials - Items
Apply to the specific item in the BOM
Item category: Stock item – must have a material master
Nonstock item – no material master
Variable-sized item –
must specify size Document item – diagrams, additional instructions
Material number
Quantity
Magal and Word | Integrated Business Processes with ERP Systems | © 201113
-
8/9/2019 Ch06 the Production Process
14/75
BOM Structure
Magal and Word | Integrated Business Processes with ERP Systems | © 201114
-
8/9/2019 Ch06 the Production Process
15/75
Demo 6.1 BOM for Bike and Wheel
Assembly
Review some of the data included in a material master
Magal and Word | Integrated Business Processes with ERP Systems | © 201115
-
8/9/2019 Ch06 the Production Process
16/75
Work Center
Basic data Name, description
Person responsible for maintaining master data
Task list usage (which routings can use this work center)
Capacities
Scheduling
Cost center
HR assignment
Magal and Word | Integrated Business Processes with ERP Systems | © 201116
-
8/9/2019 Ch06 the Production Process
17/75
Work Center Data
Magal and Word | Integrated Business Processes with ERP Systems | © 201117
-
8/9/2019 Ch06 the Production Process
18/75
-
8/9/2019 Ch06 the Production Process
19/75
GBI Work Centers
Magal and Word | Integrated Business Processes with ERP Systems | © 201119
-
8/9/2019 Ch06 the Production Process
20/75
Demo 6.2 Review GBI Work Center
Review the GBI work center
Magal and Word | Integrated Business Processes with ERP Systems | © 201120
-
8/9/2019 Ch06 the Production Process
21/75
Product Routing
Steps necessary to produce a material Operations
Sequence
Standard
Alternate
Parallel
Work center
Times
Setup, machine, labor
Magal and Word | Integrated Business Processes with ERP Systems | © 201121
-
8/9/2019 Ch06 the Production Process
22/75
Work Center Example
Magal and Word | Integrated Business Processes with ERP Systems | © 201122
-
8/9/2019 Ch06 the Production Process
23/75
Structure of a Routing
Magal and Word | Integrated Business Processes with ERP Systems | © 201123
-
8/9/2019 Ch06 the Production Process
24/75
Routing and Work Centers
Magal and Word | Integrated Business Processes with ERP Systems | © 201124
-
8/9/2019 Ch06 the Production Process
25/75
-
8/9/2019 Ch06 the Production Process
26/75
Routing for Deluxe Touring Bike
Magal and Word | Integrated Business Processes with ERP Systems | © 201126
-
8/9/2019 Ch06 the Production Process
27/75
Demo 6.3 Review Routing for a
Bike and Wheel Assembly
Review the routing for a bike and wheel assembly
Magal and Word | Integrated Business Processes with ERP Systems | © 201127
-
8/9/2019 Ch06 the Production Process
28/75
Component Assignment
Specifies the relationship between a BOM and a routing Assigns components (materials) in a BOM either to a routing
or to a specific operation within routing
If not assigned assumed to be assigned to the first operation
Magal and Word | Integrated Business Processes with ERP Systems | © 201128
-
8/9/2019 Ch06 the Production Process
29/75
Component Assignment
Magal and Word | Integrated Business Processes with ERP Systems | © 201129
-
8/9/2019 Ch06 the Production Process
30/75
Production Capability
A measure of how many units of a material a plant canproduce within a given timeframe
A data source for production planning
Magal and Word | Integrated Business Processes with ERP Systems | © 201130
-
8/9/2019 Ch06 the Production Process
31/75
Sample GBI Production Plan
Magal and Word | Integrated Business Processes with ERP Systems | © 201131
-
8/9/2019 Ch06 the Production Process
32/75
Material Master
Previously discussed views Basic data
Purchasing related
Sales related
Accounting related
Additional view needed for production
Work scheduling – plant specific
MRP – plant specific
More relevant in material planning
Will be discussed in that chapter
Magal and Word | Integrated Business Processes with ERP Systems | © 2011
32
-
8/9/2019 Ch06 the Production Process
33/75
Production Resource Tools
Movable objects required for production Shared among different work centers
Documents (instructions)
Materials (calibration tool)
Equipment (machine that is not in a fixed location)
Miscellaneous
Magal and Word | Integrated Business Processes with ERP Systems | © 2011
33
-
8/9/2019 Ch06 the Production Process
34/75
The Production Process
Magal and Word | Integrated Business Processes with ERP Systems | © 2011
34
-
8/9/2019 Ch06 the Production Process
35/75
Request Production
Planned order What material
How many
When
Generated by other processes
Fulfillment
Project management
Material planning
Can be created manually
Magal and Word | Integrated Business Processes with ERP Systems | © 2011
35
El t f th R t P d ti
-
8/9/2019 Ch06 the Production Process
36/75
Elements of the Request Production
Step
Magal and Word | Integrated Business Processes with ERP Systems | © 2011
36
-
8/9/2019 Ch06 the Production Process
37/75
Data in a Planned Order
Magal and Word | Integrated Business Processes with ERP Systems | © 2011
37
-
8/9/2019 Ch06 the Production Process
38/75
Demo 6.4 Create a Planned Order
Review how to create a planned order
Magal and Word | Integrated Business Processes with ERP Systems | © 2011
38
-
8/9/2019 Ch06 the Production Process
39/75
Authorize Production
With planned order: convert Convert to production order
Without planned order: create production order
Production order
What material is to be produced?
How many?
When?
Where will they be produced? What resources are to be used?
How much is it expected to cost?
Magal and Word | Integrated Business Processes with ERP Systems | © 2011
39
Elements of the Authorize Production
-
8/9/2019 Ch06 the Production Process
40/75
Elements of the Authorize Production
Step
Magal and Word | Integrated Business Processes with ERP Systems | © 2011
40
-
8/9/2019 Ch06 the Production Process
41/75
Data in a Production Order
Magal and Word | Integrated Business Processes with ERP Systems | © 2011
41
-
8/9/2019 Ch06 the Production Process
42/75
Structure of a Production Order
Magal and Word | Integrated Business Processes with ERP Systems | © 2011
42
-
8/9/2019 Ch06 the Production Process
43/75
Authorize Production - Outcomes
Scheduling Availability checks
Reservations
Preliminary costing Purchase requisitions
Magal and Word | Integrated Business Processes with ERP Systems | © 2011
43
Preliminary Cost Estimates for Men’s
-
8/9/2019 Ch06 the Production Process
44/75
Preliminary Cost Estimates for Men s
Off-road Bike
Magal and Word | Integrated Business Processes with ERP Systems | © 2011
44
-
8/9/2019 Ch06 the Production Process
45/75
Cost Estimates in a Production Order
Magal and Word | Integrated Business Processes with ERP Systems | © 2011
45
Planned cost: planned cost for planned quantity
Based on material and labor cost estimates
Target cost: planned cost for actual quantity Actual cost: actual cost for actual quantity
-
8/9/2019 Ch06 the Production Process
46/75
-
8/9/2019 Ch06 the Production Process
47/75
Order Release
On creation order status is created (CRTD) Order must be released (REL) to permit subsequent steps
such as
Goods movement not possible
Confirmations not possible
Documents cannot be printed
Settlement
Magal and Word | Integrated Business Processes with ERP Systems | © 2011
47
-
8/9/2019 Ch06 the Production Process
48/75
Elements of the Order Release Step
Magal and Word | Integrated Business Processes with ERP Systems | © 2011
48
-
8/9/2019 Ch06 the Production Process
49/75
Order Release
Automatic or manual If no time is needed between creation and release for
preparation, then release occurs automatically
Release at different levels
Header: All operations are released Operations: Release specific operations
Operations status: REL
Order status: PREL (partially released)
Magal and Word | Integrated Business Processes with ERP Systems | © 2011
49
-
8/9/2019 Ch06 the Production Process
50/75
Order Release - Outcomes
Execution of subsequent steps is possible Shop floor papers can be printed
Communication with PDC is possible
Magal and Word | Integrated Business Processes with ERP Systems | © 2011
50
-
8/9/2019 Ch06 the Production Process
51/75
Goods Issue
Movement type 261 Impact
Material, FI, CO documents
G/L accounts updated
Inventory updated
Reservations updated (reduced)
Costs updated (actual cost in order)
Magal and Word | Integrated Business Processes with ERP Systems | © 2011
51
-
8/9/2019 Ch06 the Production Process
52/75
Elements of the Goods Issue Step
Magal and Word | Integrated Business Processes with ERP Systems | © 2011
52
-
8/9/2019 Ch06 the Production Process
53/75
Data in a Goods Issue Step
Magal and Word | Integrated Business Processes with ERP Systems | © 2011
53
Fi i l I f G d I
-
8/9/2019 Ch06 the Production Process
54/75
Financial Impact of a Goods Issue
Magal and Word | Integrated Business Processes with ERP Systems | © 2011
54
Demo 6 6 Goods Issue to Production
-
8/9/2019 Ch06 the Production Process
55/75
Demo 6.6 Goods Issue to Production
Order
Review the steps from goods issue to production order
Magal and Word | Integrated Business Processes with ERP Systems | © 2011
55
-
8/9/2019 Ch06 the Production Process
56/75
Confirmations
Order level confirmation Operations level confirmation
Magal and Word | Integrated Business Processes with ERP Systems | © 2011
56
-
8/9/2019 Ch06 the Production Process
57/75
-
8/9/2019 Ch06 the Production Process
58/75
Data in a Confirmation
Magal and Word | Integrated Business Processes with ERP Systems | © 2011
58
-
8/9/2019 Ch06 the Production Process
59/75
Financial Impact of a Confirmation
Magal and Word | Integrated Business Processes with ERP Systems | © 201159
-
8/9/2019 Ch06 the Production Process
60/75
Demo 6.7 Confirm Production
Review confirm production
Magal and Word | Integrated Business Processes with ERP Systems | © 201160
-
8/9/2019 Ch06 the Production Process
61/75
Goods Receipt
Goods receipt into storage Movement type 101
Impact
Material, FI, CO documents
Material master update (quantity and value)
Production order update (quantity, date, costing)
Magal and Word | Integrated Business Processes with ERP Systems | © 201161
-
8/9/2019 Ch06 the Production Process
62/75
Elements of a Goods Receipt
Magal and Word | Integrated Business Processes with ERP Systems | © 201162
D i G d R i
-
8/9/2019 Ch06 the Production Process
63/75
Data in a Goods Receipt
Magal and Word | Integrated Business Processes with ERP Systems | © 201163
-
8/9/2019 Ch06 the Production Process
64/75
Financial Impact of a Goods Receipt
Magal and Word | Integrated Business Processes with ERP Systems | © 201164
Demo 6 8 Goods Receipt from
-
8/9/2019 Ch06 the Production Process
65/75
Demo 6.8 Goods Receipt from
Production
Review goods receipts from production
Magal and Word | Integrated Business Processes with ERP Systems | © 201165
-
8/9/2019 Ch06 the Production Process
66/75
Periodic Processing
Overhead calculation
Work in progress determination
Settlement
Magal and Word | Integrated Business Processes with ERP Systems | © 201166
-
8/9/2019 Ch06 the Production Process
67/75
Overhead Calculation
Indirect costs Supervisor, manager, other salaries
Utilities
Accumulated in cost centers
Periodically allocated to production orders based onpredetermined rules
Magal and Word | Integrated Business Processes with ERP Systems | © 201167
Work-in-Progress Determination
-
8/9/2019 Ch06 the Production Process
68/75
Work-in-Progress Determination Work-in-progress (WIP) inventory
Inventory between GI and GR inventory Periodically the value of what is in the production process is
calculated and posted to the general ledger
Not essential
For short production processes Value of materials is not high
GBI
Essential
When value of materials is high
Production takes weeks, months, or years
Aircraft production, construction.
Magal and Word | Integrated Business Processes with ERP Systems | © 201168
-
8/9/2019 Ch06 the Production Process
69/75
Settlement
Settle the difference between planned and actual costs(variance)
Only panned costs are posted in the GR step
Variance is settled in this step
Magal and Word | Integrated Business Processes with ERP Systems | © 201169
-
8/9/2019 Ch06 the Production Process
70/75
Financial Impact of a Settlement
Magal and Word | Integrated Business Processes with ERP Systems | © 201170
-
8/9/2019 Ch06 the Production Process
71/75
Reporting
General SAP reporting options Online lists
Work lists
Analytics
Production-specific reporting options Stock/requirement lists
Magal and Word | Integrated Business Processes with ERP Systems | © 201171
Production Information System -
-
8/9/2019 Ch06 the Production Process
72/75
y
Components
Magal and Word | Integrated Business Processes with ERP Systems | © 201172
Production Information Systems -
-
8/9/2019 Ch06 the Production Process
73/75
y
Operations
Magal and Word | Integrated Business Processes with ERP Systems | © 201173
Stock/Requirements List
-
8/9/2019 Ch06 the Production Process
74/75
Stock/Requirements List
Magal and Word | Integrated Business Processes with ERP Systems | © 201174
-
8/9/2019 Ch06 the Production Process
75/75