1 Cleaner Environment CHALLENGES IN DEVELOPMENT OF ERDMP MAHARASHTRA NATURAL GAS LTD, PUNE 28.09.2012 Sagar Varma Senior Manager( Fire & safety

Upload: dorie

Post on 13-Feb-2016

58 views

Category:

Documents


4 download

DESCRIPTION

MAHARASHTRA NATURAL GAS LTD, PUNE. CHALLENGES IN DEVELOPMENT OF ERDMP. Sagar Varma Senior Manager( Fire & safety). 28.09.2012. MAHARASHTRA NATURAL GAS LTD. MAHARASHTRA NATURAL GAS LIMITED (MNGL) A Joint Venture promoted by GAIL (India) Limited ; and - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: CHALLENGES IN DEVELOPMENT  OF  ERDMP

1

Cleaner Environment

CHALLENGES IN DEVELOPMENT

OF

ERDMP

MAHARASHTRA NATURAL GAS LTD, PUNE

28.09.2012

Sagar VarmaSenior Manager( Fire & safety)

Page 2: CHALLENGES IN DEVELOPMENT  OF  ERDMP

2

Cleaner Environment

MAHARASHTRA NATURAL GAS LIMITED (MNGL)

A Joint Venture promoted by

• GAIL (India) Limited; and

• Bharat Petroleum Corporation Limited

MAHARASHTRA NATURAL GAS LTD.

To implement

City Gas Distribution Project in

Pune, Pimpri-Chinchwad (including Hinjewadi, Talegaon & Chakan)

Page 3: CHALLENGES IN DEVELOPMENT  OF  ERDMP

3

Cleaner Environment

DAHEJ BARUCH

HAZIRA

NAVSARI

VALSAD

SILVASA

APTI BUDRUK

HAJIMALANGWADI

DAHANU

VASAIBORIVALI

TROMBAY

GHOTAW`ADE

CHINCHWADETHAL

DABHOL

PUNE

VAPI

SURAT

PANVEL

URANIIL

USAR AMBEWADI

NASIK

SAFALE

GAIL’S TRANSMISSION PIPELINES

1. DAHEJ – URAN PIPELINE

2. DABHOL – PANVEL PIPELINE

3. GHOTAWADE – CHINCHWAD PIPELINE

Page 4: CHALLENGES IN DEVELOPMENT  OF  ERDMP

4

Cleaner Environment

DFR prepared by MECON in 2002

MoP&NG allocated 0.4 MMSCMD APM Gas to Pune City in April’2004

Date of Incorporation - 13.01.2006

Date of Commencement of Business - 24.03.2006

Authorised by PNGRB on 15.04.2009

Page 5: CHALLENGES IN DEVELOPMENT  OF  ERDMP

5

Cleaner Environment

City Gate Station

19 Bar Steel Network

4 Bar PE Network

Mother Station Chinchwad

DRS

GI Installation Service RegulatorDomestic Kitchen

100 mbar PE Network

21 mbar CU

Network

Page 6: CHALLENGES IN DEVELOPMENT  OF  ERDMP

6

Cleaner Environment

Customer Base

Domestic4000

customers

Vehicles24000 auto10000 cars530 buses

Industrial37 nos.

Hotels/Small Commercial

13 commercial

Page 7: CHALLENGES IN DEVELOPMENT  OF  ERDMP

7

Cleaner Environment Major Challenge CGD companies

operate as utilities and operate in city conditions.

Our typical response to emergency is based on customer complaints.

Page 8: CHALLENGES IN DEVELOPMENT  OF  ERDMP

8

Cleaner Environment Major Challenge

Common regulation for midstream as well as downstream.

Page 9: CHALLENGES IN DEVELOPMENT  OF  ERDMP

9

Cleaner Environment

Documentation challenge

Old ERDMP reformatted to include all the 30 points of regulation, 9 schedules and 7 checklists.

Supports in the form of annexure included to give sense to the content

Page 10: CHALLENGES IN DEVELOPMENT  OF  ERDMP

10

Cleaner Environment

Documentation challenge

To include Risk analysis and

consequence mapping.

Collection of data from various departments

Page 11: CHALLENGES IN DEVELOPMENT  OF  ERDMP

11

Cleaner Environment challenges Site visit and

mockdrills Three mockdrills

conducted in span to 2 hours.

resource constraints. Offsite department

involvement

Page 12: CHALLENGES IN DEVELOPMENT  OF  ERDMP

12

Cleaner Environment Other challenges Perception of TPI delegates

Repeated Micro level changes

Page 13: CHALLENGES IN DEVELOPMENT  OF  ERDMP

13

Cleaner Environment

contents

Other Challenges

Flow of document

Longtime taken for each stage of accreditation

Foreword Definitions Executive Summary 11 chapters ( covering each

and every schedule) 20 Annexures 7 Checklists

Page 14: CHALLENGES IN DEVELOPMENT  OF  ERDMP

14

Cleaner Environment Benefits of the exercise Involvement lead to knowledge up gradation Various areas of safety management system

come to surface Comprehensive documentation Knowledge sharing with other CGD Tying of loose ends