challenges in project management sept 11,2009 slide number- 1 of31 delivering excellence through...
TRANSCRIPT
Challenges in Project Management Sept 11,2009
Slide Number- 1 of31
Delivering excellence through people
THEME LECTUREPETROFED
SEPT 11,2009( M. Rohatgi, CMD EIL)
CHALLENGES IN PROJECT MANAGEMENT
Challenges in Project ManagementSept 11,2009
Engineers India Ltd – Delivering excellence through people
Presentation Outline
Introduction
Major areas of Concern
Stages of a Project
Key Challenges
Conclusion
Challenges in Project ManagementSept 11,2009
Engineers India Ltd – Delivering excellence through people
Introduction
• Projects are growing in size and complexity-today it is common to think in terms of projects involving investments of Rs. 20000 Cr and more.
• Integration for value addition characterizes most projects e.g. Refinery-Petrochemicals. The future could see refining and gas processing or refining and coal processing integrations.
• Increasing complexity and size accompanied by a need to cut implementation time and cost
• The net result is a set of major challenges that the Project Owners, Consultants, Contractors and Suppliers have to face jointly and overcome at each stage of a project
Challenges in Project ManagementSept 11,2009
Engineers India Ltd – Delivering excellence through people
Concerns
• Delays
• Cost over runs
• Management of risk
• Resource Constraints
• Sustainability
The right approach at each stage helps to address these issues
Challenges in Project ManagementSept 11,2009
Engineers India Ltd – Delivering excellence through people
Concerns-Delays
• Lack of approvals
• Supply lead chain times
• Poor scope definition
• Changes in design and scope
• Poor Planning / unrealistic schedules
Challenges in Project ManagementSept 11,2009
Engineers India Ltd – Delivering excellence through people
Concerns-Cost Over runs
• Materials price escalation• Inadequate scope definition• Time delay• Inadequate estimating/forecasting• Regulatory approvals• Inadequate resources/ Inexperienced team• Poor risk Management• Labour costs• Design Changes
A good Project Management approach would attempt to address these issues at each stage of a project
Challenges in Project ManagementSept 11,2009
Engineers India Ltd – Delivering excellence through people
Stages of a Project - Formulation
Objective-• Define the project boundaries with limited information
available.Issues to be addressed• Industrial outlook, Competitive trends• Project for domestic demand/export or both• Location, size and scale• Access to raw materials and markets for products• Technology options• Environmental stipulations• Investment and financing outlookDesirable to have a PMC in place at this juncture
Challenges in Project ManagementSept 11,2009
Engineers India Ltd – Delivering excellence through people
Idea
Generation
Brain Storming
SWOTOptions
Alternatives
Initial
Vision Plan
Formulation-where does it all begin?
Challenges in Project ManagementSept 11,2009
Engineers India Ltd – Delivering excellence through people
Business Applications
External Factors
Market Demands & Prices
Available Crudes & Prices
Emissions & Product Quality
LegislationSupply OptionsConversion
Options
Strategic Considerations
Growth
Return on Investment
Cash Flow
Development of Vision – Influencing Factors
Available Options
Visualizing the Project
Challenges in Project ManagementSept 11,2009
Engineers India Ltd – Delivering excellence through people
Long Term Vision
Factors
Develop Options
Evaluate
Future Configuratio
n
Where TO?
How TO?
WHAT are the costs benefits, risks and financial sensitivities?
Road Map to the Future
Challenges in Project ManagementSept 11,2009
Engineers India Ltd – Delivering excellence through people
Stages of a Project-Development
Objective: • Facilitate an investment decision
Issues to be addressed• Infrastructure-raw material receipt and product
evacuation, location and site development requirements, water intake and treatment, enabling facilities for construction.
• Technology selection and integration of various processes into one composite scheme to meet the project objectives
• Investment and economic analysis• Project financing • Output-Project Feasibility Report and
recommendation of project implementation approach
Challenges in Project ManagementSept 11,2009
Engineers India Ltd – Delivering excellence through people
Stages of a Project-Definition
• Crucial Stage for the project as it is the final gate for approval or otherwise.
• Project owner should have the approval for expenditure towards Basic design and engineering, followed by FEED preparation for ISBL facilities, utility and offsite facilities.
• Detailed cost estimates and project schedules to be prepared, with appropriate value engineering carried out for cost rationalization, overall process integration, optimization of utility and offsite systems design and project implementation approach
• Output- Front end loading report with detailed cost estimates and packages that are good for inviting bids from EPC/EPCM contractors
Challenges in Project ManagementSept 11,2009
Engineers India Ltd – Delivering excellence through people
PROCESS DESIGN
DESIGN BASIS
CONCEPTUAL PROCESS DESIGN
DETAIL PROCESS DESIGN
BASIC FRONT – END DESIGN
BID PACKAGE FOR EPC/LSTK BIDDING
ENGINEERING CONSTRUCTION CONTRACTS
COMMERCIAL TERMS & CONDITIONS
SUPPORT
ADVANCE CONTROLS & OPTIMISATIONMATERIALS & MAINTENANCEENERGY & ENVIRONEMNTOPERATIONS,SAFETY & HAZARDS
All this on electronic media
FEED Implementation Sequence Encapsulated
Challenges in Project ManagementSept 11,2009
Engineers India Ltd – Delivering excellence through people
VENDORS CONTRACTORS EPC
CONTRACTORS
PROJECT MANAGEMENT
OWNER MANAGEMENT
CONFIGURATION & DESIGN BASIS
PROCESS DESIGN
DETAIL ENGG.
BID PACKAGE &
CONTRACTOR SELECTION
FRONT END ENGG
EQUIPMENT DELIVERIES
CONSTRUCTION
COMMISSIONING & HANDING OVER
EXTERNAL LINKAGES INCLUDING STATUORY
Project Management – Managing all players
Challenges in Project ManagementSept 11,2009
Engineers India Ltd – Delivering excellence through people
OWNER engages a CONTRACTOR to implement the job on EPCM basis with fixed commitment on Project Schedule at an agreed fee
The Contractual arrangement provides for the commitments to be made by contractor & shared with the owner transparently till an agreed commitment level of 65-70% of the target cost is achieved
Single Point responsibility of contractor to deliver the project as per the agreed schedule
Option of conversion of the contract to LSTK mode after typically 65-70% of the commitment of the Target cost has been achieved
Is the emerging favoured mode of Project Implementation in India as
It reduces contractor/client risks and hence optimises the Project Investment Enables early start for Schedule gains Provides for LSTK benefits with reduced overall risks Win Win both for Owner – Contractor
EIL 15
Project Implementation-OBE/LSTK
Challenges in Project ManagementSept 11,2009
Engineers India Ltd – Delivering excellence through people
EIL 16
EPCM LSTK OBE/LSTK
Overall Cost Low High Moderate
Schedule Commitment Low High High
Owner’s Risk High Low Low
Contractor Risk None High Moderate
Flexibility to Change High None Low
Contractual Issues & Change Orders
None High Low
Owners Management team Resources
High Low Low
Quality of Produce High High – Extreme vigil required
High
Popular mode of Implementation in India
•Till Early 2000
•Since 2001
•Very Popular
•Not favoured except for revamps
•Emerging
•Selectively Popular
•Non – Existent
•Gaining Popularity
Alternative Modes of Implementation
Challenges in Project ManagementSept 11,2009
Engineers India Ltd – Delivering excellence through people
Finalisation of Overall schedule
Finalization of procurement procedures Type of bidding Open or limited Imported/Indigenous Items Taxes/duties/structure Shipping, marine transport, Custom clearance, Insurance and
inland transportation philosophy Finalisation of Master Vendor list
Finalization of detailed project schedules for Engineering ,
Hardware procurement and Construction
Development of Quality Assurance plans
System finalisation for real time monitoring of activities
EIL 17
Kicking off the Implementation Process
Challenges in Project ManagementSept 11,2009
Engineers India Ltd – Delivering excellence through people
Low cost
Competitive Cycle Time
Excellent Operability
Focussed Project Management Process
Empowered Team
Front end Loading
Timely involvement of
contractors
Discipline & continuity
Technology Selection
Value Improving Process
Best Practices
Project control-a sustained exercise
Challenges in Project ManagementSept 11,2009
Engineers India Ltd – Delivering excellence through people
Schedule
Sets the parameters of measurement Essential prerequisite and analytical tool for Project Health Monitoring Torch bearer for Mid Course Corrective action Time saved is Money realised
Cost
The Key is to build in less than Estimated cost Crucial for Process Viability & hence warrants close control Facilitates the basis of Comparative Evaluation Needs in-depth Knowledge of Variables ,Market, Taxation, Competition ,
Schedule for Exercising vigil & control over costs
EIL 19
Time and Cost Control-the key drivers
Challenges in Project ManagementSept 11,2009
Engineers India Ltd – Delivering excellence through people
EIL 20
Work Break down StructureProject Details
Conceptual plan/Overall
schedule
Project quantum
Project proceduresSchedule Requirements
Functional schedules
Process
Engineering
Ordering
Manufacturing
Construction
Project control &
TurnaroundProgress Reports
Project scheduling and control
Challenges in Project ManagementSept 11,2009
Engineers India Ltd – Delivering excellence through people
LEVEL 1
CORPORATE MANAGEMENT
LEVEL - II
FUNCTIONAL MANAGEMENT
LEVEL - III
JOB LEADER
OVERALL PROJECT SCHEDULE
MASTER NETWORK KEY CONSTRUCTION NETWORK
RESOURCE BASED SCHEDULE
• ENGINEERING• PROCUREMENT• CONTRACTING• CONSTRUCTION• TURNKEY WORK
INPUT / OUTPUT SCHEDULE
• DRAWING SCHEDULE• EQUIPMENT SCHEDULE• BULK MATERIAL SCHEDULE• CONSTRUCTION SCHEDULE
ACTION
CORPORATE REVIEW
DIVISION REVIEW
OPERATING LEVEL
REVIEW
ACTION
MONTHLY ACTIVITY
LIST HOLDUP & SLIPPAGE REPORT
MONTHLY ACTIVITY
LIST HOLDUP & SLIPPAGE REPORT
ACTIONCONSOLIDATED PROGRESS REPORT
CRITICAL LIST
Project Control System
Challenges in Project ManagementSept 11,2009
Engineers India Ltd – Delivering excellence through people
EIL 22
Work Break down StructureProject Details/Data Project quantum
PFR +/- 30%
DFR +/- 10%
Investment approval +/- 10 %
Project Cost Control and monitoring
Cost Status Reports
Project specific CriticalitiesTechnology/Licensor/details
Estimate Update Increasing accuracy of Estimates
Owners Committments
Purchase Orders
Contract Award
Project Cost Control
Challenges in Project ManagementSept 11,2009
Engineers India Ltd – Delivering excellence through people
SITE INFORMATIONIMPLEMENTIONSCOPE DEFINITIONPROCESS DESIGNBASIC / FRONT END ENGG..
BID EVALUATION & VENDOR / CONTRACTOR SELECTION
DETAIL ENGINEERINGCHANGE MANAGEMENTEQUIPMENT SELECTIONEQUIPMENT DELIVERIES
CONSTRUCTIONCOMMISSIONING
COST CONTROL SCHEDULE CONTROL
LEVEL OF OPPURTUNITY DURING
* * * * *
* * *
*
Value Engineering Chain
Challenges in Project ManagementSept 11,2009
Engineers India Ltd – Delivering excellence through people
Most Critical Step
Conduct Brainstorming Peer Reviews Project risk review meetings
Assign Risk to Team
Identify Risk Manger
EIL 24
Project Risk Identification
Challenges in Project ManagementSept 11,2009
Engineers India Ltd – Delivering excellence through people
Managing Risk
Improve Risk Mgmt
Standardization/ Formalization of Processes
Reviews/
OversightDedicated/
Experienced resources
Independent assurance processes to support Key Project decisions
Internal peer reviewInternal audit
Independent Project assurance
value assurance reviews
External reviews/feedbacks/Audits
Challenges in Project ManagementSept 11,2009
Engineers India Ltd – Delivering excellence through people
Identify Risk response Plan Reduction Transfer Share ( Not Preferable) Retain Avoidance
Respond Accordingly Avoidance – Develop mitigation plan Reduction – Develop mitigation Plan Transfer – Close Risk and Transfer Share – Develop mitigation Plan Retain - Develop Contingency Plan
EIL 26
Project Risk Response Plan
Challenges in Project ManagementSept 11,2009
Engineers India Ltd – Delivering excellence through people
Develop and finalize design basis, overall, unit by unit and discipline
by discipline
Develop and finalize Scope
Weighing of options vis-avis Value Engineering
Finalization of Implementation Philosophy
Ensuring Quality, Safety and Technical excellence
Protecting Overall Time and Cost
Vendors/Contractors/EPC/LSTD selection
Monitoring Performance of Vendors/Contractors/EPC/LSTD
selection
Change Management , Pre emptive mid course corrective actions
Integrated Complex into a techno commercial viable entity
Ensure Owner’s Satisfaction
11 ingredients for a Successful Recipe
Challenges in Project ManagementSept 11,2009
Engineers India Ltd – Delivering excellence through people
Unambiguous scope definition
Clear design basis
Sound execution strategy
Management of pre project activities
Emphasis on construction driven Engineering
Consistent and extended front end engineering
Staying with performers-vendors/contractors
Monitor, control and pre-empt actions
Manage changes
Manage resources particularly human resources
Key Contributors to Success
Challenges in Project ManagementSept 11,2009
Engineers India Ltd – Delivering excellence through people
29
Need of the HourNeed of the Hour
To Marry the advantages of To Marry the advantages of LSTK & EPCM for optimal LSTK & EPCM for optimal
CAPEX and Security of ScheduleCAPEX and Security of Schedule
RecommendationsRecommendations
Mid size units standard Mid size units standard alone type 400-600 Cralone type 400-600 Cr
LARGE UNITSLARGE UNITS700-1500 Cr700-1500 Cr
•Revamp Revamp •Energy Conservation Energy Conservation •Utilities & offsiteUtilities & offsiteLSTK Mode
(Example)•Hydrogen Plant•Sulfur Block•Treating Units•Selective Polymer units
EPCM ModeMaturing to OBE•To avail cost benefits along with secured schedule•To initiate early start of the Project (savings in schedule to line up LSTK
EPCM Mode•To facilitate better & smoother Project Interfaces•Difficult to define scope for LSTK
Eye to the Future-modes to adopt
Challenges in Project ManagementSept 11,2009
Engineers India Ltd – Delivering excellence through people
Conclusion
• Large projects increasing in Complexity and Project owners as well as Service Providers have to grapple with the issue of resources.
• Increased standardization /formulation of processes, coupled with a system of reviews and oversight can help to mitigate the problem
• Good Project definition is the key to avoiding time and cost over runs.
• Proper planning and appropriate Project controls will contribute significantly towards success
• Recognize the change of the times-collaborative approach will work well-has been amply demonstrated. A supportive Owner will motivate the consultant/contractor
• Essential to have PMC participation at all stages of project development and execution.
Challenges in Project ManagementSept 11,2009
Engineers India Ltd – Delivering excellence through people