champan coal corporation
TRANSCRIPT
Chapman Coal
Corporation
• Kemal Inawel• Marini• Pisqa Arisanti
Background on Chapman Coal Corporation
• On December 31, 1977 , The Chapman Coal Corporation was investigating the feasibility of 2 mutually exclusive Projects:1. Strip Mining2. Underground Mining• Gene Graham had been involved in the development of revenue and expense projections for the two projects.
SITUATION ANALYSIS
Strip Mining
Underground Mining
Leasehold Invesment 400,000 300,000Equipment 3,000,000 1,500,000Additional Working Capital Requirements
200,000 200,000
Total 3,600,000 2,000,000
Graham made the following projections of the investment cost for each operation
THE COST PROJECTIONS
• 10 year life may be expected on either of the two prospective investments• The equipment would be depreciated over the same life on straight- line
basis over the life.• The projected Salvage Value for operation
– Strip mining = $600,000– Underground mining = $150,000
• The recommended that the strip mining project be discounted at a 10% Rate, while the underground mining proposal be analyzed with a 20% criterion.
• However the company’s cost of capital had been computed to be 8%, so head of engineering David Hughes believe that this should be the discount rate used.
• The Risk free rates is currently 6%.• The engineering personnel estimated the standard deviation relating to the
salvage value of each project:– Strip mining = $ 300,000 – Underground mining = $ 135,000
PROBLEM ANALYSIS
• The two projects are mutually exclusive (only one may be taken, or neither)
• Graham would have to determine which project would deliver the most profit at present value
Years Annual expected Earning After Taxes
Standard deviation of Earning After Taxes
Strip Mining 1-4 400,000 340,0005-7 220,000 250,000
8-10 100,000 190,000Underground Mining
1-4 360,000 315,000
5-7 230,000 276,5008-10 130,000 236,000
EARNINGS AFTER TAX
EXHIBIT 1Chapman Coal Corporation
Management's Risk - Return ProfileCoefficient of Variation Certainty Equivalent Factor
0.5 0.950.6 0.930.7 0.910.8 0.880.9 0.851 0.82
1.1 0.781.2 0.741.3 0.701.4 0.641.5 0.581.6 0.521.7 0.431.8 0.331.9 0.15
0.4 0.5 0.6 0.7 0.8 0.9 1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 2.00.00
0.10
0.20
0.30
0.40
0.50
0.60
0.70
0.80
0.90
1.00
Certainty Equivalent Factor
Years
Annual expected Earning
after Taxes
Standard deviation of
Earning After Taxes
Coefficient of variation
Certainty Equivalent
FactorExpected Cash Flow
Strip Mining
1-4 400,000 340,000 0.85 0.865 346,000
5-7 220,000 250,000 1.14 0.760 167,200
8-10 100,000 190,000 1.90 0.150 15,000
Salvage Value( 10) 600,000 300,000 0.50 0.950 570,000
Underground mining
1-4 360,000 315,000 0.88 0.850 306,000
5-7 230,000 276,500 1.20 0.740 170,200
8-10 130,000 236,000 1.82 0.300 39,000
Salvage Value( 10) 150,000 135,000 0.90 0.850 127,500
• Coefficient of Variation = Standard deviation of Earning After Taxes : Annual expected Earning after Taxes
• Expected Cash Flow = Annual expected Earning after Taxes x Certainty Equivalent Factor
Method I: Certainty Equivalence
Strip MiningYear Expected Cash Flow PV Factor at 6% Present Value
1 346,000 0.943 326,415.092 346,000 0.890 307,938.773 346,000 0.840 290,508.274 346,000 0.792 274,064.415 167,200 0.747 124,941.576 167,200 0.705 117,869.407 167,200 0.665 111,197.558 15,000 0.627 9,411.199 15,000 0.592 8,878.48
10 585,000 0.558 326,660.94TOTAL NPV 1,897,885.67
By Certainty Equivalent Method
Underground MiningYear Expected Cash Flow PV Factor at 6% Present Value
1 306,000 0.943 288,679.252 306,000 0.890 272,338.913 306,000 0.840 256,923.504 306,000 0.792 242,380.665 170,200 0.747 127,183.346 170,200 0.705 119,984.287 170,200 0.665 113,192.728 39,000 0.627 24,469.089 39,000 0.592 23,084.04
10 166,500 0.558 92,972.73TOTAL NPV 1,561,208.52
By Certainty Equivalent Method
Years
Annual expected
Earning after Taxes
PV Factor 10% PV PV Factor 8% PV
Strip Mining
1 400,000 0.909 363,600 0.926 370,400
2 400,000 0.826 330,400 0.857 342,800
3 400,000 0.751 300,400 0.794 317,600
4 400,000 0.683 273,200 0.735 294,000
5 220,000 0.621 136,620 0.681 149,820
6 220,000 0.564 124,080 0.630 138,600
7 220,000 0.513 112,860 0.583 128,260
8 100,000 0.467 46,700 0.540 54,000
9 100,000 0.424 42,400 0.500 50,000
10 100,000 0.386 38,600 0.463 46,300
Salvage Value( 10) 600,000 0.386 231,600 0.463 277,800TOTAL NVP 2,000,460 TOTAL NVP 2,169,580
Method 2: Risk Adjusted
Years
Annual expected
Earning after Taxes
PV Factor 20% PV PV Factor
8% PV
Underground Mining
1 360,000 0.833 299,880 0.926 333,360
2 360,000 0.694 249,840 0.857 308,520
3 360,000 0.579 208,440 0.794 285,840
4 360,000 0.482 173,520 0.735 264,600
5 230,000 0.402 92,460 0.681 156,630
6 230,000 0.335 77,050 0.630 144,900
7 230,000 0.279 64,170 0.583 134,090
8 130,000 0.233 30,290 0.540 70,200
9 130,000 0.194 25,220 0.500 65,000
10 130,000 0.162 21,060 0.463 60,190
Salvage Value( 10) 150,000 0.162 24,300 0.463 69,450TOTAL NVP 1,266,230 TOTAL NVP 1,892,780
By Risk Adjusted Method
THE DECISION
• According to the calculation result, all the results are negative regardless of the method and discount rate used (the investment cost > NVP)
• Therefore we decided NOT to take either alternative, as they both will result in a net loss
Investment Cost
Present Value By Certainty Equivalent
Method (6%)
Profit / (Deficit)
PV By Risk Adjusted Method
(10%&20%)
Profit / (Deficit)
PV By Risk Adjusted Method
(8%)
Profit / (Deficit)
Strip Mining 3,600,000 1,897,885.67 -1,702,114.33 2,000,460 -1,599,540 2,169,580 -1,430,420Underground Mining
2,000,000 1,561,208.52 -438,791.48 1,266,230 -733,770 1,892,780 -107,220
THE END
Thank You