Project Area Map For more information, contact: Sarah Kugler, NDOR Public Involvement // [email protected] // 402-479-4871 Doug Hoevet, District Engineer // [email protected] // 308-436-6587 This project would provide much needed roadway and bridge improvements to 9.62 miles of Interstate 80 (I-80) near Chappell, NE. The planned improvements include reconstructing the interstate pavement, replacing guardrails along the interstate, reconstructing portions of the Chappell interchange ramps, and bridgework. These improvements are essential to the efficient and safe travel of the project area, which has an average daily traffic count of 7,745, of which 60% are trucks. RD 165 RD 169 RD 171 RD 173 RD 177 RD 179 RD 181 RD 175 RD 183 30 80 385 27 RD 10 RD 10 RD 10 RD 10 RD 14 RD 16 RD 12 RD 8 80 80 385 385 30 30 27 Project Area Bridgework Mile Marker 0 1 (miles) LEGEND CHAPPELL 94 93 92 91 90 89 88 87 86 85 84 95 25A The bridges over US-385 and Union Pacific railroad will be replaced Pavement throughout the project area is in need of improvement NEBRASKA DEPARTMENT OF ROADS CHAPPELL – N-27 NH-80-2(103); C.N. 51519 Public Information Open House Meeting Thursday, March 30, 2017; 4:30 - 6:30 p.m. MST Creek Valley High School Gym 3rd St & Washington Ave, Chappell, NE

Upload: others

Post on 30-Sep-2020

20 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CHAPPELL – N-27dot.nebraska.gov/media/7917/public-meeting-handout.pdf · 2017. 4. 6. · RD 19 RD 15 RD 181 RD 183 30 80 385 2 RD 10 RD 10 RD 10 RD 10 RD 1 RD RD 1 RD 12 RD 8 80

Project Area Map

For more information, contact:Sarah Kugler, NDOR Public Involvement // [email protected] // 402-479-4871Doug Hoevet, District Engineer // [email protected] // 308-436-6587

This project would provide much needed roadway and bridge improvements to 9.62 miles of Interstate 80 (I-80) near Chappell, NE.

• The planned improvements include reconstructing the interstate pavement, replacing guardrails along the interstate, reconstructing portions of the Chappell interchange ramps, and bridgework.

• These improvements are essential to the efficient and safe travel of the project area, which has an average daily traffic count of 7,745, of which 60% are trucks.

RD 6

RD 1

65

RD 1

67

RD 1

69

RD 1

71

RD 1

73

RD 1

77

RD 1

79

RD 1

81

RD 1

75

RD 1

83

3080

385

27

RD 10 RD 10RD 10 RD 10

RD 14

RD 6

RD 16

RD 12

RD 8

80

80

385

385

30

30

27

27

Project Area

Bridgework

Mile Marker 0 1 (miles)

LEGE

ND

CHAPPELL

9493

9291

90

8988

87

86

85

84

95

25A

The bridges over US-385 and Union Pacific railroad will be replaced

Pavement throughout the project area is in need of improvement

NEBRASKA DEPARTMENT OF ROADS

CHAPPELL – N-27NH-80-2(103); C.N. 51519 Public Information Open House Meeting

Thursday, March 30, 2017; 4:30 - 6:30 p.m. MSTCreek Valley High School Gym

3rd St & Washington Ave, Chappell, NE

Page 2: CHAPPELL – N-27dot.nebraska.gov/media/7917/public-meeting-handout.pdf · 2017. 4. 6. · RD 19 RD 15 RD 181 RD 183 30 80 385 2 RD 10 RD 10 RD 10 RD 10 RD 1 RD RD 1 RD 12 RD 8 80

CHAPPELL – N-27 // NH-80-2(103); C.N. 51519

Project LocationThe proposed project would involve rebuilding approximately 9.62 miles of Interstate 80 (I-80) in Deuel County. The project would start at mile marker (MM) 84.63, just west of the Chappell Interchange 85 and extend east to MM 94.25, just west of the Nebraska Highway 27 (N-27) Interchange 95. The project would include reconstruction of the ramps at the Chappell Interchange, as well as repairing and widening or replacing bridges and resurfacing the roadway along portions of Nebraska Link 25A (L-25A). The L-25A portion of the proposed project would begin at MM 0.09 and extend 0.21 miles north.

Purpose and NeedThe purpose of the proposed project is to preserve the I-80 and L-25A transportation assets, improve the reliability of the transportation system, and perpetuate the mobility of the traveling public. The need for these proposed projects is based on the condition of the existing roadways, bridges, and ramps, and recent inspections showing that rehabilitation would be required.

Scope of WorkProposed improvements on the I-80 portion of the project would include removing the existing pavement and foundation course on the driving lanes and shoulders and rebuilding with doweled concrete pavement on a foundation course. Culverts would be extended. Guardrail would be removed and replaced. Bridges would be repaired and widened or replaced. The ramps at the Chappell Interchange would be reconstructed and street lights at the interchange would be replaced. The improvements on L-25A would consist of repairing the concrete pavement on the mainline, resurfacing the roadway with asphalt, overlaying the bridge deck with a thin epoxy coat, and sealing the bridge rails and columns. The remaining pavement at the previously closed, westbound Chappell Truck Parking Area, located at MM 87.67, will be removed and the site re-graded and seeded. Additional work would include removing the existing crossovers immediately west and east of the project.

Traffic Volumes

Interstate 80 from MM 84.63 - 94.25

Year 2018 2038

Vehicles Per Day (ADT) 7,745 8,840

% Heavy Trucks 60% 60%

Construction ScheduleConstruction is tentatively scheduled to begin as early as summer of 2018 and could be complete by fall of 2020.

Information regarding the proposed project will be made available on the NDOR website at http://roads.nebraska.gov/projects/future-projects/ by clicking on the “Chappell – N-27” link.

Accommodation of TrafficThe improvements on I-80 would be constructed under traffic. I-80 would remain open at all times with traffic shifted head to head. Ramp closures at the Chappell Interchange are proposed. The eastbound ramps for the Chappell Interchange would be closed during eastbound mainline I-80 construction to accommodate reconstruction of eastbound mainline and ramps (westbound ramps would remain open during this time). The westbound ramps for the Chappell Interchange would be closed during westbound mainline I-80 construction to accommodate reconstruction of westbound mainline and westbound ramps (eastbound ramps would remain open during this time). The bridge over I-80 (S080 08522) at the Chappell Interchange (L-25A over I-80) would remain open but would be reduced to one open lane at times to accommodate construction on the bridge.

2016 2018 20202017 2019

Preliminary Design

Design andPublic Input

Construct Eastbound Improvements

Construct Westbound Improvements

Final Designand Permitting

Anticipated Project Timeline

Right-of-WayThe proposed project would require the acquisition of additional property rights for temporary construction easements. Access to adjacent properties would be maintained during construction but may be limited at times due to phasing requirements.

Potential ImpactsMinimal wetland impacts are anticipated.

Estimated CostThe cost of the proposed project is approximately $46.1 million and would derive from federal and state funding sources. The proposed expedited interchange replacement approach at the Chappell interchange could reduce construction costs by approximately $1.6 million by eliminating the need for temporary ramps, shorten the construction time frame by approximately 3 months, and reduce traffic phasing complexities.

80

80

30

27

3017F

CHAPPELL

LODGEPOLE

RD 1

65

27

EXIT76

EXIT95

Alternate Route11.8 miles14 minutes

I-80 Route10.9 miles13 minutes

Alternate Route11.6 miles16 minutes

I-80 Route9.9 miles

11 minutes

Alternate Routes to and from Chappellwith approximate travel distance and time

25A

385

The project team is seeking public input on a proposed expedited I-80 interchange replacement approach at the Chappell interchange.

About the Proposed Approach• Half of the Chappell interchange

would remain open during construction

• The bridge on L-25A crossing over I-80 would remain open

• I-80 would remain open throughout construction and adequate signage would be provided for drivers seeking to detour to Chappell

• Alternative routes to Chappell from I-80 adds up to 1.5 miles and about 5 minutes of additional travel

Page 3: CHAPPELL – N-27dot.nebraska.gov/media/7917/public-meeting-handout.pdf · 2017. 4. 6. · RD 19 RD 15 RD 181 RD 183 30 80 385 2 RD 10 RD 10 RD 10 RD 10 RD 1 RD RD 1 RD 12 RD 8 80

The improvements on I-80 would be constructed under traffic, with two-way traffic maintained at all times.• The eastbound ramps for the Chappell Interchange would be closed during eastbound mainline I-80

construction to accommodate reconstruction of eastbound mainline and ramps (westbound ramps would remain open during this time).

• The westbound ramps for the Chappell Interchange would be closed during westbound mainline I-80 construction to accommodate reconstruction of westbound mainline and ramps (eastbound ramps would remain open during this time).

• The bridge over I-80 (S080 08522) at the Chappell Interchange (L-25A over I-80) would remain open but would be reduced to one open lane at times to accommodate construction on the bridge.

It is anticipated that eastbound I-80 improvements would be constructed in 2019 and westbound I-80 improvements in 2020.

RD 1

65

80 25A

385

80

L-25A ramps closedOpen lanes for two-way traffic

Open as usual

LEGE

ND

Chappell Interchange Access During Eastbound ConstructionApproximately May 1, 2019 - November 1, 2019

CHAPPELL – N-27 // NH-80-2(103); C.N. 51519

RD 1

65

80 25A

385

80

L-25A ramps closedOpen lanes for two-way traffic

Open as usual

LEGE

ND

Chappell Interchange Access During Westbound ConstructionApproximately May 1, 2020 - November 1, 2020