chapter 1 plant planning and power demand.pdf

Upload: -

Post on 03-Apr-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 Chapter 1 PLANT PLANNING AND POWER DEMAND.pdf

    1/30

    07/03/2013

    1

    BEF 44903 Chapter 1

    BEF 44903 Industrial Power Systems Chapter 1

    Outlines

    1.1 Plant Distribution Systems

    1.2 Voltage and Frequency Considerations

    1.3 Types of Plant Distribution Networks

    2

    1.4 Power Demand and Load Estimation

    1.5 Transformer Sizing

  • 7/28/2019 Chapter 1 PLANT PLANNING AND POWER DEMAND.pdf

    2/30

    07/03/2013

    2

    BEF 44903 Industrial Power Systems Chapter 1

    1.1 Overview of Electric Power Systems

    Generation System

    13.8 kV 15.6 kV

    Distribution System

    11 kV 66 kV

    Transmission System

    132 kV 500 kV

    3

    BEF 44903 Industrial Power Systems Chapter 1

    1.1 Example of Plant Distribution System

    4

    PanelboardFeeding

    240/415V

    Harmonic Loads

  • 7/28/2019 Chapter 1 PLANT PLANNING AND POWER DEMAND.pdf

    3/30

    07/03/2013

    3

    BEF 44903 Industrial Power Systems Chapter 1

    1.1 Planning Distribution Systems

    A distribution system deals with the distribution

    ofelectrical energy to its specific loads.

    The main purposes of planning are:

    To make the system economical (cost effective).

    To minimise power losses and maintain regulation

    within permissible limits.

    Load survey and load forecasting of the area are

    5

    necessary.

    BEF 44903 Industrial Power Systems Chapter 1

    1.1 Planning Distribution Systems

    Load survey of a particular area is carried out to find out

    the present load requirement as well as the expected

    w v y . w

    basic data should be collected for starting this work:

    9A detailed map of the area showing important features.

    9 The existing numberof houses, population and new construction

    anticipated in the area.

    6

    , , ,

    etc.

    9 The type of industry and numberof industries possible in the

    area.

    9 Development programmes implemented in the area.

  • 7/28/2019 Chapter 1 PLANT PLANNING AND POWER DEMAND.pdf

    4/30

    07/03/2013

    4

    BEF 44903 Industrial Power Systems Chapter 1

    1.1 Planning Distribution Systems

    For the purpose offorecasting load, the prospective

    consumers may be categorized as under:

    . omest c consumers, .e. res ent a ouses.

    2. Commercial consumers, i.e. shops, schools, hospitals, hotels,

    and other commercial establishments.

    3. Industrial consumers:

    a. Small industries (up to 20 kW)

    b. Medium industries (up to 100 kW)

    c. Large industries (above 100 kW)

    7

    d. Municipal consumers (i.e. street lighting, water works, parks, etc.)e. Agricultural consumers

    f. Mining industries

    BEF 44903 Industrial Power Systems Chapter 1

    1.1 Layout of Distribution Systems

    Sub-transmission Line

    132kV/66kV 66kV/11kV

    11kV Feeder

    11kV/415V

    3 PhaseConsumers

    (415V)

    Single Phase

    Secondary

    Substation

    Distribution

    SubstationPrimary

    Substation

    (66kV or 33kV)

    8

    ee er

    Industrial

    Consumer

    (240V)

  • 7/28/2019 Chapter 1 PLANT PLANNING AND POWER DEMAND.pdf

    5/30

    07/03/2013

    5

    BEF 44903 Industrial Power Systems Chapter 1

    1.1 Layout of Distribution Systems

    The high voltage from transmission line (132 kV) is step-down at the Primary Substation to 66 kV or 33 kV.

    ,carried through sub-transmission lines to different loadcentres. The length of a sub-transmission line is about 50km and they carry about 50 MW of power.

    It has been found that sending power through sub-transmission lines at 33 kV or 66 kV is economical interms oflosses (i.e. I2R) and the capital cost (i.e. cost of

    9

    conductor, insulators and supports). Most domestic, commercial and small-scale industrial

    consumers receive power at low voltage, i.e. 240V or415V. Large-scale consumers having load in excess of100 kW buy bulk power at 11 kV and above.

    BEF 44903 Industrial Power Systems Chapter 1

    1.1 Planning for Connection

    Supplies at Low Voltages of 240V and 415V

    } Maximum power requirements in kVA

    } Types and number of equipment and its

    corresponding connected capacity in kVA

    } Shunt connected reactors and capacitors in kVAr} For single-phase 240V motors with rating of greater

    than 6kVA and/or three-phase 415V motors with

    (i) Rating in HP or KVA, (ii) Types of control equipment, (iii)

    Methods of starting and starting current, (iv) Frequency of

    starting (number/hour), and (v) Rated power factor;

    } Voltage sensitive loads (indicating sensitivity)

    10

  • 7/28/2019 Chapter 1 PLANT PLANNING AND POWER DEMAND.pdf

    6/30

    07/03/2013

    6

    BEF 44903 Industrial Power Systems Chapter 1

    1.1 Planning for Connection

    Supplies at 275kV, 132kV, 33kV, 22 kV, 11kV

    and 6.6kV

    } Forall typesall types of loads:

    Maximum Active Power consumption in kW;

    Maximum Reactive Power consumption in kVAR.

    } Formotor loadsmotor loads:

    Types of control equipment;

    Methods of startin

    Magnitude and duration of the starting current;

    Frequency of starting (number/hour);

    Under voltage setting and time;

    Negative phase sequence protection;

    Sub-transient and/or locked rotor reactance of the motor.

    11

    BEF 44903 Industrial Power Systems Chapter 1

    1.1 Planning for Connection

    } Fornonlinear loadsnonlinear loads with harmonic current injections:

    Harmonic current spectrum including harmonic number and

    .

    } Forfluctuating loadsfluctuating loads:

    The rates of change of Active Power and Reactive Power

    consumption in kW/minute and kVAR/minute ,respectively,both increasing and decreasing;

    The shortest repetitive time interval between fluctuations for

    Active Power and Reactive Power in minutes; and

    The magnitude of the largest step changes in Active Power

    and Reactive Power in kW and kVAR respectively, both

    increasing and decreasing.

    12

  • 7/28/2019 Chapter 1 PLANT PLANNING AND POWER DEMAND.pdf

    7/30

    07/03/2013

    7

    BEF 44903 Industrial Power Systems Chapter 1

    1.1 Planning for Connection

    } Forvoltage sensitive loadsvoltage sensitive loads:

    steady-state voltage tolerance limits of the equipment in

    intrinsic immunity limits to short duration voltage variation;

    transient voltage tolerance limits of the equipment in

    percentage of the nominal voltage and the corresponding

    duration;

    harmonic current emission limit for equipment.

    } ForShunt Connected Reactors and CapacitorsShunt Connected Reactors and Capacitors:

    configuration and sizes of individual banks;

    types of switching and control equipment; and

    types of harmonic filtering reactors.

    13

    BEF 44903 Industrial Power Systems Chapter 1

    1.2 Voltage and Frequency Considerations

    Voltage Criteria

    } Steady-State Voltage Fluctuation (Normal Condition):

    -

    Voltage level % variation

    415V and 240V -10% & +5%

    6.6kV, 11 kV, 22kV,33kV +/- 5%132kV and 275kV -5% & +10

    14

    Voltage level % variation

    415V and 240V +/- 10%

    6.6kV, 11 kV, 22kV,33kV +10 & -10%

    132kV and 275kV +/- 10%

  • 7/28/2019 Chapter 1 PLANT PLANNING AND POWER DEMAND.pdf

    8/30

    07/03/2013

    8

    BEF 44903 Industrial Power Systems Chapter 1

    1.2 Supply Voltage Options

    Low Voltage:

    } Single-phase, two-wire, 240V, up to 12 kVA maximum

    demand

    } Three-phase, four-wire, 415V, up to 45 kVA maximum

    demand

    } Three-phase, four-wire, C.T. metered, 415V, up to

    1,000 kVA maximum demand

    15

    BEF 44903 Industrial Power Systems Chapter 1

    1.2 Supply Voltage Options

    Medium and High Voltages:

    } Three-phase, three-wire and 11 kV for load of 1,000

    kVA maximum demand and above

    } Three-phase, three-wire, 22kV or 33kV for load of

    5,000 kVA maximum demand and above} Three-phase, three-wire, 66kV, 132kV and 275kV for

    exceptionally large load of above 25 MVA maximum

    demand

    16

  • 7/28/2019 Chapter 1 PLANT PLANNING AND POWER DEMAND.pdf

    9/30

    07/03/2013

    9

    BEF 44903 Industrial Power Systems Chapter 1

    1.2 Voltage and Frequency Considerations

    Frequency Criteria

    } The supply frequency is 50 Hz 1%

    17

    BEF 44903 Industrial Power Systems Chapter 1

    1.3 Classification of Distribution Systems

    The distribution systems may be classified in

    the following ways:. ccor ng o na ure o cons ruc on

    a. Overhead distribution system (cheaper)

    b. Underground distribution system (in crowded area)

    2. According to nature of currenta. DC distribution system

    b. AC distribution system

    3. According to number of wires

    - - - -

    18

    , , ,

    3-phase 3-wire AC system, 3-phase 4-wire AC system

    4. According to the scheme of connections

    (a) Radial system

    (b) Ring system

    (c) Inter-connected system

  • 7/28/2019 Chapter 1 PLANT PLANNING AND POWER DEMAND.pdf

    10/30

    07/03/2013

    10

    BEF 44903 Industrial Power Systems Chapter 1

    1.3 Primary Distribution Lines (Feeders)

    The 33/11 kV secondary substation is established where

    the load requirement is approximately 5 MVA. Since

    y y u y

    load of1-2 MVA, the number of primary distribution lines

    emanating from a 33/11 kV secondary substation is

    about 4.

    When the load requirement increases and crosses about

    8 MVA, the losses in the 33 kV sub-transmission line

    19

    . , -transmission line. The number of primary distribution

    lines emanating from a 66/11 kV secondary substation is

    six to ten.

    BEF 44903 Industrial Power Systems Chapter 1

    1.3 Primary Distribution Lines (Feeders)

    There are 3 different ways in which the primary

    distribution lines can be laid:

    1. The radial primary circuit

    2. The loop primary circuit

    3. The ring main system (or primary network)

    20

  • 7/28/2019 Chapter 1 PLANT PLANNING AND POWER DEMAND.pdf

    11/30

    07/03/2013

    11

    BEF 44903 Industrial Power Systems Chapter 1

    1.3 Primary Distribution Lines (Feeders)

    Radial Primary Circuits

    When each circuit coming out of a substation is separate

    from the other circuits and has no inter-connection with

    any other circuit, it is called a radial circuit.

    Factory having load

    of 1 MW at 11 kV

    Circuit 1 for Factory

    Circuit 2 feeding Substation in the city

    21

    Secondary

    Substation

    Circuit 3 for Rural Areas

    BEF 44903 Industrial Power Systems Chapter 1

    1.3 Primary Distribution Lines (Feeders)

    Advantages of Radial Feeders:

    i. A heavy load very near the secondary substation.

    . so ate oa s.

    iii. An area of low load density such as a village.

    Limitations of Radial Feeders:

    i. When the load demand on the radial feeder increases, the

    length of the feeder has to be extended. This results in a greater

    -

    22

    to reach a value below the permissible limit.

    ii. When a fault occurs at any point along the length of the feeder,

    supply to all the consumers beyond this point towards the tail-

    end gets interrupted.

  • 7/28/2019 Chapter 1 PLANT PLANNING AND POWER DEMAND.pdf

    12/30

    07/03/2013

    12

    BEF 44903 Industrial Power Systems Chapter 1

    1.3 Primary Distribution Lines (Feeders)

    Loop Primary Circuits

    To overcome the limitations of the radial feeders, the

    loop primary circuit is taken to use.

    Secondary

    Substation

    Distribution Distribution

    CB4 CB5

    11 kV 11 kV

    23

    Distribution

    Substation 1

    CB1CB2

    CB3 CB6

    A

    BEF 44903 Industrial Power Systems Chapter 1

    1.3 Primary Distribution Lines (Feeders)

    Two 11 kV feeders emanate from the secondary

    substation.

    In this system, every distribution substation receives

    supply from two sides.

    In case of fault, say at point A, the circuit breaker 1 atdistribution substation 1 and circuit breaker 6 at

    distribution substation 3 will open, thus isolating the

    faulty section. The supply to the substation 1 and 3 is still

    24

    uninterrupted and continues to be received from another

    side.

    This system is generally used in towns and cities.

  • 7/28/2019 Chapter 1 PLANT PLANNING AND POWER DEMAND.pdf

    13/30

    07/03/2013

    13

    BEF 44903 Industrial Power Systems Chapter 1

    1.3 Primary Distribution Lines (Feeders)

    The reliability of supply in this system has improved in

    comparison with that in the radial system as it has an

    v u y, .

    However, it must be realized that the source of supply for

    the whole loop system is a single secondary substation.

    If a fault occur in the secondary substation causing a

    failure of the 11 kV supply source, the whole of the

    system will suffer power interruption.

    25

    BEF 44903 Industrial Power Systems Chapter 1

    1.3 Primary Distribution Lines (Feeders)

    Ring Main or Network System

    A more reliable s stem is the rin main s stem.

    SecondarySubstation A

    Distribution Distribution

    CB4 CB5

    11 kV 11 kV

    SecondarySubstation B

    CB7 CB8 CB9 CB10

    26

    Distribution

    Substation 1

    CB1CB2

    CB3 CB6

  • 7/28/2019 Chapter 1 PLANT PLANNING AND POWER DEMAND.pdf

    14/30

    07/03/2013

    14

    BEF 44903 Industrial Power Systems Chapter 1

    1.3 Primary Distribution Lines (Feeders)

    In the ring main system, there are two different sources

    of supply which are indicated as secondary substationA

    .

    The ring system has the added advantage from loop

    system is that should one of the sources of supply fail,

    say A, the whole system continues to get supply from the

    other source B.

    The ring main system is by far the most reliable for

    27

    continuity of supply. It gives a better voltage regulationand less feeder losses.

    Circuit breakers are used instead of fuses for protecting

    the transformerin ring main system due to heavier loads.

    BEF 44903 Industrial Power Systems Chapter 1

    1.3 Secondary Distribution Lines (Distributors)

    Distribution substations are a link between

    feeders and distributors.

    The standard voltage transformation at a

    distribution substation is 11 kV/415V. The

    declared consumer volta e as er Mala sian

    Distribution

    Substations11 kV Feeders 415 V Distributors

    28

    Nasional Grid is 415 V between phases and 240

    V between phase and neutral with a permissible

    voltage variation of5%.

  • 7/28/2019 Chapter 1 PLANT PLANNING AND POWER DEMAND.pdf

    15/30

    07/03/2013

    15

    BEF 44903 Industrial Power Systems Chapter 1

    1.3 Secondary Distribution Lines (Distributors)

    A consumer at the near-end of the distribution

    substation may have a voltage as high as 436 V

    (3-phase) and 252 V (single-phase) during light

    load hours whereas a consumer at the far-end

    may have a voltage as low as 395 kV (3-phase)

    and 228 V (single-phase) at peak load hours.

    The circuits for the secondary distribution

    29

    system are essentially the same as those forprimary distribution except that they are on a

    smaller scale.

    BEF 44903 Industrial Power Systems Chapter 1

    1.3 Secondary Distribution Lines (Distributors)

    When power is supplied to the consumers

    through the secondary distribution system, one

    of the following arrangements is used:

    1. Radial system

    2. Looped system3. Network system (Banked secondary system)

    30

  • 7/28/2019 Chapter 1 PLANT PLANNING AND POWER DEMAND.pdf

    16/30

    07/03/2013

    16

    BEF 44903 Industrial Power Systems Chapter 1

    1.3 Secondary Distribution Lines (Distributors)

    Radial System

    In this system, the LV distribution lines radiate out from

    the distribution substation.

    11 kV Line220 kVA 11

    kV/415V

    LV CBRadial Line 1

    Radial Line 2

    Switch-cum

    Fuse Units

    31

    n s sys em, e supp y s rom a s n g e ee er.A fault in the feeder will cause the interruption of supply

    to all consumers. Circuit breakerand switch-cum fuse

    units are used for protection purpose.

    BEF 44903 Industrial Power Systems Chapter 1

    1.3 Expanded Radial Scheme

    32

  • 7/28/2019 Chapter 1 PLANT PLANNING AND POWER DEMAND.pdf

    17/30

    07/03/2013

    17

    BEF 44903 Industrial Power Systems Chapter 1

    1.3 Secondary Distribution Lines (Distributors)

    Looped System

    In this case, the reliability of supply is better than in the

    radial system. In the case of fault on one line, the load

    can be fed from the other by connecting switch S.

    11 kV Line220 kVA 11

    kV/415V

    CB

    S

    415/240 V

    33

    However, a fault in the 11 kV feeder will cause the

    interruption of supply to all consumers. Circuit breaker

    and the fuse unit provide a protection for the transformer

    and line respectively.

    415/240 V

    BEF 44903 Industrial Power Systems Chapter 1

    Primary Selective Scheme

    34

  • 7/28/2019 Chapter 1 PLANT PLANNING AND POWER DEMAND.pdf

    18/30

    07/03/2013

    18

    BEF 44903 Industrial Power Systems Chapter 1

    1.3 Secondary Distribution Lines (Distributors)

    Banked Secondary System

    When radial secondary circuits are supplied by a single

    transformer, high starting currents of motors may cause

    objectionable voltage drops. One of the most effective

    and economical means of controlling such a voltage drop

    is the banking of distribution transformers.

    11 kV Primary Distribution Line

    35

    415/240 V Secondary Distribution Line

    T1 T2 T3 Fuse

    BEF 44903 Industrial Power Systems Chapter 1

    1.3 Secondary Distribution Lines (Distributors)

    Transformers are said to be banked when two or more

    supplied from the same primary circuit are paralleled to

    y .

    By this arrangement more than one path is providedover which high currents can flow. This results in

    lowering the extent to which the voltage fluctuates on

    the line.

    36

    Further advantages of this system:i. More reliable, have alternative supply from other transformer.

    ii. Better load distribution on each transformer.

    iii. The voltage drop in the system is reduced.

  • 7/28/2019 Chapter 1 PLANT PLANNING AND POWER DEMAND.pdf

    19/30

    07/03/2013

    19

    BEF 44903 Industrial Power Systems Chapter 1

    1.3 Secondary Distribution Lines (Distributors)

    This system is mostly used in areas oflow load

    densities, where a multiple primary and secondary

    w u .

    If a fault occurs within one of the transformers, it will be

    automatically disconnected from the line by blowing the

    two secondary line fuses and the primary transformer

    fuse without interrupting service to any consumer.

    37

    BEF 44903 Industrial Power Systems Chapter 1

    1.3 Secondary Selective Scheme

    38

  • 7/28/2019 Chapter 1 PLANT PLANNING AND POWER DEMAND.pdf

    20/30

    07/03/2013

    20

    BEF 44903 Industrial Power Systems Chapter 1

    1.3 Sparing Transformer Scheme

    39

    BEF 44903 Industrial Power Systems Chapter 1

    1.4 Load Data

    Typical range of Industrial Loads:

    } Light Industry 50 kVA to 7000 kVA

    } Heavy Industry 1,000 kVA to 200,000 kVA

    Typical Industrial Loads:

    } HVAC

    } Process equipment, pumps, compressors and fans

    } Industrial services such as boiler, water treatment

    } Workshop and laboratory equipment

    } Motor control centre

    40

  • 7/28/2019 Chapter 1 PLANT PLANNING AND POWER DEMAND.pdf

    21/30

    07/03/2013

    21

    BEF 44903 Industrial Power Systems Chapter 1

    1.4 Initial Maximum Demand Estimation

    2 methods to estimate the maximum power

    demand in feasibility/ conceptual design stage:

    } VA/m2 or W/ ft2 This is normally apply to commercial

    building where the typical loads are lighting, general

    power, and HVAC. Example: 50 100 VA/m2 for non-

    retail buildings, 60 150 VA/m2 for retail buildings.

    0.9 W/ft2 for lighting and 4.7 W/ft2 for Air Condition.

    } Maximum demand of a similar buildin / industr

    Applicable for residential, commercial, and industrialbuildings. Example: Plant A having maximum demand

    of 2 MVA then this figure can be used for a plant of

    similar capacity.

    41

    BEF 44903 Industrial Power Systems Chapter 1

    1.4 Detailed Load Estimation

    Comprehensive load estimate based on actual

    load information.

    Can be calculated either in kVA or amperes. If

    the output is given in kW, the kVA can be

    obtained using following formula:

    Future load should be considered as iven in

    )( = PFkWkVA

    spare circuits for future use.

    42

  • 7/28/2019 Chapter 1 PLANT PLANNING AND POWER DEMAND.pdf

    22/30

    07/03/2013

    22

    BEF 44903 Industrial Power Systems Chapter 1

    1.4 Diversity Factor (DF)

    For better load estimation, a proper diversity

    factor should be considered as not all

    equipment/ load operate simultaneously.

    Definition of diversity factor:

    Typical diversity factor values:

    LoadConnectedDemandMax.DF =

    Lighting load 100%

    General purpose power circuit 40% - 50%

    Main switchboard 80% - 90%

    Intermittent duty loads 50%

    43

    BEF 44903 Industrial Power Systems Chapter 1

    1.4 Example: Max. Loading for MCC (SB)

    Load

    description

    3

    /

    1

    Duty

    N or

    S

    Motor

    rating

    (kW)

    Ope-

    rating

    motor

    power

    (kW)

    PF x

    = K

    Motor

    input

    power

    Heater 3

    load

    (kVA)

    1

    load

    R

    phase

    (kVA)

    1

    load

    Y

    phase

    (kVA)

    1

    load

    B

    phase

    (kVA)

    Cooling

    tower 1 fan3 N 15 12 0.7 17.1 17.1

    Cooling

    tower 2 fan3 S 15 12 0.7 17.1 -

    Heater 3 N 5 - - - 5 5

    Fan coil 1 N 1.5 1.3 0.6 2.2 2.2

    Water pump 3 N 11 9 0.68 13.2 13.2

    Extract fan 1 N 1 0.8 0.6 1.3 1.3

    Compressor 1 N 1.5 1 0.6 1.6 1.6

    Future pump 3 N 5.5 4 0.6 6.7 6.7

    Total l oad 42.0 2.2 1.3 1.6

    44

    Total load on the MCC = 47.1 kVA

  • 7/28/2019 Chapter 1 PLANT PLANNING AND POWER DEMAND.pdf

    23/30

    07/03/2013

    23

    BEF 44903 Industrial Power Systems Chapter 1

    1.4 Example: Max. Loading for LV Switchboard

    Load

    description

    Du ty (N/ S) Connec ted

    (kW)

    Operating

    load (kW)

    K kVA

    DB 1 - - - - 30

    DB 2 - - - - 78

    MCC 1 - - - - 47.1

    MCC 2 - - - - 50

    Packaging

    machine- 37 31 0.7 44.3

    CO2compressor

    N 75 68 0.765 88.9

    ater pumpN 30 25 0.68 36.8

    Water pump 2 S 30 25 0.68 -

    Welder N 18 - 0.5 36

    Future 50

    45

    Total load on LV Switchboard = 461.1 kVA

    BEF 44903 Industrial Power Systems Chapter 1

    1.4 Old Supply Schemes for various M.D

    46

  • 7/28/2019 Chapter 1 PLANT PLANNING AND POWER DEMAND.pdf

    24/30

    07/03/2013

    24

    BEF 44903 Industrial Power Systems Chapter 1

    1.4 New Supply Schemes for various M.D

    47

    BEF 44903 Industrial Power Systems Chapter 1

    1.5 Common Connection for Transformer

    48

  • 7/28/2019 Chapter 1 PLANT PLANNING AND POWER DEMAND.pdf

    25/30

    07/03/2013

    25

    BEF 44903 Industrial Power Systems Chapter 1

    1.5 Why Delta Grounded Star

    Delta at pr imaryDelta at pr imary

    } Free of 3rd harmonics of the magnetizing currents and

    any possible homopolar current are free to circulate

    through the sides of the delta, without flowing into the

    network; thus, the magnetic fluxes remain sinusoidal

    at the secondary.

    } in case of unbalanced loads at the secondary

    winding, the reaction current absorbed by the primary

    flows only through the corresponding winding (asshown in the figure) without affecting the other two.

    49

    BEF 44903 Industrial Power Systems Chapter 1

    1.5 Why Delta Grounded Star

    GroundedGrounded StarStar atat secondarysecondary

    } To make line and phase voltages easily available.

    } For safety reasons, since, in the event of a fault

    between the MV and LV sides, the voltage at the

    secondary remains close to the phase value, thusguaranteeing higher safety for people and maintaining

    the insulation.

    50

  • 7/28/2019 Chapter 1 PLANT PLANNING AND POWER DEMAND.pdf

    26/30

    07/03/2013

    26

    BEF 44903 Industrial Power Systems Chapter 1

    1.5 Basic Installation of Industrial Plant

    51

    BEF 44903 Industrial Power Systems Chapter 1

    1.5 Methods of Transformer Installation

    MethodMethod 11 Substation with a single transformer

    In the case where theprotection device alsocarries out switching and

    isolation functions, aninterlock must be providedwhich allows access to thetransformer only when thepower supply line of the

    52

    isolated.

    Installation of the SMVswitching and isolationdevice positionedimmediately to the supplyside of the transformer.

  • 7/28/2019 Chapter 1 PLANT PLANNING AND POWER DEMAND.pdf

    27/30

    07/03/2013

    27

    BEF 44903 Industrial Power Systems Chapter 1

    1.5 Methods of Transformer Installation

    MethodMethod 22 Substation with two transformers

    with one as a spare for the other

    The circuit-breakers on theLV side must be connectedwith an I interlock whosefunction is to prevent thetransformers from operatingin parallel.

    Apart from the switching andisolation device on the

    53

    ncom ng ne GMV , sadvisable to provide aswitching, isolation andprotection device on theindividual MV risers of thetwo transformers (IMV1 andIMV2) as well.

    BEF 44903 Industrial Power Systems Chapter 1

    1.5 Methods of Transformer Installation

    MethodMethod 33 Substation with two transformers

    which operate in parallel on the same busbar

    Possible to use twotransformers with lowerrated power.

    Operation in parallel of thetransformers could causegreater problems inmanagement of the

    54

    .

    When coordinating theprotections, the fact thatthe overcurrent on the LVside is divided between thetwo transformers must betaken into consideration.

  • 7/28/2019 Chapter 1 PLANT PLANNING AND POWER DEMAND.pdf

    28/30

    07/03/2013

    28

    BEF 44903 Industrial Power Systems Chapter 1

    1.5 Methods of Transformer Installation

    MethodMethod 44 Substation with two transformers

    which operate simultaneously on two separate

    half-busbars

    Providing a CLV bus-tieand an I interlockwhich prevents the bus-tie from being closedwhen both the incomingcircuit-breakers from the

    55

    .

    This managementmethod allows a lowervalue of the short-circuitcurrent on the busbar.

    BEF 44903 Industrial Power Systems Chapter 1

    1.5 Transformer Sizing

    Transformer sizing is generally based on:

    } Total max. demand of individual/group consumer

    } Installed voltage level (kV)

    } Method of installation or arrangement

    } Short circuit capacity

    56

  • 7/28/2019 Chapter 1 PLANT PLANNING AND POWER DEMAND.pdf

    29/30

    07/03/2013

    29

    BEF 44903 Industrial Power Systems Chapter 1

    1.5 Transformer Sizing

    Short circuit capacity with infinite source

    What is %Z?

    ISCmax = ?

    kVASC = ?

    1000 kVA

    11kV 415 V

    Infinite source

    57

    %Z = 5%kVASC = ?

    BEF 44903 Industrial Power Systems Chapter 1

    1.5 Transformer Sizing

    Short circuit capacity with finite source

    SC(TX)

    MVASC(SEC) = ?

    ISCmax = ?

    1000 kVA

    11kV 415 V

    500 MVASC

    58

    %Z = 5%

    kVASC = ?

  • 7/28/2019 Chapter 1 PLANT PLANNING AND POWER DEMAND.pdf

    30/30

    07/03/2013

    BEF 44903 Industrial Power Systems Chapter 1

    1.5 Transformer Sizing

    Simple transformer-load connection

    1000 kVA

    11kV 415 V

    %Z = 5.0%

    kVASC = ?

    ISCmax = ?

    kVASC = ?

    Is the given size (1000kVA) suitable to servethe motor load?

    59

    M 80% Full loadInrush current = 6 times