Page 1: Chapter 12: Project Management1 Solutions to Chapter 12 Exercises

Chapter 12: Project Management 1

Solutions to Chapter 12 Exercises

Page 2: Chapter 12: Project Management1 Solutions to Chapter 12 Exercises

Chapter 12: Project Management 2

Exercise 1•There are four paths:

A-C-I (7 days)

A-D-G-J (13 days)

B-E-G-J (11 days)

B-F-H-J (10 days)

•Thus, the critical path is A-D-G-J and these are the activities that should be monitored most closely because if they slip, the entire project will be delayed.

Page 3: Chapter 12: Project Management1 Solutions to Chapter 12 Exercises

Chapter 12: Project Management 3

Exercise 1 concluded

• The time to complete the four paths is now:• A-C-I (5.5 days)

• A-D-G-J (11.5 days)

• B-E-G-J (12.5 days)

• B-F-H-J (11.5 days)

• The critical path is now B-E-G-J and the project completion is expected to be 12.5 days.

• Activities G and J remain as critical activities while A and D are no longer critical.

Page 4: Chapter 12: Project Management1 Solutions to Chapter 12 Exercises

Chapter 12: Project Management 4

Exercise 2

Activity TES TEF TLS TLF Slacka 0 4 0 4 0b 0 3 2 5 2c 4 5 10 11 6d 4 9 4 9 0e 3 7 5 9 2f 3 4 6 7 3g 9 12 9 12 0h 4 9 7 12 3i 5 7 11 13 6j 12 13 12 13 0

Page 5: Chapter 12: Project Management1 Solutions to Chapter 12 Exercises

Chapter 12: Project Management 5

Exercise 2: Path Slacks

Path A-C-I: Slack = 6

Path A-D-G-J: Slack = 0

Path B-E-G-J: Slack = 2

Path B-F-H-J: Slack = 10

Page 6: Chapter 12: Project Management1 Solutions to Chapter 12 Exercises

Chapter 12: Project Management 6

Exercise 3: Network Diagram

11

22

33

44

66

55

77

Page 7: Chapter 12: Project Management1 Solutions to Chapter 12 Exercises

Chapter 12: Project Management 7

Exercise 3: Activity Expected Times, Variances and Standard Deviations

1234567891011121314151617

A B C D E F GStandard

Activity Optimistic Most Likely Pessimistic te Variance Deviation1-2 5 11 11 10 1 11-3 10 10 10 10 0 01-4 2 5 8 5 1 12-6 1 7 13 7 4 23-6 4 4 10 5 1 13-7 4 7 10 7 1 13-5 2 2 2 2 0 04-5 0 6 6 5 1 15-7 2 8 14 8 4 26-7 1 4 7 4 1 1

Formulas:Cell E3 =(B3+(C3*4)+D3)/6 [copy to cells E4:E12]Cell F3 =((D3-B3)/6)^2 [copy to cells F4:F12]Cell G3 =SQRT(F3) [copy to cells G4:G12]

Page 8: Chapter 12: Project Management1 Solutions to Chapter 12 Exercises

Chapter 12: Project Management 8

Exercise 3: Path Expected Times, Variances, and Standard Deviations

Path Path Path ExpectedExpected Path Standard Time + 2.33

Path Time Variance Deviation Standard Deviations1-2-6-7 21 6 2.45 26.711-3-6-7 19 2 1.41 22.291-3-7 17 1 1 19.33

1-3-5-7 20 4 2 24.661-4-5-7 18 6 2.45 23.71

Page 9: Chapter 12: Project Management1 Solutions to Chapter 12 Exercises

Chapter 12: Project Management 9

Exercise 3: Probability Project Finishes within 17 Weeks

All paths must be considered since they all have a reasonable chance of taking longer than 17 weeks. Thus, there is a very small chance (i.e., .005%) that the project can be completed in 17 weeks or less.

123456789

10111213141516

A B C D E FSpecified Time 17

Path PathExpected Path Standard

Path Time Variance Deviation z Probability1-2-6-7 21 6 2.45 -1.63 0.0511-3-6-7 19 2 1.41 -1.42 0.0781-3-7 17 1 1 0.00 0.500

1-3-5-7 20 4 2 -1.50 0.0671-4-5-7 18 6 2.45 -0.41 0.342

Product of Probabilites 0.005%

Formulas:Cell E6 =($B$1-B6)/D6 [copy to cells E7:E10]Cell F6 =NORMSDIST(E6) [copy to cells F7:F10]Cell F11 =PRODUCT(F6:F10)

Page 10: Chapter 12: Project Management1 Solutions to Chapter 12 Exercises

Chapter 12: Project Management 10

Exercise 3: Probability Project Finishes within 24 Weeks

Only paths 1-2-6-7 and 1-3-5-7 need be considered.

123456789

10111213141516

A B C D E FSpecified Time 24

Path PathExpected Path Standard

Path Time Variance Deviation z Probability1-2-6-7 21 6 2.45 1.22 0.8901-3-6-7 19 2 1.41 3.55 1.0001-3-7 17 1 1 7.00 1.000

1-3-5-7 20 4 2 2.00 0.9771-4-5-7 18 6 2.45 2.45 0.993

Product of Probabilites 86.298%

Formulas:Cell E6 =($B$1-B6)/D6 [copy to cells E7:E10]Cell F6 =NORMSDIST(E6) [copy to cells F7:F10]Cell F11 =PRODUCT(F6:F10)

However, all paths can be easily included by simply changing cell B1 from 17 to 24. With all paths considered, there is a over an 86% chance of completing the project in 24 weeks.

Page 11: Chapter 12: Project Management1 Solutions to Chapter 12 Exercises

Chapter 12: Project Management 11

Exercise 3: Should the Project be Pursued?

• Using the spreadsheet it can be easily determined that the probability of finishing within 18 weeks is .176% and the probability of the project taking 22 weeks or longer is 48.321%.

• The expected value of the project is thus:

(.176% $10,000) + (48.321% -$5,000) = -$2398.40

• Given the negative expected value, the firm should not bid.

Page 12: Chapter 12: Project Management1 Solutions to Chapter 12 Exercises

Chapter 12: Project Management 12

Exercise 4

a 3

b 5

c 3

d 1

0

f 4

g 2h 3

e 3

i 1

The path with the longest expected time is a-b-dummy-f-h-i = 16.

Page 13: Chapter 12: Project Management1 Solutions to Chapter 12 Exercises

Chapter 12: Project Management 13

Exercise 5123456789

1011121314151617181920212223

A B C D E F GStandard

Activity Optimistic Most Likely Pessimistic te Variance DeviationA 6 7 14 8.00 1.78 1.33B 8 10 12 10.00 0.44 0.67C 2 3 4 3.00 0.11 0.33D 6 7 8 7.00 0.11 0.33E 5 5.5 9 6.00 0.44 0.67F 5 7 9 7.00 0.44 0.67G 4 6 8 6.00 0.44 0.67H 2.5 3 3.5 3.00 0.03 0.17

Formulas:Cell E3 =(B3+(C3*4)+D3)/6 [copy to cells E4:E10]Cell F3 =((D3-B3)/6)^2 [copy to cells F4:F10]Cell G3 =SQRT(F3) [copy to cells G4:G10]

Path PathExpected Path Standard

Path Time Variance DeviationA-D-G 21 2.33 1.53

A-C-E-G 23 2.78 1.67B-E-G 22 1.33 1.15B-F-H 20 0.92 0.96

Page 14: Chapter 12: Project Management1 Solutions to Chapter 12 Exercises

Chapter 12: Project Management 14

Exercise 5a continued

123456789

10111213141516

A B C D E FSpecified Time 21

Path PathExpected Path Standard

Path Time Variance Deviation z ProbabilityA-D-G 21 2.33 1.53 0.00 0.500

A-C-E-G 23 2.78 1.67 -1.20 0.115B-E-G 22 1.33 1.15 -0.87 0.193B-F-H 20 0.92 0.96 1.04 0.852

Product of Probabilites 0.947%

Formulas:Cell E6 =($B$1-B6)/D6 [copy to cells E7:E19]Cell F6 =NORMSDIST(E6) [copy to cells F7:F9]Cell F11 =PRODUCT(F6:F9)

Page 15: Chapter 12: Project Management1 Solutions to Chapter 12 Exercises

Chapter 12: Project Management 15

Exercise 5b continued

123456789

10111213141516

A B C D E FSpecified Time 22

Path PathExpected Path Standard

Path Time Variance Deviation z ProbabilityA-D-G 21 2.33 1.53 0.65 0.744

A-C-E-G 23 2.78 1.67 -0.60 0.274B-E-G 22 1.33 1.15 0.00 0.500B-F-H 20 0.92 0.96 2.09 0.982

Product of Probabilites 10.010%

Formulas:Cell E6 =($B$1-B6)/D6 [copy to cells E7:E19]Cell F6 =NORMSDIST(E6) [copy to cells F7:F9]Cell F11 =PRODUCT(F6:F9)

Page 16: Chapter 12: Project Management1 Solutions to Chapter 12 Exercises

Chapter 12: Project Management 16

Exercise 5c concluded

123456789

10111213141516

A B C D E FSpecified Time 25

Path PathExpected Path Standard

Path Time Variance Deviation z ProbabilityA-D-G 21 2.33 1.53 2.62 0.996

A-C-E-G 23 2.78 1.67 1.20 0.885B-E-G 22 1.33 1.15 2.60 0.995B-F-H 20 0.92 0.96 5.22 1.000

Product of Probabilites 87.689%

Formulas:Cell E6 =($B$1-B6)/D6 [copy to cells E7:E19]Cell F6 =NORMSDIST(E6) [copy to cells F7:F9]Cell F11 =PRODUCT(F6:F9)

Page 17: Chapter 12: Project Management1 Solutions to Chapter 12 Exercises

Chapter 12: Project Management 17

Exercise 6

# 1

# 2

# 3

# 4# 5

# 6

# 7

# 8

# 9

Page 18: Chapter 12: Project Management1 Solutions to Chapter 12 Exercises

Chapter 12: Project Management 18

Exercise 6 continued123456789

10111213141516

A B C D E F GStandard

Activity Optimistic Most Likely Pessimistic te Variance Deviation1 8 10 13 10.17 0.69 0.832 5 6 8 6.17 0.25 0.503 13 15 21 15.67 1.78 1.334 10 12 14 12.00 0.44 0.675 11 20 30 20.17 10.03 3.176 4 5 8 5.33 0.44 0.677 2 3 4 3.00 0.11 0.338 4 6 10 6.33 1.00 1.009 2 3 4 3.00 0.11 0.33

Formulas:Cell E3 =(B3+(C3*4)+D3)/6 [copy to cells E4:E10]Cell F3 =((D3-B3)/6)^2 [copy to cells F4:F10]Cell G3 =SQRT(F3) [copy to cells G4:G10]

Page 19: Chapter 12: Project Management1 Solutions to Chapter 12 Exercises

Chapter 12: Project Management 19

Exercise 6 concluded

Path 2-3-4-5-7-8-9 has the longest expected time. Thus, the project would be expected to take 66.33.

Path PathExpected Path Standard

Path Time Variance Deviation1-4-5-6-9 50.67 11.72 3.42

1-4-5-7-8-9 54.67 12.39 3.522-3-4-5-6-9 62.33 13.06 3.61

2-3-4-5-7-8-9 66.33 13.72 3.70

Page 20: Chapter 12: Project Management1 Solutions to Chapter 12 Exercises

Chapter 12: Project Management 20

Exercise 7

55 70

Actual

Plan

40

35

Time, Days

Pro

gres

s, %

Plan

55 70

1720

30

24

Time, Days

$ (000)

Page 21: Chapter 12: Project Management1 Solutions to Chapter 12 Exercises

Chapter 12: Project Management 21

Exercise 7 concluded

• Spending variance = EC - AC = 17,000 - 30,000 = -$13,000. This indicates a cost overrun of $13,000.

• Schedule variance = EC - SC = 17,000 - 24,000 = -$7,000 indicating the project is behind.

• Time variance = TE - TA = 55 -70 = -15 days indicating a 15 day delay.

Page 22: Chapter 12: Project Management1 Solutions to Chapter 12 Exercises

Chapter 12: Project Management 22

Exercise 8

Plan

ValueActual

1 TE 2 3

Time, Months

$ (000)

84

81

78

Page 23: Chapter 12: Project Management1 Solutions to Chapter 12 Exercises

Chapter 12: Project Management 23

Exercise 8 concluded• Spending variance = EC - AC = 81,000 - 78,000 =

$3,000.• Schedule variance = EC - SC = 81,000 - 84,000 = -

$3,000.• TE can be estimated from chart by determining

how much time should have elapsed according to the plan to achieve the current value completed. In this case TE is approximately 1.5 months.

• Thus, the spending variance = TE - TA = 1.5 - 2 = -0.5 month.

Page 24: Chapter 12: Project Management1 Solutions to Chapter 12 Exercises

Chapter 12: Project Management 24

Exercise 9

• Spending variance = EC - AC = 39,000 - 34,000 = $5,000.

• Schedule variance = EC - SC = 39,000 - 42,000 = -$3,000.

Page 25: Chapter 12: Project Management1 Solutions to Chapter 12 Exercises

Chapter 12: Project Management 25

Exercise 10a1234567891011121314151617181920212223242526272829303132333435363738394041424344454647484950515253

A B C D E F G H I JActivity Activity Activity Activity Activity Activity Path 1 Path 2 Path 3 Project

A B C D E F (A-C-F) (B-D-F) (B-E) Finish Time31.74 26.63 22.08 30.16 42.55 37.92 91.74 94.72 69.18 94.7230.57 23.56 24.88 26.19 48.86 32.67 88.12 82.42 72.42 88.1232.39 24.15 18.61 23.46 25.97 35.06 86.07 82.67 50.12 86.0733.63 22.74 25.68 22.19 31.69 33.66 92.97 78.59 54.43 92.9733.54 24.12 25.44 23.69 38.36 36.76 95.74 84.57 62.48 95.7434.18 17.68 19.09 26.78 32.29 29.92 83.19 74.37 49.96 83.1929.48 24.19 22.35 26.72 36.38 36.12 87.95 87.03 60.57 87.9531.82 20.48 21.27 23.22 40.52 31.10 84.19 74.81 61.00 84.1933.41 25.09 21.82 14.95 33.93 31.71 86.95 71.75 59.01 86.9530.80 26.16 19.69 17.69 35.33 33.53 84.02 77.37 61.49 84.0231.27 28.68 25.52 26.88 33.76 33.88 90.67 89.44 62.44 90.6730.07 22.68 24.16 32.87 32.59 30.60 84.83 86.15 55.27 86.1529.88 22.28 24.16 27.82 40.50 40.36 94.40 90.46 62.78 94.4030.93 25.05 24.01 27.75 46.97 23.91 78.85 76.71 72.03 78.8531.17 23.88 23.58 23.07 48.14 36.78 91.53 83.73 72.02 91.5329.56 23.95 20.84 25.02 32.60 32.78 83.18 81.75 56.55 83.1831.42 29.49 19.06 20.17 30.52 40.86 91.34 90.52 60.00 91.3431.62 24.72 22.33 30.88 41.09 27.52 81.47 83.11 65.80 83.1132.26 24.15 23.74 21.84 34.14 33.73 89.73 79.72 58.29 89.7331.66 30.27 20.64 24.08 35.54 33.53 85.84 87.89 65.81 87.8931.71 22.64 17.65 25.07 32.56 41.25 90.60 88.96 55.21 90.6031.66 28.54 20.31 13.84 31.63 37.55 89.51 79.93 60.17 89.5133.71 24.55 18.78 24.92 22.78 36.90 89.39 86.36 47.34 89.3932.00 24.40 26.39 25.76 40.33 38.55 96.94 88.71 64.73 96.9431.88 29.59 20.08 29.10 36.93 34.24 86.20 92.94 66.52 92.9431.48 25.72 25.59 25.78 27.38 33.83 90.90 85.33 53.10 90.9034.47 25.95 22.79 31.15 33.61 40.33 97.59 97.43 59.56 97.5933.14 23.87 27.24 17.60 21.37 40.63 101.02 82.10 45.25 101.0234.95 26.72 20.24 25.69 23.76 31.95 87.15 84.36 50.47 87.1531.31 24.39 22.42 28.50 31.28 32.51 86.24 85.39 55.66 86.2434.09 22.32 20.29 21.12 32.69 28.93 83.31 72.37 55.01 83.3130.17 21.20 26.01 23.78 31.51 32.84 89.02 77.82 52.71 89.0232.75 25.23 21.75 25.85 24.26 33.50 88.00 84.59 49.49 88.0033.18 21.56 21.95 17.10 36.17 35.12 90.26 73.78 57.73 90.2634.40 30.61 22.24 18.72 30.16 29.11 85.75 78.44 60.77 85.7532.00 24.21 19.67 37.33 28.22 40.12 91.79 101.66 52.43 101.6631.47 19.68 23.33 21.92 28.16 33.39 88.19 74.98 47.84 88.1932.91 23.56 27.31 22.08 42.91 25.76 85.98 71.39 66.47 85.9831.64 27.57 23.64 17.89 21.53 38.41 93.69 83.87 49.09 93.6933.01 23.41 19.38 28.45 28.79 31.92 84.31 83.77 52.20 84.3130.37 22.57 19.36 29.80 43.93 28.36 78.08 80.73 66.51 80.7331.08 20.36 23.00 21.78 33.03 36.10 90.18 78.24 53.40 90.1830.27 25.58 23.16 29.07 40.26 34.39 87.82 89.04 65.84 89.0431.66 24.09 20.97 23.61 32.56 45.16 97.79 92.86 56.65 97.7932.06 26.37 24.14 27.89 40.92 35.00 91.19 89.26 67.29 91.1932.13 22.62 20.15 21.86 42.77 37.79 90.07 82.27 65.39 90.0731.71 23.53 22.47 29.62 29.14 34.77 88.95 87.92 52.67 88.9534.73 25.49 23.51 23.34 41.17 42.19 100.43 91.01 66.65 100.4330.01 23.57 23.51 29.64 25.61 28.49 82.01 81.70 49.19 82.0131.22 25.26 21.79 29.28 45.08 37.49 90.50 92.04 70.33 92.0429.01 16.93 24.44 24.72 39.28 32.26 85.70 73.91 56.22 85.70

Page 26: Chapter 12: Project Management1 Solutions to Chapter 12 Exercises

Chapter 12: Project Management 26

Exercise 10a (concluded)54555657585960616263646566676869707172737475767778798081828384858687888990919293949596979899100101102103104105106

A B C D E F G H I J33.84 24.39 22.82 22.38 30.70 34.80 91.46 81.57 55.09 91.4630.56 25.37 25.88 30.13 30.90 40.78 97.23 96.28 56.26 97.2331.32 31.16 21.56 28.61 26.64 31.11 83.99 90.88 57.80 90.8833.01 19.87 19.25 27.95 37.54 39.25 91.51 87.07 57.41 91.5132.66 19.77 21.28 25.74 34.28 28.73 82.67 74.24 54.05 82.6733.15 17.46 25.10 23.48 39.57 33.31 91.56 74.24 57.03 91.5632.81 28.23 22.75 16.31 26.50 34.54 90.10 79.08 54.73 90.1030.45 31.96 24.26 36.33 24.67 31.12 85.83 99.40 56.63 99.4030.76 23.39 20.73 33.46 34.40 41.09 92.58 97.94 57.79 97.9432.93 21.50 19.29 31.90 51.24 36.21 88.44 89.61 72.74 89.6132.49 26.30 21.55 30.11 30.49 37.61 91.65 94.02 56.79 94.0230.97 26.64 18.60 37.18 21.54 39.69 89.26 103.51 48.18 103.5131.81 21.96 26.53 25.83 25.75 39.64 97.99 87.43 47.71 97.9932.26 27.11 21.01 24.61 33.07 28.30 81.57 80.02 60.18 81.5732.77 26.65 25.65 30.91 40.72 38.32 96.74 95.88 67.37 96.7432.27 23.96 18.42 26.15 39.00 41.17 91.86 91.28 62.96 91.8631.01 19.80 22.48 27.48 31.20 31.64 85.12 78.92 51.00 85.1234.36 27.74 20.86 17.46 32.91 31.80 87.03 77.00 60.65 87.0332.68 26.97 24.46 25.33 36.79 32.88 90.03 85.18 63.75 90.0332.19 23.51 27.25 28.90 40.35 37.06 96.50 89.47 63.87 96.5033.10 22.46 20.11 22.59 31.75 41.14 94.34 86.18 54.21 94.3433.13 27.27 23.15 20.02 39.43 35.52 91.81 82.82 66.71 91.8131.34 25.68 27.06 34.25 37.48 25.96 84.36 85.89 63.16 85.8930.99 26.32 21.15 30.72 28.80 33.39 85.53 90.43 55.12 90.4333.43 31.07 24.21 30.37 36.69 35.46 93.10 96.90 67.76 96.9030.66 25.45 20.67 30.29 33.16 38.60 89.92 94.33 58.61 94.3330.23 21.17 21.88 23.45 28.66 35.64 87.75 80.25 49.82 87.7532.95 26.09 19.81 30.30 33.65 29.42 82.18 85.81 59.74 85.8132.87 20.79 22.50 20.41 26.10 36.35 91.71 77.55 46.89 91.7134.75 26.35 19.76 26.12 19.13 39.31 93.82 91.78 45.49 93.8233.83 24.11 21.58 22.74 35.97 37.71 93.12 84.56 60.09 93.1233.66 25.53 23.44 29.48 39.06 32.51 89.62 87.51 64.59 89.6232.24 25.71 23.70 27.42 44.41 28.87 84.81 82.00 70.12 84.8132.10 25.01 20.68 32.09 28.78 40.28 93.06 97.37 53.79 97.3732.64 23.76 22.22 28.55 29.19 37.30 92.17 89.60 52.95 92.1732.07 20.42 21.26 23.83 34.53 33.22 86.55 77.47 54.95 86.5530.83 31.17 19.08 30.65 32.66 31.33 81.23 93.15 63.84 93.1529.97 29.55 22.05 28.79 28.27 38.04 90.05 96.37 57.82 96.3733.09 27.85 25.54 29.40 36.10 33.76 92.40 91.02 63.95 92.4032.63 20.02 22.41 37.54 33.62 37.46 92.50 95.02 53.64 95.0232.84 21.14 21.97 21.59 34.08 35.42 90.23 78.14 55.21 90.2332.36 26.25 24.93 16.63 43.11 37.69 94.97 80.57 69.36 94.9730.87 24.83 21.42 28.33 43.27 31.48 83.77 84.64 68.10 84.6433.59 24.57 18.85 21.36 37.76 31.52 83.95 77.45 62.33 83.9531.73 25.10 24.57 22.93 28.40 33.05 89.35 81.08 53.50 89.3531.09 18.77 22.64 42.31 31.15 34.51 88.24 95.58 49.92 95.5831.11 23.80 20.09 27.48 23.14 31.23 82.44 82.52 46.94 82.5231.59 21.69 21.88 26.99 41.61 28.94 82.41 77.62 63.31 82.4131.56 21.51 19.63 24.54 32.15 37.14 88.32 83.19 53.65 88.32

Avg 89.08 85.31 58.51 90.33S.D. 4.72 7.30 6.93 5.16Max 101.02 103.51 72.74 103.51Min 78.08 71.39 45.25 78.85

Page 27: Chapter 12: Project Management1 Solutions to Chapter 12 Exercises

Chapter 12: Project Management 27

Exercise 10b

•From the above spreadsheet, the average

project completion time is 90.33 days with

a standard deviation of 5.16 days.

•Across the 100 replications of the

simulation model, the project finished as

quickly as 78.85 days and took as long as

103.51 days.

Page 28: Chapter 12: Project Management1 Solutions to Chapter 12 Exercises

Chapter 12: Project Management 28

Exercise 10cc .

T h e a b o v e h is to g ra m c le a r ly il lu s t ra te s the u nc e r ta in t y a s so c ia te d w ith the a c tu a la m o u n t o f t im e it w ill t a k e to co m p le te the p ro je c t . A c c o rd in g to th e h is to g ra m ,th e re is a s m a ll c h a n c e th e p ro je c t c a n be c o m p le te d in le s s tha n 8 0 d a ys a n d as lig h t ly la rg e r c h a nc e it w ill t a k e m o re th a n 1 0 0 d a ys . In th is c a se , if th e m a na g e rfo c u se d o n ly o n th e p a th w ith th e lo n g e s t e xp e c te d c o m p le t io n t im e ( i.e . , p a th A -C -F ) a nd e s t im a te d th e p ro je c t c o m p le t io n t im e o n th e ba s is o f th is p a th a s 8 8 .8d a y s, the re su lt s o f the s im u la t io n su g g e s t th a t the re w o u ld b e a 6 3 p e rc e n t c h a n c eo f e x c e e d in g th is e s t im a te . In fa c t , in 2 7 p e rc e n t o f th e s im u la t io n re p lic a t io n s ,p a th B -D -F tu rn e d o u t to b e the c r it ic a l p a th .

Distribution of Project Completion Times

0

5

10

15

20

25

30

35

40

80 85 90 95 100 105

Project Completion Time

Fre

qu

en

cy

Page 29: Chapter 12: Project Management1 Solutions to Chapter 12 Exercises

Chapter 12: Project Management 29

Exercise 10d• Path A-C-F has an expected duration of 88.8 days with a standard deviation of

4.81 days. Based on this, the probability that it is completed in 80 days or less can be calculated as:

• From the z table in the Appendix A, the probability of the path being completed in 80 days or less is 3.51%. Alternatively, this can be found using Excel as follows: =normdist(80,88.8,4.81,true) = 3.37. Incidentally, the value found using Excel is actually more accurate since rounding the value of z was not required.

• Path B-D-F has an expected duration of 85.2 days and standard deviation of 7.31 days. Using Excel the probability it is completed in 80 days or less is found as: =normdist(80,85.2,7.31,true) = 23.84%.

• Path B-E has an expected duration of 59.0 days and standard deviation of 6.93 days. Using Excel the probability it is completed in 80 days or less is found as: =normdist(80,59,6.93,true) = 99.88%.

• The probability the entire project is completed in 80 days or less is calculated as (.0337)(.2384)(.9988) = 0.80%

Page 30: Chapter 12: Project Management1 Solutions to Chapter 12 Exercises

Chapter 12: Project Management 30

Exercise 10e

• The results shown in the spreadsheet to part a are consistent with the probability calculated in part d.

• In only one of the 100 replications was the project completed in 80 days or less (i.e., rep number 14).

• One percent of the replications is quite close to the 0.8% calculated in part d.