chapter 2 - optimizing the equipment room - 280614 ok

Upload: shantam

Post on 03-Jun-2018

222 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK

    1/26

    Chapter 2

    Optimizing the Equipment Room

  • 8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK

    2/26

    Outlines

    Equipment RoomWhat it is?

    Site Environmental Specification

    Space and Location Requirements

    Construction Requirements for the Equipment Room

    Environment Requirements for Operating the BTS

    Equipment Room Security: Site Boss Example

    2-2

  • 8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK

    3/26

    Equipment Room What it is?

    The equipment room is room or

    space within a building for the

    storage or installation of

    mechanical or electrical/electronic

    devices

    To optimize equipment room,

    fullfil the following requirements:

    Site Environmental Specification

    Heat Dissipation and CoolingRequirements

    Space and Location Requirements

    Construction & Environment

    Requirements for Operating the BTS

    2-3

  • 8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK

    4/26

    Site Environmental Specification

    Environmental Specifications

    2-4

  • 8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK

    5/26

    Heat Dissipation and Cooling Requirements

    The BTS chassis must be intended for mounting in a cabinet or

    other rigid framework which is fixed to the building

    A 2.2-meter or 2.6-meter rack can accommodate up to three

    BTS chassis

    There is no space limitation or minimum equipment clearances

    for the BTS

    The BTS chassis is cooled by the flow of air between the

    elements mounted in the cabinet

    The fans and air baffles ensure that sufficient air flows betweenthe elements

    The cooling system, including the baffle and fan tray, is supplied

    with each chassis and is an integral part of the BTS chassis

    2-5

  • 8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK

    6/26

    Calculating the Heat Dissipation of the BTS

    Use the following formula to calculate the heat dissipation for

    each BTS

    [(Module 1 power consumption) + (Module 2 power

    consumption) + (Module N power consumption)] x 2.3884 =

    BTU

    For example, for a BTS with 1 AU and 1 NPU (and no

    redundancy), the heat dissipation is as follows

    [(PIU = 30 Watt) + (PSU = 200 Watt) + (NPU = 65 Watt) + (AU-IDU =

    41 Watt) + (AVU = 24 Watt)] x 2.3884 = 860 BTU

    2-6

  • 8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK

    7/26

    Installation Tools (1)

    The following table lists the recommended tools and sealing

    materials required for installation

    2-7

  • 8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK

    8/26

    Installation Tools (2)

    2-8

  • 8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK

    9/26

    Space and Location Requirements

    The layout of the equipment

    room must be reasonable,

    feasible, and neat

    The BTS cabinet can be

    installed against the wall

    2-9

  • 8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK

    10/26

    Installation Directions of the Cabinets

    2-10

  • 8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK

    11/26

    Location Requirements

    Location requirements of the BTS (unit:mm)

    2-11

  • 8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK

    12/26

    Construction Requirements for the EquipmentRoom

    The equipment room consists:

    Exchange room

    Control room (area not less than 20 m2)

    Auxiliary room

    Factors such as the shortest route of the feeders, bearing

    capacity of the equipment room, power supply, and

    transmission mode should be taken into consideration

    2-12

  • 8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK

    13/26

    Requirements for the Area of the EquipmentRoom

    The room should be large enough for equipment installation

    and future capacity expansion

    The feeder window can be installed easily, and the routing of

    the feeders inside the equipment room is convenient

    It is convenient and easy for the maintenance personnel to

    install or maintain the equipment

    It is convenient to open and close the cabinet door

    2-13

  • 8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK

    14/26

    Requirements for the Height of the EquipmentRoom

    The minimum height of the equipment room refers to the

    distance between the horizontal beam or the air vent and the

    floor

    The minimum height of the equipment room should be 3

    meters

    2-14

  • 8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK

    15/26

    Requirements for the Bearing Capacity

    The equipment is quite heavy

    The checking should be done in compliance with the weight,

    basal area, position for the equipment, and structure of the

    building

    If the bearing capacity is not enough, reinforce the building

    2-15

  • 8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK

    16/26

    Requirements for the Floor

    Floorboards should be laid down firmly, and there should be

    no space between the boards

    The horizontal error per square meter should not be greater

    than 2 mm

    Cable holes in the floor should be capped with access covers

    to protect cables from rodents

    Position for the holes should be determined in compliance with

    the engineering design and the dimensions should be accurate

    to ensure easy installation

    2-16

  • 8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK

    17/26

    Requirements for the Door and Windows

    The minimum dimensions of the door are 2 meters in height

    and 1 meter in width

    The door and the windows should be sealed with dustproof

    plastic tapes

    Reflectors or colored glass should be applied to the windows

    through which sunlight directly enters the room

    2-17

  • 8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK

    18/26

    Requirements for Walls and Rooftop

    The walls and the rooftop should be durable, heat-resistant

    and leakproof

    Leakage-proof measures should be taken if there are antenna

    poles or holes in the rooftop

    The bearing capacity of the devices should also be taken into

    consideration

    Flat paint can be applied to the walls, but chalked paint is not

    recommended

    2-18

  • 8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK

    19/26

    Requirements for Dust Proofing in theEquipment Room

    Requirements for the dust concentration in the equipment

    room

    2-19

  • 8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK

    20/26

    Requirements for the Quake Proofing of theEquipment Room

    The intensity requirement of the shockproof design of the

    equipment room must be one degree higher than the local

    intensity requirement

    If the equipment room does not meet this requirement,

    reinforce the equipment room

    2-20

  • 8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK

    21/26

    Environment Requirements for Operatingthe BTS

    In the long-term operating environment, the BTS can operate

    properly for a long period

    In the short-term operating environment, the BTS must

    operate for less than 96 hours each time

    Less than 15 days each year in total to ensure proper operation

    without damaging the hardware

    The environment requirements focuses on the following

    The climatic

    Biological

    Air purity

    Mechanical stress requirements

    2-21

  • 8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK

    22/26

    Climatic Requirements

    The climatic requirements for the normal operation of the BTS

    1-222-22

  • 8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK

    23/26

    Biological Environment Requirements

    The biological requirements related to the operating

    environment are as follows:

    The environment should not be conducive for the growth of

    fungus or mildew

    There should be no rodents, such as rats

    2-23

  • 8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK

    24/26

    Air Purity Requirements

    The air should be free from explosive, conductive, magneto-

    conductive, or corrosive dust

    The density of chemically active substances should comply

    with the requirements listed in table below

    2-24

  • 8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK

    25/26

    Mechanical Stress Requirements

    Mechanical stress requirements for the normal operation of

    the BTS

    2-25

  • 8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK

    26/26

    Equipment Room Security: Site Boss Example

    2-26

    Site Boss pro vides ful l range ofhardware and sof tware tools to

    manage the passive elements at a

    Base Transc eiver Station