chapter 2 - optimizing the equipment room - 280614 ok
TRANSCRIPT
-
8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK
1/26
Chapter 2
Optimizing the Equipment Room
-
8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK
2/26
Outlines
Equipment RoomWhat it is?
Site Environmental Specification
Space and Location Requirements
Construction Requirements for the Equipment Room
Environment Requirements for Operating the BTS
Equipment Room Security: Site Boss Example
2-2
-
8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK
3/26
Equipment Room What it is?
The equipment room is room or
space within a building for the
storage or installation of
mechanical or electrical/electronic
devices
To optimize equipment room,
fullfil the following requirements:
Site Environmental Specification
Heat Dissipation and CoolingRequirements
Space and Location Requirements
Construction & Environment
Requirements for Operating the BTS
2-3
-
8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK
4/26
Site Environmental Specification
Environmental Specifications
2-4
-
8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK
5/26
Heat Dissipation and Cooling Requirements
The BTS chassis must be intended for mounting in a cabinet or
other rigid framework which is fixed to the building
A 2.2-meter or 2.6-meter rack can accommodate up to three
BTS chassis
There is no space limitation or minimum equipment clearances
for the BTS
The BTS chassis is cooled by the flow of air between the
elements mounted in the cabinet
The fans and air baffles ensure that sufficient air flows betweenthe elements
The cooling system, including the baffle and fan tray, is supplied
with each chassis and is an integral part of the BTS chassis
2-5
-
8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK
6/26
Calculating the Heat Dissipation of the BTS
Use the following formula to calculate the heat dissipation for
each BTS
[(Module 1 power consumption) + (Module 2 power
consumption) + (Module N power consumption)] x 2.3884 =
BTU
For example, for a BTS with 1 AU and 1 NPU (and no
redundancy), the heat dissipation is as follows
[(PIU = 30 Watt) + (PSU = 200 Watt) + (NPU = 65 Watt) + (AU-IDU =
41 Watt) + (AVU = 24 Watt)] x 2.3884 = 860 BTU
2-6
-
8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK
7/26
Installation Tools (1)
The following table lists the recommended tools and sealing
materials required for installation
2-7
-
8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK
8/26
Installation Tools (2)
2-8
-
8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK
9/26
Space and Location Requirements
The layout of the equipment
room must be reasonable,
feasible, and neat
The BTS cabinet can be
installed against the wall
2-9
-
8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK
10/26
Installation Directions of the Cabinets
2-10
-
8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK
11/26
Location Requirements
Location requirements of the BTS (unit:mm)
2-11
-
8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK
12/26
Construction Requirements for the EquipmentRoom
The equipment room consists:
Exchange room
Control room (area not less than 20 m2)
Auxiliary room
Factors such as the shortest route of the feeders, bearing
capacity of the equipment room, power supply, and
transmission mode should be taken into consideration
2-12
-
8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK
13/26
Requirements for the Area of the EquipmentRoom
The room should be large enough for equipment installation
and future capacity expansion
The feeder window can be installed easily, and the routing of
the feeders inside the equipment room is convenient
It is convenient and easy for the maintenance personnel to
install or maintain the equipment
It is convenient to open and close the cabinet door
2-13
-
8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK
14/26
Requirements for the Height of the EquipmentRoom
The minimum height of the equipment room refers to the
distance between the horizontal beam or the air vent and the
floor
The minimum height of the equipment room should be 3
meters
2-14
-
8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK
15/26
Requirements for the Bearing Capacity
The equipment is quite heavy
The checking should be done in compliance with the weight,
basal area, position for the equipment, and structure of the
building
If the bearing capacity is not enough, reinforce the building
2-15
-
8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK
16/26
Requirements for the Floor
Floorboards should be laid down firmly, and there should be
no space between the boards
The horizontal error per square meter should not be greater
than 2 mm
Cable holes in the floor should be capped with access covers
to protect cables from rodents
Position for the holes should be determined in compliance with
the engineering design and the dimensions should be accurate
to ensure easy installation
2-16
-
8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK
17/26
Requirements for the Door and Windows
The minimum dimensions of the door are 2 meters in height
and 1 meter in width
The door and the windows should be sealed with dustproof
plastic tapes
Reflectors or colored glass should be applied to the windows
through which sunlight directly enters the room
2-17
-
8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK
18/26
Requirements for Walls and Rooftop
The walls and the rooftop should be durable, heat-resistant
and leakproof
Leakage-proof measures should be taken if there are antenna
poles or holes in the rooftop
The bearing capacity of the devices should also be taken into
consideration
Flat paint can be applied to the walls, but chalked paint is not
recommended
2-18
-
8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK
19/26
Requirements for Dust Proofing in theEquipment Room
Requirements for the dust concentration in the equipment
room
2-19
-
8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK
20/26
Requirements for the Quake Proofing of theEquipment Room
The intensity requirement of the shockproof design of the
equipment room must be one degree higher than the local
intensity requirement
If the equipment room does not meet this requirement,
reinforce the equipment room
2-20
-
8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK
21/26
Environment Requirements for Operatingthe BTS
In the long-term operating environment, the BTS can operate
properly for a long period
In the short-term operating environment, the BTS must
operate for less than 96 hours each time
Less than 15 days each year in total to ensure proper operation
without damaging the hardware
The environment requirements focuses on the following
The climatic
Biological
Air purity
Mechanical stress requirements
2-21
-
8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK
22/26
Climatic Requirements
The climatic requirements for the normal operation of the BTS
1-222-22
-
8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK
23/26
Biological Environment Requirements
The biological requirements related to the operating
environment are as follows:
The environment should not be conducive for the growth of
fungus or mildew
There should be no rodents, such as rats
2-23
-
8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK
24/26
Air Purity Requirements
The air should be free from explosive, conductive, magneto-
conductive, or corrosive dust
The density of chemically active substances should comply
with the requirements listed in table below
2-24
-
8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK
25/26
Mechanical Stress Requirements
Mechanical stress requirements for the normal operation of
the BTS
2-25
-
8/12/2019 Chapter 2 - Optimizing the Equipment Room - 280614 OK
26/26
Equipment Room Security: Site Boss Example
2-26
Site Boss pro vides ful l range ofhardware and sof tware tools to
manage the passive elements at a
Base Transc eiver Station