chapter 3 a systems analysis of superfund

41
Chapter 3 A Systems Analysis of Superfund

Upload: others

Post on 28-Apr-2022

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Chapter 3 A Systems Analysis of Superfund

Chapter 3

A Systems Analysis of Superfund

Page 2: Chapter 3 A Systems Analysis of Superfund

ContentsPage

Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 61Current Estimates of Future Superfund Needs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 61

Uncertainty and the Need to Evaluate the Superfund Program . . . . . . . . . . . . . . . 63Alternative Approaches to Projecting Superfund Needs . . . . . . . . . . . . . . . . . . . . . . . 64Historical Performance of the Superfund Program. . . . . . . . . . . . . . . . . . . . . . . . . . . . 64

A Systems Analysis Approach to Define a Long-Term Strategic Plan 67Simulation: A Systems Analysis Method for Comparing Two Strategies

. . . . . . . . .

and Incorporating Long-Term Uncertainty . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 70Models and Reality . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 74

Use of Models and Findings . . . . . 74A Two-Part Strategy . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 83

Conclusions: Program Planning Under Uncertainty . . . . . . . . . . . . . . . . . . . . . . . . 85Effectiveness and the Future Cost of Cleanups ....., . . . . . . . . . . . . . . . . . . . . . . . . . 85

Health and Environment Effects . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 88Non-Federal Money . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 88Discount Rate . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 89Means to Address Uncertainties . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 89

Appendix A 90

List of Tables

Table No. Page3-1. Current Estimates for Cleaning Up Uncontrolled Hazardous Waste Sites . . . . . 623-2. Summary of Remedial Cleanup Actions Approved . . . . . . . . . . . . . . . . . . . . . . . . 653-3. System Definitions and Assumptions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 713-4. Summary of Simulation Scenarios ...... . . . . . . . . . . . . . . . . . . . . . . . . . . . 723-5. Illustration of How an Average Impermanence Factor of 0.5 Might Arise . . . . 733-6. Scenario 1UAF . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 783-7. Program Planning With Uncertainty . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 87

List of Figures

Figure3-1.3-2a.3-2b.3-3a.3-3b.3-4.3-5a.3-5b.3-6.3-7.3-8a.3-8b.

No. PageSuperfund System . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 67ProgramProgramProgramProgramProgramProgramProgramProgramProgramProgramProgram

Length v. Impermanence Factor . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 77Cost v. Impermanence Factor . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 77Length v. Impermanence Factor . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 79Cost v. Impermanence Factor . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 79Cost v. Impermanence Factor . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 80Length v. Impermanence Factor . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81Cost v. Impermanence Factor . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81

Costs v. Impermanence. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 84Length v. Impermanence Factor . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 86Cost v. Impermanence Factor . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 86

Page 3: Chapter 3 A Systems Analysis of Superfund

Chapter 3

A Systems Analysis of Superfund

INTRODUCTION

In the Superfund program so far, more at-tention has been paid to short-term costs andbudgets than to total program costs and pro-gram durations which can cover decades. ASuperfund program designed from a short-termperspective may not be consistent with theneed for long-term programs to permanentlydeal with the problems posed by thousands ofuncontrolled hazardous waste sites. Withoutadequate planning, the result may be a cleanupprogram that extends beyond several decades,presenting uncertain and possibly serioushealth and environmental risks.

This chapter examines how future financialneeds of the Superfund program may be as-sessed and what program strategy can meetthese needs. A simple simulation model is pre-sented which illustrates how cleanup costs,present and future, might be taken into ac-count. The past performance of the programis considered, the uncertainty of historicalcosts is recognized, and alternative strategiesare compared. The results indicate there willbe trade-offs between program cost and thetime required to mitigate the threats posed bylarge numbers of uncontrolled hazardouswaste sites.

Finally, a two-part cleanup strategy is iden-tified that shows promise as a sound, long-termapproach to the problem, especially in the faceof many uncertainties.

Current Estimates of Future Superfund Needs

Recent estimates of future financial needs ofthe Superfund program confirm the need foran expanded fund. The studies summarized intable 3-I estimate that the cost to clean up theNation’s uncontrolled hazardous waste siteswill be substantially greater than the currentfund of $1.6 billion. Their estimates range from

$6 billion to $92 billion, with all but one cal-culating the Federal share of these costs at $5billion to $26 billion. Only the Department ofCommerce (DOC) study predicts that the cur-rent Superfund of $1.6 billion can meet require-ments for cleanup. However, DOC assumedthat only 546 sites would be eligible for theFund; this estimate is already out-of-date sinceover 200 new sites have been proposed for list-ing on the current 538 site National PriorityList (NPL).

Several sources of uncertainty are responsi-ble for the wide range of estimates in table 3-1; the most important are the number of sitesrequiring cleanup and the costs of cleanup.Estimates for the total number of sites to becleaned ranged from 1,400 to over 7,000. Whilethis may appear large enough to encompasstrue lower and upper bounds, there is evidenceto the contrary. OTA finds that a more appro-priate estimate is 10,000 sites (see chapter 5),without including several categories of candi-dates for Superfund sites, e.g., as many as75,000 mining wastes sites and 100,000 cur-rently leaking underground storage tanks, pro-jected to increase to 350,000 within the next5 years.1

Similarly, estimates of cleanup costs vary agreat deal, from $1 million to $30 million persite. Also, most of the predictions of totalcleanup cost assumed that the worst sites, thoserequiring the most costly response, were cap-tured in the current estimates of the numbersof sites. This may not be so. For example, DOCestimated that those sites not already on theNPL will cost much less to clean up than NPLsites ($3.2 million per site v. $9.7 million per

1 Donald J’, Fcliciano, “Leaking Underground Storage Tanks:,~ ~Jot(~nti:~] ~~n\rironnlenta] I’rot)lcIll! “ [ T,S, [Jihrary of Congress.(;ongrcssional Resrxir(:h %r~’i(:c. lam I I, 1984.

61

Page 4: Chapter 3 A Systems Analysis of Superfund

Table 3-1 .—Current Estimates for Cleaning up Uncontrolled Hazardous Waste Sites

Department ofEPA (1 984)’ EPA (1983)2 GA03 Commerce 4

Number of sites requiring cleanup:1,500-2,500 1,400-2,200 1,270-2,546 546 NPL

23-56°/0 require 23-56°/0 require 1,250 non-NPLgroundwater response groundwater response 41 municipal

Total average cleanup costs per site (million):$6.7 -$13.3

Total costs$10.0 -$33.3

Total costs$7.6-$22.7 a

$6-$12 including $2.25-$6.75 constr. $9.7 NPLgroundwater response $5.25-$15.75 constr. $3.2 non-NPL

including groundwater $30 municipalresponse$1 .5-other costs

(unadjusted) (billion):$10.3 -$20.6 $5.6 -$33.8 $10.5

to Fund (billion):$8.4 -$16b $5.3-$26C ($1.5 surplus)-

$1.5 f

Projected years to clean sites:NA 14 for 1800 sites NA 10-15

NOTES—

ASTSWMO 5

7,113 (43States surveyed)1,500 mostserious

$1-$6$6 serious sites

$14.6 -$42.7

NA

16-23 ifconstrained bypersonnel28-90 ifconstrainedfinancially

National AudubonCMA6 Society

1,000 (27 States 2,200-7,000surveyed) 3,681 (potential) 38-56°/0 require

$4-$7 studies, removal,and containment$17-$30 studies, removal,containment, andgroundwater response

NA

$4.5e

NA

groundwater response

$8 including O&M$17 including ground-water response

$8-$92

NA

17-26 for 2,200 sites53-84 for 7,000 sites

aA~~ume~ 40 t. 60 percent of ~lte~ cleaned by prln~lpal Re~p~n~lble pafile~ (pRp~), Federal ~~~t share l.s go percent, c~~t recovery IS 47 percent for removals and 30 percent for remed!al actlon$, 85 perCent

Interest earned quarterly on prev!ous year’s balance. and 65 percent I nflat!on on removal actions, assumed 190 per year at $75 million per yearbpRp lead actions deductedcAssumes RpRs clean 29 to 44 perCent Of SitesdAnnual O&M costs are $3 I ,500, $20,900, and $117,600 for NPL, non-NPL, and munlclpal Site.$ respectlve~yestatement of E c Holmer, on behalf of the Chemical Manufacturers Assoclatlon, June 13, 1984 (This est, mate assumes no groufldwater cleanup ,l+lso might Include estimate that only 10 perceflt are orphan SlteS )fA~sumes 45 t. 55 percent cost recovev, 1 t. 15 percent of slte~ cleaned by pRps, 6,5 percent annual Construction Inflatlon, 5 percent annual general Inflation, and 85 percent annual lntereSt on cash balances9LoW estimates reflect $12 bllllon per year budget; high estimates are for $15 bll)lon per year budget

SOURCES(1) U S Environmental Protection Agency, “Extent of the Hazardous Release Problem and Future Funding Needs, CERCLA SectIon 301(a)(l)(c) Study, ” December 1964(2) U S Environmental ProtectIon Agency, Superfund Task Force Prellmlnary Assessment, December 1983(3) U S General Accounting Office, EPA’s Preliminary Estimates of Future Hazardous Waste Cleanup Costs Are Uncerfaln, GAO/RCED-64-152, May 7, 1964(4) U S Department of Commerce “Estimated Costs and Expenditures for Cleanup of the NatIon’s Uncontrolled Hazardous Waste Sites” (draft), Feb 22 1984(5) Association of State and Terrltonal Solld Waste Management Of flclals, “State Cleanup Programs for Hazardous Substance Sites and Spills,” Dec 21, 1964(6) Arthur D Little, Inc , Report to the Chemical Manufacturers” Assoclatlon, “An Analysls of the Number of lnactlve Hazardous Waste Sites That WIII Use Superfund,” July 1983(7) National Audubon Society, Testimony of Leslle Dach before the House Subcommittee on Commerce, Transportation and Touws.m, Mar 1, 1984

Page 5: Chapter 3 A Systems Analysis of Superfund

Ch. 3—A Systems Analysis of Superfund ● 63

site), However, the Environmental Protection 1.Agency’s (EPA] recently released list of pro-posed NPL sites contains contaminated aqui-fers on the island of Oahu. Although this is only 2.one very expensive site, it suggests that otherlarge contaminated aquifers might be addressedby Superfund in the future.

All the studies share one common assump- 3,

tion in their cost estimates, however—a com-plete effectiveness of cleanup technology. Thisleads to some critical questions:

Should the effectiveness of cleanup tech-nologies be considered in evaluating clean-up costs and program planning?Is the assumption that these technologiesare completely effective, warranted, and,if not, how should cost predictions bechanged?How certain are the “givens” of these pre-dictions, namely continued use of histori-cal cleanup technologies in the futureprogram?

UNCERTAINTY AND THE NEED TO EVALUATETHE SUPERFUND PROGRAM

The Superfund program was established inresponse to an emergency situation of uncer-tain proportions. Both the threats and the meas-ures to control hazardous waste sites were un-certain, but Congress decided that action wasimperative. Little attention to uncontrolledtoxic waste sites existed at the State level.Precedents existed for legislating and develop-ing regulatory programs in difficult areas. In-deed, the preamble to the Resource Conserva-tion and Recovery Act (RCRA) states that “thecourts have repeatedly sanctioned . . , otherEPA statutes where, as here, the Agency is im-plementing a complex program in an area‘fraught with scientific uncertainty where Con-gress has directed EPA to act quickly and de-cisively despite the lack of exact data’. ”2

To resolve the many uncertainties, Congressmandated several information-gathering tasksin the Superfund legislation, such as:

the designation of additional hazardoussubstances; s

the development of notification proce-dures for hazardous substance spills;4

the identification of all possible hazardouswaste sites;5

245 Federal Register 33088,WE RCLA, Section 102(a),41 birf., Section 103(a),51bid.

● the collection of information about hazard-ous substances at those sites for prelimi-nary assessments;6

Ž the establishment of the Agency for ToxicSubstances and Disease Registry to estab-lish and maintain: a) a national registry ofserious diseases and illnesses and a nation-al registry of persons exposed to toxic sub-stances, b) an inventory of information ofhealth effects of toxic substances, c) listingof areas closed to public or restricted inuse because of contamination, and d) pro-grams to study the relationships betweenexposure to toxic substances and illness; pand

● reports and studies on the experience withthe implementation of the Superfund pro-gram, including one to project “any futurefunding need remaining after the expira-tion of authority” and another to deter-mine “the extent to which the Act andFund are effective . . .“8

The uncertainties and complexities con-nected with releases of hazardous substancesare also reflected in the National ContingencyPlan (NCP), which outlines the regulatorymechanisms for Federal response to these re-

blbid., Se~ti~n IOA(e].71 bid., Section 10A(i].81bid., Section sol(a)(l),

Page 6: Chapter 3 A Systems Analysis of Superfund

64 ● Superfund Strategy

leases. Throughout the preamble to the modi-fied NCP, including the comments section,there is explicit mention of the need for flex-ibility in program design.9 In part, the need forflexibility reflects the site-specific nature of therelease and appropriate response. But flexibil-ity was also built into the NCP “to incorporateour expanding knowledge and experience indeveloping remedies.”l0

In conclusion, there were both legislative andregulatory motivations to address uncertainty.In particular, Congress mandated EPA to eval-uate effectiveness and project future financingrequirements, and EPA, in the NCP, acknowl-edged the need to continue to develop and im-prove its program, Evaluating the effectivenessof cleanup approaches is a key step in meetingthese congressional mandates.

Alternative Approaches to ProjectingSuperfund Needs

Projecting future funding needs of the Super-fund program can be approached in two ways.A descriptive approach was used in making theestimates summarized in table 3-I. This ap-proach assumes that the program will, for themost part, continue to operate as it has histori-cally, using the same methods for selectingsites for remediation and implementing thesame cleanup technologies. An average cost ofcleanup is derived from historical data, per-haps subject to various rates of inflation. Next,the expected number of sites requiring reme-diation is estimated, again relying largely onexaminations of past and current information,The percentage of sites requiring response inthe past is applied to an updated universe ofpotential sites. A range of values may be as-sumed for these parameters, to reflect samplingerrors or the inherent problems of projection,Future funding needs are determined by mul-tiplying the estimate for average cleanup costand the number of sites to be cleaned.

An alternative method of prediction is pre-scriptive, incorporating new information aswell as historical experience, It proposes andevaluates a number of cleanup strategies, not

947 Federal Register 31180-31202.1047 Federal Register 31182.

limited to those used in the past. Each strat-egy is then compared to the others on the basisof evaluation criteria and a preferable strategyis selected, The cost of the preferred strategyprovides projections for fund requirements, asmandated by the Comprehensive Environmen-tal Response, Compensation, and Liability Act(CERCLA).

The best way to evaluate the usefulness ofthe descriptive method, which is based on pastpractices, is to look at the historical perform-ance of the Superfund program. If the programhas been operating at an acceptable level of ef-ficiency and effectiveness, if uncertainties incost are adequately accounted for, and/or if noother alternatives exist, then the descriptivemethod is acceptable. The analysis below in-dicates that none of these conditions exists.

Historical Performance of theSuperfund Program

As of September 30, 1984, the Emergencyand Remedial Response Information System(ERRIS), the inventory of uncontrolled hazard-ous substance sites from which NPL sites areselected, contained 18,900 sites. EPA antici-pates that the list will grow to between 22,000and 25,000 sites.11 Preliminary assessments hadbeen conducted at 10,700 sites and site inspec-tions completed at 3,600 sites.l2 Of the 1,700sites scored with EPA’s Hazard Ranking Sys-tem, 538 have been selected for the NationalPriority List and an additional 238 sites havebeen proposed for listing.13

The first 2½ years of the Superfund programprogressed slowly, but the pace has acceleratedsince May 1983. At the end of fiscal year 1982,57 removal actions at both NPL and non-NPLsites had been initiated; after 2 more years, atotal of 422 had been started. Of this total, only17 were planned removal actions.14

IY LJ. s. IZrlVlrOnrnenta] Protection Agency, “Extent of the Haz-ardous Release problem and Future Funding Needs, CERCLASection 301(a)(l)(C) Study” (Washington, DC: Office of SolidWaste and Emergency Response, December 1984).

‘z Ibid.‘s Ibid.14u .S. Environmental Protection Agency, “The Effectiveness

of the Superfund Program, CERCLA Section 301(a) (l)(A] Study”(Washington, DC: Office of Emergency and Remedial Response,December 1984). These statistics include CERCLA-financed, en-forcement-lead, and responsible party actions.

Page 7: Chapter 3 A Systems Analysis of Superfund

The remedial aspects of the program, whichpertain to long-term cleanups, are occurringmore slowly. By the end of fiscal year 1982 onlyabout 60 remedial investigation and feasibilitystudies (RI/FS) had been initiated; but by theend of fiscal year 1984, 315 RI/FSs had beenstarted. l5 Remedial design has begun on 56sites. Six sites have been designated as clean.Of the remedial cleanup actions currentlyunderway or approved, most responses havebeen removal of hazardous materials for off-site disposal, or onsite containment, or both.Table 3-2 summarizes remedial actions takenfor 24 sites.l6

The institutional framework for respondingto uncontrolled sites is in place. Despite ini-tial problems, the program is beginning to oper-ate more swiftly and smoothly. Many moresites have moved into the RI/FS and designstudy stages, As more studies are completed,more sites will move into the constructionphase. However, only 30 percent of the 538sites now on the NPL are receiving remedialcleanup attention.

It is also necessary to understand what is be-ing done, and what the implications of currentactions are for the future. Most of the cleanupactions approved so far involve removal and/orexcavation, followed by offsite disposal. Al-though the facilities where Superfund wastesare taken are regulated under RCRA, these reg-ulations do not assure detection and preven-tion of groundwater contamination. There is

Table 3-2.—Summary of Remedial CleanupActions Approved

Cleanup actions approved Number of decisions.Removal/offsite disposal

with or without source control . 14Removal/offsite disposal with some

incineration . . . . . 1Alternative water supply . . . . . . . . . 3Alternative water supply with

treatment . . . . . . . . . . . . . . . . . . . . . . . . . . 2Treatment (1 aeration; 1 air-stripping). . . . 2Source control and onsite treatment . . . . 2SOURCE U S Environmental ProtectIon Agency, “The Effect weness of the Super

fund program, CERCLA SectIon 301(a) (1)(A) December 1984

Ch. 3—A Systems Analysis of Superfund ● 65

a strong likelihood that a number of RCRA fa-cilities may become Superfund sites, somemight even be able to qualify as Superfund sitesnow, and some already have.

This issue is examined in more depth inchapter 5 and leads to the conclusions thatremoval followed by disposal is not an effec-tive or efficient cleanup option, environmen-tally or economically, unless removed wastesare destroyed, detoxified, treated, or stabilizedin some fashion prior to redisposal.

Without the measures just specified, offsiteremoval will probably only relocate the hazardand transfer the risk. Furthermore, offsite re-moval usually leaves some (often considerable)residual surface waste in the form of contami-nated soil that can threaten groundwater. Off-site removal does not address problems ofgroundwater already contaminated at the site.While partial cleanups have been common,source control and containment have also beenused after removal to address groundwaterproblems, While the short-term costs of theseremedial methods often compare favorablywith other options, their long-term effective-ness can be greatly limited by site conditions,such as hydrogeology, rainfall, and geomor-phology. l7

Another response to groundwater contami-nation is to provide an alternative drinkingwater supply. (Note that water for other uses,such as bathing, often is not supplied eventhough health effects may be significant.)Sometimes this response is appropriate, for ex-ample when the alternate water is easily acces-sible and not too costly and when the affectedpopulation is not large. However, with ground-water now providing 50 percent of the Nation’sdrinking water, this can be a viable long-termalternative for only a limited number of sites.It is not an alternative for large populations.There is a limit to how many aquifers can beforesaken.

The groundwater problem is receiving atten-tion; EPA has recently established an Office of

1 TTh~; ~xper]ence at the Stri ngfe]]ow Acid Pits i]] ustrates manyof the problems that can arise with continued use of cr)nta i n-ment [see chapter 1],

Page 8: Chapter 3 A Systems Analysis of Superfund

66 • Superfund Strategy

Groundwater and developed a groundwaterprotection strategy. l8 The EPA has also ac-knowledged that groundwater contaminationat Superfund sites has not yet been extensivelyaddressed. When it is addressed, it will greatlyincrease the cost of the program,

The performance of cleanup actions duringthe last 4 years of the Superfund program donot support the use of the descriptive methodfor predicting future costs. The approved ac-tions are weighted heavily in favor of least-costoptions that are available now. While they areoften called proven, the long-term effectivenessof these options is highly uncertain, and theymay be ineffective even in the short term. Thetotal costs of cleanup using these technologiesare not accurately represented by the sum oftheir construction costs and first year operat-ing and maintenance costs, On the contrary,these options are likely to prove costly in thelong term. Additional remedial measures at theoriginal sites or at other redisposal sites maybe required as a consequence of the originalcleanup technology decisions. In a sense anenvironmental deficit is created for future gen-erations.

The final consideration is whether new, moreefficient technologies exist or can be devel-oped. The descriptive prediction method, rely-ing on historical cleanup decisions, assumeslittle technological change or improvement.OTA has found that there are substantial op-portunities to develop permanent, cost-effec-tive cleanup technologies (see chapter 6). Manyinnovative cleanup technologies, ranging frommethods of biological and chemical treatmentto thermal destruction show great promise, buttheir development and demonstration are ham-pered by several institutional problems, includ-ing the fact that the Superfund program hasnot recognized their potential long-term costeffectiveness.

Thus, when the state of knowledge is con-sidered, coupled with the experiences of the

l~FOr In Ore information see U ,S, Congress, Office Of ‘reChml-o~y Assessment, Protecting the Nation (lroundwater FromContamination, OTA-O-233 (Washington, DC: U.S. Governmentf)rinting Office, October 1984).

program and the potential for new technolo-gies, it is clear that projections of the costs ofthe Superfund program must be based on:

Ž a comparison of alternative strategies; and● future development, demonstration, and

use of innovative, permanent cleanup tech-nologies,

The desirability of defining a preferred long-term strategy becomes greater as evidence ac-cumulates that many more sites may needcleanup. The long-term costs of traditionalcleanup technologies, possibly acceptable witha relatively small number of sites, grows bur-densome as the number of sites rises–with thenumber going as high as 2,000, 10,000, or more,Policy and planning decisions based mostly onlow short-term costs may hamper programprogress, if site after site deteriorates and mustbe recleaned, and as still more sites are discov-ered, Under such conditions, the total cost andtime required to fulfill the Superfund mandatemay become unacceptable to society,

The need to reevaluate and perhaps definea new program strategy is not a new concept.It was suggested by William Hedeman, EPA’sSuperfund chief:

And it seems to me that the more fundamen-tal question that has to be asked is whetheror not the program and the structure and stat-utory base that has been established thus farto deal with this problem is really the mostsensible way to go. Whether indeed we don’thave as much of a national problem in the areaof abandoned hazardous waste as we had inthe 1930s and 40s in terms of flood control,or as we had in the 1970s with contaminatedair and contaminated water? And we haven’tinadvertently set into motion a system witha problem that is so convoluted and complexand difficult to manage that it could collapseof its own weight rather than accomplishingthe results that were ever intended?19

1g” A Conversation With Superfund Chief Bill Hedeman, ” TheEnkrironrnenta! Forum, August 1983.

Page 9: Chapter 3 A Systems Analysis of Superfund

Ch. 3—A Systems Analysis of Superfund ● 6 7

A SYSTEMS ANALYSIS APPROACH TO DEFINEA LONG-TERM STRATEGIC PLAN

Has the current Superfund program “inad-vertently set into motion a system with a prob-lem that is so convoluted and complex and dif-ficult to manage that it could collapse of itsown weight rather than accomplishing the re-sults that were . . . intended?” The critical steptoward developing a better program strategyis to realize that, in fact, the Superfund pro-gram, with its response mechanisms for threatsposed by uncontrolled hazardous waste sites,is a complex system,

The Superfund system can be viewed as aseries of interacting issues, conditions, anddecisions. The mechanics of the system are de-

picted in figure 3-1. The primary inputs arelisted in the box labeled issues/conditions.These include the potential number of Super-fund sites, public demands and perceptionsabout the threats posed by these sites, and thetechnologies available to deal with them. Allof these components affect Federal policy de-cisions.

Superfund policy decisions at the Federallevel define an upper limit on the resources tomanage the problem, provide the frameworkfor management, and set the goals of the pro-gram, Furthermore, Federal policy dictateswhat sites are eligible for consideration. For

Figure 3.1 .—Superfund System

Issues/conditions

Ž Potential numberof sites

— CurrentERRIS sites

— ActiveSubtitle Cfacilities

— Closed andactiveSubtitle D

● Existingtechnologies

● Existingqualifiedpersonnel

● Health andenvironmentaleffects data

. Public demandsand perceptions

● Responsibleparties

• State programsand funds

Federalpolicy

decisions

● Fund size andduration

● States’ sharerequirements

● Sites selectioncriteria

● Cleanup goals

● CERCLA enforce-ment and recovery

● RCRA rules andenforcement

● TechnologyRD&D

● Research oneffects fromhazardouswaste

. Technicalpersonnel

Programmanagement

decisions

● Number of siteseligible forfund (NPL)

• Measures ofimmediate andlong-term risk

● Method ofremedial tech-nology selection

● Application ofcleanup goalsat sites

● Allocation offund

Ž Oversight/guidance forcontractors,responsibleparties, andstates

● Selection ofinitialresponses

● Selection ofremedialcleanups

● Selection ofother actions

Program goals orevaluation

criteria

• Total cleanupcosts

. Duration

● Environmentalprotectioneffectiveness

. Equity/fund

SOURCE: Off Ice of Technology Assessment

Page 10: Chapter 3 A Systems Analysis of Superfund

68 • Superfund Strategy

instance, EPA has decided that sites with onlyenvironmental problems, which do not posethreats to human health, do not now qualifyfor Superfund attention, The Hazard RankingSystem has no component to account for nat-ural resource damages that do not affect hu-man health directly. Even though Congress didnot establish this policy, it did limit resourcesfor the program.

In addition, non-Superfund policy decisionsmay influence the Superfund program, For ex-ample, policy changes in the RCRA programfor hazardous and solid waste land disposal fa-cilities may alter the frequency at which newSuperfund sites enter the pool, depending onimprovements in prevention, detection, andcorrection of leaks and groundwater contam-ination. Federal policy also affects how the fi-nancial requirements placed on the States mightaffect the cleanup of facilities. Many sites mayfall into the 50 percent State matching sharecategory.

Broad Federal policies are eventually trans-lated into a program strategy via program man-agement policies. Management decisions onranking criteria and methodology determinewhich sites are included on the NPL. Programmanagement policies also govern the allocationof resources to eligible sites and define whichcleanup technologies are employed. These de-cisions are extremely complex because they,too, entail many interdependencies and inter-actions. For example, cleanup technology deci-sions are dependent not only on what technol-ogies are available and at what cost, but alsoon the availability of funds and qualified per-sonnel, the nature of cleanup goals, and thethreats posed by uncontrolled hazardous wastesites. Management decisions by EPA define thescope and form the strategy, even if uninten-tionally, of the cleanup program.

The resultant program strategy may in turnlead to secondary, long-term consequences thatalso affect the system, The remedial actionsalter the risks associated with the remediatedsites but, if they are not wholly effective, theymay impose future costs and risks. Decisionsto remove and dispose of waste offsite may

pose threats at other sites, which, in turn, mayresult in further demands on Superfund re-sources. Thus, current program decisions af-fect future system inputs and needs. The his-torical emphasis in the Superfund program hasbeen on detailed site-by-site analyses, with lit-tle, if any, analysis of intersite effects. This isone reason why responses have usually en-tailed offsite disposal. But cleanup on a site-by-site basis is not necessarily an effective na-tional cleanup. Considering each uncontrolledsite independently may also lead to inconsis-tency; sites posing similar risks in differentlocations may be dealt with differently. More-over, the long-term effects of all the interac-tions may not be obvious unless viewed sys-tematically.

The complexity of the Superfund programsuggests that projections of needs or changesof the program strategy should be tackled ina systems framework, using the discipline ofsystems analysis, With the interdependenciesand interactions defined, program strategies canbe evaluated more objectively and thoroughly,

Definition of Goals

An obvious Superfund objective is to mini-mize the cost of cleaning up uncontrolled sites.This goal raises an interesting question,namely, costs to whom? Focusing only on thecosts to the Fund can lead to distortions. Forinstance, long-term operating and maintenance(O&M) costs are the States’ responsibility. Con-cern with only the costs to the Fund, therefore,might emphasize cleanup technologies withlower capital costs even if the total cleanupcosts will ultimately be very high (and higherthan other options) because of high operatingand maintenance costs. Although the currentmethodology used in feasibility studies for se-lecting remedial action does deal with O&Mcosts, three points should be made. First, fund-ing estimates currently include only the initialyear of O&M costs regardless of estimatesmade in the feasibility studies. Second, the fea-sibility studies often choose optimistic esti-mates despite limited experience with the O&Mcosts of the remedial technology options, Fur-

Page 11: Chapter 3 A Systems Analysis of Superfund

Ch. 3—A Systems Analysis of Superfund Ž 69

thermore, limited experience with the applica-tion of the current technology options to haz-ardous waste problems coupled with undueconcern about short-term costs might lead totechnology decisions that fail to accomplish along-term, permanent remedy,

Thus, to prevent distortions, all expendi-tures—from the Fund, from the States, andfrom responsible parties—must be included inthe estimate of total long-term costs. This ap-proach is highly flexible. In considering alter-native or additional goals, the costs to specificparties can be derived, assumed, or comparedafter preferred solutions to the problem aregenerated, and the results can affect the cri-teria for the next iteration on the solutions.

If minimizing cleanup costs were the onlygoal, the solution would be to do nothing atzero cost. The goal that forces the program tooperate is maximizing effectiveness in protect-ing human health and the environment. In theCERCLA 301(a)(l)(A) study, effectiveness is re-lated to the “Government’s ability to respondto and mitigate the effects of releases of haz-ardous substances, ” This implies that effective-ness is the avoidance or mitigation of risks tohealth and the environment. This is thecongressional mandate.

One CERCLA provision specifies that reme-dial actions are to be chosen that:

. . . provide for that cost-effective responsewhich provides a balance between the needfor protection of public health and welfareand the environment at the facility under con-sideration and the availability of amountsfrom the Fund .. .20

According to this provision, cleanup actionsare supposed to be cost effective and, at thesame time, the Fund is to be allocated in a bal-anced fashion nationwide. The cost effective-ness criterion could be viewed as total programcost effectiveness as well as site-specific costeffectiveness. However, if affected by real orperceived budget limitations, choosing whatappears to be the most cost-effective way of

q: EK[, A, Sc(:t ion 104(r.](4)

dealing with each site individually could re-duce the cost effectiveness of the national sys-tem. The analysis in this chapter addresses theproblem of how to simulataneously achieve siteand national cost effectiveness.

The fund-balancing requirement raises acomplex issue of equity, costs, and effective-ness. Furthermore, without a reliable measureof effectiveness, there is no way to determinewhether a particular Superfund strategy is costeffective, nor can adherence to the fund-bal-ancing provision be evaluated (see chapter 4).

Another goal that has received limited atten-tion is minimizing the time required to com-plete the program. This goal is reflected in theidea of a mandatory cleanup schedule. Thelonger a site remains uncontrolled, the greaterthe risk may be. The risks may be the sameeach year and simply accumulate or they mightincrease over time as leaching progresses andas contaminants migrate further into the envi-ronment.

Whether or not total program length is a validmeasure for risk, the public perceives it assuch. For this reason, a Superfund programthat emphasizes permanent cleanup actionsmight still pose problems if it left sites, andtheir affected communities, waiting for clean-up for extended lengths of time (e. g., beyond50 years). Program length defines the planninghorizon for the program and, therefore, theperiod over which the costs and benefits ofeach program strategy should be evaluated.The effects of excluding longer term costs inthe planning horizon may be dramatic, as shownlater in this chapter,

Such goals—proper accounting of costs overtime, effective cleanup, and timeliness—can beused to evaluate different Superfund programstrategies and choose among them. BecauseFederal and program management policies de-termine the cleanup strategy, the evaluationprocess can elucidate how these policies affectthe performance of the strategy. Understand-ing the system dynamics can help to definehow Federal policy and program managementpolicy might change to improve program per-formance.

Page 12: Chapter 3 A Systems Analysis of Superfund

70 ● Superfund Strategy

Simulation: A Systems Analysis Method forComparing Two Strategies and Incorporating

Long-Term Uncertainty

Systems analysis can be used for simula-tion—a model that mimics events occurring inthe real system. In the context of the Superfundprogram, the primary event is a cleanup action.A wide range of policy and management deci-sions may alter the numbers, types, and ratesof occurrence of the responses. These decisionscan be tested using simulation for their effectson the performance of the system, In the dis-cussion that follows, the objective is to evaluatethe effects of the uncertainty in costs on pro-gram duration after a first site response andon total program costs under different programcleanup strategies.

Future Costs and an Impermanence Factor

The importance of examining the effects ofuncertain and unforeseen future costs associ-ated with a site cleanup cannot be overstated.As has been shown, effects of uncertainty aboutlong-term costs of cleanup technologies havenot been considered to any great extent, despiteevidence that the technologies typically em-ployed today may incur total costs significantlyin excess of their short-term costs. Programplanning based on short-term costs may resultnot only in an unexpectedly costly program,but in one that lasts over a very long time. Itis particularly important to evaluate the effectsof uncertainty on long-term cleanup costs be-fore more money is spent on costly remedialcleanups.

An “impermanence factor” is defined to re-flect the uncertainty of near-term cost estimatesfor response. Additional future costs, above thenear-term costs of “impermanent” actions,may be incurred due to the need for additionalactions, or operating and maintenance costs,or compensation for health and environmentaldamage. How the impermanence factor is in-tegrated into the model differs according to thecleanup strategy chosen.

Program Cleanup Strategies

Two extreme cleanup strategies are exam-ined. These interim and permanent strategiesare useful as boundary conditions, clarifyingthe importance of certain cleanup strategiestoward which the actual Superfund programcould move. A third strategy, a variation of thepermanent strategy and representative of thetwo-part plan described in chapters 1 and 2 isalso analyzed.

In the interim strategy, successive interim ac-tions, which are not permanent, are taken. Fu-ture costs are incurred and are a function ofthe impermanence factor and the cost of inter-im cleanup, In the basic permanent strategy,initial actions (with technologies and costs thesame as the interim actions of the interim strat-egy) are undertaken for the first 15 years of theprogram. Like the interim responses, initial ac-tions are impermanent, but no site receives asecond impermanent action. After 15 years,cost-effective permanent technologies are as-sumed available; permanent cleanups are thenperformed on all sites, both those never re-sponded to and those requiring a second ac-tion because of a previous impermanent action.Explicit in this strategy is the concept of con-certed but limited initial actions with plans for]ong-term permanent cleanup. Future costs inthis strategy are a function of the imperma-nence factor (from the early responses) and thecosts of permanent cleanups.

Under the two-part cleanup strategy, lesscostly, impermanent initial actions are per-formed (only once) on all NPL sites until per-manent cleanups are cost effective and avail-able. As in the basic permanent strategy, afterthe 15-year development period, permanent ac-tions are mandatory. In this variation, a largernumber of initial actions are taken, but they areless extensive, less expensive actions, thus pre-serving funds for developing and implement-ing permanent cleanup plans. This strategy isdiscussed later; the model description willfocus on the two primary strategies.

Page 13: Chapter 3 A Systems Analysis of Superfund

Ch. 3—A Systems Analysis of Superfund ● 7 1

Model Description

In OTA’s simulation model actions are under-taken annually; a particular class of actions—interim or initial—incurs future costs depend-ing on the degree of impermanence and the dis-tribution of costs over time.

The usefulness of the model lies not in pro-jecting actual Superfund program costs orSuperfund program duration, but rather in un-derstanding the dynamics of the system underuncertainty. The model tells us what mighthappen. To correctly interpret the results of themodel, the elements that characterize the sys-tem must be understood. In this modeling ex-ercise, these elements fall into two categories:1) system definitions and assumptions, and 2)uncertain elements to be tested.

The values of system definitions and assump-tions are specified and are not varied. This isdone because their behaviors and values areknown with relative certainty, or the uncertain-ty inherent in them is not suspected to influ-ence the aspects of the system being tested, orthe effects of the uncertainty can be easily in-tuited. Table 3-3 summarizes the system defini-tions and assumptions of the model. The sys-tem definitions, such as how the budget isallocated among the different sites, relate to thesystem as a whole. The assumptions about pa-rameters relate to specific cleanup actions.

The first definition given in table 3-3 is thenumber of uncontrolled sites eligible for theFederal fund; this figure changes as the NPLis revised periodically. Parameters such ascleanup costs and appropriate cleanup technol-ogy differed enough to warrant dividing thesites into two categories: those with only sur-face contamination and those with both sur-face and groundwater contamination. Thisbreakdown, and the costs for each class of site,correspond to early estimates by EPA.21 Thecleanup costs, $6 million for a surface cleanupand $12 million including groundwater reme-dial action, include only the short-term costsof those remedial technology actions currently

z 1 [].s, EnY, iro nrn~nta] ~]rote~tion Agency, ,$uperfund ‘~as~~“orce Pre/irninarJ Assessment, I)w,. 8, 1983.

Table 3.3.—System Definitions and Assumptions(not varied in model)

System definitions:● 546 sites currently (initially) eligible for Superfund money• Two categories of sites:

—Sites with only surface contamination—Sites requiring groundwater response and surface

response● 20°/0 of sites eligible for Fund use require groundwater

responsea

. Each annual budget is distributed between surface andgroundwater responses so that the same percentage ofsites of each type are responded to annually

Assumptions about parameters to be held constant:. Average interim action costs (estimates of currently used

technologies) b (for interim strategy and initial action ofthe basic permanent strategy):–$6 million/site for surface response only—$1 2 million/site including groundwater response

• Average initial action costs (for two-part strategy only):–$1 million/site for surface response only—$3 million/site including groundwater response

● Time required to complete actions:—3 years: Interim surface response—6 years: Interim groundwater response—3 years: Permanent surface cleanup—10 years: Permanent groundwater cleanup

a 56 percent of the N PL sites exhlblted groundwater contamination but only 23

percent were estimated to require treatment (U S Environmental Protect IonAgency, .%perfund Task Force Pre//mlnary Assessment, Dec 8, 1984) Groundwater releases have been recorded at 75 percent of the N PL sites For NPL s!teswhere releases have not yet occurred 90 percent had potential ground waterrelease scores over 15 and 70 percent had scores over 30 out of 45 These datasuggest that this IS a very conservative estimate

bAn average cleanup cost of about $9 m!lllon was given tn the 301(a)(l)(C) studyThts figure was for all types of cleanup actions (over 13 types) not accountingfor States’ shares, recovery and voluntary cleanup This est!mate correspondsto a 50 percent rate of sites requlnng groundwater cleanup

SOURCE Off Ice of Technology Assessment

used. These costs, therefore, are the averagecosts of interim responses. The model conserv-atively estimates that 20 percent of the siteswould require groundwater response, althoughmore than three-quarters of NPL sites havegroundwater problems,

A method of allocating a fixed annual budget(or total, unadjusted costs to all parties) to thesites is also defined. The annual budgets aredistributed to surface and groundwater responsesso that the same percentage of each type of siteis addressed. This allocation method may beoverly optimistic with regards to the attentionthat groundwater has received historically.22

ZZA statist i[; a] analysls perforrne~ on those s I t(; s for ~~’h I (:hmonies mere obligated prior to mid-l 983 revealed that sites withhigher levels of groundwater contamination, as reflected b~’ theirHRS scores, bore a negative relationship with Fund-finan[:edactions, See Haro]d C. Barnett, “The Allocation of Superfund,198(1-1 983, ” f)epartment of Economics, [Jniversitj of RhodeIsland.

Page 14: Chapter 3 A Systems Analysis of Superfund

72 ● Superfund Strategy

Only two NPL sites now have an active reme-dial program for contaminated groundwater.

Finally, because the program length is anevaluation criterion, certain assumptions abouttime are made. It has been estimated that theaverage remedial response takes 3 years tocomplete. 23 Since surface responses providemost of the experience, this estimate is in-creased to 6 years for groundwater actions.These estimates are for interim actions. Sinceno permanent cleanup has been implemented,its duration is speculative. It is assumed thatpermanent surface cleanups take 3 years tocomplete, and permanent cleanups of ground-water contamination take 10 years.

For those elements of the system that are ill-defined, different options are tested for theireffects on the system. A simulation scenariois defined by choosing one option for each ele-ment. These choices are summarized in table3-4.

Because this model could not consider site-specific data on risk and fund balancing, onlytotal program cost and total program length areexamined in any detail. Undiscounted totalcosts are used, but later an analysis of discount-ing is presented, While some of the followingfindings are deductive, others refer directly toparticular results from the scenarios tested.Complete scenario results are given in the ap-pendix to this chapter, along with a more de-tailed examination of the model.

The Interim Strategy

The primary element of uncertainty to betested is the cleanup strategy, The interim strat-egy assumes no permanent cleanup technologyis used; thus all cleanups are interim actionsand their short-term costs do not represent thetotal costs of dealing with the site or the wastes.Use of interim responses implies the need forinvolved operation and maintenance (O&M),the costs of which have not been included inthe short-term costs, The possibility of subse-quent and repetitive remedial actions involv-ing additional future costs and additional O&Mcosts also are not included, Interim actions in-—

““~~t~nt of the Ha~ar~ous Release Problem ~n(i Future Funcf -in~ ~twls, ~ IZ RC1.A Se~ti~n SO l(a)(l )(C) Study, ’ op. cit.

Table 3-4.—Summary of Simulation Scenarios(choose one from each element of uncertainty)’

Element of uncertainty: Options

Cleanup strategy:Ž Interim strategy— Interim actions result in repeated

future costs.● Permanent strategy—An interim action during the first

15 years results in a future cost, which is a permanentcleanup. Permanent cleanups start after 15 years andresult in no future costs themselves.

● Two-part strategy —Less costly initial response only (notmore than once per site) over first 15 years. Afterwards,if required, a permanent cleanup with no future costs.

Future costs of impermanent cleanup actions:Impermanence factor varied between O and 1.

Average permanent cleanup costs:1.$24 M—surface cleanup

$60 M—groundwater cleanup2.$12 M—surface cleanup

$30 M–groundwater cleanupTime distribution of future cleanup actions:

U. Future actions occur uniformly over 30 years after aninterim action.

E. Future actions occur ear/y, i.e., 5 years after an interimaction.

L. Future actions occur late, i.e., 30 years after an interimaction,

Budget:A. Initial period (5 yr) budget is $1.6B; growth @ 100°/0 each

successive period.B. Initial period (5 yr) budget is $1.6B; growth @ 10°/0 each

successive period.C. Initial period (5 yr) budget is $9B; growth @ 30°/0 each

successive period.D. Each period (5 yr) budget is $9B.S. Initial period (5 yr) budget is $5B; growth @ 100°/0 for

each of next 3 periods then @ 20°/0 for each successiveperiod.

Number of new sites per year for the first 15 years:0 . 0F. 100M. 200G. 200 for years 1-5; 800 for years 6-10; and 1,000 for years

11-15.aFor ~Xa~Ple, scenario IUAF has the following values option 1 for averwe Per’manent cleanup costs, option U for time distribution of future cleanup actions,option A for budget, and option F for the number of new s!tes per year Thescenarto is run for both strategies, the Interim and Permanent, and the lmper.manence factor IS varied in both strategies between zero and one

SOURCE. Of ftce of Technology Assessment

elude offsite disposal of wastes and contami-nated materials, and traditional onsite controland containment techniques.

To capture future costs, the impermanencefactor is used. This factor is itself uncertain,so values for the factor between O and 1 aretested in different scenarios. The imperma-nence factor averages the future costs of all in-terim actions over the whole system. (Note thatthe future costs of interim actions may vary

Page 15: Chapter 3 A Systems Analysis of Superfund

widely among the individual responses, butthis model can deal only with averages.) An il-lustration of how an average impermanencefactor might be derived from various cleanupactions is given in table 3-5.

The average impermanence factor can be in-terpreted in a number of ways. To illustrate oneinterpretation, suppose each initial interim sur-face response, costing $6 million, has an im-permanence factor of 50 percent (0.50). Thenthe second action required for each interim ac-

tion will cost only $3 million per site. But thissecond action will also be interim, and there-fore will result in a third response, at half thecost of the second, and so on. The result is adecreasing geometric series with a finite sum.That is, each interim action requires anotherinterim action, whose cost is related to the cost

of the previous action by the impermanencefactor. In other words, the sites slowly ap-proach cleanliness, or the repeated cleanupprocess finally becomes effective.

The second way to interpret the imperma-nence factor is that an interim action only hasa probability of requiring another interim ac-tion. If required, the future action will have thesame unit response cost. An impermanencefactor of 50 percent (0.50], in this case, wouldmean that half of all interim actions require anadditional interim action, In other words, outof 100 initial interim actions performed at a

T y p e

P a r t i a l r e m o v a l

P a r t i a l r e m o v a l

Table 3-5.— Illustration of How an

Cleanup actionsPercent

(off site disposal) 10

(offsite disposal) pluso n s i t e c o n t a i n m e n t 40

Onsite containment . . . . . 20Onsite containment/treatment . . . 20Alternative water supply or relocation

o f r e s i d e n t s 10

aRernal rider of s{tes have a zero Impermanence factor

SOURCE Off Ice of Technology Assessment

Ch. 3—A Systems Analysis of Superfund ● 73

cost of $6 million per site, 50 interim actionswill be required at the same unit cost, Thesein turn will result in 25 interim actions andso forth. (As before, cleanup of the system ofsites slowly becomes effective. ) More compli-cated interpretations that explicitly incorporatelong-term operating and maintenance costscould also be constructed. However, the modelmay underestimate such costs since they arerepresented as decreasing with time for imper-manence factors less than 1.

Another uncertainty is the timing of futurecosts. Because the program ends when the ex-penditures stop, it is necessary to investigatea number of alternatives. One option is that thefuture costs of an interim action occur uni-formly over 30 years after completing the ac-tion. The other options are that the future costsoccur every 5 years or every 30 years, choiceswhich represent optimistic and pessimisticestimates of the time over which interim re-sponses are effective. (Note that interim actionsare performed over time, so that the entire pro-gram lasts substantially beyond 30 years.)

The Permanent Strategy

For the permanent cleanup strategy, themodel assumes that permanent remedial tech-nologies for all types of site problems will beavailable in 15 years. (Some are available now. )

Average Impermance Factor of 0.5 Might Arise

Sites incurringfuture costs Contribution

to averagePotential source of Impermanence impermanence

future cost Percent a factor factor

Future action at disposal 50siteFuture action onsite

Future action at disposal 30siteFuture action onsiteHigh O&M costsFuture action onsite 75High O&M costs 50

Future action onsite 20

Average

2.0 010

1,5 0.18

1,0 0.150.5 0.05

1.0 0.02

mpermanence factor 0.50

Page 16: Chapter 3 A Systems Analysis of Superfund

74 ● Superfund Strategy

Technologies that might fall into this class arediscussed in chapter 6. Under this strategy, per-manent cleanups become not only available butmandatory after 15 years. During the first 15years only initial actions where an imperma-nence factor is applicable are used, but no fu-ture impermanent actions may follow, only fu-ture permanent actions. The number of initialactions depends on funding during the first 15years. Therefore, the effect of different budgetlevels is tested. When the permanent cleanupsbecome available, they are used on sites thathave never been treated as well as sites that re-ceived initial responses. The 15-year periodsimulates the time needed to develop and dem-onstrate more cost-effective permanent clean-up technologies, as well as other efforts to im-prove institutional capabilities (see chapters 1and 2).

Models and Reality

Systems models have been used in a varietyof disciplines to aid in planning and decision-making. Some models are dependent on natu-ral phenomena that are easily quantifiable; thisfacilitates the analysis of model results. Othermodels cannot be easily verified because theydepend on difficult-to-measure phenomena,such as behavior. The strategies modeled inthis analysis are of the latter type. Other modelscould have been chosen. Some might define theconcept of impermanence differently; othersmight have modeled impermanence in a more

complex way. To effectively use models, it isimportant to understand their assumptions andlimitations.

A basic assumption of the interim strategyis that there is no learning from experience.This assumption leads to drastic results, As thesystem’s average impermanence factor ap-proaches the value 1, total program costs andduration approach infinity, The model does notrepresent reality at average impermanence fac-tors of 1 or greater; in reality, program costscannot approach infinity. The program costsmay become very large, but in reality decisionswill be made to stop the program—any pro-gram—from approaching infinity. The interimstrategy does, however, represent a boundarycondition for what the future could be. Thelack of an explicit long-term strategic plan forthe uncontrolled site problem, and the contin-ued emphasis on remedial actions with sub-stantial unforeseen future costs suggest that theinterim strategy approximates current reality.The purpose of the modeling exercise is tocompare a strategy that emphasizes seeminglymore expensive cleanups that have low or high-ly predictable future costs (modeled here aszero) with one that follows the historical path.Even without such a plan, the cleanup programwill evolve and improve, but how long will theprocess take and what will be the costs? Theinterim strategy gives insights into these ques-tions by addressing the costs of not learningfast enough from experience,

USE OF MODEL AND FINDINGS

OTA has used its model to perform an anal-ysis of Superfund, not to attempt to design aprogram. Thus, it is only meant to be illustra-tive. Other models could be devised. Follow-ing are examples of how OTA’s model can beused as an aid to decisionmaking and the find-ings that it generates in terms of program costsand duration, Various scenarios under both theinterim and permanent strategies are com-pared and a variation of a permanent strategy

(representing the two-part strategy proposed inchapters 1 and 2) is illustrated. 24

Question: Is it possible that after taking aninterim cleanup action, each additional futureinterim cleanup action will cost as much ormore? That is, can a given class of interim

Z4Deta1]ed information on a]] components of ~rrA’s model, themathematical formulations, and how the results were generatedcan he found in the appendix to this chapter,

Page 17: Chapter 3 A Systems Analysis of Superfund

Ch. 3—A Systems Analysis of Superfund • 75

cleanup technologies have an impermanencefactor of 1 or greater? What would happen inthe long term under an interim cleanup strat-egy if this were true?

Findings: The experience of the Superfundprogram to date, although limited, suggests thatit is possible that second interim actions cancost as much or more than the first interim re-sponses. 25

If only interim cleanup technologies areavailable and if each additional interim action

costs as much or more than the first, the totalundiscounted program cost will be infinite andthe program will continue indefinitely (unlessterminated). It is unlikely that this would be thecase for all sites, but repeated, expensive, in-effective cleanup at even a few sites could haveserious consequences for the program.

Another possibility, however unlikely, shouldalso be mentioned: an interim technologymight accomplish little besides dispersing thecontamination, This might be appropriate atsome sites. Eventually, with extensive disper-sion, hazardous concentrations might becomelow enough to be regarded as acceptable or thetoxic substances might degrade. If this oc-curred, an interim cleanup strategy with an im-permanence factor of 1 or greater might resultin finite program cleanup costs and length.However, attempts at isolating hazardous wasteswould have to be abandoned and society wouldhave to accept the health risks that were pres-ent before very low concentrations of hazard-ous substances were attained, Furthermore,dispersion might increase exposure.

—~jr’or I nst a 11{ [~ ~t s! r I ngff;l ]oit’ a n ] nter i m remedial action Y$’a ~, ,,

tak\~Il to prc~[:nt ()~erfl{)w of (,onta m inated liquid into the com -munlt~ of (;I(;II ~Iron, ‘1’hf: action increased the capacit} of the\ itt: f I’(I m ah[)u t ~ million to 8.2 mill lon ~allons, Howr;\rer, this

Ia \() ‘‘I nc: r(~asml t hc (1 r i \ 1 ng ~)oten! ial for (:o nta m] na nts in the re-~ I (i (I a I \l LIdg[?+ a n (1 po II(I a 11 II ~’ iu m to leach i n to the u nderlyi n Hgrou ndwat cr. F’urth(~rm{Jre, the addition of lime and kiln dustto nl:utralizc matcrial~ at the site in(:reased the irnlumc of con-ta}n inat[?d soil. F’or thc~[; an(l [)thcr reason~, further cleanup atStr]ngfellt)w WII1 (Ix(.{!c(i the (,(~~t~ of the first interim action,((;f:orgf> ] ‘1’rt:zf~h, “ [;n~in[~f~rlng (;asc Stud} of the Strin~fcllowSlll)[’rf(][l{l Sit f~\, ” I ( ]nt ra(:t[jr \t tIfl~ prcpa rod for the office of‘1’[J( hn[)logt .~i~f~tsmcnt, Al]gu>t 1984, ]

Question: Will an interim cleanup strategyalways lead to infinite program costs andlength?

Findings: As long as the average imperma-nence factor is less than 1, the total cost andduration of the program will be finite becauseadditional future costs will decrease over time.Consider a case when the impermanence fac-tors for both interim surface and interimgroundwater cleanup are 5 percent (0.05). Thefirst interim surface cleanups cost $6 millionper site. Under the assumption that future ac-tions are required, 5 years after each interimaction, the second cleanups average $300,000per site. Ten years after the first action, the ad-ditional costs will be$15,OOO per site, and after15 years, only $750 per site. So after 15 years,

for all practical purposes, a permanent cleanupwill have been achieved by a series of four in-terim cleanups at a total cost of slightly over$6,300,000 per site. Similarly, the long-term un-discounted average cost per groundwater clean-up would be about $12,600,000.

These two costs can be thought of as the persite interim cleanup costs adjusted for futurecosts. Just as the cost of cleanup for one siteis finite, the total cleanup costs for all sites re-quiring remedial action are also finite. The timeit will take to complete the program also willbe finite but will be determined by several fac-tors, which will be explored later. Furthermore,depending on the costs of permanent cleanupsand preferences on program length, an interimcleanup strategy might be the preferred strategy.

Question: Based on evaluation criteria of totalprogram cost (to all sources, not just Superfund)and program length, under what conditionswould the interim cleanup strategy be prefera-ble to the permanent cleanup strategy?

Findings: Many of the assumptions listed intable 3-3 may affect the values of these two eval-uation criteria. But it is primarily the averagecosts of an interim cleanup technology classand permanent cleanup technology class, andthe impermanence factor (signifying the level

Page 18: Chapter 3 A Systems Analysis of Superfund

76 . Superfund Strategy

of future costs) that determine total programcost and length. For example:

Under some conditions the interimcleanup strategy is clearly preferable: whenfuture costs of interim cleanups are verylow (i.e., impermanence factors are verylow), and the cost of permanent cleanupsis high compared to the cost of interimcleanup. If health and environmental risksdo not exist or are small, it makes sensenot to spend money to develop and usepermanent cleanup technologies becausethe interim strategy costs less and the pro-gram progresses about as quickly.Under other conditions, the permanentstrategy is preferable, Even when the costsof interim cleanups adjusted for futurecosts are equal to the costs of permanenttechnologies, the interim strategy pro-gresses more slowly than the permanentstrategy, Because greater health and envi-ronmental risks may be incurred with thelonger program, the permanent strategy ispreferred.When the adjusted interim cleanup costsare higher than the costs of permanentcleanups, program costs under the interimstrategy skyrocket and the program pro-gresses much more slowly. Total long-termcosts and risks would be minimized by de-voting resources to the development anduse of permanent cleanup technologies.If the adjusted costs of interim cleanupsare moderately lower than those of perma-nent cleanups, there will be trade-offs be-tween program cost and duration; the per-manent strategy will cost more but pro-gress more rapidly, Strategy decisionswould have to be made based on other cri-teria, most importantly the reduction oravoidance of risk, which would favor thepermanent strategy.

Figures 3-2a and 3-2b illustrate how the im-permanence factor influences program clean-up costs and the time to initiate 90 percent of

the work26 underScenario 1UAF.specific at ions.)

each strategy, according to(See table 3-4 for scenario

With an impermanence factor of 15 percent(0,15), the program length under each strategyis the same. However, at this impermanencefactor the total program cost under the interimstrategy is about $18 billion, considerably lessthan about $32 billion under the permanentstrategy, Under Scenario 1UAF, then, for im-permanence factors less than or equal to therelatively low value of about 0.15, the interimcleanup strategy is preferable in terms of totalprogram cost and program length.

In contrast, in Scenario 1UAF, when the im-permanence factor reaches 0.76, the total costsof both strategies are equal, but the interimstrategy leads to a much longer—probably un-acceptably longer—program, Cleanup takesseveral decades with the permanent cleanupstrategy, but well over 100 years with the in-terim strategy, For impermanence factorsabove 0,76, the interim cleanup strategy costsrise rapidly; the cost, as well as the programduration become highly unfavorable.

In the range of impermanence factors be-tween 0.15 and 0.76, choices must be made be-tween program cleanup cost and programlength, For example, at 0.5 the permanent strat-egy costs $50.8 billion; under the interim strat-egy it is only $29.5 billion. The program lengthunder the interim strategy is, however, 8 3years, about double that of the permanent strat-egy (41 years), The trade-off between programduration and cost is $507 million for each yearthe program is shortened. If it were worth $507

million per year to eliminate the risks in theentire system (an average of only several hun-

~eF~r imp~rmanen(; e factors less than 1.(), the interi rn strat-egy represents a decay process. Thus, a progress percentile mustbe used to measure program duration. The progress percentileof 90 percent, used in the findings, is the number of years afterthe start of the program to initiate 90 percent of all the cleanupactions ultimately required. Results for progress percentiles arefound in the appendix,

Page 19: Chapter 3 A Systems Analysis of Superfund

Ch. 3—A Systems Analysis of Superfund ● 7 7

Figure 3-2a.— Program Length v. Impermanence FactorScenario 1UAF

120 I

110

100

90

I

I

80

70

60

50

40

30

20

i n

InterimIII

I

I1 I

0 0.2 0.4 0.6

Impermanence factorSOURCE Off Ice of Technology Assessment

0.8 1

140

120

100

80

60

40

20

Figure 3-2b.– Program Cost v. Impermanence FactorScenario 1UAF

Interim

Permanent

II

I I I 10 0.2 0.4 0.6 0.8 1

Impermanence factorSOURCE Off Ice of Technology Assessment

Page 20: Chapter 3 A Systems Analysis of Superfund

78 ● Superfund Strategy

dred thousand dollars per site per year), thenthe permanent strategy would be preferred.Knowing the risk consequences of interimcleanups is important to an intelligent programselection.

In general, as the impermanence factor rises,the cost advantage of the interim strategy (dol-lars saved for each additional program year)shrinks (see table 3-6). If 50 years is judged, forexample, to be the longest program the publicis likely to accept, then in Scenario 1UAF thepermanent strategy is always preferred for im-permanence factors greater than 0.3.

Knowledge about actual future costs is vitalto understanding the relative benefits of the dif-ferent strategies. As it becomes clearer that cer-tain cleanup technologies are impermanent(e.g., containment and land disposal), then theeconomic and environmental advantages of de-veloping and using permanent cleanups be-come clearer. Only with low impermanencefactors is the interim strategy advantageous.

Question: Since the costs of permanent tech-nologies are quite speculative, how wouldprogram strategy preferences change if theaverage costs of the permanent technologieschanged?

Findings: If the costs of permanent cleanupswere to decrease, as might happen over timewith experience or improvement, the perma-nent cleanup strategy is preferred to the in-terim cleanup strategy over a wider range ofimpermanence factors. The impermanencefactor at which the costs of both strategies isequal drops, narrowing the trade-off range. In

Scenario 2UAF, the cost of a permanent sur-face cleanup averages $12 million (versus $24million per site as in Scenario 1UAF) and thecost of a permanent groundwater cleanup is$30 million (versus $60 million). The results ofScenario 2UAF are given in figures 3-3a and3-3b. The point where costs are equal drops toslightly below 0.53, compared to 0.76 in Sce-nario 1UAF (see figures 3-2a and 3-2 b). Addi-tionally, where trade-offs occur (impermanencefactors between 0.1 and 0.53), the penalty forchoosing the permanent strategy, higher pro-gram cost, is reduced.

This static analysis of two different sets ofpermanent costs can be extrapolated to under-stand the effects of permanent cleanup costsdecreasing as the program gains experience(i.e., the “learning curve” effect). As cost-effec-tive permanent technologies are used more,program costs and duration both decrease.

The opposite may occur. If the cost of thepermanent cleanups were higher than antici-pated, the interim strategy would be preferredover a broader range of impermanence factorsand the differences in the costs of the two pro-grams over the trade-off range would be larger.

Certainly as the costs of permanent cleanupsdecline, the permanent strategy becomes moreappealing. If, however, permanent cleanupscosts are underestimated, there is a risk of in-correctly choosing the permanent strategy.

Question: How does the budget affect cleanupstrategy decisions and the evaluation criteriavalues under each strategy?

Table 3-6.–Scenario 1UAF

Average impermanence factor

0.1 0.3 0.5 0.6 0.7 0.8 0.9Interim strategy:Program cost (in billions) . . . . . . . . . . $16.4 $21.0 $29.5 $36.8 $49.1 $73.7 $147.3Program durationa (years). . . . . . . . . . 17 49 83 113 >140 >140 >140Permanent strategy:Program cost (in billions) . . . . . . . . . $31.4 $41.1 $50.8 $55.6 $60.5 $65.3 $70.2Program durationa (years). . . . . . . . . . 21 44 44 45Trade-off b ($ B/year) . . . . . . . . . . . . . . $1.256 $0.507 $0.269 <$0.119aMeasured by the time to start 90 percent Of the cleanup workbonly applied [n range where tradeoffs occur

SOURCE Off Ice of Technology Assessment

Page 21: Chapter 3 A Systems Analysis of Superfund

Ch. 3—A Systems Analysis of Superfund ● 7 9

Figure 3-3a. —Program Length v. Impermanence FactorScenario 2UAF

120

110

100

40I

30 I PermanentI

20 - - I1 110 I I

0 0.2 0.4 0.6 0.8 1

Impermanence factor

SOURCE Off Ice of Technology Assessment

Figure 3-3b .—Program Cost v. Impermanence FactorScenario 2UAF

140

120

100

80

60

Permanent40 -

20

0 0.2 0.4 0.6 0.8 1

Impermanence factorSOURCE Off Ice of Technology Assessment

Page 22: Chapter 3 A Systems Analysis of Superfund

80 ● Superfund Strategy

Findings: The size of the budget (for all rev-enue sources, not just Superfund) devoted tocleanup activity influences cleanup strategydecisions differently,” depending on the levelof the future costs of impermanent cleanups.Inadequate budgets can bias selection towardthe interim strategy and increase long-termrisks from cleanups.

If the adjusted costs of interim cleanups areequal to or greater than the permanent cleanupcosts, then the less spent on interim cleanupswhen permanent technologies are being devel-oped, the greater the program savings.

First, consider the permanent strategy. Dur-ing the first 15 years, only initial actions areundertaken. A higher budget during the earlyyears of the program permits more initial ac-tions and therefore results in greater total costs,The program costs under the permanent clean-up strategy with two different budget levels arecompared in figure 3-4. Over the range of im-

zTN~te that even though the budget continues to grow (for alloptions but D) through the duration of the program, after time,not all the available budget is used. Since future actions are takenonly as required, as they taper off, less and less money is re-quired.

permanence factors where the permanent strat-egy has the lower cost, program costs are great-er for the larger budget scenario (Scenario1UCF) than for the more limited budget sce-nario (Scenario 1UAF). While this suggests thatno initial actions be taken if future costs arevery high, recall that there are no explicit riskcriteria in this model. It may be necessary totake some interim actions to mitigate risk whenno permanent cleanup technology is available,or to consider other options, such as relocationof residents.

Now compare the interim strategy and thepermanent strategy, If the adjusted costs of in-terim cleanups are less than those of perma-nent cleanups, more confidence is needed aboutlow levels of future cost before a larger budgetis devoted to interim cleanups. This makessense: it is desirable to be more certain aboutthe effectiveness of a particular cleanup strat-egy before more money is invested in it. Theeffect of increasing the annual budget is dem-onstrated by comparing Scenarios 1UAF (lowbudget) and 1UCF (high budget) in figures3-2a and 2b and 3-5a and 5b. As the budget isincreased, the interim cleanup strategy leads

Figure 3-4.— Program Cost v. Impermanence FactorPermanent Strategy (Scenario 1UAF & 1UCF)

80

70

- - - - - - - — - - - - - - - - - - - - - -

60 —

50 “Low budget

II

40

I

30 —

I

20 I I I 10 0.2 0.4 0.6 0.8 1

Impermanence factorSOURCE :Office of Technology Assessment

Page 23: Chapter 3 A Systems Analysis of Superfund

110

100

90

80

70

60

50

40

30

20

Ch. 3—A Systems Analysis

Figure 3-5a.— Program Length v. Impermanence FactorScenario 1UCF

of Superfund ● 8 1

‘ - -

- -

IIIII

Interim

/ /

IIIIII

!II

I

I1

I 1.

10 I I0 0.2 0.4 0.6 0.8

Impermanence factorSOURCE Off Ice of Technology Assessment

140

120

100

80

60

40

20

Figure 3-5b.—Program Cost v. Impermanence FactorScenario 1UCF

Interim

. — — - — - —- -— — — - - — —- - - - -. - -

PermanentIIIIIIII

o 0.2 0.4 0.6 0.8 1Impermanence factor

SOURCE Off Ice of Technology Assessment

Page 24: Chapter 3 A Systems Analysis of Superfund

82 ● Superfund Strategy

to a shorter program over a narrower range ofimpermanence factors: up to 0.15 for the lowbudget scenario versus up to 0.10 for the highbudget scenario. The downward shift occursbecause the program duration is reduced underboth strategies as the budget increases.

Thus, an increased annual budget can affectcleanup strategy decisions. Similarly, reducingthe annual budget also can affect the strategydecisions. In particular, a lower annual budget(e.g., lower spending by Superfund and respon-sible parties) makes the interim cleanup strat-egy appear attractive over a wider range of fu-ture cost levels.

Spending less on unproven technologies isa logical way to conduct cleanups where manyuncertainties exist. However, this approach tostrategy selection does not eliminate the uncer-tainty of future costs or risks resulting fromprogram delay and inaction—it only minimizespotentially ineffective expenditures. It does notassure that the real future costs be reasonableor that the interim strategy is preferable. Fur-thermore, limiting this type of spending mayhamper the cleanup program. Therefore, pres-sures to limit expenditures on cleanup togetherwith uncertainty resolution or alternative plan-ning would be preferable. One answer is to usethe two-part strategy, as discussed below.

Question: Will a substantial increase in thenumber of sites affect cleanup strategy de-cisions?

Findings: As chapter 5 points out the num-ber of sites that will require cleanup is uncer-tain. An increase in the number of sites willobviously increase program costs and duration;in addition, increasing the number of sites tobe cleaned up exaggerates some of the abovefindings, Most notably, increasing the numberof sites without a comparable increase in thebudget has the same effect as a more con-strained budget. The consequence is that theinterim cleanup strategy is preferred, withmore uncertainty in future costs (i.e., over awider range of impermanence factors).

The program length under the interim clean-up strategy is more sensitive to the time dis-tribution of the required future actions than to

budget constraints. The converse is true of pro-gram duration under the permanent cleanupstrategy; program length will be extended pri-marily due to budget constraints. Therefore, aninterim cleanup strategy can be made to appearmore attractive than the permanent strategy bynot providing enough money fast enough.

Question: How would discounting futurecosts affect cleanup strategy decisions?

Findings: Discounting places more weight onnear-term costs and less on long-term costs. Forboth the interim and permanent cleanup strat-egies, as the impermanence factor increases,long-term costs become greater and are stretchedover longer periods of time. Therefore, as im-permanence increases, discounting reduces theprogram cost. Under the interim cleanup strat-egy, impermanent actions continue through thecourse of the program; however, under the per-manent strategy, future costs result only fromimpermanent actions taken in the first 15 years.For this reason, the interim strategy has greatercosts occurring later in the program. Thus, pro-gram cleanup costs under the interim strategyare more sensitive to discounting than are pro-gram costs under the permanent strategy.

Low and moderate discount rates affect strat-egy decisions by increasing the trade-off rangebetween the two strategies, The application ofa 2 percent per year discount rate to Scenario1ECO is illustrated in figure 3-6. The trade-offrange is extended because the impermanencefactor at which the present value of both theprogram costs is equal is shifted higher (from0.76 to over 0.85). Even though the range of im-permanence factors over which the permanentstrategy costs less is shortened, the programduration remains high so long that choosingthe interim strategy is difficult to justify,

As higher discount rates are applied, a deci-sionmaker becomes indifferent to the two strat-egies in terms of cost and prefers the perma-nent strategy because of its shorter length. Ata 10 percent per year discount rate, both strat-egies become almost insensitive to future costlevels. Figure 3-7 illustrates a 10 percent dis-count rate applied to Scenario 1ECO. Becausethe two cleanup strategies are similar over the

Page 25: Chapter 3 A Systems Analysis of Superfund

Ch. 3—A Systems Analysis of Superfund ● 8 3

Figure 3-6. —Program Costs v. ImpermanenceUndiscounted and discounted costs (Scenario 1ECO)

II

8

1 1 II II

I I0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1

Impermanence factor

- — - lnt D = OI n t e r i m I n t e r i m

s t r a t e g y s t r a t e g y

u n d i s c o u n t e d d i s c o u n t e d

at 20/0

SOURCE Off Ice of Technology Assessment

first 15 years, at very high discount rates thepresent value of both program costs do not dif-fer by much. Costs incurred beyond year 15contribute little to the present value cleanupcosts of either program. At high discount rates,the permanent strategy is preferred because itprovides a much shorter program,

This application of discounting is limited toprogram evaluation, It helps make long-termstrategic decisions. With this model, the stra-tegic decisions made with discounted futurecosts generally are the same as those with un-discounted costs; preference for the interimstrategy occurs only with certain and low fu-ture costs. No useful information for year-by-year financial planning is generated. Further-more, to accurately identify the total costs ofthe cleanup program, other factors such as in-flation and interest earned on cash balances,would have to be considered.

— Perm D = O ‘ -- Perm D = 2° o

Permanent Permanentstrategy strategyundiscounted discounted

at 2%

A Two-Part Strategy

What are the implications of these compari-sons between interim versus permanent clean-up strategies for a variation of the permanentstrategy with initial responses at all NPL sites(representing the two-part strategy describedin chapters 1 and 2)?

Under the two-part strategy, technologiessimilar to those defined as interim technologieswould be used for lower cost initial responsesthan those considered in the basic permanentstrategy, Initial responses are not designed tobe effective for long periods. The purpose ofthis cheaper, more limited response is to pre-vent sites from getting worse, and to controlnear-term releases of hazardous substancesinto the environment and, hence, exposures tothem. Low-cost initial responses are one partof interim, impermanent approaches now be-

Page 26: Chapter 3 A Systems Analysis of Superfund

84 ● Superfund Strategy

o 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1

Impermanence factor

-—- lntD = O .0000.00=- Int D = 10°/0Interim Interimstrategy strategyundiscounted discounted

at 100/0SOURCE Off Ice of Technology Assessment

ing described as cleanups. Low-cost initial re-sponses could include pumping to containplumes of contamination in aquifers, covers tokeep out water, excavation and temporary stor-age of wastes and contaminated soil aboveground (greatly reducing the use of below groundbarriers), and environmental monitoring. Incontrast to the current immediate removals,more money would be spent and removal ofwastes to operating land disposal sites wouldbe avoided.

A strategy of low-cost initial responses wouldachieve rapid risk reduction at many sites,thereby responding in an equitable manner topublic demands for protection and visible prog-ress. OTA’s modeling, however, suggests thatthe costs of initial responses should be low

— Perm D = O --- Perm D = 10°/0Permanent Permanentstrategy strategyundiscounted discounted

at 10%

(about 10 percent of permanent cleanup costs),and that they should be followed not by otherimpermanent responses, but rather by a per-manently effective response. In this strategythe conservative assumption is made that 90percent of all sites will need a permanentcleanup; that is, 10 percent of the initial re-sponses will subsequently be found to be suf-ficient.

In this variation of the permanent strategythe costs of initial responses are: $1 million persite for surface response and $3 million per siteto initially respond to groundwater contamina-tion, Additionally, to examine the effect ofmany more sites, after all sites are discovered,10,546 sites are to be cleaned and a higherbudget is allocated. (Table 3-4 defines Scenario

Page 27: Chapter 3 A Systems Analysis of Superfund

Ch. 3—A Systems Analysis of Superfund • 85

1USG.) This variation was compared with theinterim cleanup strategy under the same sce-nario.

The results are illustrated in figures 3-8a and3-8b. They show that at an assumed imperma-nence factor of 0.9, the total program cost ofthe two-part strategy is about $310 billion. Atan impermanence factor of about 0.73 in theinterim strategy, the two strategies have thesame program cost ($310 billion).

The two-part strategy is preferable to the in-terim strategy on the grounds of program dura-tion, except for impermanence factors underabout 0.25. If the impermanence of the interimresponses is greater than 0.73, then the two-part strategy is preferred both in terms of totalcost and program duration. When total pro-gram costs are the same for both strategies, theinterim strategy results in an unacceptably longprogram (longer than 100 years).

Strategy decisions between the two-part strat-egy and the interim strategy are interestinglyaltered if high discount rates are used. Withvery high discount rates, the present value ofprogram cleanup costs under either strategy

become insensitive to the impermanence of thecleanup response. The costs incurred in theearliest years of the program determine the(present value) program cost. However, sinceinitial actions are less costly than interim ac-tions, with high discount rates the two-partstrategy will result in lower discounted pro-gram costs, in addition to shorter programs,than the interim cleanup strategy. If there issufficient justification for a high discount rate,then the two-part strategy with low-cost initialresponses is preferable over all levels of imper-manence.

In summary, the two-part strategy used ini-tial (and emergency] responses as a first pri-ority for allocating program resources, with re-maining funds spent on permanent cleanupsat sites that have been “isolated, ” “decontrolled,”or “stabilized.” Exactly how funds would be al-located (the order of actions and cleanups)under this third strategy considering budget,qualified personnel, and technology constraintsis an extremely difficult problem. Its solutiondepends on the resolution of the cleanup goalsissue (see chapter 4) and a systematic approachto the problem that illuminates trade-offs.

CONCLUSIONS: PROGRAM PLANNING UNDER UNCERTAINTY

The results of the simulation exercise indi-cate that cleanup costs and program durationshow a high degree of sensitivity to a numberof uncertain factors. The potential effects ofplanning without considering these uncertain-ties also can be derived from the simulationfindings. The probability of adverse effects ofuncertainties could be limited in a carefullyplanned program, Table 3-7 presents the sourcesof uncertainties in the Superfund program asidentified by OTA, the dangers posed by plan-ning without considering them, and offers op-tions to mitigate their adverse effects.

Effectiveness and the Future Cost of Cleanups

A primary element of uncertainty is the ef-fectiveness of the cleanup responses and theirfuture costs. OTA’s findings indicate that it isdesirable to develop, demonstrate, and use per-manent cleanups if the effectiveness of the in-terim cleanup and its future costs are uncer-tain. The interim cleanup strategy is preferredonly if future costs are known to be small, Thisis because the interim strategy results in an ex-tremely long program (despite an advantage intotal cleanup cost) for a wide range of interim

Page 28: Chapter 3 A Systems Analysis of Superfund

86 ● Superfund Strategy

o

90

80

70

60

50

40

30

20

Figure 3-8a .—Program Length v. Impermanence FactorScenario 1USG

IIIII

II Two-partI ~

I iII

III I

I II II II I

1 00 0.2 0.4 0.6 0.8

Impermanence factorSOURCE Off Ice of Technology Assessment

Figure 3-8b.—Program Cost v. Impermanence FactorScenario 1USG

Interim

- - - - - - - - - — - - - - - - - - - - - — -

1 II

I I I I Iu 0.2 0.4 0.6 0.8

Impermanence factorSOURCE Off Ice of Technology Assessment

Page 29: Chapter 3 A Systems Analysis of Superfund

Ch. 3—A Systems Analysis of Superfund ● 8 7

Table 3-7.—Program Planning With Uncertainty

Dangers of planningwithout consideration of uncertainty

Effectiveness and future cost of cleanups:Inadequate funds and program infrastructure;

● Cleanup delays. Increasing risks and cleanup costs

Inefficient resource expenditures and cleanup choices:● Cleanup is not cost effective in the long term● Risks are aggravated rather than mitigated

Loss of public confidence

Number of sites requiring response:Inadequate funds and program infrastructure;

● Cleanup delays. Increasing risks and cleanup costs

Inefficient resource allocation:● Worst sites are not addressed

—Risks and cleanup costs increase—Cleanup delays

● Less hazardous sites are “over-cleaned”Loss of public confidence

Health and environmental effects:Inefficient resource allocation:

● Worst sites are not addressed—Risks and cleanup costs increase—Cleanup delays

● Less hazardous sites are ‘‘over-cleaned”. Ineffective technologies continue to be used

Loss of public confidence

Non-Federal money:Inadequate funds and program infrastructure:

● Cleanup delays• Increasing risks and cleanup costs

Inefficient resource expenditures and cleanup choices● Cleanup is not cost effective in long term● Risks are aggravated rather than mitigated

Discount rate:Inadequate funds:

● Cleanup delays. Increasing risks and cleanup costs

Inefficient resource expenditures and cleanup choices:Ž Cost effective responses not chosen. Risks are transferred,

SOURCE Off Ice of Technology Assessment

cleanup future costs. A mistake in estimatingfuture costs of interim cleanups carries thepenalty of a drastic, unanticipated, lengthen-ing of the program—and of a period of perhapshigh risk–under the interim strategy. For high-er levels of future cost, the interim strategy re-sults in both unacceptably high cleanup costsand program duration.

A program designed without considerationof cleanup response effectiveness and futurecosts is likely to result in a lack of money andinadequate program infrastructure. Even ifmore money is expeditiously provided, it is

Options to hedqe against adverse effects

Incorporate future costs and cleanup effectiveness incleanup strategy decisionsLimit costly impermanent cleanupsDevelop long-term strategic plan for developing andusing permanent cleanups

Consider all likely sources of sites; and potential forsites to enter program over long termDevelop long-term strategic plan based on revisedestimates

Ž “Recontrol” responses at maximum number of sites. Resolve cleanup goals sequentially as improved

information is available● Develop detailed strategic plan for long-term

permanent cleanups

● Use conservative estimates; refine estimates withexperience

• Exclude discount rate or use conservative discountrate; test sensitivity of cleanup strategy decisionsto rates

unlikely that the program infrastructure, or in-stitutional delivery system, will be able to growrapidly enough for timely responses. Indeed,a contributing factor to the slow startup of the1980 program was simply the time required fororganization and staffing. Further delays in thecleanup program may result in site deteriora-tion and increasing risks. In turn, the costs ofcleanup may escalate, impose greater financialburdens and delays; a crisis situation could en-sue, In EPA’s words, the program could be“overwhelmed. ” In addition, delays in cleanupand the use of ineffective cleanups may con-tribute to loss of public confidence.

Page 30: Chapter 3 A Systems Analysis of Superfund

88 ● Superfund Strategy

To deal with uncertainty about cleanup ef-fectiveness and future costs, more realistic esti-mates can be used. For instance, life-time orlife-cycle O&M costs could be included incleanup cost estimates. The implications of in-corporating realistic O&M costs can be signif-icant, EPA has estimated average annual O&Mcosts at $400,000 per site, The average Federalcleanup cost per site, less the first year O&M,is about $7.5 million, This is comparable to theaverage cleanup costs used in the model whichshows that if O&M costs are the only futurecosts of interim cleanup, and are incurred overonly 5 years, then the corresponding imperma-nence factor is about 0.27. Thus, the inclusionof realistic O&M costs can reduce the marginfor error.

Number of Sites

The number of sites that will ultimately re-quire cleanup is another source of uncertaintywhich, if not adequately taken into account,could seriously impact the cleanup program.Insufficient money and an underdevelopedprogram infrastructure could result from over-ly optimistic (under) estimates of the numberof sites to clean, The program grows too slowlyfor effective response and further delays resultin site deterioration and increasing risks, in-creasing costs, further delays, and loss of pub-lic confidence.

Health and Environment Effects

Although health and environmental issuescould not be incorporated into OTA’s simplemodel, high uncertainties of their effects existand their importance is felt in making trade-offs, If health and environmental effects are notbetter understood, and cleanup goals betterdefined, any program will potentially misallo-cate resources. Without effective cleanup goalsit is difficult to judge the effectiveness of clean-ups, A rush to “cleanup” sites by, for exam-ple, mandating cleanup schedules, before goalsare established could result in too many initialresources being devoted to: 1) the use of inef-fective technologies; and 2) the less hazardoussites, depriving worse sites of attention.

One reliable way to plan with uncertaintiesin a dynamic system is to resolve the cleanupgoal issue sequentially, incorporating new in-formation as it becomes available, while tak-ing more limited initial responses, and “recon-troling” a maximum number of sites. At thesame time, other initiatives should focus onplanning for more extensive, permanent clean-ups that will be needed at some sites, andwhich can be accomplished gradually.

Non-Federal Money

How much of cleanup costs will be providedby potentially responsible parties (PRPs), in-come from cost recovery, and States’ shares?EPA estimates it will recover 47 percent forremovals and 30 percent for remedial actions(see table 3-1).

The limited experiences of the program sug-gest that lower contributions will be received.As of September 30, 1984, cost recoveries havetotaled $6.6 million, less than 1 percent of totalobligations and disbursements toward hazard-ous substance response.28 One cause of thesehigh estimates is the assumption that rates ofrecovery will be comparable to those for earlyremovals conducted under the Clean Water Act.

Direct cleanup actions by responsible partiesare projected by EPA at 40 to 60 percent, Sim-ilarly, estimates from GAO range from 29 to44 percent for RP lead activities (see table 3-1).The uncertainty of both these estimates maybe heightened by the much larger numbers ofsites and sums of money that could be involved.Additionally, it might be expected that it willbecome more difficult to identify some respon-sible parties as the program progresses andolder, abandoned sites are identified, Whilemany sites in the larger estimate maybe small-er, industrial surface impoundments, whichmay have associated with them lower remedialcosts and fewer (often single), identifiable re-sponsible parties, others may be large munici-

Z8U. S. Environmental protection Agency, “Hazardous SUb-stance Response Trust Fund Receipts, Obligations, and Dis-bursements, CERCLA Sections 301(a)(l)(B) and (D)” [Washing-ton, DC: Office of Solid Waste and Emergency Response,December 1984).

Page 31: Chapter 3 A Systems Analysis of Superfund

pal landfills. This broader, more costly aspectof the program may stress the States’ willing-ness to provide their matching shares of con-struction costs.

Discount Rate

The differences between present and futurevalues of cleanup expenditures and risks resultfrom uncertainty over future values of money,inflation, and risks. Cleanup costs and risksmay occur over a period of decades. Discount-ing is used in program evaluations and plan-ning to adjust the costs and risks to presentvalue. The discount rate, an expression of thetime value of money, should reflect how societyvalues current versus future consumption.

To illustrate how costs and risks might be val-ued differently over time, consider a decision-maker faced with the choice of a program thatcosts $5 billion now and $5 billion over the next20 years and a program that costs $10 billionnow. The choice might be simplified if it couldbe shown that the $10 billion program reducesrisk more over the next 20 years and if a relia-ble dollar number could be calculated for therisk reduction. However, in reality, the differ-ence in risk reduction associated with programoptions is rarely simple.

Controversy arises over the choice of discountrates for public investrnents.29 One school ofthought holds that society should have a longerplanning horizon than individuals, which meansthat public discount rates should be lower thanprivate rates, Furthermore, since future gen-erations have no way to express their prefer-ences, an unimaginative society may err on theside of too high discount rates, from the point

-— —z~~~[)r ~)rli,~lte s~c;tor jnkestrnents, the discount rate is apJ]lied

t{) kno~tn in~estmeni costs and anticipated benefits, both ofwrhi(:h (:an u~ually be (.a]culated easil~’ in dollars. The appro-j)riate dit(:ount rate is usuallj’ the corporate internal rate of re-turn on capital or the rate of return on alternative in~’estment(J~)pf) rtll n it if:s.

Ch. 3—A Systems Analysis of Superfund ● 8 9

of view of their descendants. Many would arguethat this is happening now.

OTA makes no attempt here to resolve theseissues. However, discounting often has utility,and the selection will influence the allocationof resources, the level of social welfare, andcleanup strategy. If the discount rate is too highthe Superfund program may be underplanned.

Means to Address Uncertainties

The potential risks arising from uncertaintycan be mitigated in several ways. Clearly, re-solving the uncertainties would be the most ef-ficient approach, Resources can be devoted tolearning how many sites will require cleanup,understanding health and environmental risks,developing cleanup goals, and deciding on arealistic, achievable level of non-Federal con-tributions. However, the cleanup program cannot wait for total and perfect knowledge. Rath-er, the program plan should be sequentially re-fined as new information is available.

The effectiveness of currently used cleanuptechnologies and the extreme sensitivity of pro-gram duration and cost to these uncertaintiessuggest that efforts are needed to develop per-manent cleanup technologies. Limited initialresponses in the near-term make economic andenvironmental sense only if they are part of along-term, flexible strategic plan whose goal ispermanent cleanup. Otherwise, public confi-dence will not be obtained.

There are intrinsic conflicts between maxi-mizing the number of limited initial responses,and their effectiveness over time, and keepingtheir costs low to save enough money for ex-pensive permanent cleanups. In addition, therewill be competition for money and people forresearch, demonstration, and use of permanenttechnologies, and enforcement. Furthermore,a method to allocate and schedule cleanupsefficiently must be part of a long-term strate-gic plan,

38-745 0 - 85 - 4

Page 32: Chapter 3 A Systems Analysis of Superfund

90 ● Superfund Strategy

APPENDIX A

This appendix provides detailed information onthe mathematical formulations and assumptionsused in OTA’s model discussed in chapter 3.

Undiscounted Program CostDefinitions of Cleanup Strategies

If costs are not discounted, total program costscan be derived without the use of simulation. Threestrategies are defined and discussed in terms ofcosts and cost comparisons.

Interim Cleanup Strategy

The total undiscounted program costs adjustedfor future costs, TCI, under the interim cleanupstrategy can be expressed mathematically as:

T CI = CIX + iCIX + i2C IX + i3C IX + i4C IX + . . . (1,1)

where:C I = average near-term cost of an interim action.X = number of s i tes to clean up.i = average system impermanence factor of interim

actions.In equation (1.1), the first term is total near-term

costs of interim actions. The remaining terms, whichcons t i t u t e a geome t r i c s e r i e s , r ep re sen t t o t a l f u tu r ecosts of al l future act ions. (It s h o u l d b e n o t e d t h a tif O&M costs are included in i , they may be under-s t a t e d i f i < 1 , s i n c e t h e t e r m s d e c r e a s e , ) F o r a l li < 1 , t h i s s e r i e s c o n v e r g e s , s o t h a t :

T CI = CIX/(l -i) (1.2)

T h u s , t h e a v e r a g e a d j u s t e d c o s t p e r s i t e u n d e r t h ei n t e r i m s t r a t e g y i s :

A v g ( T C I) = C I/(1-i) (1.3)

Equation (1.2) elucidates the use of the imperma-nence f ac to r i n t he i n t e r im s t r a t egy . Rea r r ang ing

t e r m s r e v e a l s :T CI = CIX + iTCI (1.3a)

The total cost of the interim strategy is composedo f t h e t o t a l n e a r - t e r m c o s t , CIX, p lus to t a l fu tu rec o s t s , i T CI. I n t h e m o d e l , h o w e v e r , e q u a t i o n ( 1 , 2 )w a s o n l y u s e d a s a t o o l f o r t e r m i n a t i n g s c e n a r i o st h a t e x c e e d e d c o m p u t e r m e m o r y . A c t u a l c o s t c a l -culat ions were made on the basis of equation (1.1) .C l e a r l y , n o s c e n a r i o w i t h a s y s t e m i m p e r m a n e n c efactor equal to or greater than 1 was run since, on

the basis of either equations (1.1) or (1.2), total costw i l l be i n f i n i t e .

Basic Permanent Cleanup Strategy

The total undiscounted program costs adjustedf o r f u t u r e c o s t s , T CI, u n d e r t h e p e r m a n e n t c l e a n u ps t r a t e g y c a n b e e x p r e s s e d m a t h e m a t i c a l l y a s :

T CP = CIYX + CpiYX + CP(1 - Y)X (1.4)

w h e r e :

C P = average cost of a permanent act ionY = percent of all sites addressed by an initial action

during the first 15 years of the program. This per-centage will be dependent on funding availabil-ity during the 15 years.

T h e f i r s t t e r m i n e q u a t i o n ( 1 . 4 ) r e p r e s e n t s n e a r -t e r m c o s t s o f t h e i m p e r m a n e n t i n t e r i m a c t i o n s t a k -en in the first 15 years. In the basic permanentcleanup strategy, the interim actions are the sameas the interim actions under the interim strategy:the technologies are the same, the costs are thesame, and the impermanence factor is the same.The second term is the future costs of initial actionsrelating to the need for second but permanent ac-tions. This term may misestimate total costs sincepermanent cleanup costs after an initial action maybe more or less than costs of permanent cleanupsat sites that have had no response, The last termis the costs of permanent cleanup at sites that haveno response. The average cost per site under thepermanent cleanup strategy is:

(1.5]

Two-Part Strategy

The two-part strategy is a variation of the perma-nent strategy and differs from the basic permanentstrategy in that the initial responses are not neces-sarily the same as those of the interim strategy, Theunit cost is less for an initial response than for aninterim response. Therefore, the impermanencefactors may be different for initial responses andinterim responses. The total cost of the variationof the permanent strategy, TCPV, may be ex-pressed as:

T Cpv = C I VYX + Cp ivYX + CP(l - Y)X (1 .6)

where:c

IV = average near-term cost of an initial action.

iV—— impermanence factor for ini t ial act ions.

Page 33: Chapter 3 A Systems Analysis of Superfund

New Sites

In all of the strategies, new sites are discoveredduring the first 15 years of the program. These sitesmay be responded to in the following year. Slightdeviations from the above cost formulae occur asa result of sites entering the system in the 15th year.In the basic permanent strategy and the two-partstrategy, these sites only receive permanentcleanups.

Cost Comparisons of the Interim andBasic Permanent Strategies

Since the interim actions considered in the inter-im and basic permanent strategies are identical,equations (1. 1) and (1.4) can be equated and solvedfor in terms of i. The impermanence factor at whicheither total program costs or average program costsare equal under either strategy, i*, is called the crit-ical impermanence and is expressed as:

,*1 = 1 - CI/CP (1.7)

At this impermanence factor, we are indifferentto the cleanup strategies, on a cost basis. For all i< i*, the interim strategy is preferred if only costis considered and duration [discussed below) is ig-nored. For all i > i*, the permanent strategy is un-ambiguously preferred.

Cost Comparisons of the Interim andTwo-Part Permanent Strategies

The difference between the interim actions of theinterim strategy and the initial actions of the two-part permanent strategy demand a different costcomparison method than that stated above. Givenequations (1. 1) and (1.6), a total cost for the two-parts t r a t e g y c a n b e b a s e d o n a s p e c i f i c v a l u e f o r iV .

T h e i m p e r m a n e n c e f a c t o r f o r t h e i n t e r i m s t r a t e g y ,i , c a n t h e n b e d e t e r m i n e d a n d r e s u l t s i n t h e s a m eto t a l co s t . I f t he impe rmanence f ac to r f o r i n t e r ima c t i o n s i s a b o v e t h i s l e v e l , t h e n t h e t w o - p a r t p e r -m a n e n t s t r a t e g y i s u n a m b i g u o u s l y p r e f e r r e d .

Program Duration With UncertainTechnology Effectiveness

While undiscounted program costs can be de-rived mathematically, simulation must be employedto determine program duration under each strat-egy and to determine the effects of discounting,which is time dependent, on cleanup strategy deci-sions. A simulation model, programmed using LOTUS1-2-3, was developed to mimic cleanup actions, theimpermanence of those actions, and additional ac-

Ch. 3–A Systems Analysis of Superfund

tions resulting from impermanence, over time,

● 91

Thefollowing discussions are focused on the interimand basic permanent strategies. While the discus-sions are related to the two-part permanent strate-gy, modifications in analysis would have to bemade.

Impermanence Factor

In the model, two impermanence factors wereused: i(sc), the impermanence factor for interimsurface actions, and i(gw), the impermanence fac-tor for interim groundwater actions. This break-down is consistent with previous calculations sincethese two cleanup types are assumed to be inde-pendent of one another. The independence assump-tion may compound the conservative estimate ofthe percent of sites requiring groundwater response(20 percent) since it does not permit sites with sur-face contamination to deteriorate in a way thatcauses groundwater contamination. In fact, surfacecontamination often leads to ground water contam-ination. If, however, the impermanence factor forsurface contaminated sites is high, it may capturethe future costs associated with deterioration. Totalprogram costs under the interim strategy can be ex-pressed as:T CI = C I s c - Yg w) X / ( l - i ( s c ) )

+ C I g w( Yg wX)/(l - i(gw)) (3.1)

where:c

I s caverage near-term cost of an interim surfaceaction.

c Igw = average near-term cost of an interim groundwa-ter action.

Y gw = percentage of all sites requiring groundwater re-sponse.

Similarly, total program costs under the perma-nent strategy are:T CP = C Isc Y(l-Y gw )X + CIgw YX gwX

+ CPSC(l-YYgw)(i(sc)Y + (1-Y))X+ C p g wY g w (i(gw)Y + (1-Y))X (3.2)

where:c Psc = average cost of a permanent surface action.c Pg-

. average cost of a permanent groundwater action.w Separability of costs relating to surface actionsand groundwater actions permits the derivation ofindividual critical impermanence factors, i*(sc)and i *(gw), the impermanence factors where costsassociated with surface actions and groundwateractions, respectively, are equal under either strat-egy. These are:

i*(sc) = 1 - CIsc/CPsc (3.3a]

i*(gw) = 1 - C Igw/CPgw (3.3b)

Page 34: Chapter 3 A Systems Analysis of Superfund

92 . Superfund Strategy

The composite or average impermanence factorcan be determined from equations (3.3a and b). Forexample, the average critical impermanence fac-tor, i*, can also be expressed as:

i*= i*(sc)(l - YgW) + i*(gw)Ygw (3.4)

The simulation was verified using equations (3.3a,b,and 3.4). These results are discussed and were alsoused to ascertain program durations when the un-discounted program costs of both strategies wereequal.

Base Case Simulation

To model the system, various system definitionsand assumptions about model parameters are re-quired. These model definitions (presented in table3-3) represent conservative estimates of their realworld analogs.

To calibrate the model, a base case is generatedwhere the uncertain estimates are defined to closelymatch current real world estimates. Although it isincorrect to use the term interim cleanup strategyif the impermanence factor is zero, simulation ofthis case provides a base case and comparison withcurrent EPA estimates of program costs and length.The zero impermanence assumption appears to beconsistent with EPA’s exclusion of future costsfrom cost estimates for currently used technologies.Budget options A and C were the lowest budgetsthat gave base case program durations similar toEPA estimates (see table A-l).

Uncertain Assumptions and Model Sensitivity

To determine program durations under each strat-egy, it is necessary to make assumptions about theimpermanence of interim actions, the number of

sites that will require cleanup, the annual budgetdevoted to cleanup actions, how the budget is allo-cated among sites, when future costs are incurred,average costs of permanent technologies, and dis-count rates. The performance of each strategy wastested under different scenarios defined in table3-4. The goal of this exercise is to clarify a cleanupstrategy toward which the Superfund program couldmove if there is uncertainty about the permanenceof currently used technologies. If the model is over-ly sensitive to some assumptions (namely, when thefuture costs occur, the annual budget, the costs ofpermanent technologies and discount rates), thenfew if any general unqualified statements can bemade about cleanup strategy decisions under un-certainty, If, however, the results remain generallythe same while each element of uncertainty is var-ied, then the model can provide meaningful con-clusions about cleanup strategy decisionmaking.First, the methods of incorporating these assump-tions into the model are discussed; the sensitivityof the model to these assumptions follows.

Assumptions About Timing

While the assumptions about how long it takesto perform an interim cleanup are founded in ex-periential data, little data exists on which to baseassumptions about how long after an impermanentaction future costs are incurred, That future costsdo, indeed, result from impermanent actions hasnot been recognized much less quantified. The sen-sitivity of the model to assumptions about the tim-ing of future costs was tested, Three options wereused: 1) early occurrences (every 5 years), 2) lateoccurrences (every 30 years), and 3) occurrencesuniform over 30 years. In the early option, there

Table A-1 .—Comparison of Simulation Base Case With Current Estimatesa

EPA (1984) EPA (1983) Base caseTotal costs (billion) . . . . . . . . . . . . . . . . . . . . . . . . . $7.6 -$22.7Projected time to clean sites . . . . . . . . . . . . . . . . NANumber of sites. . . . . . . . . . . . . . . . . . . . . . . . . . . . 1,500-2,500Total average cleanup cost per site , . . . . . . . . . . $8.84’

Percent of sites requiringgroundwater response . . . . . . . . . . . . . . . . . . . . NA

Average length of response . . . . . . . . . . . . . . . . . NA

$10.3 -$20.614 years for 1,800 sites1,400-2,200$6 M$12 M including groundwater

response

23-560/o3 yearsd

$14.716-17 yearsb

2,046$6 M$12 M including groundwater

response

20%3 years6 years including

groundwater responsea For sources and additional information see table 3.1 of this chapterbRange corresponds to Budget Options A and CcDoes not Include tnltlal remed!al measuresdu s Environmental ProtectIon Agency, “CERCLA 301(a)(l)(c) Study, ” draft, December 1984

SOURCE As noted

Page 35: Chapter 3 A Systems Analysis of Superfund

would be rapid response and early information onthe level of impermanence. The late option corre-sponds to the 30-year period required under RCRAfor post-closure care of disposal facilities. The uni-form distribution reflects that sites and cleanupswill vary.

Some Examples of Timing

The mathematical formulation follows, but sev-eral simple, nonmathematical examples are givenfirst.

(I) Assume the interim strategy, surface cleanupsonly, with an impermanence factor of 0.5, and the5-year timing option. Then, of every 100 primarycleanups started in year 1 of the program, there willbe 50 secondary cleanups at the same cost as theprimaries (or 100 secondaries at half the cost of theprimaries) started in year 9 of the program, and 25tertiaries at the same cost as the primaries (or 100tertiaries at one-quarter the cost of the primaries)started in year 17 of the program. The secondariesare started in the ninth year of the program, ratherthan the sixth, because they are started 5 years afterthe completion of the primaries, and it takes 3 yearsto perform a surface cleanup.

(II) Assume the interim strategy, surface clean-ups only, impermanence factor of 0.5, and the uni-form timing option. Then, 120 primary cleanupsstarted in year 1 of the program will be followedby three sets consisting of: a) 10; b) 20; and c) 30secondaries at the same cost as the primaries (or:a) 20; b) 40; c) 60 secondaries at half the cost of theprimaries) which will be started in years 9, 19, and34 of the program. That is, the “uniform” distribu-tion is not continuously uniform, but is clumpedi n three bunches. (This choice was made for easeof computing; a more accurate representation of adiscrete uniform distribution using more and small-er intervals could have been used with a faster com-puter. ) Note also, that tertiary and higher order ac-tions following early secondary cleanups overlapwith later secondary cleanups of the same primaryset.

(III) Assume the permanent strategy, with surfacecleanups only, and impermanence factor of 0.5 andthe uniform timing option. This means that, if 120initial responses are started in year 1 of the pro-gram, 10 require a future action in year 9, 20 in year19, and 30 in year 34; these 60 sites are slated forpermanent cleanup. The sites that require addition-al action in year 9 cannot be addressed until year15 or later; they go into a pool of sites that will re-ceive permanent cleanup in the future.

Ch. 3—A Systems Analysis of Superfund . 93—

How the Model Handles Timing, Mathematically

Future costs are incorporated into the model bypooling future action requirements. Let Fsc (t) andFgw(t) denote the costs of future actions that be-come necessary at time t due to previous interimsurface and groundwater actions, respectively. LetX sc(t) and Xgw(t) indicate the number of interimsurface and groundwater actions started in yeart. For future costs incurred on the early schedule,the undiscounted costs of actions that enter the poolfor future action in year t are related to previousactions so that:

(4.1a)

(4,11))

The 8-year lag in future costs for interim surfaceactions reflects the 3 years required to complete theaction and the 5 years after that before which futureactions are required. Similarly the 11-year lag forinterim ground water actions includes 6 years tocomplete the action.

If the future actions are required after 30 years,the lags become 33 years for interim surface re-sponse and 36 years for interim groundwater re-sponse, so that:

(4.2a)

(4.2b)

For future actions that are required on a 30-yearuniform schedule, the time distribution is repre-sented discretely in the model, with costs incurred5, 15, and 30 years after completion of the interimactions. The undiscounted costs of actions requiredin year t are related to previous actions as:

As before, the lags of 3 and 6 years reflect com-pletion time for interim surface and groundwaterresponse, respectively,

In all of the cases above, the future costs of aninterim action are a function of the number of ac-tions taken, the costs of those actions, and their im-permanence.

In the permanent strategy, impermanence of theinitial actions results in permanent response. Let

actions taken in year t due to previous imperma-nent actions, The future costs associated with theinitial actions can be represented mathematically’in a way similar to equations (4.1a-4.3b), depend-ing on the time distribution of future actions. For

Page 36: Chapter 3 A Systems Analysis of Superfund

94 ● Superfund Strategy

example, if future actions are required under theearly time distribution, they are:

Psc(t) = i(sc)CPscX sC(t -8 (4.4a)

P g W(t) = i(gw)CP g W X g W(t -11 (4.4b)

In this case, costs resulting from impermanentactions are a function of the number of imperma-nent actions taken, the impermanence of those ac-tions, and the costs of permanent cleanup.

Comments on Timing

The assumptions about the time distribution offuture actions may directly determine the programduration, although it is typically these assumptionstogether with budget assumptions that do so. If thebudget is large enough, and grows quickly enough,then the bulk of the cleanup efforts can be achievedearlier in the program. However, the results of im-permanent actions linger. For instance, if therewere no budget constraints, under the permanentstrategy all initial responses would be taken in thefirst year. The latest future groundwater actionsthat would result from these impermanent actionswould be dealt with in the 37th year (6 years to com-plete the action and 30 years until additional ac-tion is required), The shortest program attained inthe modeling effort for the permanent strategy was26 years. This reflected the last initial groundwatercleanups starting in the 15th year. Six years is re-quired to complete the initial response, then futureactions can be started 5 years later, under the earlytime distribution of future action occurrence. Ofcourse, with expensive enough permanent clean-ups, high enough impermanence factors, and/or alow enough budget, the program would be longer,as there would not be enough money to do all per-manent cleanups in the year they came due.

Any of the time lags before future actions aretaken may be lengthened because of the budget con-straints. Because the model incorporates no meas-ure of risk, future actions may be deferred withoutpenalty, Therefore, in this model, no distinction ismade in allocating the budget between sites requir-ing first time response and sites requiring addition-al response. (The only exception is for permanentresponses under the permanent strategy during thefirst 15 years; they are not permitted,)

Budget Allocation

Each annual budget is allocated so that the fundis distributed in a deterministic way among surfaceand groundwater responses, primary and follow-on responses, Consider first the interim strategy,

If SSC(t) indicates the number of sites that havenever been addressed requiring surface responsein year t, and Sgw(t) is similarly defined for sitesrequiring groundwater response, then an alloca-tion percentage, Yt, is defined for an annualbudget in year t, B(t), as follows:

The percentage is similar during the first 15 yearsof the permanent strategy except there are no termsfor future costs. Instead, the future costs enter themodel when permanent cleanups are pursued, afterthe 15th year. The percentage then becomes:

The effect of this allocation is response to siteswith surface and groundwater contamination in thesame proportion as their occurrence. If the imper-manence factors for interim and initial actions forsurface and groundwater contamination are thesame, this proportion is maintained through thesimulation; that is, the initial 80 percent surface to20 percent groundwater occurrence assumed in themodel stays constant as the program runs. (Notethat groundwater responses are more expensivethan surface response by a factor of 3 in mostsimulations; therefore if the ratio of occurrence is80:20, the budget is split as 0.57 :0.43, the ratio ofcost.) If, however, the impermanence factors aredifferent the proportion will change. For example,if the groundwater responses have higher imper-manence, more attention and money will be de-voted to groundwater response as the program pro-gresses.

One outcome of this allocation method is that nopreference is given to primary actions under eitherstrategy. It is possible, therefore, that with a lowenough budget and high enough impermanencefactor, nearly all funds could be devoted to second-ary and higher order interim actions in the interimstrategy and secondary but permanent actions inthe permanent strategy. This is particularly strik-ing if future actions are required on the early timedistribution schedule, While the real-world impli-cations of this are unappealing, i.e., sites are notaddressed and deteriorate, this poses few problemsin terms of affecting the performance of the strate-gies in the simulation. The correct amount of mon-ey is spent and it is the length of time these expend-itures continue that determines program length,

Measuring Program Duration

To evaluate the strategies in terms of programlength and examine the effects of different timedistributions of future cost occurrences, a method

Page 37: Chapter 3 A Systems Analysis of Superfund

of measuring program duration was

Ch. 3—A Systems Analysis of Superfund ● 9 5

required. Pro-gram duration could be measured in terms of thelast year where expenditures are made for an ac-tion. Since responses extend over time, this way ofmeasuring duration would shorten program lengthby at most 10 years, the time required to completethe longest response—the permanent groundwatercleanup.

By definition the interim cleanup strategy for i< 1 represents a decay process, meaning that fewerand fewer interim actions are taken over time. Itwould be misleading to measure program durationby the time needed to initiate the final single ac-tion (or fraction, thereof, since real variables wereused). By the same token, it would be equally mis-leading to only consider the time required to initi-ate all first interim actions since these might con-stitute only a very small fraction of the totalprogram under the interim strategy.

To resolve this dilemma, program progress wasmeasured in terms of the year at which differentpercentages of all expected cleanups were under-taken. The percentiles are 30, 50, 70, 90, 95, and100 percent. Assuming that the model did delineatebetween primary and future actions, a simple inter-pretation of progress percentiles can be given. Forinstance, under the interim cleanup strategy, if i(sc).= i(gw) = 0.7, the 30 percent program progressmight mean (depending on the timing of future ac-tions) that at most all first interim cleanups werecompleted, and no future actions had started. Fori(sc) = i(gw) > 0.7, the 30 percent program progressmark would have to include additional future ac-tions. In general, the minimum program progresslevel required to cleanup all sites with an interimaction exactly once, under the interim strategy is:

X(%) = 100(1 - i) (6. 1)

The inverse relationship may bias strategy deci-sions toward the interim strategy for low imperma-nce factors if low program progress percentiles areused to measure duration. For example, if a 30 per-cent program progress level is used for i = 0.1under the interim strategy, this represents no morethan the first cleanup of only one-third of the sites.For this reason, the 90 percent program progresslevel, which could represent first cleanup of all sitesif the i = 0.1 (the lowest impermanence factortested], was used to measure program progress.

Model Sensitivity

Each strategy was simulated for impermanencefactors where total costs were supposed to be equalfor the two strategies. Varying budgets (options A,B, C, and D) were run to verify that cleanup actionswere modeled properly and that correct programcosts were generated, and to derive correspondingprogram durations. Results are given in table A-2.All program costs were equal at the critical imper-manence factors, i*(sc) = 0.75 and i*(gw) = 0,8,thereby verifying this aspect of the model,

Despite the mathematical justification for meas-uring program duration in terms of the 90 percentprogram progress level, to arrive at a verifiable con-clusion each strategy was compared in terms ofprogram duration at all program progress levels.(See tables A-3a and A-3b for simulation results atdifferent impermanence factor levels.) At the criti-cal impermanence factors for permanent cost op-tion 1, where program costs of the two strategiesare equal, the interim strategy performs poorly interms of program duration even at the 30 percentprogram progress level (refer to tables A-4a andA-4 b).

Table A-2.—Simulation of Cleanup Program ProgressRanges of Years in Which Required Cleanups are Initiated’

Total Program Cost $63.6 Billion

Selected percentages of sites ‘ ‘

3 0 % 50 % 70 “/0 90 “/0 95 ‘J/o 100 “/0— - .

1. Initial Budget-= $1.6 B; i(sc) = 0.75; i(gw) = 0.8Cleanup strategy:

Interim ... ... 19-48 31-90 48-140+ 84-140+ 110-140 + 140 +P e r m a n e n t . . . 12-19 16-47 22-65 26-79 26-82 27-85

II. Initial Budget = $9.0 B; i(sc) = 0.75; i(gw) = 0.8Cleanup strategy:

Interim . . . . . . . . . . . 14-37 25-75 42-140+ 79-140+ 104-140+ 140 +Permanent . . . . . . . 7 14 19-40 24-53 25-56 26-59

aflange de f(n(t!onsI Shortest programs correspond to scenario 1 EAF longest programs to scenario ILBFII Shortest programs correspond to scenario 1 ECF longest programs to scenario 1 LDF

SOURCE Off Ice of Technology Assessment

Page 38: Chapter 3 A Systems Analysis of Superfund

96 . Superfund Strategy

m I m I m m ’ m I m I

m I m I m m I

m I m

m m I m I

m m I m I m I

m I m I m I

m I

m I

m , m I

Page 39: Chapter 3 A Systems Analysis of Superfund

Ch. 3—A Systems Analysis of Superfund ● 9 7

Table A-4a.—Summary of Simulation ResultsWith Budget Options A and Ba

Program Duration Ranges for i = 0.1 to 0.9b

(in years).

Permanent strategy lntenm strategyTime distribution option: cost range cost range

Program progress $31.4 $70 2BC $16.4 $147 3BCUnifor~ (U;:1 0 0 0/0 51 101 140 +9 5 ‘ ~ o 28 47 38 140 +9 0 ’10 . , 21 45 17 140+7 0 “ o 15 27 16 140 +50 “’0 13 18 13 140 +30°10 : : : : : : : 10 13 11 81Early (E):1 0 0 0 / ’ 0 26 28 41 140 +95° 0 : : 21 27 22 140 +90 0/0 21 26 17 140+7 0 ° 1 0 15 23 16 10550 “/0 ., 13 17 13 643 0 0 / o . 10 13 11 37Late (L):100 ‘/0 51 119 140 +9 5 0/0 42 48 47 140 +900/’. 21 47 17 140 +7 0 0 10 15 41 16 140 +50 0/0 13 18 13 140 +300/0 : : : : : 10 13 11 111

apermanent cleanup costs option 1 and new sites option Fbshort ~rogram5 Correspond to budget oPtlon A and I O 1 Long programs cor

respond to budget opt!on B and I O 9CLOW cost corresponds to budget option A and I O 1 High cost corresponds

to budget option B and I O 9

SOURCE Office of Technology Assessment

Since under either strategy, for i < i*, the interimstrategy is preferred on the basis of cost. But pro-gram durations under the interim strategy so great-ly exceed those of the permanent strategy at the crit-ical impermanence factor that trade-offs betweenprogram cost and duration are expected. Therefore,the hypothesis for cleanup strategy decisionmak-ing based on two evaluation criteria at this pointis: Regardless of when future costs occur and howwe choose to measure program progress:

1. The permanent strategy is preferred unequiv-ocally for i > i * because it is both cheaper andshorter.

2. For i < i*, there are trade-offs between pro-gram cost and length.

3. At some level of impermanence, the interimstrategy is preferred both in terms of programcost and duration.

To be sure the method of measuring programprogress or assumptions about the time distributionof future costs do not disprove this hypothesis, sen-sitivity analysis is performed.

All program progress levels for each strategywere calculated while varying values of i = (O. 1,0.3, 0.5, 0.6, 0.7, 0.8, and 0.9). To properly ascer-tain the shortest and longest program duration, the

Table A-4b.—Summary of Simulation ResultsWith Budget Options C and Da

Program Duration Ranges for i = 0.1 to 0.9b

(in years)

Permanent s t ra tegy Interlrn st rategyTime distribution option: cost r a n g e cos t range

Program progress $23.2 $71 8BC $16.4 $147 3BC

Uniform (U);1000/0 ., 51 98 140 +950/0 ., ... : 29 45 35 140 +9 0 0/ 0 . , 16 41 16 140 +700/o . . 12 25 12 140 +500/o : 7 15 7 140 +

300/o ., 3 7 3 76

Early (E):100”/’0 . 26 27 39 140 +95 0/, ., 17 26 16 140 +90°/’c 16 25 15 140 +700/o : : ., 12 21 11 10050”1O 7 15 7 593O”1O : : : 3 7 3 32

Late (L):1 0 0 0/’0 51 115 140 +9 5 0 ’ , 38 47 41 140 +9 0 0 / o 16 45 16 140 +70”10 12 37 12 140 +500/0 : : : : : : : 7 15 7 140 +300/0 ... 3 7 3 105

a permanent cleanup costs option 2 and new sites option Fbshort programs correspond to budget oPtlon C and I O 1 Long programs cor.

respond to budget option D and I O 9c LOW cost corresponds to budget option C and I O 1 High cost corresponds

to budget option D and I O 9

SOURCE Off Ice of Technology Assessment

time distributions of future costs and budgets werealso varied. The shortest program under each strat-egy is achieved for the high growth rate budget op-tions, A and C, and for the early future cost timedistribution. The longest program under each strat-egy occurred for the low growth budget option Band D and for the late future cost t i me distribution.This information is given in tables A-5 and A-6.

Examination of these tables shows that the hy-pothesis is supported, since parts 1 and 3 are true,and 2 is intuitive. Regardless of when future costsoccur and our measurement of program duration,the permanent strategy is preferred for i > i*.Again regardless of these assumptions, the interimstrategy is preferred only at low impermanence val-ues and/or if program duration is measured atbiased low program progress levels.

Solving the Allocation and SchedulingPrograms: Systems Modeling

as a Management Tool

While simulation models enable comparison be-tween strategies, they require that the strategiesfirst be defined. The simulation so far defined only

Page 40: Chapter 3 A Systems Analysis of Superfund

98 ● Superfund Strategy

two extreme and inflexible strategies. It is not likely,in a real program, that choice would be reducedto a very expensive permanent solution on the onehand or an ineffective impermanent solution,which is not even cheap, on the other, More likely,different levels of cleanup would be warranted atsites according to their different levels of healthrisks and environmental threats. There appears tobe a trend emerging at EPA where cleanup wouldbe approached in stages. The notion of “operableunits” has been put forth in draft versions of therevised NC,. Essentially, the remedial responsesystem will be approached in terms of phased-incleanup, which for most sites will separate surfacefrom subsurface cleanups (this is not necessarilytechnically sound). Cleanup will assume the formof a three-stage process.1 This approach could besomewhat consistent with the “hedge-against-un-certainty” strategy defined earlier,

With cleanups structured into three-stage proc-esses, a cleanup strategy could define or provideguidance for long-term allocation and schedulingpolicies, i.e., the tactics of the program. Decisionsmust be made about which sites are cleaned to whatlevel and when each stage of cleanup is imple-mented. These are difficult management policy de-cisions for a number of reasons.

First, the crucial element for evaluating schedul-ing and allocation tactics is a measure of risk and/orcleanup goals. Such measures or goals could: 1) de-fine the urgency and level of cleanup on a site-spe-cific basis; 2) aid in designating sites requiring dif-ferent levels of cleanup; 3) provide information forassessing cost effectiveness on an intersite basis,which could be used to measure the equity of clean-up schedules and allocations over all sites; and 4)maintain consistency within the cleanup strategy.

Second, it is necessary to relate various cleanupactions to levels of risk reduction or avoidance.Without defining such relationships, it is not pos-sible to evaluate the site-specific cost effectivenessof cleanup options, In evaluating the cost effective-ness of the cleanup options it may be necessary tonot only consider immediate risks but potentialrisks as well. A particular option may not appearvery cost effective when considering only the near-term risks but may be extremely cost effective inlight of longer term risks,

This complication touches on the third difficulty,that of evaluating cleanup action cost effectivenesson an intersite basis, The problems arise due to theinterrelationship between allocation and schedul-

ing. Limitations on budget, the availability of per-manent cleanup technology, or the degree to whichprogram infrastructure is developed will likely de-lay some remedial actions or some stages of reme-dial action. While initial responses may retard thedeterioration of a site, some sites will continue todegrade. For this reason, scheduling and allocationof the Superfund among sites are deeply linkedwith projected or potential risks and costs of reme-dial measures. Trade-offs are likely between moreextensive actions and initial responses in the nearterm, and between permanent cleanup actions atdifferent sites in the long term,

The fourth management problem to address is theenormous number of possible allocation and sched-uling sequences. There will be many possible clean-up action-risk reduction relationships, all of whichmay have different levels of cost effectiveness de-pending on when the actions are undertaken. Thepossibility of 2,000 to 10,000 sites and three stagesof response represents well over a trillion possiblesequences, Even though some will be patent non-sense and experience can eliminate others, a meth-od for evaluating allocation schedules will beindispensable to efficient and equitable fund dis-tribution, especially in a program of such magni-tude and subject to intense public scrutiny.

Simulation could provide valuable comparativeinformation among schedules if measurements ofrisk and the interrelationships of allocation andscheduling were reflected in the model. However,to arrive at preferred schedules, simulation meth-ods would require defining them all and exhaus-tively testing them; this would most likely be com-putationally infeasible. Thus, simulation may notbe the most useful tool for deciding managementpolicies at the tactical level.

Fortunately, there are systems techniques thatoffer greater flexibility than simulation. Such tech-niques might include linear and nonlinear program-ming, dynamic programming, and decision analy-sis methods, all in a multicriteria context given thatthere would be more than one evaluation criterion.One of the largest applications of such mathemati-cal models is in financial and investment planning,e.g., capital budgeting, cashflow analysis, portfoliomanagement, etc. z Mathematical models would notrequire predefining tactics; the preferable tacticswould be the output solution,

Modeling the system might begin with site clas-sification, a step that might also be time dependent.

—ZF J Fabozzl ~nd J. I’alcnte. “ h4athcnlati[ a] Programming rn Amer]-

(.a n ( :[)nlparli[~~. A Sample SU rvey, fnterfa~ (,. s, iol 7, No 1, .N(I\ ember1976, ])p, 9:1-98

Page 41: Chapter 3 A Systems Analysis of Superfund

. . —

In addition to the classification scheme presentedin EPA’s ground water protection strategy, certainStates, e.g., New York, hate alread~ implementeda site classification scheme as a method of allo-cati n,g cleanup actions. The effects of deferringcleanup actions at particular site classes could bereflected b}’ a deterioration coefficient. The clete-riorat ion coefficient might transform deferred sitesfrom one classification to another. The variables inthe mode] could relate spec ifi(: classes of sites andclean up actions tl, at would also be time dependent.Again it is the value of these ~ariables in the modelsolution that would pro~ide the tactics.

These ~ariables might represent ho~t’ many ac-tions using a specific technolog] ~~’ere ap~)lied tohow’ man~ sites of a particular (:lass in a giien ~ear.Remedial actions would also alter the site classifica-t ion. This problem might be formulated to m inirnizeprogram cost and duration subject to a (;leanup goal(constraint. The level of cleanup might be increasedto rcfle(;t the effects of increasing margins of safetj’,a n d SO1 LI t i o ns (: ou Id be compared on t h e basis o f.s~rstem cost effe(:tiveness. The solution-the distri-bution of remedial technologies o~rer sites as a func-tion of time-could also be used as a managementtool. This (:ould be (lone h~r more (:losel~ exa min-i ng sit f]-spec ific data to determi nc ~trh ich sites

Ch. 3—A Systems Analysis of Superfund ● 9 9

would actually undergo clea nu]) using that type oftechnology.

While it may appear to be an ambitious under-taking, efforts are being taken already to incorpor-ate limited but useful health information into deci-sionmaking. EPA is formalizing its risk assessmentguidelines and attempts are being made to appl~’them to hazardous waste disposal site cleanup, Fur-thermore, site-specific hazardous ~~aste i nforma-tion is accumulating as RI/FSs are completed. Otherdata are becoming available as the }Iazard Rank-ing System is applied to more and more sites. FOI.e x a m p l e t h e El RS has been appl ied to o~er 1 , 7 0 0sites. ~ ‘rhe next step is to de~’elol) a n d formal i Ze ar i s k m a n a g e m e n t s t r a t e g y t h a t wroul(] ac(; ount forintersite cost-effecti~’e trade-offs o~’er t i me. Moreextensive and systematic use of the informationa~’ ai 1 abl e now a n d i n t h e fu t L1 re is desirable. I)e\’ el-oping a strategy for the partial s}rstem that (:oul(ibe refined as health and eniironrn[:nt al effe(;ts dataare enhanced is also appro~)ri ate. ‘1’o (: a]]t u re thed}rnarnics of the s~rstem, a s}rstems a])~)roa(:h couldbe considered.

IL I s I,:n\ I I IJl)[llol)t, i] I)r(]t (,( t 1( 111 ,,IH(,I1( \ t :\tt,lll [Ii t 1)(, t I <1/,11 (1( )(1. 1<(,I(,cI\(I 1]1 ot]l(,fu dIIIi f;~it~ir(, f;l)ll(iln~ NI,(IIIS ( :11{( I, \ S(I t[,]fl {() 1[11~[ I ~[( ‘]Stll(fi ,’ F’l[l(il [<(,1)(1[ t [)(,( (,[111)(,1 I ‘1[!4