chapter 3 project management. projects are typically characterized as: –one-time, large scale...

26
Chapter 3 Project Management

Upload: jarvis-dowers

Post on 31-Mar-2015

216 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Chapter 3 Project Management. Projects are typically characterized as: –one-time, large scale operations –consuming large amount of resources –requiring

Chapter 3

Project Management

Page 2: Chapter 3 Project Management. Projects are typically characterized as: –one-time, large scale operations –consuming large amount of resources –requiring

Project Management

Projects are typically characterized as:– one-time, large scale operations– consuming large amount of resources– requiring a long time to complete– a complex set of many activities

3 Important Project Management Functions:– Planning – determine what needs to be done– Scheduling – decide when to do activities– Controlling – see that it’s done right

Page 3: Chapter 3 Project Management. Projects are typically characterized as: –one-time, large scale operations –consuming large amount of resources –requiring

PERT/CPM project management technique(Program Evaluation & Review Technique)/(Critical Path Method)

• Inputs– list of activities– precedence relationships– activity durations

• Outputs– project duration– critical activities– slack for each activity

Page 4: Chapter 3 Project Management. Projects are typically characterized as: –one-time, large scale operations –consuming large amount of resources –requiring

1 2Excavate

& pour footings

Pour foundation

Install drains

Project Network for House Construction

3

6

7

4

8

9

5

10

11

12

16

1813

1715

14

Install roughelectrical & plumbing

Pourbasement

floorInstall

cooling &heating

Erectframe & roof

Laybrickwork

Laystormdrains

Installdrywall

Layflooring

Installfinished

plumbing

Installkitchen

equipmentPaint

Finishroof

Installroof

drainage

Finishgrading

Finishfloors

Pourwalks;

Landscape

Finishelectrical

work

Finishcarpeting

Page 5: Chapter 3 Project Management. Projects are typically characterized as: –one-time, large scale operations –consuming large amount of resources –requiring

CPMA project has the following activities and precedence

relationships:

Immediate Immediate Predecessor Predecessor

Activity Activities Activity Activitiesa -- f c,eb a g bc a h b,dd a i b,de b j f,g,h

Construct a CPM network for the project using:1.) Activity on arrow2.) Activity on node

Page 6: Chapter 3 Project Management. Projects are typically characterized as: –one-time, large scale operations –consuming large amount of resources –requiring

Activity on Arrow(Initial Network)

Page 7: Chapter 3 Project Management. Projects are typically characterized as: –one-time, large scale operations –consuming large amount of resources –requiring

Activity on Arrow(Final Network)

a

b

c

d

e

f

g

hi

j

Page 8: Chapter 3 Project Management. Projects are typically characterized as: –one-time, large scale operations –consuming large amount of resources –requiring

Activity on Node

Page 9: Chapter 3 Project Management. Projects are typically characterized as: –one-time, large scale operations –consuming large amount of resources –requiring

Critical Path

path any route along the network from start to finish

Critical Path path with the longest total duration

This is the shortest time the project can be completed.

Critical Activity an activity on the critical path

*If a critical activity is delayed, the entire project will be delayed. Close attention must be given to critical activities to prevent project delay. There may be more than one critical path.

To find critical path: (brute force approach)

1. identify all possible paths from start to finish

2. sum up durations for each path

3. largest total indicates critical path

Page 10: Chapter 3 Project Management. Projects are typically characterized as: –one-time, large scale operations –consuming large amount of resources –requiring

1

2 6

4 7

53

b = 2

d = 4

g = 9

h = 9

f = 8c = 5

a = 6

k = 6

j = 7

i = 4

e = 3

Page 11: Chapter 3 Project Management. Projects are typically characterized as: –one-time, large scale operations –consuming large amount of resources –requiring

Slack Times

Earliest Start (ES) – the earliest time an activity can startES = largest EF of all immediate predecessors

Earliest Finish (EF) – the earliest time an activity can finishEF = ES + activity duration

Latest Finish (LF) – the latest time an activity can finishwithout delaying the project

LF = smallest LS of all immediate followers

Latest Start (LS) – the latest time an activity can start without delaying the project

LS = LF – activity duration

Page 12: Chapter 3 Project Management. Projects are typically characterized as: –one-time, large scale operations –consuming large amount of resources –requiring

Slack Times

Slack how much an activity can be delayed

without delaying the entire project

Slack = LF – EF or Slack = LS – ES

Slack

EF LF

ES LS

Page 13: Chapter 3 Project Management. Projects are typically characterized as: –one-time, large scale operations –consuming large amount of resources –requiring

c = 10

g = 12

f = 1

7b =15

a = 10 e = 15

i = 7

d = 20

h = 9

Page 14: Chapter 3 Project Management. Projects are typically characterized as: –one-time, large scale operations –consuming large amount of resources –requiring

b = 4

d = 5

h = 5

i = 3

c = 5

a = 5g = 4

j = 6

e = 5

f = 6

Page 15: Chapter 3 Project Management. Projects are typically characterized as: –one-time, large scale operations –consuming large amount of resources –requiring

Input Table for Microsoft Project(Example 10.1, page 387)

Page 16: Chapter 3 Project Management. Projects are typically characterized as: –one-time, large scale operations –consuming large amount of resources –requiring

Gantt Chart for Microsoft Project(Example 10.1, page 387)

Page 17: Chapter 3 Project Management. Projects are typically characterized as: –one-time, large scale operations –consuming large amount of resources –requiring

Project Network for Microsoft Project(Example 10.1, page 387)

Page 18: Chapter 3 Project Management. Projects are typically characterized as: –one-time, large scale operations –consuming large amount of resources –requiring

Activity Crashing(Time-Cost Tradeoffs)

An activity can be performed in less time than normal, but it costs more.

Problem: If project needs to be completed earlier than normal, which activity durations should be decreased so as to minimize additional costs?

Guidelines:• Only crash critical activities• Crash activities one day at a time• Crash critical activity with lowest crashing cost per day

first• Multiple critical paths must all be crashed by one day

Page 19: Chapter 3 Project Management. Projects are typically characterized as: –one-time, large scale operations –consuming large amount of resources –requiring

Activity Crashing Example

Crash project as much as possible.

Activity DurationCrashedDuration

ActivityCost

CrashedCost

CrashingCost/day

a 3 2 40 45

b 4 3 50 54

c 8 5 50 68

d 5 4 30 33

c = 8 d = 5

b = 4a = 3

Minimum duration = 9 days; Total additional cost = $30

Page 20: Chapter 3 Project Management. Projects are typically characterized as: –one-time, large scale operations –consuming large amount of resources –requiring

Program Evaluation & Review Technique(PERT)

3 duration time estimates

– optimistic (to), most likely (tm), pessimistic (tp)

Activity duration:

mean te = (to + 4tm + tp) / 6

variance Vt = [(tp – to) / 6]2

Path duration:

mean of path duration = T = Σ te

variance of path duration = σ2 = Σ Vt

Page 21: Chapter 3 Project Management. Projects are typically characterized as: –one-time, large scale operations –consuming large amount of resources –requiring

X = T ± Zσpath

Z is number of standard deviations that X is from the mean.

Example: If the mean duration of the critical path is 55 days and the variance of this path is 16, what is the longest the project should take using a 95% confidence level?

Page 22: Chapter 3 Project Management. Projects are typically characterized as: –one-time, large scale operations –consuming large amount of resources –requiring
Page 23: Chapter 3 Project Management. Projects are typically characterized as: –one-time, large scale operations –consuming large amount of resources –requiring

probabilityof being late

.05

actualproject

duration

T55

X

Zσcp

Page 24: Chapter 3 Project Management. Projects are typically characterized as: –one-time, large scale operations –consuming large amount of resources –requiring

PERT Example

If the expected duration of a project is 40 days and the variance of the critical path is 9 days, what is the probability that the project will complete in less than 45 days?

in more than 35 days?

in less than 35 days?

in between 35 and 45 days?

Page 25: Chapter 3 Project Management. Projects are typically characterized as: –one-time, large scale operations –consuming large amount of resources –requiring

probabilityof being late

actualproject

duration

T40

45

Zσcp

Page 26: Chapter 3 Project Management. Projects are typically characterized as: –one-time, large scale operations –consuming large amount of resources –requiring

PERT Example

The expected duration of a project is 200 days, and the standard deviation of the critical path is 10 days. Predict a completion time that you are 90% sure you can meet.