chapter 3: public sector infrastructure and asset investment · chapter 3: public sector...

54
33 CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key ndings of the Committee: 3.1 Across the general government sector, net infrastructure investment totalled $4.1 billion in 2008-09, an increase from $3.9 billion in the previous year. 3.2 Overall, actual expenditure was 7 per cent less than the revised estimate for 2008-09, but there were signicant variations for individual departments. 3.3 Of the 194 major infrastructure projects reported to the Committee, the actual expenditure was within 10 per cent of the estimated expenditure in 27 per cent of cases. $652 million less than budgeted was spent, with 53 per cent of major infrastructure projects under-spending by a signicant amount, primarily due to project delays and rescheduling. $207 million more than budgeted was spent on other projects, with 20 per cent of major infrastructure projects over-spending by a signicant amount, mostly due to projects progressing ahead of schedule. 3.4 In total, 48 per cent of projects had revised completion dates compared to original estimates, with 12 per cent being brought forward and 36 per cent being delayed. Of those projects which had revised completion dates in 2007-08, approximately half revised their completion dates again in 2008-09. 3.5 The Department of Treasury and Finance and Major Projects Victoria provide services to support government departments in planning and managing infrastructure projects. 3.1. Introduction The net infrastructure investment across the general government sector in 2008-09 totalled $4.1 billion, which included ‘school modernisation, extension and re-building works as part of the Government’s Victorian Schools Plan; major hospital redevelopments such as the Royal Melbourne Hospital; key water projects; and various road and rail upgrades.’ 42 The expenditure is broken down by department in Table 3.1. This spending is an increase on the $3.9 billion spent in 2007-08, continuing the Government’s trend of increased spending on infrastructure. 43 New asset investment projects with a TEI of $3.2 billion were announced in the 2008-09 Budget, in addition to $1.1 billion provided in the 2007-08 Budget Update. 44 A number of projects were expanded and accelerated during 2008-09 as a result of the Global Financial Crisis. 45 Signicant Commonwealth grants that were unanticipated at the time of the 2008-09 Budget were also received during the year, primarily connected with education, social housing and transport projects. These are discussed further in Chapter 7 of this report. 42 Department of Treasury and Finance, Financial Report for the State of Victoria 2008-09, p.3 43 Public Accounts and Estimates Committee, Report on the 2009-10 Budget Estimates – Part Two, October 2009, p.53 44 Department of Treasury and Finance, Budget Paper No. 2 – Strategy and Outlook 2008-09, p.12 45 Department of Treasury and Finance, Financial Report for the State of Victoria 2008-09, October 2009, p.9

Upload: others

Post on 13-Jun-2020

16 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

33

CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT

Key fi ndings of the Committee:

3.1 Across the general government sector, net infrastructure investment totalled $4.1 billion in 2008-09, an increase from $3.9 billion in the previous year.

3.2 Overall, actual expenditure was 7 per cent less than the revised estimate for 2008-09, but there were signifi cant variations for individual departments.

3.3 Of the 194 major infrastructure projects reported to the Committee, the actual expenditure was within 10 per cent of the estimated expenditure in 27 per cent of cases. $652 million less than budgeted was spent, with 53 per cent of major infrastructure projects under-spending by a signifi cant amount, primarily due to project delays and rescheduling. $207 million more than budgeted was spent on other projects, with 20 per cent of major infrastructure projects over-spending by a signifi cant amount, mostly due to projects progressing ahead of schedule.

3.4 In total, 48 per cent of projects had revised completion dates compared to original estimates, with 12 per cent being brought forward and 36 per cent being delayed. Of those projects which had revised completion dates in 2007-08, approximately half revised their completion dates again in 2008-09.

3.5 The Department of Treasury and Finance and Major Projects Victoria provide services to support government departments in planning and managing infrastructure projects.

3.1. Introduction

The net infrastructure investment across the general government sector in 2008-09 totalled $4.1 billion, which included ‘school modernisation, extension and re-building works as part of the Government’s Victorian Schools Plan; major hospital redevelopments such as the Royal Melbourne Hospital; key water projects; and various road and rail upgrades.’42 The expenditure is broken down by department in Table 3.1.

This spending is an increase on the $3.9 billion spent in 2007-08, continuing the Government’s trend of increased spending on infrastructure.43 New asset investment projects with a TEI of $3.2 billion were announced in the 2008-09 Budget, in addition to $1.1 billion provided in the 2007-08 Budget Update.44

A number of projects were expanded and accelerated during 2008-09 as a result of the Global Financial Crisis.45 Signifi cant Commonwealth grants that were unanticipated at the time of the 2008-09 Budget were also received during the year, primarily connected with education, social housing and transport projects. These are discussed further in Chapter 7 of this report.

42 Department of Treasury and Finance, Financial Report for the State of Victoria 2008-09, p.3

43 Public Accounts and Estimates Committee, Report on the 2009-10 Budget Estimates – Part Two, October 2009, p.53

44 Department of Treasury and Finance, Budget Paper No. 2 – Strategy and Outlook 2008-09, p.12

45 Department of Treasury and Finance, Financial Report for the State of Victoria 2008-09, October 2009, p.9

Page 2: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

Report on the 2008-09 Financial and Performance Outcomes

34

Table 3.1 shows that the Government’s overall total expenditure on non-fi nancial assets was 7 per cent less than the revised estimate for 2008-09. However, within that, there were signifi cant variations for individual departments between the revised estimate and the actual expenditure. Four departments had variations exceeding $100 million each, including one department with a variation in excess of $300 million.

Table 3.1: Purchase of non-fi nancial as sets 2008-09

Actual expenditure

2008-09

Revised estimated

expenditure 2008-09

Variation

($ million) ($ million) (%) ($ million)

Department of Education and Early Childhood Development

474.2 792.0 -40.1 -317.8

Department of Human Services 717.0 592.4 21.0 124.6

Department of Innovation, Industry and Regional Development

446.4 293.0 52.4 153.4

Department of Justice 227.0 199.7 13.7 27.3

Department of Planning and Community Development

27.7 23.8 16.4 3.9

Department of Premier and Cabinet 36.7 62.2 -41.0 -25.5

Department of Primary Industries 29.4 13.1 124.4 16.3

Department of Sustainability and Environment

50.2 201.8 -75.1 -151.6

Department of Transport 881.0 891.1 -1.1 -10.1

Department of Treasury and Finance 43.8 47.1 -7.0 -3.3

Parliament 9.3 7.4 25.7 1.9

Regulatory bodies and other part budget funded agencies

204.1 207.1 -1.4 -3

General government unallocated & adjustments

.. (82.6)

Total purchase of non-fi nancial assets

3,146.8 3,248.1 -3.1 -101.3

Less proceeds from asset sales (268.2) (190.5) 40.8 -77.7

Net contribution to other sectors of government

1,172.7 1,295.0 -9.4 -122.3

Net investment in fi xed assets 4,051.3 4,352.6 -6.9 -301.3

Source: Department of Treasury and Finance, response to the Committee’s 2008-09 Financial and Performance Outcomes Questionnaire – Part Two, received 12 February 2010, p.6

Page 3: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

35

Chapter 3: Public Sector Infrastructure and Asset Investment

3.2. Departmental explanations from instances of variations in asset spending against 2008-09 expenditure projections

The Committee asked all departments to provide details of asset investment projects identifi ed in Budget Information Paper No.1 – Public Sector Asset Investment Program 2008-09, with a TEI in excess of $10 million for which expenditure was expected to occur during 2008-09. Details sought by the Committee included:

estimated and actual expenditure;

specifi c reasons for any variations greater than 10 per cent between the estimated and the actual expenditure for 2008-09;

TEI and remaining expenditure;

the original, revised and forecast completion dates for each project; and

specifi c reasons for any variations between the original, revised and forecast completion dates.

3.3. Major infrastructure projects where actual expenditure varied from estimates for 2008-09

The information supplied by departments documented a range of discrepancies between actual expenditure and the 2008-09 Budget allocations. Of the 194 projects reported to the Committee, in only 27 per cent of cases was the actual expenditure within 10 per cent of the estimated amount. The Committee sought explanations for those projects where expenditure varied by more than 10 per cent from the estimate. The Committee also sought details of projects with budgeted expenditure for 2008-09 where no expenditure occurred.

In total, the expenditure on these 194 projects was $444.8 million less than budgeted. That fi gure is made up of under-expenditure on projects totalling $651.9 million and over-expenditure amounting to $207.2 million.

The details supplied by departments are provided in Table 3.5 and Table 3.7 and summarised in Table 3.2.When examining these tables, it is important to recognise that they present a ‘point in time’ view of the progress towards project completion and that a negative or positive expenditure variation does not necessarily mean a change in the overall TEI for the project. Variations may have a number of causes, including a shift in the planned expenditure pattern, which does not necessarily affect the overall project cost. Projects where there have been revised completion dates are discussed in Section 3.4.

Page 4: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

Report on the 2008-09 Financial and Performance Outcomes

36

Table 3.2: Major infrast ructure projects’ actual expenditure compared to budget for 2008-09 (summary)

Department

Total number

of projects

Variation between actual and estimated expenditure Projects

with zero expenditure

>10% less than estimated

Within ±10% of estimate

>10% more than estimated

(No.) (%) (%) (%) (No.)

Education and Early Childhood Development 22 50.0 18.2 31.8 0

Human Services 52 46.2 23.1 30.8 3

Innovation, Industry and Regional Development 12 66.7 16.7 16.7 0

Justice 22 77.3 9.1 13.6 2

Planning and Community Development 3 66.7 33.3 0.0 0

Premier and Cabinet 2 0.0 100.0 0.0 0

Primary Industries 1 100.0 0.0 0.0 0

Sustainability and Environment 19 42.1 57.9 0.0 3

Transport 61 50.8 31.1 18.0 1

Treasury and Finance 0 0.0 0.0 0.0 0

Total 194 52.6 27.3 20.1 9

Source: Departmental responses to the Committee’s 2008-09 Financial and Performance Outcomes Questionnaire – Part Two and clarifi cation questions

3.3.1 Major infrastructure projects with actual expenditure lower than estimated in 2008-09

There were 102 projects (53 per cent) where actual expenditure in 2008-09 was less than estimated by greater than 10 per cent. Together these under-expenditures resulted in $633.9 million less than budgeted being spent.46 Table 3.2 provides a summary by department. Table 3.5 provides the departments’ explanations for these variances.

The most common reason given for under-expenditure was project delays, most frequently delays associated with construction, permits or contracts. Reasons for project delays are discussed further in Section 3.4. Overall, as can be seen from Table 3.3, there is a clear concurrence between delayed projects and projects with signifi cant under-spends (i.e. 10 or more per cent less than budgeted) – 63 per cent of delayed projects had under-spends and 43 per cent of projects with under-spends also had delays.

46 An additional $18.0 million less than budgeted was spent on projects which under-spent by less than 10 per cent.

Page 5: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

37

Chapter 3: Public Sector Infrastructure and Asset Investment

Table 3.3: Major infrast ructure projects with variances in under-expenditure greater than 10 per cent, by department

Department

Projects with both delays and signifi cant

under-spend

As a proportion of delayed projects

As a proportion of projects with under-spends

(No.) (%) (%)

Education and Early Childhood Development(a) 7 70.0 63.6

Human Services 8 53.3 33.3

Innovation, Industry and Regional Development 6 66.7 75.0

Justice 9 81.8 52.9

Planning and Community Development 1 50.0 50.0

Premier and Cabinet 0 0.0 0.0

Primary Industries 0 0.0 0.0

Sustainability and Environment 0 0.0 0.0

Transport 13 59.1 41.9

Treasury and Finance 0 0.0 0.0

Total 44 62.9 43.1

Note:

(a) Completion dates were not provided for one project.

Source: Departmental responses to the Committee’s 2008-09 Financial and Performance Outcomes Questionnaire – Part Two and clarifi cation questions

Table 3.3 also shows that in 57 per cent of cases, expenditure was less than estimated for reasons other than project delays.

In some instances, less money was required than had been budgeted because project costs were less than had been anticipated.

For a number of projects, less expenditure than budgeted occurred because of revisions to project schedules which did not lead to delays to the projects’ end-dates. In some cases, elements of projects had been brought forward in the previous year (so that expenditure budgeted for 2008-09 was spent in 2007-08). In other cases, elements of projects were postponed (so that expenditure budgeted for 2008-09 is to be spent in 2009-10). A variety of reasons led to this rescheduling, such as:

works had been accelerated in 2007-08 due to favourable circumstances then;

information and communication technology equipment was postponed to allow for server reconfi guration;

property market impacts;

linking planned State funding with new Commonwealth stimulus funding; and

timber expected to be reusable turned out to need replacement.

Page 6: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

Report on the 2008-09 Financial and Performance Outcomes

38

There were also several cases where the apparent under-spend was attributed to budgeted funding being spent as output funding rather than as asset funding. Similarly, a decision to deliver a project through a Public Private Partnership meant that originally planned funding is now not to be spent.

There were nine projects with a TEI over $10 million where funds were budgeted to be spent in 2008-09 but where no funds were actually spent. The explanations are provided in Table 3.4.

Table 3.4: Major infrastructure projects with no expenditure in 2008-09

Project BIP No 1 Budget 2008-09

estimated expenditure($ million)

Explanation for variance

Department of Human Services

Colac Area Health, Polwarth Nursing Home – Residential Aged Care Strategy (Colac)

0.2(a)Project complete.

Geelong Hospital Radiotherapy Service (Geelong) 0.7(a) Project complete.

HealthSMART Shared Information and Communication Technology (ICT) Operations (Statewide)

6.7

The planned refresh program was postponed to 2009-10 to allow server reconfi guration. The project is still scheduled to meet original end-date of June 2012.

Department of Justice

Melbourne North Police Station – Construction (Carlton–North Melbourne)

7.6

Project recorded zero net expenditure for 2008-09 as a result of a refund of property purchase costs from DTF and delays in the site search and compulsory acquisition process. The original site identifi ed for compulsory acquisition proved unsuitable due to contamination and, accordingly, a second site was identifi ed and the compulsory acquisition process recommenced. The TEI for this project was revised to $23.9m as part of the mid-year budget update.

VICSES Support – Construction and Asset Enhancement (Statewide)

5.3Project had no capital expenditure for 2008-09 following s.30 FMA budget transfer to output. This process has not affected the completion date.

Department of Sustainability and Environment

National Water Initiative – Macalister – Construction (Boisdale)

1.3

The Commonwealth required further information regarding water savings prior to approval of the milestone payment. Southern Rural Water Corporation provided the additional information in 2009-10 and the milestone payment is now expected to occur in March 2010. The project remains on course to deliver estimated water savings of 15 gigalitres for the environment in the Macalister and Thomson rivers.

Sustainable Water Initiatives – Maintenance (Statewide) 4.5

In 2008-09 this program was expected to fund works associated with the Werribee Vision Project. Approvals for stage one and two have been completed with the last four stages still requiring approval prior to the allocation of funding. Funding has been carried over into 2009-10 to allow for gaining the necessary approvals.

Wonthaggi Desalination Project 30.0 The Desalination Plant is being delivered through a Public Private Partnership.(b)

Page 7: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

39

Chapter 3: Public Sector Infrastructure and Asset Investment

Project BIP No 1 Budget 2008-09

estimated expenditure($ million)

Explanation for variance

Department of Transport

Murray River Bridge Replacements – Crossings (Corowa, Echuca and Robinvale)

3.0

Project impacted by stakeholder and planning issues relating to bridge alignment.

Notes:

(a) Figure reported as 0 by the Department – this fi gure comes from Department of Treasury and Finance, Budget Information Paper No. 1 – Public Sector Asset Investment Program 2008-09, pp. 40–1.

(b) Information supplied by the Committee.

Source: Departmental responses to the Committee’s 2008-09 Financial and Performance Outcomes Questionnaire – Part Two, except where noted

Page 8: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

Report on the 2008-09 Financial and Performance Outcomes

40

Tabl

e 3.

5:

Maj

o r in

fras

truc

ture

pro

ject

s w

ith a

ctua

l exp

endi

ture

low

er th

an e

stim

ated

in 2

008-

09

Proj

ect

BIP

No

1 B

udge

t 20

08-0

9 es

timat

ed

expe

nditu

re

2008

-09

Act

ual

expe

nditu

re

Varia

nce

Expl

anat

ion

for v

aria

nce

Expe

nditu

re

2005

-06

to

2007

-08

Tota

l Es

timat

ed

Inve

stm

ent

Rem

aini

ng

expe

nditu

re

($ m

illio

n)($

mill

ion)

(%)

($ m

illio

n)

($ m

illio

n)(%

)

Dep

artm

ent o

f Edu

catio

n an

d Ea

rly C

hild

hood

Dev

elop

men

t

Alb

ert P

ark

Sec

onda

ry

Col

lege

– R

epla

cem

ent

Sch

ools

(Alb

ert P

ark)

13.0

5.9

-54.

6Va

rianc

e is

due

to d

emol

ition

an

d re

med

iatio

n w

orks

del

ayin

g co

mm

ence

men

t of c

onst

ruct

ion.

Th

e co

ntra

ct w

as a

war

ded

in D

ecem

ber 2

008.

2.0

16.0

50.5

Ben

digo

Edu

catio

n P

lan

– E

agle

haw

k –

Eag

leha

wk

Sec

onda

ry C

olle

ge –

S

tage

2 (E

agle

haw

k)

4.4

1.8

-58.

9Va

rianc

e is

due

to th

e fi n

alis

atio

n of

te

nder

doc

umen

ts ta

king

long

er th

an

orig

inal

ly a

ntic

ipat

ed, a

s a

resu

lt of

pr

ojec

t sco

pe b

eing

revi

ewed

to fi

t with

in

budg

etar

y co

nstra

ints

.

0.0

12.0

85.0

Ben

digo

Edu

catio

n P

lan

– K

anga

roo

Flat

– K

anga

roo

Flat

Sec

onda

ry C

olle

ge –

S

tage

2 (K

anga

roo

Flat

)

2.2

1.2

-47.

0Va

rianc

e is

due

to th

e fi n

alis

atio

n of

te

nder

doc

umen

ts ta

king

long

er th

an

orig

inal

ly a

ntic

ipat

ed, a

s a

resu

lt of

pr

ojec

t sco

pe b

eing

revi

ewed

to fi

t with

in

budg

etar

y co

nstra

ints

.

0.0

11.0

89.5

Bet

ter S

choo

ls T

oday

(v

ario

us s

choo

ls)

5.5

1.5

-73.

2Th

e pr

ogra

m w

as fi

nalis

ed in

200

8-09

. Th

e ex

pend

iture

in 2

008-

09 w

as

adju

sted

to $

1.47

5M a

s 20

07-0

8 ex

pend

iture

exc

eede

d th

e an

nual

al

loca

tion.

18.5

20.0

0.0

Bet

ter S

choo

ls T

oday

20

08-0

9 (v

ario

us)

35.0

11.4

-67.

3Va

rianc

e is

due

to m

any

scho

ols

com

bini

ng fu

ndin

g fro

m th

is p

rogr

am

with

fund

s pr

ovid

ed u

nder

the

Eco

nom

ic

Stim

ulus

Pac

kage

(ES

P) i

n or

der t

o de

rive

the

max

imum

adv

anta

ge fo

r in

divi

dual

pro

ject

s.

0.0

35.0

67.3

Page 9: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

41

Chapter 3: Public Sector Infrastructure and Asset Investment

Proj

ect

BIP

No

1 B

udge

t 20

08-0

9 es

timat

ed

expe

nditu

re

2008

-09

Act

ual

expe

nditu

re

Varia

nce

Expl

anat

ion

for v

aria

nce

Expe

nditu

re

2005

-06

to

2007

-08

Tota

l Es

timat

ed

Inve

stm

ent

Rem

aini

ng

expe

nditu

re

($ m

illio

n)($

mill

ion)

(%)

($ m

illio

n)

($ m

illio

n)(%

)

Bro

adm

eado

ws

Reg

ener

atio

n –

Reg

ener

atio

n –

Erin

bank

S

econ

dary

Col

lege

and

H

illcr

est S

econ

dary

C

olle

ge (B

road

mea

dow

s)

8.1

7.0

-13.

3Va

rianc

e is

due

to d

elay

in te

nder

ing

proc

ess

as th

e de

sign

had

to b

e re

vise

d to

be

with

in b

udge

t.

1.0

10.4

22.9

Com

mun

ity F

acili

ties

Fund

(var

ious

)2.

61.

0-5

9.8

The

cont

ract

was

fi na

lised

in 2

008-

09.

The

expe

nditu

re in

200

8-09

was

ad

just

ed to

$1.

039M

as

2007

-08

expe

nditu

re e

xcee

ded

the

annu

al

allo

catio

n.

24.7

29.5

0.0

Dan

deno

ng –

R

egen

erat

ion

– D

ande

nong

Hig

h,

Cle

elan

d S

econ

dary

C

olle

ge a

nd D

ovet

on

Sec

onda

ry C

olle

ge –

S

tage

2 (D

ande

nong

)

0.9

0.6

-31.

0Va

rianc

e is

due

to th

e de

lay

in a

war

ding

th

e co

ntra

ct a

s th

e sc

ope

of w

ork

chan

ged

at th

e de

sign

and

dev

elop

men

t st

age.

Con

stru

ctio

n ac

cele

rate

d in

20

09-1

0.

0.0

10.0

93.6

John

Mon

ash

Sci

ence

S

choo

l – M

onas

h U

nive

rsity

, Cla

yton

C

ampu

s (C

layt

on)

14.0

8.1

-42.

0Va

rianc

e is

due

to th

e na

ture

of b

uild

ing

wor

ks a

nd e

xpen

ditu

re in

200

8-09

whi

ch

was

low

er th

an e

stim

ated

at b

udge

t fo

rmul

atio

n tim

e bu

t will

acc

eler

ate

shar

ply

in th

e fi r

st h

alf o

f 200

9-10

.

1.2

20.0

53.4

Page 10: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

Report on the 2008-09 Financial and Performance Outcomes

42

Proj

ect

BIP

No

1 B

udge

t 20

08-0

9 es

timat

ed

expe

nditu

re

2008

-09

Act

ual

expe

nditu

re

Varia

nce

Expl

anat

ion

for v

aria

nce

Expe

nditu

re

2005

-06

to

2007

-08

Tota

l Es

timat

ed

Inve

stm

ent

Rem

aini

ng

expe

nditu

re

($ m

illio

n)($

mill

ion)

(%)

($ m

illio

n)

($ m

illio

n)(%

)

Vario

us S

choo

ls –

Le

adin

g S

choo

ls F

und

– M

oder

nisa

tion

(var

ious

sch

ools

)

2.8

1.1

-59.

0Th

is in

itiat

ive

com

pris

ed n

umer

ous

proj

ects

.Th

e va

rianc

e is

due

to a

sig

nifi c

ant

num

ber o

f pro

ject

s be

ing

dela

yed

in p

lann

ing

stag

e an

d re

vise

d im

plem

enta

tion

time

fram

es d

ue

to s

choo

ls e

nter

ing

into

clu

ster

ar

rang

emen

ts o

r sch

ools

com

bini

ng

fund

ing

from

this

pro

gram

with

oth

er

capi

tal w

orks

pro

ject

s.

9.4

12.1

13.3

Wes

tern

Hei

ghts

R

egen

erat

ion

– R

egen

erat

ion

– W

este

rn

Hei

ghts

Sec

onda

ry

Col

lege

– T

hree

C

ampu

ses

(Ham

lyn

Hei

ghts

)

13.6

0.8

-94.

2Va

rianc

e is

due

to th

e do

cum

enta

tion

bein

g su

spen

ded

pend

ing

reso

lutio

n of

the

Join

t Use

Agr

eem

ent a

nd

land

acq

uisi

tion

issu

es w

ith th

e C

ity

of G

reat

er G

eelo

ng. C

onst

ruct

ion

com

men

ced

in N

ovem

ber 2

009.

0.0

13.8

94.3

Dep

artm

ent o

f Hum

an S

ervi

ces(a

)

Col

ac A

rea

Hea

lth,

Pol

war

th N

ursi

ng H

ome

–Res

iden

tial A

ged

Car

e S

trate

gy (C

olac

)(b)

0.2

0.0

-100

.0P

roje

ct c

ompl

ete.

11.5

13.4

0.0

Page 11: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

43

Chapter 3: Public Sector Infrastructure and Asset Investment

Proj

ect

BIP

No

1 B

udge

t 20

08-0

9 es

timat

ed

expe

nditu

re

2008

-09

Act

ual

expe

nditu

re

Varia

nce

Expl

anat

ion

for v

aria

nce

Expe

nditu

re

2005

-06

to

2007

-08

Tota

l Es

timat

ed

Inve

stm

ent

Rem

aini

ng

expe

nditu

re

($ m

illio

n)($

mill

ion)

(%)

($ m

illio

n)

($ m

illio

n)(%

)

Dis

abili

ty S

ervi

ces

Stra

tegi

c R

efur

bish

men

t an

d R

epla

cem

ent

Pro

gram

Sta

ge 2

(S

tate

wid

e)

8.2

1.5

-81.

6B

oth

the

SR

RP

and

the

Col

anda

pr

ojec

ts h

ave

achi

eved

fi na

ncia

l clo

sure

. A

dela

y in

con

stru

ctio

n of

the fi n

al s

uite

of

hou

ses

has

occu

rred

due

to th

e de

velo

pmen

t of a

join

t cap

ital p

rogr

am

betw

een

Dis

abili

ty S

ervi

ces

DH

S

and

the

Offi

ce o

f Hou

sing

Inno

vativ

e H

ousi

ng O

ppor

tuni

ties

Pro

gram

(IH

OP

). Th

is h

as re

sulte

d in

the

over

all e

nd-d

ate

bein

g am

ende

d to

late

200

9. P

roje

ct

rem

ains

with

in o

rigin

al T

EI.

3.5

15.0

66.5

Eas

tern

Hea

lth M

enta

l H

ealth

Red

evel

opm

ent

Sta

ge 1

(Box

Hill

, R

ingw

ood

Eas

t)

7.5

6.3

-15.

9A

ll co

nstru

ctio

n w

orks

com

plet

e w

ith

only

out

stan

ding

min

or w

ork

pack

ages

to

be

com

plet

e. P

roje

ct in

fi na

ncia

l co

mpl

etio

n ph

ase.

22.6

31.3

7.7

Ele

ctro

nic

Pre

scrib

ing

in

Key

Vic

toria

n H

ospi

tals

(S

tate

wid

e)

13.6

7.2

-47.

1D

elay

s as

soci

ated

with

fi na

lisin

g ag

enci

es to

par

ticip

ate

in th

e ro

llout

of

the

new

sys

tem

resu

lted

in d

elay

s to

th

e ov

eral

l im

plem

enta

tion

sche

dule

. A

genc

y pa

rtici

patio

n ha

s no

w b

een

fi nal

ised

, with

the

proj

ect e

nd-d

ate

adju

sted

to D

ecem

ber 2

010.

7.4

21.0

30.5

Gee

long

Hos

pita

l E

mer

genc

y D

epar

tmen

t R

edev

elop

men

t (G

eelo

ng)

4.4

3.9

-11.

4A

ll co

nstru

ctio

n w

orks

com

plet

e an

d fa

cilit

y op

erat

iona

l. P

roje

ct is

in fi

nanc

ial

com

plet

ion

phas

e.

22.9

27.6

2.9

Gee

long

Hos

pita

l R

adio

ther

apy

Ser

vice

(G

eelo

ng)(b

)

0.7

0.0

-100

.0P

roje

ct c

ompl

ete.

14.3

15.3

0.0

Page 12: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

Report on the 2008-09 Financial and Performance Outcomes

44

Proj

ect

BIP

No

1 B

udge

t 20

08-0

9 es

timat

ed

expe

nditu

re

2008

-09

Act

ual

expe

nditu

re

Varia

nce

Expl

anat

ion

for v

aria

nce

Expe

nditu

re

2005

-06

to

2007

-08

Tota

l Es

timat

ed

Inve

stm

ent

Rem

aini

ng

expe

nditu

re

($ m

illio

n)($

mill

ion)

(%)

($ m

illio

n)

($ m

illio

n)(%

)

Gra

ce M

cKel

lar C

entre

–R

edev

elop

men

t Sta

ge 2

(G

eelo

ng)

2.1

0.4

-79.

0Th

e pr

ojec

t red

evel

opm

ent h

as a

chie

ved

occu

patio

n in

Jun

e 20

07. T

here

are

a

num

ber o

f min

or e

nhan

cem

ents

/min

or

wor

ks (t

hat f

all w

ithin

the

mas

ter p

lan)

th

at a

re b

eing

fi na

lised

and

pro

gres

sing

w

ithin

the

rem

aini

ng p

roje

ct fu

nds.

Fi

nanc

ial r

econ

cilia

tion

of th

e pr

ojec

t is

near

ing

com

plet

ion.

44.7

52.8

3.2

Gro

veda

le A

ged

Car

e Fa

cilit

y D

evel

opm

ent

(Gro

veda

le)

3.2

2.6

-16.

3C

onst

ruct

ion

com

plet

e. P

roje

ct in

fi n

anci

al c

ompl

etio

n ph

ase

20.2

23.4

2.2

Hea

lthS

MA

RT

Sha

red

Info

rmat

ion

and

Com

mun

icat

ion

Tech

nolo

gy (I

CT)

O

pera

tions

(Sta

tew

ide)

6.7

0.0

-100

.0Th

e pl

anne

d re

fresh

pro

gram

was

po

stpo

ned

to 2

009-

10 to

allo

w s

erve

r re

confi

gur

atio

n. T

he p

roje

ct is

stil

l sc

hedu

led

to m

eet o

rigin

al e

nd-d

ate

of

June

201

2.

0.0

26.9

100.

0

Hei

delb

erg

Rep

atria

tion

Hos

pita

l Men

tal H

ealth

R

edev

elop

men

t (H

eide

lber

g)

7.3

0.1

-98.

7Va

rianc

e du

e to

del

ay in

con

stru

ctio

n st

art d

ate

due

to m

odifi

catio

ns to

orig

inal

de

sign

, fol

low

ing

inte

rnal

revi

ews.

C

onst

ruct

ion

end-

date

d ha

s be

en

amen

ded

to O

ctob

er 2

010.

0.0

13.5

99.3

Hos

pita

l Ene

rgy

Sup

ply

Pro

ject

(Sta

tew

ide)

10.0

2.0

-79.

6D

elay

s in

the

proc

urem

ent o

f maj

or

piec

es o

f pla

nt (p

rinci

pally

die

sel

gene

rato

rs) h

as re

sulte

d in

a d

elay

to

over

all p

roje

ct. P

roje

ct is

now

exp

ecte

d to

be

com

plet

ed b

y Ju

ly 2

010.

0.0

23.6

91.4

Kew

Res

iden

tial S

ervi

ces

Red

evel

opm

ent (

Kew

)5.

80.

5-9

1.2

Con

stru

ctio

n w

orks

com

plet

e. R

emed

ial

wor

ks a

re c

ontin

uing

and

are

exp

ecte

d to

be

com

plet

e by

Jun

e 20

10. P

roje

ct is

in

fi na

ncia

l com

plet

ion

phas

e.

31.1

82.8

2.0

Page 13: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

45

Chapter 3: Public Sector Infrastructure and Asset Investment

Proj

ect

BIP

No

1 B

udge

t 20

08-0

9 es

timat

ed

expe

nditu

re

2008

-09

Act

ual

expe

nditu

re

Varia

nce

Expl

anat

ion

for v

aria

nce

Expe

nditu

re

2005

-06

to

2007

-08

Tota

l Es

timat

ed

Inve

stm

ent

Rem

aini

ng

expe

nditu

re

($ m

illio

n)($

mill

ion)

(%)

($ m

illio

n)

($ m

illio

n)(%

)

Med

ical

Equ

ipm

ent

Rep

lace

men

t Pro

gram

20

08-0

9 (S

tate

wid

e)

35.0

30.4

-13.

2A

ll fu

ndin

g fo

r 200

8-09

has

bee

n co

mm

itted

. Sev

eral

larg

e in

voic

es

asso

ciat

ed w

ith a

num

ber o

f hig

h-co

st

med

ical

equ

ipm

ent i

tem

s st

ill to

be

paid

. P

roje

ct to

be fi n

anci

ally

com

plet

e by

Ju

ne 2

010.

0.0

35.0

13.2

Met

ropo

litan

and

Rur

al

Am

bula

nce

Ser

vice

s –

Sta

tion

Upg

rade

s (S

tate

wid

e)

7.4

6.6

-10.

7Fi

nalis

atio

n of

the

loca

tion

of th

e K

nox

faci

lity

due

to a

loca

l pla

nnin

g is

sue

resu

lted

in a

del

ay to

the

com

men

cem

ent o

f con

stru

ctio

n fo

r th

is s

ite. A

site

has

now

bee

n pr

ocur

ed

and

cons

truct

ion

com

men

ced,

with

the

over

all p

roje

ct e

xpec

ted

to b

e co

mpl

eted

by

Jun

e 20

10.

2.2

11.7

25.5

Nor

th R

ichm

ond

Com

mun

ity H

ealth

C

entre

Rel

ocat

ion

(Nor

th

Ric

hmon

d)

1.0

0.3

-69.

5To

wn

plan

ning

issu

es a

ffect

ed

prog

ress

ion

of th

e pr

ojec

t has

resu

lted

in a

n ov

eral

l del

ay in

the

proj

ect.

An

alte

rnat

e si

te h

as b

een

iden

tifi e

d an

d th

e pr

ojec

t has

reco

mm

ence

d an

d pr

ogre

ssin

g to

the

revi

sed

prog

ram

.

4.3

22.5

79.6

Nor

thea

st H

ealth

W

anga

ratta

– N

ursi

ng

Hom

e R

edev

elop

men

t (W

anga

ratta

)

0.6

0.2

-67.

7C

onst

ruct

ion

com

plet

e. P

roje

ct in

fi n

anci

al c

ompl

etio

n ph

ase

with

ou

tsta

ndin

g in

voic

es to

be

paid

.

10.0

10.5

3.0

Nor

ther

n H

ospi

tal

Red

evel

opm

ent S

tage

2a

(Epp

ing)

1.2

0.3

-75.

0C

onst

ruct

ion

wor

ks c

ompl

ete.

Del

ays

in th

e fi n

alis

atio

n of

an

envi

ronm

enta

l au

dit o

n th

e si

te d

elay

ed c

ompl

etio

n of

the

over

all p

roje

ct. R

emed

ial w

orks

ar

e co

ntin

uing

and

are

exp

ecte

d to

be

com

plet

e by

Jun

e 20

10. P

roje

ct is

in

fi nan

cial

com

plet

ion

phas

e.

23.3

24.5

3.8

Page 14: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

Report on the 2008-09 Financial and Performance Outcomes

46

Proj

ect

BIP

No

1 B

udge

t 20

08-0

9 es

timat

ed

expe

nditu

re

2008

-09

Act

ual

expe

nditu

re

Varia

nce

Expl

anat

ion

for v

aria

nce

Expe

nditu

re

2005

-06

to

2007

-08

Tota

l Es

timat

ed

Inve

stm

ent

Rem

aini

ng

expe

nditu

re

($ m

illio

n)($

mill

ion)

(%)

($ m

illio

n)

($ m

illio

n)(%

)

Pla

cem

ent a

nd S

uppo

rt R

esid

entia

l Fac

ility

R

enew

al S

trate

gy –

Sta

ge

6 (S

tate

wid

e)

6.9

5.6

-18.

5A

dela

y in

fi na

lisin

g te

nder

ing

docu

men

ts fo

r tw

o of

the

requ

ired

14

hous

es re

sulte

d in

an

initi

al u

nder

spen

d fo

r the

pro

ject

as

com

men

cem

ent o

f co

nstru

ctio

n w

as d

elay

ed. H

owev

er,

the

proj

ect i

s no

w p

rogr

essi

ng a

head

of

the

initi

al fo

reca

st e

nd-d

ate

due

to

favo

urab

le b

uild

ing

cond

ition

s.

6.9

14.2

11.7

Roy

al M

elbo

urne

Hos

pita

l B

rickw

ork

Rec

tifi c

atio

n (P

arkv

ille)

1.8

1.0

-47.

5U

rgen

t bric

kwor

k re

ctifi

catio

n w

orks

co

mpl

eted

. Pro

ject

is in

fi na

ncia

l co

mpl

etio

n ph

ase,

with

out

stan

ding

in

voic

es to

be

paid

by

June

201

0.

25.7

27.7

3.7

Sun

shin

e H

ospi

tal

Exp

ansi

on a

nd

Red

evel

opm

ent –

Sta

ge 1

(S

unsh

ine)

11.1

7.6

-31.

7D

elay

in a

ppoi

ntm

ent o

f con

stru

ctio

n m

anag

er, w

hich

del

ayed

sta

rt of

wor

ks

on s

ite. R

esch

edul

ed w

orks

to b

e co

mpl

eted

with

Sta

ge 2

.

6.2

20.0

31.1

Sun

shin

e H

ospi

tal

Exp

ansi

on a

nd

Red

evel

opm

ent –

Sta

ge 2

(S

unsh

ine)

13.3

6.0

-54.

6P

roje

cted

cas

h fl o

w o

ver-

estim

ated

in

fi rst

yea

r of c

onst

ruct

ion

prog

ram

me.

O

vera

ll, p

roje

ct is

pro

gres

sing

to o

rigin

al

sche

dule

.

0.0

73.5

91.8

Sup

er C

linic

s (M

etro

polit

an)

1.2

0.9

-30.

0C

onst

ruct

ion

on a

ll th

ree

site

s (C

raig

iebu

rn, M

elto

n an

d Li

lyda

le) i

s co

mpl

ete.

The

pro

ject

is in

fi na

ncia

l co

mpl

etio

n/de

fect

s lia

bilit

y ph

ase

with

ou

tsta

ndin

g in

voic

es to

be

paid

.

40.8

41.7

0.1

War

rack

nabe

al

Nur

sing

Hom

e S

tage

1

Red

evel

opm

ent

(War

rack

nabe

al)

0.9

0.4

-56.

6M

ain

cons

truct

ion

wor

ks c

ompl

eted

w

ithin

orig

inal

tim

elin

es. P

roje

ct is

in

fi nan

cial

com

plet

ion/

defe

ct li

abili

ty

phas

e.

20.0

21.5

4.8

Page 15: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

47

Chapter 3: Public Sector Infrastructure and Asset Investment

Proj

ect

BIP

No

1 B

udge

t 20

08-0

9 es

timat

ed

expe

nditu

re

2008

-09

Act

ual

expe

nditu

re

Varia

nce

Expl

anat

ion

for v

aria

nce

Expe

nditu

re

2005

-06

to

2007

-08

Tota

l Es

timat

ed

Inve

stm

ent

Rem

aini

ng

expe

nditu

re

($ m

illio

n)($

mill

ion)

(%)

($ m

illio

n)

($ m

illio

n)(%

)

War

rnam

bool

Hos

pita

l R

edev

elop

men

t – S

tage

1B

(War

rnam

bool

)

4.5

2.9

-34.

9Th

e un

ders

pend

is d

ue to

a d

elay

in

cons

truct

ion

of th

e am

bula

nce

stat

ion

due

to is

sues

ass

ocia

ted

with

site

se

lect

ion.

The

se is

sues

hav

e no

w b

een

rect

ifi ed

and

the

proj

ect i

s pr

ogre

ssin

g to

the

revi

sed

sche

dule

with

com

plet

ion

expe

cted

in F

eb 2

011.

0.0

70.1

95.8

Dep

artm

ent o

f Inn

ovat

ion,

Indu

stry

and

Reg

iona

l Dev

elop

men

t

Aut

omot

ive

Cen

tre o

f E

xcel

lenc

e, K

anga

n B

atm

an T

AFE

(Doc

klan

ds)

– S

tage

2

10.0

6.0

-40.

4Th

is p

roje

ct is

at t

his

poin

t abo

ut

2 m

onth

s be

hind

pro

gram

but

stil

l an

ticip

ated

to b

e co

mpl

eted

in J

une/

July

20

11.

The

dela

y to

the

proj

ect c

an b

e at

tribu

ted

to:

th

e re

med

iatio

n of

soi

l con

tam

inat

ion

arou

nd a

dec

omm

issi

oned

mai

n tru

nk

sew

er; a

nd

the

desi

gn te

am n

ot m

eetin

g ke

y do

cum

enta

tion

mile

ston

e da

tes.

1.2

30.0

76.3

Page 16: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

Report on the 2008-09 Financial and Performance Outcomes

48

Proj

ect

BIP

No

1 B

udge

t 20

08-0

9 es

timat

ed

expe

nditu

re

2008

-09

Act

ual

expe

nditu

re

Varia

nce

Expl

anat

ion

for v

aria

nce

Expe

nditu

re

2005

-06

to

2007

-08

Tota

l Es

timat

ed

Inve

stm

ent

Rem

aini

ng

expe

nditu

re

($ m

illio

n)($

mill

ion)

(%)

($ m

illio

n)

($ m

illio

n)(%

)

Chi

shol

m In

stitu

te o

f TA

FE –

Tra

de (A

utom

otiv

e &

Log

istic

s) T

rain

ing

Cen

tre (D

ande

nong

) –

Com

mon

wea

lth s

uppo

rted

proj

ect

3.7

0.3

-90.

6Th

e de

lay

to th

e pr

ojec

t can

be

attri

bute

d to

:

the

desi

gn te

am b

eing

una

ble

to m

eet

docu

men

tatio

n m

ilest

one

date

s du

e to

unc

erta

inty

at t

he T

AFE

on

the fi n

al

proj

ect s

cope

; and

co

nstru

ctio

n te

nder

s re

ceiv

ed

exce

eded

the

proj

ect b

udge

t and

the

desi

gn w

as s

ubje

cted

to a

n ex

tens

ive

valu

e m

anag

emen

t pro

cess

.A

build

er h

as n

ow b

een

appo

inte

d an

d co

nstru

ctio

n pr

ogre

ss c

laim

s w

ill e

nsur

e a

stea

dy c

ash fl o

w.

0.0

11.5

97.0

Nor

ther

n M

elbo

urne

In

stitu

te o

f TA

FE –

C

ampu

s re

deve

lopm

ent

stag

e 1

(Epp

ing)

3.0

1.6

-44.

5Th

e de

lay

to th

e pr

ojec

t can

be

attri

bute

d to

:

the

initi

al p

rogr

am a

nd p

roje

ct c

ash

fl ow

for t

he d

ocum

enta

tion

phas

e of

th

e pr

ojec

t was

opt

imis

tic a

s to

the

time

to s

ettle

issu

es; a

nd

the

tend

ers

rece

ived

exc

eede

d th

e pr

ojec

t bud

get a

nd th

e de

sign

has

be

en s

ubje

cted

to a

n ex

tens

ive

valu

e m

anag

emen

t pro

cess

.Th

e to

tal p

roje

ct c

ost h

as n

ow b

een

redu

ced

to m

atch

pro

ject

fund

ing

and

a bu

ilder

has

bee

n ap

poin

ted.

0.0

10.5

84.3

Page 17: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

49

Chapter 3: Public Sector Infrastructure and Asset Investment

Proj

ect

BIP

No

1 B

udge

t 20

08-0

9 es

timat

ed

expe

nditu

re

2008

-09

Act

ual

expe

nditu

re

Varia

nce

Expl

anat

ion

for v

aria

nce

Expe

nditu

re

2005

-06

to

2007

-08

Tota

l Es

timat

ed

Inve

stm

ent

Rem

aini

ng

expe

nditu

re

($ m

illio

n)($

mill

ion)

(%)

($ m

illio

n)

($ m

illio

n)(%

)

Par

kvill

e G

arde

ns

(Com

mon

wea

lth G

ames

Vi

llage

) – S

ocia

l hou

sing

co

mpo

nent

– C

onst

ruct

ion

(Mel

bour

ne)

9.7

1.6

-83.

3Th

ere

has

been

sig

nifi c

antly

less

ex

pend

iture

on

the

Par

kvill

e G

arde

ns

proj

ect t

han

was

orig

inal

ly a

ntic

ipat

ed

larg

ely

attri

bute

d to

the

slow

dow

n in

the

resi

dent

ial m

arke

t as

a re

sult

of e

cono

mic

con

ditio

ns. T

his

has

resu

lted

in th

e po

stpo

nem

ent o

f cer

tain

w

orks

(nam

ely

the

cons

truct

ion

of th

e Lo

t 8 to

wnh

ouse

s an

d fre

eway

wal

l ap

artm

ents

) and

has

mea

nt th

at th

e G

over

nmen

t’s re

quire

men

t to

prov

ide

fi nan

cial

sup

port

for e

lem

ents

suc

h as

env

ironm

enta

l enh

ance

men

ts to

th

e fre

eway

apa

rtmen

ts h

as in

turn

be

en d

efer

red.

Thi

s is

in li

ne w

ith th

e de

velo

pmen

t agr

eem

ent a

llow

ing

the

deve

lope

r up

to 2

012-

13 w

ith o

ptio

ns to

co

mpl

ete

the

deve

lopm

ent.

The

need

to u

nder

take

con

tam

inat

ion

asse

ssm

ents

and

ass

ocia

ted

clea

n up

s to

ena

ble

cons

truct

ion

to c

omm

ence

has

al

so c

ontri

bute

d to

the

dela

y.W

ith re

spec

t to

the

valu

e m

anag

emen

t pr

ogra

m th

at h

as ta

ken

plac

e, th

ere

has

been

real

ignm

ent i

n th

e pr

ogra

mm

ing

and

loca

tion

of c

erta

in u

ses

whi

ch in

tu

rn th

at h

as m

eant

that

cer

tain

act

iviti

es

have

bee

n re

sche

dule

d/de

ferr

ed.

25.4

35.1

23.1

Page 18: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

Report on the 2008-09 Financial and Performance Outcomes

50

Proj

ect

BIP

No

1 B

udge

t 20

08-0

9 es

timat

ed

expe

nditu

re

2008

-09

Act

ual

expe

nditu

re

Varia

nce

Expl

anat

ion

for v

aria

nce

Expe

nditu

re

2005

-06

to

2007

-08

Tota

l Es

timat

ed

Inve

stm

ent

Rem

aini

ng

expe

nditu

re

($ m

illio

n)($

mill

ion)

(%)

($ m

illio

n)

($ m

illio

n)(%

)

Prin

ces

Pie

r Res

tora

tion

(Por

t Mel

bour

ne)

11.6

2.5

-78.

4S

ignifi c

ant a

mou

nts

of th

e ex

istin

g tim

ber,

whi

ch w

as in

itial

ly th

ough

t to

be re

usab

le, r

equi

red

repl

acin

g w

hich

im

pact

ed o

n th

e bu

dget

and

tim

ing

of th

is p

roje

ct. A

dditi

onal

fund

ing

of

$20

mill

ion

was

app

rove

d as

par

t of

the

2009

-10

Bud

get t

o de

mol

ish

the

entir

e P

rince

s P

ier d

eck

stru

ctur

e an

d re

cons

truct

196

m o

f the

dec

k (o

rigin

al

Sta

ge 1

sco

pe),

and

rest

ore

and

refu

rbis

h th

e ga

teho

use

(Sta

ge 2

).

2.4

14.0

65.1

Vict

oria

Uni

vers

ity

– C

onso

lidat

ion

of

Eng

inee

ring

and

ICT

– C

omm

onw

ealth

sup

porte

d pr

ojec

t

0.1

0.1

-36.

3P

roje

ct c

ompl

eted

slig

htly

und

er b

udge

t.13

.513

.60.

3

Will

iam

Ang

liss

Inst

itute

of

TA

FE –

New

teac

hing

fa

cilit

y an

d ca

mpu

s re

deve

lopm

ent –

C

omm

onw

ealth

sup

porte

d pr

ojec

t

9.1

7.7

-15.

3Th

e fi n

al p

aym

ent i

s ou

tsta

ndin

g as

the

TAFE

and

the

build

er a

re fi

nalis

ing

the

cost

of v

aria

tions

to b

e pa

id fr

om p

roje

ct

cont

inge

ncy.

3.0

12.1

11.4

Wod

onga

Inst

itute

of

TAFE

– N

atio

nal l

ogis

tics

and

driv

er s

kills

trai

ning

ce

ntre

(Wod

onga

)

4.0

0.0

-99.

0Th

e de

lay

for t

he p

roje

ct w

as d

ue to

the

inab

ility

to a

cqui

re a

sui

tabl

e si

te fo

r the

co

nstru

ctio

n of

the

cent

re.

0.0

15.5

103.

0

Page 19: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

51

Chapter 3: Public Sector Infrastructure and Asset Investment

Proj

ect

BIP

No

1 B

udge

t 20

08-0

9 es

timat

ed

expe

nditu

re

2008

-09

Act

ual

expe

nditu

re

Varia

nce

Expl

anat

ion

for v

aria

nce

Expe

nditu

re

2005

-06

to

2007

-08

Tota

l Es

timat

ed

Inve

stm

ent

Rem

aini

ng

expe

nditu

re

($ m

illio

n)($

mill

ion)

(%)

($ m

illio

n)

($ m

illio

n)(%

)

Dep

artm

ent o

f Jus

tice(c

)

Ara

rat P

olic

e S

tatio

n (P

olic

e S

tatio

ns P

rogr

am

2007

-08)

– C

onst

ruct

ion

(Ara

rat)

6.0

0.9

-85.

5Vi

ctor

ian

Civ

il an

d A

dmin

istra

tive

Trib

unal

(VC

AT) p

roce

sses

del

ayed

ex

pect

ed p

rogr

ess

of th

is p

roje

ct d

urin

g 20

08-0

9. T

he T

EI f

or th

is p

roje

ct w

as

revi

sed

to $

10.5

3m a

s pa

rt of

the

mid

-yea

r bud

get u

pdat

e pr

oces

s.

1.0

13.5

64.2

Bay

side

Pol

ice

Sta

tion

(Pol

ice

Sta

tions

Pro

gram

20

07-0

8) –

Con

stru

ctio

n (S

andr

ingh

am)

5.9

4.5

-23.

7A

com

petit

ive

mar

ket d

eliv

ered

low

er

than

ant

icip

ated

pro

ject

cos

ts. T

he T

EI

for t

his

proj

ect w

as re

vise

d to

$15

.03m

as

par

t of t

he m

id-y

ear b

udge

t upd

ate.

Th

is h

as n

ot a

ffect

ed th

e co

mpl

etio

n da

te.

0.7

13.0

75.6

Box

Hill

Pol

ice

Sta

tion

(Pol

ice

Sta

tions

Pro

gram

20

07-0

8) –

Con

stru

ctio

n (B

ox H

ill)

6.6

4.0

-39.

4A

com

petit

ive

mar

ket d

eliv

ered

low

er

than

ant

icip

ated

pro

ject

cos

ts. T

he T

EI

for t

his

proj

ect w

as re

vise

d to

$19

.76m

as

par

t of t

he m

id-y

ear b

udge

t upd

ate.

Th

is h

as n

ot a

ffect

ed th

e co

mpl

etio

n da

te.

1.6

16.5

85.7

Bui

ldin

g C

onfi d

ence

in

Cor

rect

ions

Con

stru

ctio

n/A

sset

E

nhan

cem

ent (

Sta

tew

ide/

Rur

al)

78.2

30.0

-61.

6Th

e de

cisi

on to

del

iver

the

new

A

rara

t pris

on th

roug

h a

Pub

lic P

rivat

e P

artn

ersh

ip, a

long

with

ass

ocia

ted

plan

ning

and

con

tract

ual i

ssue

s, h

as

re-p

hase

d fu

ndin

g fo

r thi

s pr

ojec

t. Th

e TE

I was

revi

sed

to $

315.

04m

dur

ing

the

mid

-yea

r bud

get u

pdat

e as

a re

sult

of a

Sec

tion

30 tr

ansf

er. T

his

has

not

affe

cted

the

com

plet

ion

date

.

0.0

316.

690

.0

Page 20: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

Report on the 2008-09 Financial and Performance Outcomes

52

Proj

ect

BIP

No

1 B

udge

t 20

08-0

9 es

timat

ed

expe

nditu

re

2008

-09

Act

ual

expe

nditu

re

Varia

nce

Expl

anat

ion

for v

aria

nce

Expe

nditu

re

2005

-06

to

2007

-08

Tota

l Es

timat

ed

Inve

stm

ent

Rem

aini

ng

expe

nditu

re

($ m

illio

n)($

mill

ion)

(%)

($ m

illio

n)

($ m

illio

n)(%

)

Car

rum

Dow

ns P

olic

e S

tatio

n (P

olic

e S

tatio

ns

Pro

gram

200

7-08

) –

Con

stru

ctio

n (C

arru

m

Dow

ns)

6.1

0.5

-92.

0P

roje

ct d

elay

ed d

ue to

pro

tract

ed s

ite

iden

tifi c

atio

n an

d ac

quis

ition

pro

cess

. Th

e TE

I for

this

pro

ject

was

revi

sed

to

$8.1

86m

as

part

of th

e m

id-y

ear b

udge

t up

date

.

0.9

14.0

48.3

Evi

dent

iary

Aud

io V

isua

l R

ecor

ding

Equ

ipm

ent –

R

epla

cem

ent (

Mel

bour

ne)

7.5

5.2

-31.

3P

roje

ct d

elay

ed d

ue to

pro

tract

ed te

nder

pr

oces

s. T

his

has

not a

ffect

ed th

e co

mpl

etio

n da

te. T

he T

EI f

or th

is p

roje

ct

was

revi

sed

to $

18.1

87m

as

part

of th

e m

id-y

ear b

udge

t upd

ate.

0.0

19.0

68.4

Infri

ngem

ent M

anag

emen

t an

d E

nfor

cem

ent

Ser

vice

s –

Enh

ance

men

t/ E

quip

men

t (S

tate

wid

e)

2.5

1.8

-29.

8P

roje

ct d

elay

ed d

ue to

con

tract

or

expe

rienc

ing

issu

es in

the

com

plet

ion

of

the

requ

irem

ents

defi

niti

on a

nd d

esig

n ph

ases

of t

he p

roje

ct. T

his

has

not

affe

cted

the

com

plet

ion

date

.

2.5

27.9

84.8

Inte

grat

ed C

ourts

M

anag

emen

t Sys

tem

(IC

MS

) – A

sset

E

nhan

cem

ent (

Sta

tew

ide)

9.2

8.0

-12.

2P

roje

ct d

elay

ed d

ue to

issu

es in

rollo

ut

of th

e ca

se m

anag

emen

t sof

twar

e.

24.2

32.3

0.0

Just

ice

Sys

tem

Maj

or

Crim

es R

esou

rcin

g N

eeds

Ass

et E

nhan

cem

ent

(Sta

tew

ide)

0.8

0.2

-77.

2P

roje

ct d

elay

ed d

ue to

cha

nges

to

pro

ject

sco

pe a

nd s

yste

m

impl

emen

tatio

n is

sues

. The

TE

I for

this

pr

ojec

t was

revi

sed

to $

12.7

66m

as

part

of th

e m

id-y

ear b

udge

t upd

ate

proc

ess.

11.4

13.6

3.8

Page 21: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

53

Chapter 3: Public Sector Infrastructure and Asset Investment

Proj

ect

BIP

No

1 B

udge

t 20

08-0

9 es

timat

ed

expe

nditu

re

2008

-09

Act

ual

expe

nditu

re

Varia

nce

Expl

anat

ion

for v

aria

nce

Expe

nditu

re

2005

-06

to

2007

-08

Tota

l Es

timat

ed

Inve

stm

ent

Rem

aini

ng

expe

nditu

re

($ m

illio

n)($

mill

ion)

(%)

($ m

illio

n)

($ m

illio

n)(%

)

Kyn

eton

Pol

ice

Sta

tion

(Pol

ice

Sta

tions

Pro

gram

20

07-0

8) –

Con

stru

ctio

n (K

ynet

on)

5.3

0.7

-86.

7P

roje

ct d

elay

ed d

ue to

pro

tract

ed

coun

cil p

lann

ing

proc

ess,

add

ition

al

cond

ition

s im

pose

d by

Her

itage

Vic

toria

w

hich

resu

lted

in a

rede

sign

of t

he

site

mas

ter-

plan

and

a p

ortio

n of

the

build

ing.

The

TE

I for

this

pro

ject

was

re

vise

d to

$12

.241

m a

s pa

rt of

the

mid

-yea

r bud

get u

pdat

e.

0.2

11.0

102.

7

Lily

dale

Pol

ice

Sta

tion

– C

onst

ruct

ion

(Lily

dale

)11

.53.

2-7

2.7

Pro

ject

del

ayed

due

to p

rotra

cted

co

unci

l pla

nnin

g pr

oces

s.

2.2

13.5

60.3

Mel

bour

ne L

egal

Pre

cinc

t M

aste

r Pla

n –

Old

Cou

nty

Cou

rt R

efur

bish

men

t –

Con

stru

ctio

n/E

nhan

cem

ent

(Mel

bour

ne)

17.5

3.0

-82.

9P

roje

ct d

elay

ed d

ue to

iden

tifi c

atio

n an

d re

mov

al o

f haz

ardo

us w

aste

(asb

esto

s),

whi

ch in

turn

del

ayed

the

cont

ract

or

appo

intm

ent.

0.0

22.5

86.7

Mel

bour

ne N

orth

Pol

ice

Sta

tion

– C

onst

ruct

ion

(Car

lton–

Nor

th

Mel

bour

ne)

7.6

0.0

-100

.0P

roje

ct re

cord

ed z

ero

net e

xpen

ditu

re

for 2

008-

09 a

s a

resu

lt of

a re

fund

of

prop

erty

pur

chas

e co

sts

from

DTF

and

de

lays

in th

e si

te s

earc

h an

d co

mpu

lsor

y ac

quis

ition

pro

cess

. The

orig

inal

site

id

entifi

ed

for c

ompu

lsor

y ac

quis

ition

pr

oved

uns

uita

ble

due

to c

onta

min

atio

n an

d, a

ccor

ding

ly, a

sec

ond

site

was

id

entifi

ed

and

the

com

puls

ory

acqu

isiti

on

proc

ess

reco

mm

ence

d. T

he T

EI f

or th

is

proj

ect w

as re

vise

d to

$23

.9m

as

part

of

the

mid

-yea

r bud

get u

pdat

e.

0.6

15.9

100.

5

Mod

erni

sing

Cor

onia

l S

ervi

ces

– C

onst

ruct

ion

(Mel

bour

ne)

6.0

4.2

-29.

5P

roje

ct d

elay

ed d

ue to

iden

tifi c

atio

n of

la

tent

site

con

tam

inat

ion.

1.

031

.783

.4

Page 22: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

Report on the 2008-09 Financial and Performance Outcomes

54

Proj

ect

BIP

No

1 B

udge

t 20

08-0

9 es

timat

ed

expe

nditu

re

2008

-09

Act

ual

expe

nditu

re

Varia

nce

Expl

anat

ion

for v

aria

nce

Expe

nditu

re

2005

-06

to

2007

-08

Tota

l Es

timat

ed

Inve

stm

ent

Rem

aini

ng

expe

nditu

re

($ m

illio

n)($

mill

ion)

(%)

($ m

illio

n)

($ m

illio

n)(%

)

Moo

rabb

in C

ourt

– C

ompl

ex: C

onst

ruct

ion

(Moo

rabb

in)

0.5

0.4

-11.

0Th

is p

roje

ct c

omm

ence

d in

200

3-04

an

d w

as p

ract

ical

ly c

ompl

eted

dur

ing

2008

-09.

The

resi

dual

fund

s fa

cilit

ated

fi n

anci

al c

lose

of t

he p

roje

ct d

urin

g 20

09-1

0.

21.2

28.1

1.2

Sw

an H

ill P

olic

e S

tatio

n (P

olic

e S

tatio

ns P

rogr

am

2007

-08)

– C

onst

ruct

ion

(Sw

an H

ill)

6.1

4.8

-21.

6P

roje

ct b

enefi

ted

from

a lo

wer

con

tract

am

ount

than

the

orig

inal

con

stru

ctio

n bu

dget

. Und

er s

pend

was

not

a re

sult

of a

ny s

lippa

ge o

f the

pro

ject

pro

gram

. Th

e TE

I for

this

pro

ject

was

revi

sed

to $

16.0

75m

as

part

of th

e m

id-y

ear

budg

et u

pdat

e. T

his

has

not a

ffect

ed th

e co

mpl

etio

n da

te.

1.7

15.0

64.3

VIC

SE

S S

uppo

rt –

Con

stru

ctio

n an

d A

sset

E

nhan

cem

ent (

Sta

tew

ide)

5.3

0.0

-100

.0P

roje

ct h

ad n

o ca

pita

l exp

endi

ture

for

2008

-09

follo

win

g s.

30 F

MA

budg

et

trans

fer t

o ou

tput

. Thi

s pr

oces

s ha

s no

t af

fect

ed th

e co

mpl

etio

n da

te.

3.9

11.8

59.9

Dep

artm

ent o

f Pla

nnin

g an

d C

omm

unity

Dev

elop

men

t

Foot

scra

y Tr

ansi

t City

Upg

rade

21

.37.

2-6

6.3

The

over

all c

ompl

etio

n da

te fo

r thi

s pr

ojec

t rem

ains

201

0. T

he u

pdat

ed

expe

nditu

re p

rofi l

e refl e

cts

revi

sion

s to

the

proj

ect s

ched

ule

and

cash

fl ow

fo

llow

ing

the

awar

d of

the

tend

er.

10.2

46.1

62.3

Tran

sit C

ities

: Rev

italis

ing

Cen

tral D

ande

nong

Upg

rade

Wor

ks

(Dan

deno

ng)

59.7

40.4

-32.

4A

sset

inve

stm

ent c

over

s la

nd a

cqui

sitio

n an

d co

nstru

ctio

n of

pro

ject

s re

latin

g to

Lon

sdal

e S

treet

and

City

Stre

et.

Adj

ustm

ents

to th

e ex

pend

iture

profi l

e refl e

ct u

pdat

ed p

roje

ct s

ched

ules

.

109.

724

3.4

38.4

Page 23: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

55

Chapter 3: Public Sector Infrastructure and Asset Investment

Proj

ect

BIP

No

1 B

udge

t 20

08-0

9 es

timat

ed

expe

nditu

re

2008

-09

Act

ual

expe

nditu

re

Varia

nce

Expl

anat

ion

for v

aria

nce

Expe

nditu

re

2005

-06

to

2007

-08

Tota

l Es

timat

ed

Inve

stm

ent

Rem

aini

ng

expe

nditu

re

($ m

illio

n)($

mill

ion)

(%)

($ m

illio

n)

($ m

illio

n)(%

)

Dep

artm

ent o

f Prim

ary

Indu

strie

s

Res

ourc

e R

ight

s A

lloca

tion

and

Man

agem

ent P

rogr

am

1.7

0.2

-90.

9Va

rianc

e du

e to

the

proc

urem

ent o

f P

rogr

am M

anag

emen

t res

ourc

es b

eing

de

laye

d. O

rigin

al p

hasi

ng e

stim

ate

for

this

pro

cure

men

t req

uire

d re

adju

stm

ent

how

ever

, thi

s de

lay

will

hav

e no

impa

ct

on p

roje

ct o

utco

mes

.Th

e R

esou

rce

Rig

hts

Allo

catio

n an

d M

anag

emen

t Pro

gram

(RR

AM

) is

a D

PI fl

ags

hip

prog

ram

. The

eng

agem

ent

of a

sen

ior e

xper

ienc

ed p

rogr

am

man

ager

with

exp

ertis

e in

bus

ines

s an

d IC

T tra

nsfo

rmat

ion

prog

ram

s w

as

criti

cal t

o th

e pr

ogra

ms

succ

ess.

The

en

gage

men

t of t

he s

peci

alis

t pro

gram

m

anag

er w

as d

elay

ed d

ue to

the

lack

of

reso

urce

ava

ilabi

lity

in th

e IC

T la

bour

m

arke

t dur

ing

mid

to la

te 2

008.

The

R

RA

M P

rogr

am C

ontro

l Boa

rd a

nd D

PI

man

agem

ent u

nder

took

an

exte

nsiv

e re

crui

tmen

t pro

cess

prio

r to

succ

essf

ully

en

gagi

ng a

sui

tabl

y ex

perie

nced

pr

ogra

m m

anag

er w

ho c

omm

ence

d w

ith

the

Dep

artm

ent o

n 20

Oct

ober

200

8.

011

.798

.7

Dep

artm

ent o

f Sus

tain

abili

ty a

nd E

nviro

nmen

t

Bus

hfi re

Rec

over

y 20

07-0

8 –

Stra

tegy

(S

tate

wid

e)

6.8

0.4

-94.

5Th

is p

rogr

am d

id n

ot h

ave

a si

gnifi

cant

un

ders

pend

as

the

maj

ority

of b

udge

ted

expe

nditu

re fo

r 200

8-09

was

inst

ead

spen

t as

outp

ut fu

ndin

g, in

clud

ing

repa

irs a

nd m

aint

enan

ce to

ass

ets

dam

aged

in th

e bu

shfi r

es.

1.7

11.9

28.6

Page 24: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

Report on the 2008-09 Financial and Performance Outcomes

56

Proj

ect

BIP

No

1 B

udge

t 20

08-0

9 es

timat

ed

expe

nditu

re

2008

-09

Act

ual

expe

nditu

re

Varia

nce

Expl

anat

ion

for v

aria

nce

Expe

nditu

re

2005

-06

to

2007

-08

Tota

l Es

timat

ed

Inve

stm

ent

Rem

aini

ng

expe

nditu

re

($ m

illio

n)($

mill

ion)

(%)

($ m

illio

n)

($ m

illio

n)(%

)

Impr

ovin

g Vi

ctor

ia’s

N

atur

al T

ouris

m

Attr

actio

ns –

Nat

iona

l P

arks

Upg

rade

s (S

tate

wid

e)

5.0

3.3

-33.

9Th

is p

rogr

am d

id n

ot h

ave

a si

gnifi

cant

un

ders

pend

as

mos

t of t

he re

mai

nder

of

budg

eted

exp

endi

ture

for 2

008-

09 w

as

inst

ead

spen

t as

outp

ut fu

ndin

g.

1.8

11.1

42.0

Mel

bour

ne Z

oo S

eal

Poo

l Red

evel

opm

ent –

C

onst

ruct

ion

(Par

kvill

e)

7.0

5.9

-15.

1P

roje

ct d

ue to

be

com

plet

ed in

the

2009

-10 fi n

anci

al y

ear.

10.0

20.0

15.0

Nat

iona

l Wat

er In

itiat

ive

– M

acal

iste

r – C

onst

ruct

ion

(Boi

sdal

e)

1.3

0-1

00.0

The

Com

mon

wea

lth re

quire

d fu

rther

in

form

atio

n re

gard

ing

wat

er s

avin

gs p

rior

to a

ppro

val o

f the

mile

ston

e pa

ymen

t. S

outh

ern

Rur

al W

ater

Cor

pora

tion

prov

ided

the

addi

tiona

l inf

orm

atio

n in

20

09-1

0 an

d th

e m

ilest

one

paym

ent i

s no

w e

xpec

ted

to o

ccur

in M

arch

201

0.

The

proj

ect r

emai

ns o

n co

urse

to d

eliv

er

estim

ated

wat

er s

avin

gs o

f 15

giga

litre

s fo

r the

env

ironm

ent i

n th

e M

acal

iste

r an

d Th

omso

n riv

ers.

18.7

20.0

6.7

Sus

tain

able

Man

agem

ent

of V

icto

ria’s

Par

ks –

R

enew

(Sta

tew

ide)

8.4

5.1

-39.

7Th

is p

rogr

am d

id n

ot h

ave

a si

gnifi

cant

un

ders

pend

as

mos

t of t

he re

mai

nder

of

budg

eted

exp

endi

ture

for 2

008-

09 w

as

inst

ead

spen

t as

outp

ut fu

ndin

g.

31.4

55.2

27.8

Page 25: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

57

Chapter 3: Public Sector Infrastructure and Asset Investment

Proj

ect

BIP

No

1 B

udge

t 20

08-0

9 es

timat

ed

expe

nditu

re

2008

-09

Act

ual

expe

nditu

re

Varia

nce

Expl

anat

ion

for v

aria

nce

Expe

nditu

re

2005

-06

to

2007

-08

Tota

l Es

timat

ed

Inve

stm

ent

Rem

aini

ng

expe

nditu

re

($ m

illio

n)($

mill

ion)

(%)

($ m

illio

n)

($ m

illio

n)(%

)

Sus

tain

able

Wat

er

Initi

ativ

es –

Mai

nten

ance

(S

tate

wid

e)

4.5

0-1

00.0

In 2

008-

09 th

is p

rogr

am w

as e

xpec

ted

to fu

nd w

orks

ass

ocia

ted

with

the

Wer

ribee

Vis

ion

Pro

ject

. App

rova

ls fo

r st

age

one

and

two

have

bee

n co

mpl

eted

w

ith th

e la

st fo

ur s

tage

s st

ill re

quiri

ng

appr

oval

prio

r to

the

allo

catio

n of

fu

ndin

g. F

undi

ng h

as b

een

carr

ied

over

in

to 2

009-

10 to

allo

w fo

r gai

ning

the

nece

ssar

y ap

prov

als.

018

.275

.1

Vict

oria

n W

ater

Tru

st

Ass

ets

– U

pgra

des

(var

ious

)

16.3

6.0

-63.

0Th

is fu

ndin

g w

as a

lloca

ted

to a

rang

e of

out

put i

nitia

tives

. In

addi

tion,

fund

ing

was

car

ried

over

into

200

9-10

for f

urth

er

deve

lopm

ent o

n bu

sine

ss c

ases

for

proj

ects

.

104.

215

2.6

8.4

Won

thag

gi D

esal

inat

ion

Pro

ject

30.0

00.

0Th

e D

esal

inat

ion

Pla

nt is

bei

ng

deliv

ered

thro

ugh

a P

ublic

Priv

ate

Par

tner

ship

.(d)

2.0

32.0

0.0

Dep

artm

ent o

f Tra

nspo

rt(c

)

Acc

essi

ble

Pub

lic

Tran

spor

t in

Vict

oria

: D

isab

ility

Dis

crim

inat

ion

Act

(DD

A) C

ompl

ianc

e fo

r Tra

in, T

ram

and

Bus

(s

tate

wid

e)

41.8

33.3

-20.

3R

efl e

cts

impa

ct o

f acc

eler

atio

n of

wor

ks

in 2

007-

08.

56.4

129.

230

.5

Page 26: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

Report on the 2008-09 Financial and Performance Outcomes

58

Proj

ect

BIP

No

1 B

udge

t 20

08-0

9 es

timat

ed

expe

nditu

re

2008

-09

Act

ual

expe

nditu

re

Varia

nce

Expl

anat

ion

for v

aria

nce

Expe

nditu

re

2005

-06

to

2007

-08

Tota

l Es

timat

ed

Inve

stm

ent

Rem

aini

ng

expe

nditu

re

($ m

illio

n)($

mill

ion)

(%)

($ m

illio

n)

($ m

illio

n)(%

)

Bar

won

Hea

ds B

ridge

R

epla

cem

ent (

Bar

won

H

eads

)

13.9

2.8

-79.

9Fi

nalis

atio

n of

the

brid

ge d

esig

n w

as

dela

yed

by th

e he

ritag

e pe

rmit

appr

oval

pr

oces

s an

d ad

ditio

nal c

onsu

ltatio

n w

ith th

e co

mm

unity

ove

r the

des

ign.

Th

e de

sign

has

bee

n fi n

alis

ed, t

he

perm

it is

sued

and

the

cont

ract

aw

arde

d in

May

200

9.

3.2

22.3

73.1

Ber

wic

k C

ranb

ourn

e R

oad

Dup

licat

ion

(3km

– 5

km

) – P

ound

R

d to

Tho

mps

ons

Rd

(Cra

nbou

rne

Nor

th, C

lyde

N

orth

)

4.9

3.7

-24.

5P

roje

ct is

now

ope

n to

traffi c

.8.

715

.017

.3

Bre

akw

ater

Roa

d U

pgra

de (B

elm

ont,

Gee

long

)

10.0

1.9

-81.

0D

ue to

long

er th

an e

xpec

ted

plan

ning

sc

hem

e am

endm

ent a

ppro

vals

and

ad

ditio

nal c

onsu

ltatio

n on

pro

ject

s de

sign

with

affe

cted

land

owne

rs.

2.1

40.0

90.0

Cau

lfi el

d–D

ande

nong

R

ail C

orrid

or S

tage

Tw

o –

Wes

tall

Rai

l Upg

rade

(S

prin

gval

e)

19.6

6.8

-65.

3R

evis

ed c

ontra

ct a

ppro

val t

imel

ines

.0

151.

195

.4

Cau

lfi el

d–D

ande

nong

R

ail C

orrid

or –

Sta

ge O

ne

– C

ranb

ourn

e S

tabl

ing

and

Sta

tion

Upg

rade

(C

ranb

ourn

e)

25.0

21.5

-14.

0P

roje

ct c

ompl

eted

– fi

nal c

laim

s on

ly

rem

ain.

11.6

35.1

5.7

Con

gest

ion

Impr

ovem

ents

P

rogr

am (v

ario

us)

14.4

9.2

-36.

1D

eliv

ery

for s

ome

proj

ects

resc

hedu

led

due

to fi

nalis

atio

n of

sco

pe a

nd c

ounc

il ap

prov

als.

2.2

30.0

62.0

Page 27: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

59

Chapter 3: Public Sector Infrastructure and Asset Investment

Proj

ect

BIP

No

1 B

udge

t 20

08-0

9 es

timat

ed

expe

nditu

re

2008

-09

Act

ual

expe

nditu

re

Varia

nce

Expl

anat

ion

for v

aria

nce

Expe

nditu

re

2005

-06

to

2007

-08

Tota

l Es

timat

ed

Inve

stm

ent

Rem

aini

ng

expe

nditu

re

($ m

illio

n)($

mill

ion)

(%)

($ m

illio

n)

($ m

illio

n)(%

)

Coo

laro

o S

tatio

n (C

oola

roo)

10.0

6.9

-31.

0Aw

ard

of m

ain

cont

ract

has

now

oc

curr

ed.

0.1

36.0

80.8

Cou

ntry

Rai

l Fre

ight

N

etw

ork

Mai

nten

ance

(n

on M

etro

var

ious

)’

23.7

18.6

-21.

5U

pgra

de o

f gol

d lin

es c

ompl

eted

. R

emai

ning

bud

get a

pplie

d to

the

upgr

ade

of s

ilver

line

s as

par

t of t

he

2009

-10

Bud

get.

023

.721

.5

Cra

igie

burn

Sta

tion

Trac

k U

pgra

de (C

raig

iebu

rn)

13.0

9.4

-27.

7R

efl e

cts

resc

hedu

ling

of a

ctiv

ities

to

2009

-10.

029

.868

.1

Cra

nbou

rne

Fran

ksto

n R

oad

Dup

licat

ion

(10.

2km

–11.

9km

) –

Cen

tre R

d to

Wes

tern

Por

t H

wy

(Lan

gwar

rin)

2.9

1.9

-34.

5P

roje

ct c

ompl

eted

ahe

ad o

f sch

edul

e.6.

811

.423

.7

Cra

nbou

rne

Fran

ksto

n R

oad

Dup

licat

ion

(Hal

l R

oad

and

the

Wes

tern

P

ort H

ighw

ay)

10.8

7.1

-34.

3M

inor

resc

hedu

ling.

2.3

30.0

68.7

Fern

tree

Gul

ly R

oad

Wid

enin

g –

Jells

Roa

d to

S

tud

Roa

d (S

core

sby)

24.4

12.6

-48.

4S

ervi

ce re

loca

tion

activ

ities

resc

hedu

led

follo

win

g th

e Fe

brua

ry 2

009

bush

fi re

s.5.

632

.042

.8

Gee

long

Rai

l Acc

ess

Impr

ovem

ent P

roje

ct

(Cor

io/N

orth

Gee

long

)

18.7

15.0

-19.

8M

ain

wor

ks c

ompl

eted

Dec

embe

r 200

8,

link

of C

orio

goo

ds li

ne w

ith w

harv

es

com

plet

ed J

une

2009

.

10.8

33.4

21.3

Gee

long

Rin

g R

oad

Sta

ge

4B (A

ngle

sea

Roa

d to

P

rince

s H

ighw

ay W

est,

City

of G

reat

er G

eelo

ng)

5.0

1.1

-78.

0R

esch

edul

ing

of s

ome

plan

ning

act

iviti

es

to 2

009-

10.

065

.098

.3

Page 28: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

Report on the 2008-09 Financial and Performance Outcomes

60

Proj

ect

BIP

No

1 B

udge

t 20

08-0

9 es

timat

ed

expe

nditu

re

2008

-09

Act

ual

expe

nditu

re

Varia

nce

Expl

anat

ion

for v

aria

nce

Expe

nditu

re

2005

-06

to

2007

-08

Tota

l Es

timat

ed

Inve

stm

ent

Rem

aini

ng

expe

nditu

re

($ m

illio

n)($

mill

ion)

(%)

($ m

illio

n)

($ m

illio

n)(%

)

Geo

rge

Stre

et B

ridge

New

Brid

ge to

link

Geo

rge

Stre

et to

Brig

hton

Roa

d (D

ande

nong

)

6.0

3.1

-48.

3M

inor

resc

hedu

ling.

Con

tract

s no

w

awar

ded.

8.8

17.5

32.6

Lave

rton

Rai

l Upg

rade

(L

aver

ton)

23.1

16.9

-26.

8R

efl e

cts

resc

hedu

ling

of a

ctiv

ities

to

2009

-10.

092

.081

.6

Met

ropo

litan

Tra

in C

ontro

l R

elia

bilit

y (M

elbo

urne

)28

.415

.5-4

5.4

Res

ched

ule

of a

ctiv

ities

to 2

009-

10.

18.2

87.9

61.7

Met

ropo

litan

Tra

in S

afet

y C

omm

unic

atio

ns S

yste

m

(Met

ro v

ario

us)

48.3

23.6

-51.

1P

aym

ents

hav

e be

en re

-pha

sed

base

d on

con

tract

mile

ston

es.

12.5

134.

973

.2

Met

ropo

litan

Tra

in

Ser

vice

s (M

etro

var

ious

)12

3.5

105.

5-1

4.6

Min

or re

sche

dulin

g.32

.556

5.8

75.6

Mur

ray

Riv

er B

ridge

R

epla

cem

ents

Cro

ssin

gs (C

orow

a,

Ech

uca

and

Rob

inva

le)

3.0

0-1

00.0

Pro

ject

impa

cted

by

stak

ehol

der a

nd

plan

ning

issu

es re

latin

g to

brid

ge

alig

nmen

t.

015

.010

0.0

New

Tic

ketin

g S

olut

ion

– Te

chno

logy

and

In

stal

latio

n (S

tate

wid

e)

149.

981

.2-4

5.8

Refl

ect

s ch

ange

s to

pro

ject

sch

edul

ing

follo

win

g ro

llout

in re

gion

al V

icto

ria.

153.

346

0.9

44.0

Nor

th E

ast R

ail

Rev

italis

atio

n P

roje

ct

(var

ious

)

18.2

11.3

-37.

9R

esch

edul

ing

of w

orks

by

the

Aus

tralia

n R

ail T

rack

Cor

pora

tion

(AR

TC).

059

.881

.1

Nor

th M

elbo

urne

Sta

tion

Inte

rcha

nge

Upg

rade

(N

orth

Mel

bour

ne)

10.0

8.5

-15.

0R

esch

edul

e of

som

e w

orks

into

200

9-10

. P

roje

ct c

ompl

eted

Nov

embe

r 200

9.28

.638

.63.

9

Page 29: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

61

Chapter 3: Public Sector Infrastructure and Asset Investment

Proj

ect

BIP

No

1 B

udge

t 20

08-0

9 es

timat

ed

expe

nditu

re

2008

-09

Act

ual

expe

nditu

re

Varia

nce

Expl

anat

ion

for v

aria

nce

Expe

nditu

re

2005

-06

to

2007

-08

Tota

l Es

timat

ed

Inve

stm

ent

Rem

aini

ng

expe

nditu

re

($ m

illio

n)($

mill

ion)

(%)

($ m

illio

n)

($ m

illio

n)(%

)

Prin

ces

Hig

hway

Wes

t –

Sta

ge 1

(Wau

rn P

onds

to

Win

chel

sea,

City

of

Gre

ater

Gee

long

, G

eelo

ng)

5.0

0.2

-96.

0R

esch

edul

ing

of s

ome

plan

ning

and

de

velo

pmen

t act

iviti

es to

200

9-10

.0

110.

099

.8

Reg

iona

l Arte

rial R

oad

and

Brid

ge L

inks

(non

-M

etro

var

ious

)

1.9

1.6

-15.

8R

esch

edul

ing

of p

lann

ing

activ

ities

for

the

Ech

uca–

Moa

ma

Brid

ge p

roje

ct.

8.6

41.9

8.1

Sm

artB

us: G

reen

Orb

ital

– N

unaw

adin

g to

Airp

ort

Wes

t (M

etro

var

ious

)

13.6

9.5

-30.

1R

esch

edul

ing

of a

ctiv

ities

to 2

009-

10.

1.8

29.3

61.8

Tayl

ors

Roa

d (1

5.2k

m to

15

.8km

) – B

ypas

s/N

ew

Roa

d –

Syd

enha

m R

d to

E

ast E

spla

nade

– G

rade

S

epar

atio

n (S

t Alb

ans)

8.1

4.7

-42.

0P

roje

ct c

ompl

eted

Nov

embe

r 200

8.37

.354

.022

.2

Tram

and

Bus

Prio

rity

Pro

gram

(Met

ro v

ario

us)

6.0

3.8

-36.

7M

inor

resc

hedu

ling.

036

.289

.5

Vigi

lanc

e C

ontro

l and

E

vent

Rec

ordi

ng S

yste

m

(VIC

ER

S) o

n M

etro

polit

an

Trai

ns (M

etro

var

ious

)

20.0

6.6

-67.

0R

esch

edul

ing

to a

lign

with

trai

n av

aila

bilit

y.14

.337

.343

.7

Wes

tern

Por

t Hig

hway

D

uplic

atio

n (0

km–4

km)

Cra

nbou

rne

Fran

ksto

n R

d to

Nor

th R

d (L

angw

arrin

, C

ranb

ourn

e S

outh

)

18.7

9.7

-48.

1P

roje

ct c

ompl

eted

.17

.936

.825

.0

Page 30: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

Report on the 2008-09 Financial and Performance Outcomes

62

Notes:

(a) TEIs for the Department of Human Services are revised rather than original fi gures.

(b) Figure reported as 0 by the Department – this fi gure comes from Department of Treasury and Finance, Budget Information Paper No. 1 – Public Sector Asset Investment Program 2008-09, pp. 40–1; explanation for variance from Department’s response to questionnaire part 2, question 2.1(h).

(c) TEIs for the Department of Justice and the Department of Transport are as published in the 2008-09 Budget Information Paper No. 1.

(d) Information supplied by the Committee.

Source: Departmental responses to the Committee’s 2008-09 Financial and Performance Outcomes Questionnaire – Part Two, except where noted

3.3.2 Major infrastructure projects with actual expenditure higher than estimated in 2008-09

There were 39 projects (20 per cent) in 2008-09 in which departments spent in excess of 10 per cent more than had been estimated (see Table 3.2). Together they amounted to $190.8 million more being spent than budgeted.47 Table 3.6 provides a summary by department. Table 3.7 provides detailed explanations by department for these variances.

The main reason given for over-expenditure was projects proceeding ahead of schedule, with 72 per cent of project over-expenditures attributed to this cause (see Table 3.6). In many cases, favourable building conditions were cited as the reason. In some cases this meant that projects’ end-dates could be brought forward, but in many instances the end-date remained unchanged.

Table 3.6: Major infr astructure projects with variances in over-expenditure greater than 10 per cent, by department

Department

Projects proceeding

ahead of schedule

Other reasons for higher

expenditureTotal

Education and Early Childhood Development 4 3 7

Human Services 16 0 16

Innovation, Industry and Regional Development 2 0 2

Justice 2 1 3

Planning and Community Development 0 0 0

Premier and Cabinet 0 0 0

Primary Industries 0 0 0

Sustainability and Environment 0 0 0

Transport 4 7 11

Treasury and Finance 0 0 0

Total (No.) 28 11 39

Total (%) 71.8 28.2 100

Source: Departmental responses to the Committee’s 2008-09 Financial and Performance Outcomes Questionnaire – Part Two

47 An additional $16.4 million more than budgeted was spent on projects which over-spent by less than 10 per cent.

Page 31: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

63

Chapter 3: Public Sector Infrastructure and Asset Investment

Other reasons provided for higher-than-estimated expenditure included:

under-expenditure in 2007-08 leading to funds being carried forward to 2008-09 and spent then;

unanticipated needs to remove high-risk site contaminants from construction sites;

alterations to the schedule or milestones leading to adjusted cash fl ows;

additional design and investigation activities being required; and

land acquisition costing more than originally estimated.

Page 32: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

Report on the 2008-09 Financial and Performance Outcomes

64

Tabl

e 3.

7:

Maj

or in

fras

truc

ture

pro

ject

s w

ith a

ctua

l exp

endi

ture

hig

her t

han

estim

ated

in 2

008-

09

Proj

ect

BIP

No

1 B

udge

t 20

08-0

9 es

timat

ed

expe

nditu

re

2008

-09

Act

ual

expe

nditu

re

Varia

nce

Expl

anat

ion

for v

aria

nce

Expe

nditu

re

2005

-06

to

2007

-08

Tota

l Es

timat

ed

Inve

stm

ent

Rem

aini

ng

expe

nditu

re

($ m

illio

n)($

mill

ion)

(%)

($ m

illio

n)

($ m

illio

n)(%

)

Dep

artm

ent o

f Edu

catio

n an

d Ea

rly C

hild

hood

Dev

elop

men

t

Ben

digo

Edu

catio

n P

lan

– Fl

ora

Hill

– F

lora

Hill

and

G

olde

n S

quar

e S

econ

dary

C

olle

ge (F

lora

Hill

)

2.8

5.3

90.5

Varia

nce

is d

ue to

tend

erin

g an

d co

nstru

ctio

n w

ork

proc

eedi

ng a

head

of

sche

dule

.

0.0

10.0

46.5

Bro

adm

eado

ws

Reg

ener

atio

n –

Hum

e S

enio

r Cam

pus

– B

road

mea

dow

s S

econ

dary

C

olle

ge, H

illcr

est

Sec

onda

ry C

olle

ge,

Erin

bank

Sec

onda

ry

Col

lege

– S

tage

1

(Wes

tmea

dow

s)

1.1

2.6

133.

2Va

rianc

e is

due

to c

onst

ruct

ion

wor

k pr

ocee

ding

ahe

ad o

f sch

edul

e.

0.0

12.0

78.1

Mar

ibyr

nong

Sec

onda

ry

Col

lege

– S

ports

Sch

ool a

t M

arib

yrno

ng (M

arib

yrno

ng)

4.8

9.6

99.1

The

cons

truct

ion

timel

ine

was

am

ende

d du

e to

late

nt s

ite c

ondi

tions

. The

app

rove

d TE

I is

now

$ 1

4.67

4M. T

he T

EI i

ncre

ase

and

expe

nditu

re v

aria

nce

are

both

due

to

cost

s as

soci

ated

with

rem

oval

of h

igh-

risk

site

con

tam

inan

ts.

The

TEI i

ncre

ase

($4.

674M

) was

abl

e to

be

fund

ed fr

om s

avin

gs fr

om o

ther

pro

ject

s

2.2

10.0

-18.

4

Rel

ocat

able

Cla

ssro

om

Ren

ewal

(var

ious

)4.

24.

610

.2–

0.0

26.0

82.2

Tech

nica

l Win

gs a

nd T

rade

E

quip

men

t for

Gov

ernm

ent

Sch

ools

– (v

ario

us)

1.0

1.2

16.7

Varia

nce

is d

ue to

con

stru

ctio

n w

ork

proc

eedi

ng a

head

of s

ched

ule.

15

.050

.067

.7

Page 33: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

65

Chapter 3: Public Sector Infrastructure and Asset Investment

Proj

ect

BIP

No

1 B

udge

t 20

08-0

9 es

timat

ed

expe

nditu

re

2008

-09

Act

ual

expe

nditu

re

Varia

nce

Expl

anat

ion

for v

aria

nce

Expe

nditu

re

2005

-06

to

2007

-08

Tota

l Es

timat

ed

Inve

stm

ent

Rem

aini

ng

expe

nditu

re

($ m

illio

n)($

mill

ion)

(%)

($ m

illio

n)

($ m

illio

n)(%

)

Ultr

anet

(var

ious

sch

ools

)11

.013

.421

.9Fo

llow

ing

the

com

plet

ion

of n

egot

iatio

ns,

a co

ntra

ct w

as s

igne

d in

Jun

e 20

09 a

nd

paym

ents

mad

e in

acc

orda

nce

with

the

term

s of

the

cont

ract

.Th

e B

IP 1

200

8-09

est

imat

e w

as

supp

lem

ente

d by

a c

arry

forw

ard

of fu

nds

from

200

7-08

.

3.4

60.5

72.2

Vict

oria

n C

olle

ge o

f the

A

rts S

econ

dary

Sch

ool

(VC

AS

S) a

nd O

ther

P

roje

cts

– R

epla

cem

ent

Sch

ool (

Sou

thba

nk)

11.3

12.9

14.8

Varia

nce

is d

ue to

con

stru

ctio

n w

ork

proc

eedi

ng a

head

of s

ched

ule.

5.

320

.09.

0

Dep

artm

ent o

f Hum

an S

ervi

ces(a

)

Box

Hill

Hos

pita

l O

utpa

tient

s an

d D

ialy

sis

Cen

tre a

nd A

ssoc

iate

d W

orks

(Box

Hill

)

1.5

2.0

34.4

Favo

urab

le b

uild

ing

cond

ition

s al

low

ed

early

wor

ks to

be

acce

lera

ted

for i

nitia

l st

ages

of c

onst

ruct

ion.

Mai

n co

nstru

ctio

n w

orks

com

plet

ed in

Jun

e 20

08 a

ccor

ding

to

sch

edul

e. M

ajor

pla

nnin

g w

ork

to

be u

nder

take

n as

par

t of t

he o

vera

ll re

deve

lopm

ent o

f the

site

. Ant

icip

ated

to

be c

ompl

eted

by

Mar

ch 2

010.

35.8

38.2

1.2

Cau

lfi el

d G

ener

al M

edic

al

Cen

tre L

ogis

tics

Bui

ldin

g an

d A

ssoc

iate

d W

orks

(C

aulfi

eld)

1.4

1.6

14.9

Favo

urab

le b

uild

ing

cond

ition

s al

low

ed

early

wor

ks to

be

acce

lera

ted

for i

nitia

l st

ages

of c

onst

ruct

ion.

Mai

n co

nstru

ctio

n w

orks

are

pro

gres

sing

to s

ched

ule,

w

ith th

e pr

ojec

t end

-dat

e re

mai

ning

un

chan

ged.

20.9

23.5

4.0

Page 34: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

Report on the 2008-09 Financial and Performance Outcomes

66

Proj

ect

BIP

No

1 B

udge

t 20

08-0

9 es

timat

ed

expe

nditu

re

2008

-09

Act

ual

expe

nditu

re

Varia

nce

Expl

anat

ion

for v

aria

nce

Expe

nditu

re

2005

-06

to

2007

-08

Tota

l Es

timat

ed

Inve

stm

ent

Rem

aini

ng

expe

nditu

re

($ m

illio

n)($

mill

ion)

(%)

($ m

illio

n)

($ m

illio

n)(%

)

Cau

lfi el

d G

ener

al M

edic

al

Cen

tre R

edev

elop

men

t S

tage

2 (C

aulfi

eld)

5.0

7.7

53.1

Favo

urab

le b

uild

ing

cond

ition

s al

low

ed

early

wor

ks to

be

acce

lera

ted

for i

nitia

l st

ages

of c

onst

ruct

ion.

Mai

n co

nstru

ctio

n w

orks

are

pro

gres

sing

to s

ched

ule,

w

ith th

e pr

ojec

t end

-dat

e re

mai

ning

un

chan

ged.

1.7

28.0

66.8

Dan

deno

ng H

ospi

tal

Em

erge

ncy

Dep

artm

ent

Red

evel

opm

ent

(Dan

deno

ng)

0.9

1.8

99.0

Favo

urab

le b

uild

ing

cond

ition

s al

low

ed

early

wor

ks to

be

acce

lera

ted

for i

nitia

l st

ages

of c

onst

ruct

ion.

Mai

n co

nstru

ctio

n w

orks

are

pro

gres

sing

to s

ched

ule,

w

ith th

e pr

ojec

t end

-dat

e re

mai

ning

un

chan

ged.

0.0

25.0

92.8

Fran

ksto

n H

ospi

tal S

tage

2

(Ope

ratin

g Th

eatre

E

xpan

sion

and

Crit

ical

C

are

Red

evel

opm

ent)

(Fra

nkst

on)

11.0

13.9

26.3

Favo

urab

le b

uild

ing

cond

ition

s al

low

ed

early

wor

ks to

be

acce

lera

ted

for i

nitia

l st

ages

of c

onst

ruct

ion.

Mai

n co

nstru

ctio

n w

orks

are

pro

gres

sing

ahe

ad o

f sch

edul

e.

Pro

ject

ant

icip

ated

to b

e co

mpl

eted

by

Sep

tem

ber 2

010.

6.7

45.0

54.3

Kin

gsto

n C

entre

Kitc

hen

Upg

rade

and

Ass

ocia

ted

Wor

ks (H

eath

erto

n)

8.0

14.0

74.7

Favo

urab

le b

uild

ing

cond

ition

s al

low

ed

early

wor

ks to

be

acce

lera

ted

for i

nitia

l st

ages

of c

onst

ruct

ion.

Mai

n co

nstru

ctio

n w

orks

are

pro

gres

sing

to s

ched

ule,

w

ith th

e pr

ojec

t end

-dat

e re

mai

ning

un

chan

ged.

11.5

32.8

22.4

Kin

gsto

n C

entre

R

edev

elop

men

t – S

tage

2

(Che

ltenh

am)

2.2

2.7

24.6

Favo

urab

le b

uild

ing

cond

ition

s al

low

ed

early

wor

ks to

be

acce

lera

ted

for i

nitia

l st

ages

of c

onst

ruct

ion.

Mai

n co

nstru

ctio

n w

orks

are

pro

gres

sing

to s

ched

ule,

w

ith th

e pr

ojec

t end

-dat

e re

mai

ning

un

chan

ged.

0.0

45.0

94.0

Page 35: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

67

Chapter 3: Public Sector Infrastructure and Asset Investment

Proj

ect

BIP

No

1 B

udge

t 20

08-0

9 es

timat

ed

expe

nditu

re

2008

-09

Act

ual

expe

nditu

re

Varia

nce

Expl

anat

ion

for v

aria

nce

Expe

nditu

re

2005

-06

to

2007

-08

Tota

l Es

timat

ed

Inve

stm

ent

Rem

aini

ng

expe

nditu

re

($ m

illio

n)($

mill

ion)

(%)

($ m

illio

n)

($ m

illio

n)(%

)

Latro

be C

omm

unity

H

ealth

Ser

vice

– M

orw

ell

Red

evel

opm

ent (

Mor

wel

l)

2.0

6.7

237.

4Fa

vour

able

bui

ldin

g co

nditi

ons

allo

wed

ea

rly w

orks

to b

e ac

cele

rate

d fo

r ini

tial

stag

es o

f con

stru

ctio

n. M

ain

cons

truct

ion

wor

ks a

re p

rogr

essi

ng to

sch

edul

e,

with

the

proj

ect e

nd-d

ate

rem

aini

ng

unch

ange

d.

0.0

21.0

67.9

Nat

halia

Dis

trict

H

ospi

tal a

nd A

ged

Car

e R

edev

elop

men

t (N

atha

lia)

7.0

7.8

11.1

Favo

urab

le b

uild

ing

cond

ition

s al

low

ed

early

wor

ks to

be

acce

lera

ted

for i

nitia

l st

ages

of c

onst

ruct

ion.

Con

stru

ctio

n w

orks

co

mpl

eted

in D

ecem

ber 2

009,

ahe

ad o

f sc

hedu

le. P

roje

ct in

fi na

ncia

l com

plet

ion

phas

e.

2.4

18.0

43.6

Nor

ther

n H

ospi

tal –

M

enta

l Hea

lth E

xpan

sion

an

d S

hort

Sta

y U

nit

Con

stru

ctio

n (E

ppin

g)

4.1

9.4

128.

4Fa

vour

able

bui

ldin

g co

nditi

ons

allo

wed

ea

rly w

orks

to b

e ac

cele

rate

d fo

r ini

tial

stag

es o

f con

stru

ctio

n. M

ain

cons

truct

ion

wor

ks a

re p

rogr

essi

ng to

sch

edul

e,

with

the

proj

ect e

nd-d

ate

rem

aini

ng

unch

ange

d.

1.5

27.9

61.0

Oliv

ia N

ewto

n-Jo

hn C

ance

r C

entre

(Hei

delb

erg)

5.

06.

122

.5Fa

vour

able

bui

ldin

g co

nditi

ons

allo

wed

ea

rly w

orks

to b

e ac

cele

rate

d fo

r ini

tial

stag

es o

f con

stru

ctio

n. M

ain

cons

truct

ion

wor

ks a

re p

rogr

essi

ng to

sch

edul

e,

with

the

proj

ect e

nd-d

ate

rem

aini

ng

unch

ange

d.

0.0

25.0

75.5

Pen

insu

la C

omm

unity

H

ealth

Ser

vice

R

edev

elop

men

t (H

astin

gs)

6.0

7.8

30.3

Favo

urab

le b

uild

ing

cond

ition

s al

low

ed

early

wor

ks to

be

acce

lera

ted

for i

nitia

l st

ages

of c

onst

ruct

ion.

The

faci

lity

was

offi c

ially

ope

ned

in S

epte

mbe

r 200

9,

ahea

d of

sch

edul

e. P

roje

ct in

fi na

ncia

l co

mpl

etio

n ph

ase.

3.2

13.0

15.2

Page 36: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

Report on the 2008-09 Financial and Performance Outcomes

68

Proj

ect

BIP

No

1 B

udge

t 20

08-0

9 es

timat

ed

expe

nditu

re

2008

-09

Act

ual

expe

nditu

re

Varia

nce

Expl

anat

ion

for v

aria

nce

Expe

nditu

re

2005

-06

to

2007

-08

Tota

l Es

timat

ed

Inve

stm

ent

Rem

aini

ng

expe

nditu

re

($ m

illio

n)($

mill

ion)

(%)

($ m

illio

n)

($ m

illio

n)(%

)

Roy

al M

elbo

urne

Hos

pita

l E

mer

genc

y D

epar

tmen

t R

edev

elop

men

t (P

arkv

ille)

23.8

26.6

11.7

Favo

urab

le b

uild

ing

cond

ition

s al

low

ed

early

wor

ks to

be

acce

lera

ted

for i

nitia

l st

ages

of c

onst

ruct

ion.

All

cons

truct

ion

wor

ks c

ompl

ete

with

the

faci

lity

offi c

ially

op

ened

in O

ctob

er 2

009.

Pro

ject

is in

fi n

anci

al c

ompl

etio

n ph

ase.

25.5

54.7

4.7

Sta

wel

l Hea

lth a

nd

Com

mun

ity C

entre

R

edev

elop

men

t (S

taw

ell)

10.0

12.9

28.6

Favo

urab

le b

uild

ing

cond

ition

s al

low

ed

early

wor

ks to

be

acce

lera

ted

for i

nitia

l st

ages

of c

onst

ruct

ion.

Mai

n co

nstru

ctio

n w

orks

are

pro

gres

sing

to re

vise

d sc

hedu

le.

2.6

20.0

22.8

Sun

bury

Day

Hos

pita

l (S

unbu

ry)

1.0

2.4

142.

7O

rigin

al c

ash fl o

ws

for t

he p

roje

ct w

ere

cons

erva

tivel

y ba

sed

for e

arly

sta

ges.

M

ain

cons

truct

ion

wor

ks a

re p

rogr

essi

ng

to s

ched

ule,

with

the

proj

ect e

nd-d

ate

rem

aini

ng u

ncha

nged

.

0.0

14.0

82.7

Wes

tern

Hos

pita

l R

edev

elop

men

t Sta

ge 1

(F

oots

cray

)

3.1

16.4

437.

7A

ccel

erat

ed c

ash fl o

w d

ue to

con

stru

ctio

n w

orks

on

prio

rity

infra

stru

ctur

e up

grad

es

adva

ncin

g ah

ead

of s

ched

ule.

Pro

activ

e m

anag

emen

t allo

wed

phy

sica

l wor

ks to

co

mm

ence

ear

lier.

Pro

ject

is p

rogr

essi

ng

to s

ched

ule

with

the

proj

ect e

nd-d

ate

rem

aini

ng u

ncha

nged

.

4.0

24.8

17.4

Dep

artm

ent o

f Inn

ovat

ion,

Indu

stry

and

Reg

iona

l Dev

elop

men

t

Ben

digo

Inst

itute

of T

AFE

Cha

rlest

on R

oad

Cam

pus

rede

velo

pmen

t (B

endi

go)

0.8

0.9

11.5

Varia

nce

as a

resu

lt of

the

proj

ect b

eing

sl

ight

ly a

head

of s

ched

ule.

0.

011

.091

.1

Page 37: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

69

Chapter 3: Public Sector Infrastructure and Asset Investment

Proj

ect

BIP

No

1 B

udge

t 20

08-0

9 es

timat

ed

expe

nditu

re

2008

-09

Act

ual

expe

nditu

re

Varia

nce

Expl

anat

ion

for v

aria

nce

Expe

nditu

re

2005

-06

to

2007

-08

Tota

l Es

timat

ed

Inve

stm

ent

Rem

aini

ng

expe

nditu

re

($ m

illio

n)($

mill

ion)

(%)

($ m

illio

n)

($ m

illio

n)(%

)

Sou

th W

est I

nstit

ute

of

TAFE

– W

arrn

ambo

ol

Sta

ge 3

rede

velo

pmen

t (S

tate

fund

ed c

ompo

nent

)

2.5

8.7

247.

3Th

e 20

08-0

9 es

timat

ed e

xpen

ditu

re

did

not i

nclu

de a

ny u

nspe

nt c

arry

over

fro

m 2

007-

08. T

he p

roje

ct e

xper

ienc

ed

sign

ifi ca

nt d

elay

s du

ring

2007

-08

whi

ch

resu

lted

in a

sig

nifi c

ant u

nder

spen

d. T

he

budg

et w

as s

ubse

quen

tly re

phas

ed to

in

corp

orat

e a

revi

sed

budg

et fo

r 200

8-09

of

$7.

37 m

illio

n. O

ver e

xpen

ditu

re re

sulte

d fro

m th

e pr

ojec

t bei

ng a

head

of t

he re

vise

d sc

hedu

le.

1.1

11.0

10.8

Dep

artm

ent o

f Jus

tice(b

)

Bru

nsw

ick

and

Col

lingw

ood

Pol

ice

Com

plex

es –

U

pgra

des

(Bru

nsw

ick

and

Col

lingw

ood)

2.6

3.8

44.1

Pro

ject

incu

rred

add

ition

al c

osts

as

a re

sult

of id

entifi

cat

ion

and

disp

osal

of

haza

rdou

s m

ater

ials

(asb

esto

s) a

nd

conc

eale

d re

dund

ant p

lant

and

equ

ipm

ent.

4.9

12.2

0.0

Org

anis

ed C

rime

and

Cou

nter

Ter

roris

m –

Ass

et

Enh

ance

men

t (S

tate

wid

e)

0.2

2.2

1225

.6A

lthou

gh o

vera

ll pr

ojec

t was

del

iver

ed

behi

nd s

ched

ule,

the

annu

al 2

008-

09

proj

ect s

ched

ule

was

acc

eler

ated

, re

sulti

ng in

the

2008

-09

over

spen

d va

rianc

e. T

he T

EI f

or th

is p

roje

ct w

as

revi

sed

to $

17.2

88m

as

part

of th

e m

id-y

ear b

udge

t upd

ate.

14.3

15.4

0.0

Pol

ice

Sta

tions

Prio

rity

Upg

rade

Pro

gram

– A

sset

E

nhan

cem

ent (

Sta

tew

ide)

2.0

3.4

71.6

Pro

ject

sch

edul

e w

as a

ccel

erat

ed. T

his

has

not a

ffect

ed th

e co

mpl

etio

n da

te.

0.0

10.0

65.7

Dep

artm

ent o

f Tra

nspo

rt(b

)

Bas

s H

ighw

ay D

uplic

atio

n –

Sta

ge 1

Kin

g R

oad

to

Woo

lmer

Roa

d (B

ass,

A

nder

son)

9.0

10.6

17.8

Min

or re

sche

dulin

g.6.

027

.138

.4

Page 38: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

Report on the 2008-09 Financial and Performance Outcomes

70

Proj

ect

BIP

No

1 B

udge

t 20

08-0

9 es

timat

ed

expe

nditu

re

2008

-09

Act

ual

expe

nditu

re

Varia

nce

Expl

anat

ion

for v

aria

nce

Expe

nditu

re

2005

-06

to

2007

-08

Tota

l Es

timat

ed

Inve

stm

ent

Rem

aini

ng

expe

nditu

re

($ m

illio

n)($

mill

ion)

(%)

($ m

illio

n)

($ m

illio

n)(%

)

Bas

s H

ighw

ay D

uplic

atio

n S

tage

5 –

Gra

ntvi

lle to

Kin

g R

oad

(Gra

ntvi

lle)

2.7

6.3

133.

3P

roje

ct c

ompl

eted

.17

.223

.60.

0

Cal

der H

ighw

ay U

pgra

de18

.326

.243

.2R

esch

edul

ing

of la

nd s

ales

to 2

009/

10.

246.

230

6.2

1.0

Dyn

on P

ort R

ail L

ink

(Mel

bour

ne)

34.5

40.2

16.5

Pro

ject

com

plet

ed J

uly

2009

.83

.812

5.1

0.0

Nep

ean

Hw

y B

ridge

R

epla

cem

ent–

Mor

dial

loc

Cre

ek (K

ings

ton

City

)

3.2

3.7

15.6

Acc

eler

atio

n of

wor

ks d

urin

g 20

08-0

9.6.

510

.20.

0

Pou

nd R

oad

– S

outh

G

ipps

land

Hig

hway

Sou

th G

ipps

land

Fre

eway

In

ters

ectio

n U

pgra

de

(Dan

deno

ng)

1.3

1.6

23.1

Add

ition

al d

esig

n an

d in

vest

igat

ion

activ

ities

wer

e un

derta

ken.

0.0

36.8

95.7

Reg

iona

l Rol

lings

tock

(n

on-M

etro

var

ious

)23

.827

.415

.1P

aym

ents

hav

e be

en re

phas

ed b

ased

on

cont

ract

mile

ston

es.

55.2

100.

217

.5

Saf

er R

oad

Infra

stru

ctur

e P

rogr

am 3

(var

ious

)80

.010

1.9

27.4

Ahe

ad o

f bud

get d

urin

g 20

08-0

9 as

a

resu

lt of

the

acce

lera

tion

of w

orks

.55

.072

2.2

78.3

Wes

t Gat

e –

Mon

ash

Free

way

s Im

prov

emen

t P

acka

ge (M

etro

var

ious

)

360.

241

1.1

14.1

Ahe

ad o

f bud

get d

urin

g 20

08-0

9 as

a

resu

lt of

the

acce

lera

tion

of w

orks

.16

0.8

1100

.048

.0

Wes

tern

Hig

hway

R

ealig

nmen

t – A

ntho

ny’s

C

uttin

g (M

elto

n to

Bac

chus

M

arsh

)

5.0

7.7

54.0

Land

acq

uisi

tion

slig

htly

hig

her t

han

estim

ated

.0.

040

.080

.8

Page 39: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

71

Chapter 3: Public Sector Infrastructure and Asset Investment

Proj

ect

BIP

No

1 B

udge

t 20

08-0

9 es

timat

ed

expe

nditu

re

2008

-09

Act

ual

expe

nditu

re

Varia

nce

Expl

anat

ion

for v

aria

nce

Expe

nditu

re

2005

-06

to

2007

-08

Tota

l Es

timat

ed

Inve

stm

ent

Rem

aini

ng

expe

nditu

re

($ m

illio

n)($

mill

ion)

(%)

($ m

illio

n)

($ m

illio

n)(%

)

Wes

tern

Hig

hway

: Dee

r P

ark

Byp

ass

and

Leak

es

Roa

d In

terc

hang

e U

pgra

de

(Dee

r Par

k)

95.1

114.

920

.8P

roje

ct c

ompl

eted

Apr

il 20

09 a

head

of

sche

dule

.23

1.6

331.

00.

0

Not

es: (a

) TE

Is fo

r the

Dep

artm

ent o

f Hum

an S

ervi

ces

are

revi

sed

rath

er th

an o

rigin

al fi

gure

s

(b)

TEIs

for t

he D

epar

tmen

t of J

ustic

e an

d th

e D

epar

tmen

t of T

rans

port

are

as p

ublis

hed

in th

e 20

08-0

9 B

udge

t Inf

orm

atio

n P

aper

No.

1

Sou

rce:

D

epar

tmen

tal r

espo

nses

to th

e C

omm

ittee

’s 2

008-

09 F

inan

cial

and

Per

form

ance

Out

com

es Q

uest

ionn

aire

– P

art T

wo

and

clar

ifi ca

tion

ques

tions

Page 40: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

Report on the 2008-09 Financial and Performance Outcomes

72

3.4. Major i nfrastructure projects with revised completion dates

The Committee sought information from departments regarding infrastructure projects with TEIs in excess of $10 million and budgeted expenditure in 2008-09 which had revised completion dates. In total, there were 94 projects with revised completion dates. Completion dates were brought forward in 24 cases (26 per cent) and postponed in 70 cases (74 per cent). A breakdown by department can be seen in Table 3.8.

Table 3.8: Major infrastructure projects’ completion dates compared to original estimates (summary)

Department Total projects

Brought forward

On time Delayed

(No.) (%) (%) (%)

Education and Early Childhood Development(a) 22 0.0 50.0 45.5

Human Services 52 17.3 53.8 28.8

Innovation, Industry and Regional Development 12 0.0 25.0 75.0

Justice 22 4.5 45.5 50.0

Planning and Community Development 3 0.0 33.3 66.7

Premier and Cabinet 2 0.0 50.0 50.0

Primary Industries 1 0.0 100.0 0.0

Sustainability and Environment 19 26.3 73.7 0.0

Transport 61 14.8 49.2 36.1

Treasury and Finance 0 0.0 1.0 2.0

Total 194 12.4 51.0 36.1

Note: (a) Details of the expected completion date for one project were not supplied.

Source: Departmental responses to the Committee’s 2008-09 Financial and Performance Outcomes Questionnaire – Part Two

The Committee asked departments to provide the reasons for the revised end-dates and these have been presented in Table 3.9 and Table 3.10.

The Committee notes that most departments provided limited meaningful information regarding why works were accelerated.

A range of explanations was provided for those projects that were delayed. In a number of cases, the cause of delays was beyond the control of the project. Issues such as the discovery of asbestos and soil contamination delayed some building projects. Some road works were delayed by adverse weather conditions. In other cases, delays were caused by timber that had been thought to be reusable proving not to be and the discovery of the remains of an early courthouse requiring an archaeological survey.

Delays were also caused by agencies which were beyond the State Government’s control, such as other agencies undertaking projects on adjacent or connected sites, delays to funding from the Commonwealth Government and private companies being placed into administration. Similarly, delays to council approvals, a university taking longer than expected to fi nalise a project’s scope and objections being taken to the Victorian Civil and Administrative Tribunal may also have been beyond the control of the departments.

Page 41: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

73

Chapter 3: Public Sector Infrastructure and Asset Investment

The Committee also notes, however, that a number of the explanations provided by departments suggest issues with planning processes on the departments’ part. These included:

fi nalisation of tender documents taking longer than expected;

redesigns of projects and revisions of project scope; and

projects having to be revised because tenders exceeded project budgets.

The Committee notes that in some cases, these issues caused signifi cant delays, with a number of projects experiencing delays of one to two years for these reasons.

In addition, whilst delays connected with getting other agencies on board and due to town planning issues may in some cases be beyond government departments’ control, in other cases such matters may be refl ective of poor planning or poor project execution by departments. A number of these delays also resulted in the postponement of project completion dates by one to two years.

Almost 63 per cent of projects with delays also had under-spends on their 2008-09 budgets (see Table 3.3), highlighting the inter-connectedness of timeliness and budgets. The Committee notes that there are times when unforeseeable events occur which can delay projects. However, it would appear that there is scope for improvement in departments’ project planning processes to reduce the number of delays.

The Committee also enquired specifi cally about projects for which departments had reported revised completion dates to the Committee in 2007-08.48 Of the 37 projects that continued into 2008-09 where completion dates had previously been revised, approximately half were revised again in 2008-09. Six projects (16 per cent) had completion dates brought forward and 13 projects (35 per cent) had the completion dates further postponed.49

The explanations for these revisions were similar to those generally provided for project delays, primarily adjustments to project scope and site contamination. Delays associated with fi nalising agency participation and contractors being unable to start when originally planned also contributed.50

As with the delays in general, some of these factors are unforeseeable, but some may be avoidable with improved project planning processes. This further emphasises the importance of departments having access to expert guidance both at project initiation and throughout the management of projects, as discussed further in Section 3.5.

48 See Public Accounts and Estimates Committee, Report on the 2007-08 Financial and Performance Outcomes, May 2009, pp.97–101

49 Departmental responses to the Committee’s 2008-09 Financial and Performance Outcomes Questionnaire – Part Two

50 ibid.

Page 42: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

Report on the 2008-09 Financial and Performance Outcomes

74

Tabl

e 3.

9:

Maj

or in

fras

tr uc

ture

pro

ject

s w

ith c

ompl

etio

n da

tes

brou

ght f

orw

ard

Proj

ect

Orig

inal

co

mpl

etio

n da

te

Rev

ised

co

mpl

etio

n da

te

(if a

pplic

able

)

Expl

anat

ion

for r

evis

ion

Dep

artm

ent o

f Hum

an S

ervi

ces

Nor

ther

n H

ospi

tal R

edev

elop

men

t Sta

ge

2a (E

ppin

g)Ju

l-07

Apr

-07

Con

stru

ctio

n co

mpl

ete

and

oper

atio

nal.

Pro

ject

is in

fi na

ncia

l com

plet

ion

phas

e.

Gro

veda

le A

ged

Car

e Fa

cilit

y D

evel

opm

ent (

Gro

veda

le)

Jun-

08M

ay-0

8C

onst

ruct

ion

com

plet

e. P

roje

ct is

in fi

nanc

ial c

ompl

etio

n ph

ase.

Leon

gath

a H

ospi

tal C

ampu

s S

tage

1

Res

iden

tial A

ged

Car

e (L

eong

atha

)Fe

b-10

Apr

-09

All

cons

truct

ion

wor

ks c

ompl

ete

ahea

d of

orig

inal

tim

elin

es. P

roje

ct in

fi na

ncia

l com

plet

ion

phas

e.

Alfr

ed C

entre

Sta

ge 2

(Pra

hran

)Ju

n-10

Jun-

09Fi

rst s

tage

of c

onst

ruct

ion

prog

ress

ed a

head

of s

ched

ule.

Pro

ject

com

plet

ed a

head

of

orig

inal

tim

elin

es.

Pen

insu

la C

omm

unity

Hea

lth S

ervi

ce

Red

evel

opm

ent (

Has

tings

)A

pr-1

0O

ct-0

9Fa

vour

able

bui

ldin

g co

nditi

ons

allo

wed

ear

ly w

orks

to b

e ac

cele

rate

d fo

r ini

tial s

tage

s of

co

nstru

ctio

n. T

he fa

cilit

y w

as o

ffi ci

ally

ope

ned

in S

epte

mbe

r 200

9, a

head

of s

ched

ule.

P

roje

ct in

fi na

ncia

l com

plet

ion

phas

e.

Roy

al M

elbo

urne

Hos

pita

l Em

erge

ncy

Dep

artm

ent R

edev

elop

men

t (P

arkv

ille)

Dec

-09

Oct

-09

Favo

urab

le b

uild

ing

cond

ition

s al

low

ed e

arly

wor

ks to

be

acce

lera

ted

for i

nitia

l sta

ges

of

cons

truct

ion.

All

cons

truct

ion

wor

ks c

ompl

eted

ahe

ad o

f sch

edul

e, w

ith th

e fa

cilit

y offi c

ially

op

ened

in O

ctob

er 2

009.

Pro

ject

is in

fi na

ncia

l com

plet

ion

phas

e.

Nat

halia

Dis

trict

Hos

pita

l and

Age

d C

are

Red

evel

opm

ent (

Nat

halia

)M

ar-1

0D

ec-0

9Fa

vour

able

bui

ldin

g co

nditi

ons

allo

wed

ear

ly w

orks

to b

e ac

cele

rate

d fo

r ini

tial s

tage

s of

co

nstru

ctio

n. A

ll co

nstru

ctio

n w

orks

com

plet

ed a

head

of s

ched

ule,

with

the

faci

lity

offi c

ially

op

ened

in O

ctob

er 2

009.

Pro

ject

is in

fi na

ncia

l com

plet

ion

phas

e.

Pla

cem

ent a

nd S

uppo

rt R

esid

entia

l Fa

cilit

y R

enew

al S

trate

gy –

Sta

ge 6

(S

tate

wid

e)

Mar

-11

Mar

-10

Ele

ven

of th

e pl

anne

d fo

urte

en h

ouse

s ar

e co

mpl

eted

and

occ

upie

d. R

emai

ning

hou

ses

sche

dule

d to

be

com

plet

ed in

Mar

ch 2

010.

Thi

s pr

ojec

t was

com

plet

ed a

head

of t

he o

rigin

al

fore

cast

com

plet

ion

date

due

to fa

vour

able

bui

ldin

g co

nditi

ons.

Fran

ksto

n H

ospi

tal S

tage

2 (O

pera

ting

Thea

tre E

xpan

sion

and

Crit

ical

Car

e R

edev

elop

men

t) (F

rank

ston

)

Feb-

11S

ep-1

0M

ain

cons

truct

ion

wor

ks a

re p

rogr

essi

ng a

head

of s

ched

ule,

for c

ompl

etio

n by

Sep

tem

ber 2

010.

Dep

artm

ent o

f Sus

tain

abili

ty a

nd E

nviro

nmen

t

Mel

bour

ne Z

oo S

eal P

ool R

edev

elop

men

t - C

onst

ruct

ion

(Par

kvill

e)Ju

n-10

Dec

-09

The

proj

ect w

as c

ompl

eted

ahe

ad o

f sch

edul

e du

e to

the

Zoo

usin

g its

inte

rnal

labo

ur to

fa

st tr

ack

the

land

scap

ing

and

inte

rpre

tatio

n w

ork.

In a

dditi

on, t

he s

eals

and

pen

guin

s se

ttled

wel

l int

o th

e ne

w fa

cilit

y an

d th

eref

ore

the

exhi

bit c

ould

ope

n ah

ead

of s

ched

ule.

Page 43: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

75

Chapter 3: Public Sector Infrastructure and Asset Investment

Proj

ect

Orig

inal

co

mpl

etio

n da

te

Rev

ised

co

mpl

etio

n da

te

(if a

pplic

able

)

Expl

anat

ion

for r

evis

ion

Nat

iona

l Wat

er In

itiat

ive

- Mac

alis

ter -

C

onst

ruct

ion

(Boi

sdal

e)E

nd o

f 201

1D

ec-1

0Th

e C

omm

onw

ealth

and

Sta

te a

gree

d to

pro

vide

fund

ing

to e

nabl

e ac

cele

rate

d m

ilest

ones

.

Sus

tain

able

Wat

er In

itiat

ives

- M

aint

enan

ce (S

tate

wid

e)Ju

n-12

Jun-

11Th

e tim

ing

of a

vaila

ble

fund

ing

will

allo

w th

e w

orks

to b

e co

mpl

eted

by

June

201

1.

Wim

mer

a-M

alle

e P

ipel

ine

Pro

ject

- S

tate

C

ompo

nent

- C

onst

ruct

ion

(Mal

lee/

Wim

mer

a)Ju

n-15

Apr

-10

The

Com

mon

wea

lth a

nd S

tate

bro

ught

forw

ard

fund

ing

so th

e pr

ojec

t cou

ld b

e ac

cele

rate

d in

reco

gniti

on o

f the

unp

rece

dent

ed d

roug

ht a

nd th

e ur

gent

nee

d to

sec

ure

wat

er s

uppl

y fo

r th

e W

imm

era-

Mal

lee

regi

on.

Wim

mer

a-M

alle

e P

ipel

ine

Pro

ject

- C

omm

onw

ealth

Com

pone

nt -

Con

stru

ctio

n (M

alle

e/W

imm

era)

Jun-

15A

pr-1

0

The

Com

mon

wea

lth a

nd S

tate

bro

ught

forw

ard

fund

ing

earli

er s

o th

e pr

ojec

t cou

ld b

e ac

cele

rate

d in

reco

gniti

on o

f the

unp

rece

dent

ed d

roug

ht a

nd th

e ur

gent

nee

d to

sec

ure

wat

er s

uppl

y fo

r the

Wim

mer

a-M

alle

e re

gion

Dep

artm

ent o

f Tra

nspo

rt

Cau

lfi el

d–D

ande

nong

Rai

l Cor

ridor

Sta

ge O

ne –

Cra

nbou

rne

Sta

blin

g an

d S

tatio

n U

pgra

de (C

ranb

ourn

e)

Jun-

09La

te 2

008

Pro

ject

acc

eler

ated

and

com

plet

ed a

head

of s

ched

ule.

Cra

nbou

rne

Fran

ksto

n R

oad

Dup

licat

ion

(10.

2km

–11.

9km

) – C

entre

Rd

to W

este

rn

Por

t Hw

y (L

angw

arrin

)

Feb-

09La

te 2

008

Pro

ject

com

plet

ed.

Der

rimut

Roa

d D

uplic

atio

n (3

.5km

–5.

12km

) – H

ogan

s R

d to

Say

ers

Rd

(Hop

pers

Cro

ssin

g)

Mar

-09

Late

200

8P

roje

ct a

ccel

erat

ed a

nd c

ompl

eted

ahe

ad o

f sch

edul

e.

Dup

licat

ion

of T

hom

pson

Roa

d –

Cra

nbou

rne

Dec

-09

Mid

200

9R

oad

open

ed m

id 2

009.

Gee

long

Rin

g R

oad

– B

ypas

s/N

ew R

oad

(Gee

long

)D

ec-0

9M

id 2

009

Pro

ject

com

plet

ed.

Hum

e H

ighw

ay –

Don

nybr

ook

Roa

d In

terc

hang

e –

Gra

de S

epar

atio

n (B

ever

idge

, Cra

igie

burn

)

Jun-

09E

arly

200

9P

roje

ct c

ompl

eted

.

Nor

th M

elbo

urne

Sta

tion

Inte

rcha

nge

Upg

rade

(Nor

th M

elbo

urne

)D

ec-1

0La

te 2

009

Pro

ject

com

plet

ed.

Page 44: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

Report on the 2008-09 Financial and Performance Outcomes

76

Proj

ect

Orig

inal

co

mpl

etio

n da

te

Rev

ised

co

mpl

etio

n da

te

(if a

pplic

able

)

Expl

anat

ion

for r

evis

ion

Trac

k D

uplic

atio

n: C

lifto

n H

ill to

Wes

tgar

th

(Met

ro v

ario

us)

Jun-

10M

id 2

009

Trai

ns b

egan

runn

ing

over

the

new

brid

ge in

Jan

200

9, w

ith p

ract

ical

com

plet

ion

by m

id

2009

. Onl

y m

inor

wor

ks fo

r com

plet

ion

early

201

0.

Wes

tern

Hig

hway

: Dee

r Par

k B

ypas

s an

d Le

akes

Roa

d In

terc

hang

e U

pgra

de (D

eer

Par

k)

Dec

-09

1st h

alf 2

009

Pro

ject

com

plet

ed a

head

of s

ched

ule.

Sou

rce:

D

epar

tmen

tal r

espo

nses

to th

e C

omm

ittee

’s 2

008-

09 F

inan

cial

and

Per

form

ance

Out

com

es Q

uest

ionn

aire

– P

art T

wo

and

clar

ifi ca

tion

ques

tions

Page 45: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

77

Chapter 3: Public Sector Infrastructure and Asset Investment

Tabl

e 3.

10:

Maj

or in

f ras

truc

ture

pro

ject

s w

ith c

ompl

etio

n da

tes

dela

yed

Proj

ect

Orig

inal

co

mpl

etio

n da

te

Rev

ised

co

mpl

etio

n da

te (i

f ap

plic

able

)

Expl

anat

ion

for r

evis

ion

Dep

artm

ent o

f Edu

catio

n an

d Ea

rly C

hild

hood

Dev

elop

men

t

Alb

ert P

ark

Sec

onda

ry C

olle

ge -

Rep

lace

men

t S

choo

ls (A

lber

t Par

k)M

ay-1

0S

ep-1

0S

ite c

onta

min

atio

n re

quire

d m

ore

com

plex

rem

edia

tion

and

dela

yed

the

cons

truct

ion

com

men

cem

ent.

Ben

digo

Edu

catio

n P

lan

- Reg

ener

atio

n -

Kan

garo

o Fl

at S

econ

dary

Col

lege

(Kan

garo

o Fl

at)

May

-09

Sep

-10

Fina

lisat

ion

of te

nder

doc

umen

ts ta

king

long

er th

an o

rigin

ally

ant

icip

ated

.

Bro

adm

eado

ws

Reg

ener

atio

n - R

egen

erat

ion

- Bro

adm

eado

ws

Sec

onda

ry C

olle

ge

and

Bro

adm

eado

ws

Prim

ary

Sch

ool

(Bro

adm

eado

ws)

Mar

-09

Sep

-09

An

early

chi

ldho

od c

entre

was

add

ed a

s a

varia

nce

to th

e pr

ojec

t sco

pe.

Bro

adm

eado

ws

Reg

ener

atio

n - R

egen

erat

ion

- Erin

bank

Sec

onda

ry C

olle

ge a

nd H

illcr

est

Sec

onda

ry C

olle

ge (B

road

mea

dow

s)

Sep

-09

Nov

-09

Sta

ge 2

of c

onst

ruct

ion

was

aw

arde

d to

the

sam

e bu

ilder

, who

was

wor

king

on

both

site

s co

ncur

rent

ly, w

hich

del

ayed

the

com

plet

ion

of s

tage

1.

Mar

ibyr

nong

Sec

onda

ry C

olle

ge -

Spo

rts

Sch

ool a

t Mar

ibyr

nong

(Mar

ibyr

nong

)D

ec-0

9A

pr-1

0Th

e co

nstru

ctio

n tim

elin

e w

as a

men

ded

due

to la

tent

site

con

ditio

ns.

Wes

tern

Hei

ghts

Reg

ener

atio

n - R

egen

erat

ion

- Wes

tern

Hei

ghts

Sec

onda

ry C

olle

ge -

Thre

e C

ampu

ses

(Ham

lyn

Hei

ghts

)

Dec

-10

Mar

-11

Res

olut

ion

of th

e Jo

int U

se A

gree

men

t and

land

pur

chas

e is

sues

with

the

City

of G

reat

er

Gee

long

was

ach

ieve

d an

d co

nstru

ctio

n co

mm

ence

d.

Ben

digo

Edu

catio

n P

lan

- Eag

leha

wk

- E

agle

haw

k S

econ

dary

Col

lege

- S

tage

2

(Eag

leha

wk)

May

-09

Sep

-10

Fina

lisat

ion

of te

nder

doc

umen

ts ta

king

long

er th

an o

rigin

ally

ant

icip

ated

.

Ben

digo

Edu

catio

n P

lan

- Kan

garo

o Fl

at -

Kan

garo

o Fl

at S

econ

dary

Col

lege

- S

tage

2

(Kan

garo

o Fl

at)

May

-09

Sep

-10

Fina

lisat

ion

of te

nder

doc

umen

ts ta

king

long

er th

an o

rigin

ally

ant

icip

ated

.

Dan

deno

ng -

Reg

ener

atio

n - D

ande

nong

Hig

h,

Cle

elan

d S

econ

dary

Col

lege

and

Dov

eton

S

econ

dary

Col

lege

- S

tage

2 (D

ande

nong

)

Jun-

10Ja

n-11

Del

ay in

aw

ardi

ng th

e co

ntra

ct a

s th

e sc

ope

of w

ork

chan

ged

at th

e de

sign

and

de

velo

pmen

t sta

ge.

Page 46: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

Report on the 2008-09 Financial and Performance Outcomes

78

Proj

ect

Orig

inal

co

mpl

etio

n da

te

Rev

ised

co

mpl

etio

n da

te (i

f ap

plic

able

)

Expl

anat

ion

for r

evis

ion

John

Mon

ash

Sci

ence

Sch

ool -

Mon

ash

Uni

vers

ity, C

layt

on C

ampu

s (C

layt

on)

Nov

-09

Mar

-10

Pro

ject

com

plet

ion

revi

sed

due

to a

djac

ent w

orks

bei

ng c

ompl

eted

by

Mon

ash

Uni

vers

ity.

Dep

artm

ent o

f Hum

an S

ervi

ces

Box

Hill

Hos

pita

l Out

patie

nts

and

Dia

lysi

s C

entre

and

Ass

ocia

ted

Wor

ks (B

ox H

ill)

Jun-

08M

ar-1

0Fa

vour

able

bui

ldin

g co

nditi

ons

allo

wed

ear

ly w

orks

to b

e ac

cele

rate

d fo

r ini

tial s

tage

s of

co

nstru

ctio

n. M

ain

cons

truct

ion

wor

ks c

ompl

eted

in J

une

2008

acc

ordi

ng to

sch

edul

e.

Maj

or p

lann

ing

wor

k to

be

unde

rtake

n as

par

t of t

he o

vera

ll re

deve

lopm

ent o

f the

site

. A

ntic

ipat

ed to

be

com

plet

ed b

y M

arch

201

0.

Cau

lfi el

d G

ener

al M

edic

al C

entre

Log

istic

s B

uild

ing

and

Ass

ocia

ted

Wor

ks (C

aulfi

eld)

Mar

-08

Dec

-09

A re

visi

on o

f the

ser

vice

pla

n re

sulte

d in

a fu

rther

revi

ew o

f the

mas

terp

lan,

del

ayin

g th

e fu

ll si

te d

evel

opm

ent.

Ove

rall,

the

proj

ect w

as c

ompl

eted

by

its re

vise

d en

d-da

te o

f D

ecem

ber 2

009.

Cau

lfi el

d G

ener

al M

edic

al C

entre

R

edev

elop

men

t Sta

ge 2

(Cau

lfi el

d)N

ov-1

0D

ec-1

0P

roje

ct p

rogr

essi

ng to

sch

edul

e.

Dis

abili

ty S

ervi

ces

Stra

tegi

c R

efur

bish

men

t an

d R

epla

cem

ent P

rogr

am S

tage

2

(Sta

tew

ide)

Mar

-09

Feb-

10Th

e In

nova

tive

Hou

sing

Opp

ortu

nitie

s P

rogr

am (I

HO

P) p

ortio

n of

the

proj

ect h

as b

een

amen

ded

to F

ebru

ary

2010

, due

to fi

nalis

atio

n of

the

targ

et c

lient

gro

up a

nd in

corp

orat

ion

into

the

Dep

artm

ent’s

pub

lic a

nd s

ocia

l hou

sing

dev

elop

men

t pro

gram

.

Eas

tern

Hea

lth M

enta

l Hea

lth R

edev

elop

men

t S

tage

1 (B

ox H

ill, R

ingw

ood

Eas

t)A

pr-0

9Ju

n-09

Som

e m

inor

del

ays

to th

e pr

ojec

t wer

e ex

perie

nced

due

to g

ende

r sen

sitiv

ity is

sues

id

entifi

ed

as p

art o

f the

des

ign

deve

lopm

ent p

hase

. The

se is

sues

wer

e re

quire

d to

be

addr

esse

d in

con

sulta

tion

with

the

agen

cy b

efor

e th

e de

sign

pro

ject

cou

ld b

e fi n

alis

ed a

nd

cons

truct

ion

com

men

ced.

Ele

ctro

nic

Pre

scrib

ing

in K

ey V

icto

rian

Hos

pita

ls (S

tate

wid

e)Ju

n-09

Dec

-10

Del

ays

asso

ciat

ed w

ith fi

nalis

ing

agen

cy p

artic

ipat

ion

resu

lted

in d

elay

s. P

roje

ct e

xpec

ted

to b

e co

mpl

eted

by

Dec

201

0.

Gee

long

Hos

pita

l Em

erge

ncy

Dep

artm

ent

Red

evel

opm

ent (

Gee

long

)D

ec-0

8M

ar-0

9P

roje

ct c

ompl

ete

and

is in

fi na

ncia

l com

plet

ion

phas

e. M

inor

def

ect a

nd fa

ult r

epor

t is

the

reas

on fo

r the

revi

sed

com

plet

ion

date

of M

arch

200

9.

Gra

ce M

cKel

lar C

entre

– R

edev

elop

men

t S

tage

2 (G

eelo

ng)

Jun-

07Ju

n-09

The

mai

n pr

ojec

t red

evel

opm

ent w

as c

ompl

ete

and

faci

litie

s op

erat

iona

l in

June

200

7 ac

cord

ing

to s

ched

ule.

A. n

umbe

r of m

inor

enh

ance

men

ts/m

inor

wor

ks id

entifi

ed

with

in

the

orig

inal

rnas

terp

lan

wer

e un

derta

ken

follo

win

g co

mpl

etio

n of

the

mai

n fa

cilit

y, d

elay

ing

over

all fi

nan

cial

com

plet

ion

of th

e pr

ojec

t. A

Il w

orks

hav

e no

w b

een

com

plet

ed.

Kew

Res

iden

tial S

ervi

ces

Red

evel

opm

ent

(Kew

)A

pr-0

8Ju

n-09

Del

ays

to c

onst

ruct

ion

of th

e on

-site

hou

ses

aros

e du

ring

the

proj

ect d

ue to

cha

nge

in

owne

rshi

p of

the

lead

con

tract

or. T

he o

ff-si

te h

ouse

s w

ere

com

plet

ed a

ccor

ding

to th

e or

igin

al s

ched

ule,

with

on-

site

hou

ses

com

plet

ed b

y th

e re

vise

d en

d-da

te.

Page 47: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

79

Chapter 3: Public Sector Infrastructure and Asset Investment

Proj

ect

Orig

inal

co

mpl

etio

n da

te

Rev

ised

co

mpl

etio

n da

te (i

f ap

plic

able

)

Expl

anat

ion

for r

evis

ion

Kin

gsto

n C

entre

Kitc

hen

Upg

rade

and

A

ssoc

iate

d W

orks

(Hea

ther

ton)

Dec

-08

Dec

-10

Crit

ical

add

ition

al in

frast

ruct

ure

wor

ks, a

s w

ell a

s co

st o

verr

uns

asso

ciat

ed w

ith te

nder

on

Pro

duct

ion

Kitc

hen

has

caus

ed d

elay

s to

the

over

all p

roje

ct a

nd T

EI.

Add

ition

al T

EI h

as

been

fund

ed fr

om te

nder

sav

ings

from

the

Cas

ey A

ged

Car

e D

evel

opm

ent.

Wor

ks a

re

prog

ress

ing

to re

vise

d pr

ogra

m a

nd s

ched

uled

for c

ompl

etio

n in

late

201

0.

Nor

th R

ichm

ond

Com

mun

ity H

ealth

Cen

tre

Rel

ocat

ion

(Nor

th R

ichm

ond)

Dec

-09

Dec

-11

Tow

n pl

anni

ng is

sues

affe

cted

pro

gres

sion

of t

he p

roje

ct, r

esul

ting

in a

n ov

eral

l del

ay.

Faci

lity

rede

sign

and

esc

alat

ion

of c

onst

ruct

ion

cost

s ov

er th

e ex

tend

ed d

evel

opm

ent

perio

d ha

s re

sulte

d in

incr

ease

d co

sts

for t

he o

vera

ll pr

ojec

t. A

dditi

onal

TE

I has

bee

n fu

nded

from

sav

ings

with

in o

ther

TE

I fun

ded

proj

ects

. An

alte

rnat

e si

te h

as b

een

iden

tifi e

d an

d th

e pr

ojec

t has

reco

mm

ence

d.

Roc

hest

er a

nd E

lmor

e D

istri

ct H

ealth

S

ervi

ce :

Roc

hest

er T

heat

re a

nd H

ospi

tal

Red

evel

opm

ent (

Roc

hest

er)

Sep

-09

Mar

-10

Asb

esto

s di

scov

ered

dur

ing

dem

oliti

on w

orks

has

resu

lted

in a

revi

sed

end-

date

of

Mar

-201

0.

Sta

wel

l Hea

lth a

nd C

omm

unity

Cen

tre

Red

evel

opm

ent (

Sta

wel

l)D

ec-0

9Fe

b-10

Min

or d

elay

s ex

perie

nced

due

to u

nfor

esee

n si

te c

ondi

tions

. Pro

gres

sing

to re

vise

d sc

hedu

le, w

ith a

pra

ctic

al c

ompl

etio

n da

te o

f Feb

ruar

y 20

10.

War

rack

nabe

al N

ursi

ng H

ome

Sta

ge 1

R

edev

elop

men

t (W

arra

ckna

beal

)M

ay-0

8Ju

n-09

Red

esig

ns o

n pl

anni

ng o

ptio

ns c

ause

d in

itial

con

stru

ctio

n de

lays

. Mai

n co

nstru

ctio

n w

orks

co

mpl

eted

with

in o

rigin

al ti

mel

ines

. Pro

ject

is in

fi na

ncia

l com

plet

ion/

defe

ct li

abili

ty p

hase

.

War

rnam

bool

Hos

pita

l Red

evel

opm

ent –

Sta

ge

1 (W

arrn

ambo

ol)

Sep

-10

Feb-

11Fi

nalis

atio

n an

d pr

ocur

emen

t of a

new

site

for t

he a

mbu

lanc

e st

atio

n ha

s re

sulte

d in

an

over

all d

elay

to th

e pr

ojec

t. A

ll w

orks

com

plet

ed e

xcep

t for

the

com

plet

ion

of th

e ne

w

ambu

lanc

e st

atio

n. A

ntic

ipat

ed to

be

com

plet

ed b

y Fe

brua

ry 2

011.

Dep

artm

ent o

f Inn

ovat

ion,

Indu

stry

and

Reg

iona

l Dev

elop

men

t

Aut

omot

ive

Cen

tre o

f Exc

elle

nce,

Kan

gan

Bat

man

TA

FE (D

ockl

ands

) – S

tage

2Ju

n-11

Sep

-11

The

proj

ect h

as b

een

dela

yed

due

to th

e ne

cess

ary

rem

edia

tion

of s

oil c

onta

min

atio

n ar

ound

a d

ecom

mis

sion

ed m

ain

trunk

sew

er.

Ben

digo

Inst

itute

of T

AFE

– C

harle

ston

Roa

d C

ampu

s re

deve

lopm

ent (

Ben

digo

)Ju

n-09

Jun-

11A

dela

y in

com

plet

ing

the

tend

er d

ocum

enta

tion

has

been

exp

erie

nced

. Pro

ject

ant

icip

ated

to

be

com

plet

ed b

y Ju

ne 2

011.

The

proj

ect w

as o

rigin

ally

fund

ed fo

r $6.

0 m

illio

n w

ith a

com

plet

ion

date

of J

une

2009

. A

revi

ew o

f the

pro

ject

sco

pe re

sulte

d in

the

addi

tiona

l Sta

te fu

ndin

g of

$5.

0 m

illio

n w

ith a

co

nseq

uent

late

r com

plet

ion

date

.

Page 48: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

Report on the 2008-09 Financial and Performance Outcomes

80

Proj

ect

Orig

inal

co

mpl

etio

n da

te

Rev

ised

co

mpl

etio

n da

te (i

f ap

plic

able

)

Expl

anat

ion

for r

evis

ion

Chi

shol

m In

stitu

te o

f TA

FE –

Tra

de

(Aut

omot

ive

& L

ogis

tics)

Tra

inin

g C

entre

(D

ande

nong

) – C

omm

onw

ealth

sup

porte

d pr

ojec

t

Dec

-09

Jun-

11Th

e de

lay

to th

e pr

ojec

t can

be

attri

bute

d to

:

The

desi

gn te

am w

as u

nabl

e to

mee

t doc

umen

tatio

n m

ilest

one

date

s du

e to

un

certa

inty

at t

he T

AFE

on

the fi n

al p

roje

ct s

cope

; and

co

nstru

ctio

n te

nder

s re

ceiv

ed e

xcee

ded

the

proj

ect b

udge

t and

the

desi

gn w

as

subj

ecte

d to

an

exte

nsiv

e va

lue

man

agem

ent p

roce

ss.

A bu

ilder

has

now

bee

n ap

poin

ted

and

cons

truct

ion

prog

ress

cla

ims

will

ens

ure

a st

eady

ca

sh fl

ow.

Nor

ther

n M

elbo

urne

Inst

itute

of T

AFE

Cam

pus

rede

velo

pmen

t Sta

ge 1

(Epp

ing)

Jan-

11Ju

n-11

Ther

e w

as a

del

ay o

f app

roxi

mat

ely

six

wee

ks w

hile

Val

ue M

anag

emen

t Stu

dy to

ok p

lace

. Th

e de

sign

team

was

una

ble

to m

eet t

he d

ocum

enta

tion

mile

ston

e da

tes.

The

tend

ers

rece

ived

exc

eede

d th

e pr

ojec

t bud

get a

nd th

e de

sign

has

bee

n su

bjec

ted

to a

n ex

tens

ive

valu

e m

anag

emen

t pro

cess

whi

ch h

as a

dded

six

mon

ths

to th

e pr

ojec

t pr

ogra

m.

Prin

cess

Pie

r Res

tora

tion

(Por

t Mel

bour

ne)

Dec

-09

Dec

-10

The

proj

ect h

as b

een

dela

yed

due

to th

e ne

ed to

repl

ace

sign

ifi ca

nt a

mou

nts

of th

e ex

istin

g tim

ber,

whi

ch w

as in

itial

ly th

ough

t to

be re

usab

le. A

dditi

onal

fund

ing

of $

20 m

illio

n to

com

plet

e th

e w

orks

has

bee

n ap

prov

ed.

Sou

th W

est I

nstit

ute

of T

AFE

– W

arrn

ambo

ol

stag

e 3

rede

velo

pmen

t (S

tate

fund

ed

com

pone

nt)

Dec

-08

Jul-0

9G

roun

d ex

cava

tion

afte

r dem

oliti

on re

veal

ed th

e fo

otin

gs o

f an

orig

inal

cou

rt ho

use.

The

su

bseq

uent

arc

haeo

logi

cal s

urve

y ha

d an

impa

ct o

n th

e pr

ogra

m.

Tend

ers

rece

ived

exc

eede

d th

e pr

ojec

t bud

get a

nd th

e de

sign

was

sub

ject

ed to

an

exte

nsiv

e va

lue

man

agem

ent p

roce

ss, r

e-do

cum

enta

tion

and

re-te

nder

ing.

Tech

nica

l Edu

catio

n C

entre

s (v

ario

us)

Jun-

09N

ov-0

9S

tate

fund

ing

for T

echn

ical

Edu

catio

n C

entre

s (T

EC

) con

sist

s of

four

pro

ject

s, o

f whi

ch

thre

e ar

e on

sch

edul

e. Is

sues

sur

roun

ding

the

exis

ting

Bre

w T

ower

at t

he B

alla

rat

Tech

nica

l Edu

catio

n C

entre

are

sig

nifi c

antly

impa

ctin

g on

this

pro

ject

. As

the

Sch

ool o

f M

ines

car

par

k pr

ojec

t is

inte

rlink

ed w

ith th

e B

alla

rat T

echn

ical

Edu

catio

n C

entre

, thi

s pr

ojec

t is

impa

cted

by

the

lack

of p

rogr

ess.

Ana

lyse

s of

the

optio

ns to

pro

ceed

are

bei

ng

unde

rtake

n su

bjec

t to

Min

iste

rial a

ppro

val.

Vict

oria

Uni

vers

ity –

Con

solid

atio

n of

E

ngin

eerin

g an

d IC

T –

Com

mon

wea

lth

supp

orte

d pr

ojec

t

Jun-

07M

ay-0

8Th

e pr

ojec

t com

plet

ed in

May

200

8. T

he d

elay

s to

the

com

plet

ion

date

wer

e at

tribu

ted

to th

e U

nive

rsity

not

bei

ng a

ble

to s

ettle

on

a fi n

al s

cope

for t

he p

roje

ct. F

inal

pro

ject

pa

ymen

ts w

ere

with

held

unt

il th

e bu

ilder

com

plet

ed m

ajor

rect

ifi ca

tions

.

Page 49: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

81

Chapter 3: Public Sector Infrastructure and Asset Investment

Proj

ect

Orig

inal

co

mpl

etio

n da

te

Rev

ised

co

mpl

etio

n da

te (i

f ap

plic

able

)

Expl

anat

ion

for r

evis

ion

Will

iam

Ang

liss

Inst

itute

of T

AFE

– N

ew

teac

hing

faci

lity

and

cam

pus

rede

velo

pmen

t –

Com

mon

wea

lth s

uppo

rted

proj

ect

May

-08

Dec

-08

The

initi

al p

roje

ct p

rogr

am d

id n

ot ta

ke in

to a

ccou

nt th

e di

ffi cu

lties

of w

orki

ng o

n a

very

tig

ht in

ner c

ity c

ampu

s an

d th

e is

sues

of h

azar

dous

mat

eria

ls re

mov

al d

isco

vere

d in

the

1930

s bu

ildin

gs th

at h

ad to

be

dem

olis

hed.

Dep

artm

ent o

f Jus

tice

Ara

rat P

olic

e S

tatio

n (P

olic

e S

tatio

ns P

rogr

am

2007

-08)

– C

onst

ruct

ion

(Ara

rat)

Jun-

10O

ct-1

0P

roje

ct d

elay

ed d

ue to

the

plan

ning

pro

cess

pro

gres

sing

thro

ugh

the

Vict

oria

n C

ivil

and

Adm

inis

trativ

e Tr

ibun

al (V

CAT

).

Bru

nsw

ick

and

Col

lingw

ood

Pol

ice

Com

plex

es

– U

pgra

des

(Bru

nsw

ick

and

Col

lingw

ood)

Jun-

08A

ug-0

9P

roje

ct d

elay

ed a

s a

resu

lt of

iden

tifi c

atio

n an

d di

spos

al o

f haz

ardo

us m

ater

ials

(asb

esto

s)

and

conc

eale

d re

dund

ant p

lant

and

equ

ipm

ent.

Mel

bour

ne N

orth

Pol

ice

Sta

tion

– C

onst

ruct

ion

(Car

lton–

Nor

th M

elbo

urne

)N

ov-0

6A

ug-1

0P

roje

ct s

ignifi c

antly

del

ayed

due

to o

rigin

al s

ite id

entifi

ed

for c

ompu

lsor

y ac

quis

ition

pro

ved

unsu

itabl

e du

e to

con

tam

inat

ion

and,

acc

ordi

ngly,

a s

econ

d si

te w

as id

entifi

ed

and

the

com

puls

ory

acqu

isiti

on p

roce

ss re

com

men

ced.

Car

rum

Dow

ns P

olic

e S

tatio

n (P

olic

e S

tatio

ns

Pro

gram

200

7-08

) – C

onst

ruct

ion

(Car

rum

D

owns

)

Jun-

10A

ug-1

0P

roje

ct d

elay

ed d

ue to

pro

tract

ed s

ite id

entifi

cat

ion

and

acqu

isiti

on p

roce

ss.

Inte

grat

ed C

ourts

Man

agem

ent S

yste

m

(ICM

S) –

Ass

et E

nhan

cem

ent (

Sta

tew

ide)

Sep

-09

Dec

-10

Pro

ject

del

ayed

due

to th

e co

ntra

ctor

hav

ing

sign

ifi ca

nt is

sues

in th

e de

sign

and

roll-

out o

f th

e so

ftwar

e, a

long

with

var

iatio

ns to

the

orig

inal

sco

pe. T

he c

apita

l bud

get f

or th

is p

roje

ct

has

been

fully

spe

nt, h

owev

er n

o fu

rther

ass

et fu

ndin

g w

ill b

e so

ught

from

DTF

with

the

rem

aind

er o

f the

fund

ing

to c

ome

from

out

put b

udge

t and

ope

ratio

nal c

ost s

avin

gs.

Just

ice

Sys

tem

Maj

or C

rimes

Res

ourc

ing

Nee

ds –

Ass

et E

nhan

cem

ent (

Sta

tew

ide)

Mar

-06

Apr

-10

The

initi

al s

tage

of t

he p

roje

ct w

as s

ignifi c

antly

del

ayed

due

to c

hang

es to

the

syst

em

requ

irem

ents

, the

pro

ject

team

and

man

agem

ent.

The

proj

ect w

as th

en fu

rther

del

ayed

w

hen

the

priv

ate

sect

or s

uppl

ier f

aile

d to

del

iver

ser

vice

s an

d w

as te

rmin

ated

, lea

ding

to

the

proj

ect m

anag

emen

t dec

isio

n to

dev

elop

the

syst

em in

-hou

se in

Mar

ch 2

008.

Thi

s le

d to

cha

nges

to th

e pr

ojec

t sco

pe, a

s w

ell a

s th

e pl

anne

d tw

o-ph

ase

deliv

ery

of th

e sy

stem

be

ing

chan

ged

to a

sin

gle

deliv

ery.

The

sys

tem

is n

ow in

its fi n

al s

essi

ons

of te

stin

g pr

ior t

o go

live

in A

pril

2010

.

Kyn

eton

Pol

ice

Sta

tion

(Pol

ice

Sta

tions

P

rogr

am 2

007-

08) –

Con

stru

ctio

n (K

ynet

on)

Jun-

10A

ug-1

0P

roje

ct d

elay

ed d

ue to

pro

tract

ed c

ounc

il pl

anni

ng p

roce

ss, a

long

with

add

ition

al

cond

ition

s im

pose

d by

Her

itage

Vic

toria

, whi

ch re

sulte

d in

a re

desi

gn o

f the

site

mas

ter

plan

and

a p

ortio

n of

the

build

ing.

Page 50: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

Report on the 2008-09 Financial and Performance Outcomes

82

Proj

ect

Orig

inal

co

mpl

etio

n da

te

Rev

ised

co

mpl

etio

n da

te (i

f ap

plic

able

)

Expl

anat

ion

for r

evis

ion

Lily

dale

Pol

ice

Sta

tion

– C

onst

ruct

ion

(Lily

dale

)Ju

n-09

Mar

-10

Pro

ject

del

ayed

due

to p

rotra

cted

cou

ncil

plan

ning

pro

cess

.

Mel

bour

ne L

egal

Pre

cinc

t Mas

ter P

lan

– O

ld

Cou

nty

Cou

rt R

efur

bish

men

t – C

onst

ruct

ion/

Enh

ance

men

t (M

elbo

urne

)

Jun-

10Ju

l-10

Pro

ject

del

ayed

due

to id

entifi

cat

ion

and

rem

oval

of h

azar

dous

was

te (a

sbes

tos)

whi

ch in

tu

rn d

elay

ed th

e ap

poin

tmen

t of c

ontra

ctor

.

Mod

erni

sing

Cor

onia

l Ser

vice

s –

Con

stru

ctio

n (M

elbo

urne

)Ju

n-11

Jun-

13P

roje

ct d

elay

ed d

ue to

iden

tifi c

atio

n of

late

nt s

ite c

onta

min

atio

n. In

add

ition

, Fed

eral

fu

ndin

g ($

13.0

M) f

or th

e ne

w D

onor

Tis

sue

Ban

k Vi

ctor

ia (D

TBV

) fur

ther

del

ayed

pr

ojec

t doc

umen

tatio

n an

d co

mm

ence

men

t of c

onst

ruct

ion.

The

Dep

artm

ent i

s se

ekin

g to

con

solid

ate

a nu

mbe

r of f

undi

ng s

ourc

es, i

nclu

ding

this

pro

ject

(alo

ng w

ith

Mor

tuar

y S

ervi

ces

and

the

DTB

V) i

nto

a si

ngle

pro

ject

title

d “S

tate

Cor

onia

l Ser

vice

s R

edev

elop

men

t (S

CS

R)”

.

Org

anis

ed C

rime

and

Cou

nter

Ter

roris

m –

A

sset

Enh

ance

men

t (S

tate

wid

e)Ju

n-08

Nov

-08

Pro

ject

com

plet

e. T

his

proj

ect c

onta

ined

mul

tiple

seg

men

ts a

cros

s bo

th th

e D

epar

tmen

t of

Jus

tice

and

Vict

oria

Pol

ice.

The

maj

ority

of t

hese

seg

men

ts w

ere

com

plet

ed a

s pe

r the

or

igin

al s

ched

ule.

How

ever

, the

fi na

l tw

o se

gmen

ts w

ere

dela

yed

beca

use

of p

rocu

rem

ent

issu

es a

nd w

ere

subs

eque

ntly

com

plet

ed b

y N

ovem

ber 2

008.

Dep

artm

ent o

f Pla

nnin

g an

d C

omm

unity

Dev

elop

men

t

Foot

scra

y Tr

ansi

t City

– U

pgra

deJu

n-10

Dec

-10

The

foot

brid

ge is

exp

ecte

d to

be

com

plet

ed b

y Ju

ne 2

010.

Dev

elop

men

t of t

he fo

reco

urts

an

d re

mov

al o

f old

foot

brid

ge a

re e

xpec

ted

to b

e co

mpl

eted

by

Dec

embe

r 201

0.

Rec

tang

ular

Spo

rts S

tadi

um –

Con

stru

ctio

n (O

lym

pic

Par

k)M

ar-0

8M

ay-1

0Th

e sc

hedu

le o

f wor

ks fr

om th

e m

ain

cont

ract

or h

as b

een

adju

sted

to refl e

ct th

e re

vise

d co

nstru

ctio

n pr

ogra

m fo

r an

incr

ease

in s

eatin

g ca

paci

ty a

nd te

nant

fi t-o

ut w

orks

sin

ce th

e or

igin

al p

rogr

am s

ched

ule.

Dep

artm

ent o

f Pre

mie

r and

Cab

inet

Mel

bour

ne R

ecita

l Cen

tre (M

RC

) & M

elbo

urne

Th

eatre

Com

pany

(MTC

) – C

onst

ruct

ion

Jan-

07M

ar-0

9O

rigin

al c

ompl

etio

n da

te w

as re

vise

d du

e to

site

spe

cifi c

issu

es (s

uch

as g

roun

d co

ntam

inat

ion

and

grou

nd w

ater

), ac

oust

ic v

ibra

tion

isol

atio

n re

quire

men

ts, a

nd c

hang

es

to e

nsur

e th

e fu

nctio

nalit

y an

d vi

abili

ty fo

r the

MTC

thea

tre a

nd M

RC

.

Dep

artm

ent o

f Tra

nspo

rt

Bar

won

Hea

ds B

ridge

Rep

lace

men

t (B

arw

on

Hea

ds)

Sep

-09

Late

201

0C

ompl

etio

n da

te w

as re

vise

d ea

rly in

pro

ject

due

to p

lann

ing

issu

es.

Page 51: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

83

Chapter 3: Public Sector Infrastructure and Asset Investment

Proj

ect

Orig

inal

co

mpl

etio

n da

te

Rev

ised

co

mpl

etio

n da

te (i

f ap

plic

able

)

Expl

anat

ion

for r

evis

ion

Bas

s H

ighw

ay D

uplic

atio

n –

Sta

ge 1

Kin

g R

oad

to W

oolm

er R

oad

(Bas

s, A

nder

son)

Jan-

10M

id 2

010

Com

plet

ion

date

revi

sed

due

to a

dver

se w

eath

er.

Bas

s H

ighw

ay D

uplic

atio

n S

tage

5 –

Gra

ntvi

lle

to K

ing

Roa

d (G

rant

ville

)Ju

n-08

Ear

ly 2

009

Pro

ject

com

plet

ed.

Bre

akw

ater

Roa

d U

pgra

de (B

elm

ont,

Gee

long

)Fe

b-09

Late

201

1R

evis

ed c

ompl

etio

n da

te refl e

cts

impa

ct o

f pla

nnin

g sc

hem

e am

endm

ent.

Cal

der H

ighw

ay U

pgra

deD

ec 0

61st

hal

f 200

9P

roje

ct c

ompl

eted

. No

chan

ge to

com

plet

ion

date

ove

r the

last

12

mon

ths.

Rev

ised

co

mpl

etio

n da

te refl e

cted

del

ays

in fu

ndin

g co

mm

itmen

t fro

m th

e fe

dera

l gov

ernm

ent.

Con

gest

ion

Impr

ovem

ents

Pro

gram

(var

ious

)Ju

n-10

2nd h

alf 2

010

By

June

201

0, o

nly

one

proj

ect r

emai

ns to

be

com

plet

ed. M

inor

resc

hedu

ling

due

to

fi nal

isat

ion

of s

cope

and

cou

ncil

appr

oval

s.

Cra

nbou

rne

Fran

ksto

n R

oad

Dup

licat

ion

(Hal

l R

oad

and

the

Wes

tern

Por

t Hig

hway

)M

ar-1

01st

hal

f 201

0M

inor

resc

hedu

ling.

Dup

licat

ion

of T

hom

pson

Roa

d –

Car

rum

D

owns

Dec

-09

Ear

ly 2

010

Com

plet

ion

date

revi

sed

due

to a

dver

se w

eath

er.

Fern

tree

Gul

ly R

oad

Wid

enin

g –

Jells

Roa

d to

S

tud

Roa

d (S

core

sby)

Jul-0

9La

te 2

009

Pro

ject

com

plet

ed –

min

or re

sche

dulin

g.

Gee

long

Rai

l Acc

ess

Impr

ovem

ent P

roje

ct

(Cor

io/N

orth

Gee

long

)A

ug-0

6M

id 2

009

Pro

ject

com

plet

ed. C

ompl

etio

n in

Jun

e 20

09 refl e

cts

the

com

plet

ion

of s

tand

ard-

gaug

e ra

il co

nnec

tion

into

the

north

ern

part

of th

e P

ort o

f Gee

long

.

Gee

long

Rin

g R

oad

Sta

ge 4

(Gee

long

Rin

g R

oad

to A

ngle

sea

Roa

d –

City

of G

reat

er

Gee

long

)

Oct

-10

Late

201

0

Geo

rge

Stre

et B

ridge

– N

ew B

ridge

to li

nk

Geo

rge

Stre

et to

Brig

hton

Roa

d (D

ande

nong

)Ju

n-08

Mid

201

0Fi

nalis

atio

n of

pro

ject

sco

pe a

nd d

esig

n to

ok lo

nger

than

ant

icip

ated

.

Met

ropo

litan

Tra

in C

ontro

l Rel

iabi

lity

(Mel

bour

ne)

Jun-

10La

te 2

010

No

chan

ge o

f com

plet

ion

date

ove

r las

t 12

mon

ths.

Met

ropo

litan

Tra

in S

afet

y C

omm

unic

atio

ns

Sys

tem

(Met

ro v

ario

us)

Dec

-10

Late

201

1Aw

ard

of m

ain

wor

ks c

ontra

ct o

ccur

red

late

r tha

n pl

anne

d. N

o ch

ange

of c

ompl

etio

n da

te

over

last

12

mon

ths.

Page 52: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

Report on the 2008-09 Financial and Performance Outcomes

84

Proj

ect

Orig

inal

co

mpl

etio

n da

te

Rev

ised

co

mpl

etio

n da

te (i

f ap

plic

able

)

Expl

anat

ion

for r

evis

ion

New

Tic

ketin

g S

olut

ion

– Te

chno

logy

and

In

stal

latio

n (S

tate

wid

e)20

0820

10N

o ch

ange

of c

ompl

etio

n da

te o

ver l

ast 1

2 m

onth

s.

Nor

th E

ast R

ail R

evita

lisat

ion

Pro

ject

(var

ious

)M

id 2

010

Late

201

0Th

is is

a p

rogr

am o

f wor

ks, w

hich

man

y as

pect

s w

ill b

e co

mpl

eted

on

sche

dule

. Som

e de

lay

has

resu

lted

from

the

chan

ged

loca

tion

of a

faci

lity

and

the

defe

rral

of c

omm

issi

onin

g w

orks

.

Reg

iona

l Rol

lings

tock

(non

-Met

ro v

ario

us)

Jul-0

91st

hal

f 201

0R

evis

ed c

ompl

etio

n da

te refl e

cts

the

prov

isio

n of

add

ition

al tr

ains

fund

ed in

200

8-09

.

Tayl

ors

Roa

d (1

5.2k

m to

15.

8km

) – B

ypas

s/N

ew R

oad

– S

yden

ham

Rd

to E

ast E

spla

nade

Gra

de S

epar

atio

n (S

t Alb

ans)

Jun-

08La

te 2

008

Pro

ject

com

plet

ed –

min

or re

sche

dulin

g.

Vigi

lanc

e C

ontro

l and

Eve

nt R

ecor

ding

S

yste

m o

n M

etro

polit

an T

rain

s (V

ICE

RS

) (M

etro

var

ious

)

Jun-

08La

te 2

011

Sev

eral

issu

es c

ontri

bute

d to

the

revi

sed

timef

ram

e, in

clud

ing:

RTB

U w

ithdr

awin

g as

sist

ance

from

VIC

ER

S fo

r thr

ee m

onth

s in

ear

ly 2

006;

Sie

men

s br

akin

g is

sue

dive

rting

te

chni

cal r

esou

rces

in 2

006/

07; I

nteg

rian

acqu

isiti

on a

nd d

iver

sion

of r

esou

rces

to U

S

proj

ects

, cou

pled

with

the

com

pany

bei

ng p

lace

d in

to a

dmin

istra

tion

in 2

007/

08; a

nd

unav

aila

bilit

y of

trai

ns fr

om J

uly

to O

ctob

er 2

008.

Rev

ised

com

plet

ion

date

refl e

cts

the

reso

lutio

n of

sof

twar

e is

sues

and

ens

urin

g th

at s

yste

m p

erfo

rman

ce is

sta

ble.

Vine

yard

Roa

d (O

beid

Driv

e an

d M

itche

lls

Lane

, Sun

bury

)D

ec-0

9M

id 2

010

Min

or re

sche

dulin

g.

Who

le o

f Gov

ernm

ent –

Tra

nsit

Citi

es –

B

alla

rat S

econ

d S

tatio

n (B

alla

rat)

End

200

8M

id 2

009

Pro

ject

com

plet

ed. N

o ch

ange

to c

ompl

etio

n da

te o

ver t

he la

st 1

2 m

onth

s.

Wod

onga

Rai

l Byp

ass

(Wod

onga

)O

ct-0

4O

ct-1

0N

o ch

ange

to c

ompl

etio

n da

te o

ver t

he la

st 1

2 m

onth

s.

Sou

rce:

D

epar

tmen

tal r

espo

nses

to th

e C

omm

ittee

’s 2

008-

09 F

inan

cial

and

Per

form

ance

Out

com

es Q

uest

ionn

aire

– P

art T

wo

and

clar

ifi ca

tion

ques

tions

Page 53: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

85

Chapter 3: Public Sector Infrastructure and Asset Investment

3.5. Supporting departments’ project planning and management

Overall, in only 27 per cent of cases were projects delivered within 10 per cent of their 2008-09 budget. Similarly, only 51 per cent of projects currently underway expect to meet their original completion dates. This indicates that departments are experiencing some diffi culties accurately estimating required budgets and timelines. To ensure effi cient and effective delivery of infrastructure programs, it is important that departments have expert guidance when undertaking initial project planning and through the life of projects.

Based on explanations given to the Committee in this inquiry, it appears that departments would benefi t from expert guidance with respect to:

identifying all required steps of a project;

accurately estimating the timing of steps;

ensuring that project scope is fully and correctly identifi ed at the start of the project; and

successfully incorporating the needs of stakeholders, including agencies and councils, into scope defi nition and timeline planning.

In its Report on the 2007-08 Financial and Performance Outcomes, the Committee recommended that:51

Departments establish knowledge management processes and systems that facilitate the sharing of expert knowledge and lessons learnt in the planning and timing of major infrastructure projects. This is essential in the planning stages of a project.

The Government’s response indicated that the Government was seeking to achieve this through a number of means, primarily through work undertaken by the Department of Treasury and Finance. This included the establishment of a Gateway Supervisory Committee to share lessons learnt from major infrastructure investment projects, the Investment Lifecycle Guidance publications, business case training sessions and a Project Management Community of Practice.52

The Department of Treasury and Finance and Major Projects Victoria (for projects nominated under the Project Development and Construction Management Act 1994) play key roles in supporting departments to plan and manage their projects. In both cases, little information is made publicly available about how effective and effi cient these project management and support services have been. To ensure that these bodies are providing as much benefi t as possible, it is important that the effectiveness and effi ciency of their support in terms of infrastructure project outcomes be assessed and reported.

51 Public Accounts and Estimates Committee, Report on the 2007-08 Financial and Performance Outcomes, May 2009, recommendation 7, p.79

52 Victorian Government, Responses to the Recommendations of Public Accounts and Estimates Committee’s 79th Report on the 2007-08 Financial and Performance Outcomes, November 2008, p.7

Page 54: CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT · CHAPTER 3: PUBLIC SECTOR INFRASTRUCTURE AND ASSET INVESTMENT Key fi ndings of the Committee: 3.1 Across the general

Report on the 2008-09 Financial and Performance Outcomes

86

The Committee notes that the Department of Treasury and Finance, along with other government agencies such as the Victorian Auditor-General’s Offi ce, do produce a number of guidance materials and best practice guides for departments to use in managing asset investment projects. However, these products are only useful in as much as they are successfully integrated into departments’ activities. It is therefore important for the Department of Treasury and Finance to monitor the uptake of its advice by departments, so that it can modify its products to improve uptake or results if required.

Recommendation 5: The Department of Treasury and Finance establish measures, and report on their success against them in its annual reports, to assess the performance of its programs facilitating project planning and management in terms of:

(a) the extent to which the Department’s advice is actually incorporated into project planning and management by agencies; and

(b) the extent to which the Department’s programs actually improve agencies’ ability to deliver projects on time and on budget.

The Department of Treasury and Finance consider whether it should facilitate project management training for project managers in other departments so as to assist departments to implement its advice and guidance.