chapter v – analysis and discussion

Upload: bryesanggalang

Post on 30-May-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/14/2019 Chapter v Analysis and Discussion

    1/8

    CHAPTER VANALYSIS AND DISCUSSION

    5.1 SupplyConveyance Analysis

    A supply-conveyance analysis is an approximate method for evaluating whether the supply satisfies the

    demand in a system. In this the actual demand being feed by the supply tanks will be compared to the

    design demand of the system based from fixture unit values.

    5.1.1 Supply from Underground Reservoir Tank to the Elevated Cylindrical Water Tank

    Water will be pumped from the underground reservoir tank to the elevated water tank using 2 transfer

    pumps. The riser pipe that will convey the water to the tank has a total length of approximately 140 m.

    The water will passed in a number of elements of pipe fittings and pump as shown in the table below.

    Elements Quantity diameter equivalent length total length

    90 Elbow 21 75 1.3 27.3

    Gate Valve 4 75 0.9 3.6

    Tees 2 75 2.9 5.8

    Flow Control

    valve 2 75 0.9 1.8

    Check Valve 2 75 1 2

    Transfer Pump 2 75 - -

    Total Additional Length 40.5

    5.1.1.2 Water Level at the Elevated Cylindrical Water Tank

    Using Bernoulli equation, the water level in the Elevated water tank will be approximate. Considering 2

    points for the Bernoulli equation, first point was the water level in the underground reservoir tank and the

    second point will be the water level at the elevated tank. The equation will be:

  • 8/14/2019 Chapter v Analysis and Discussion

    2/8

    Since both reservoirs was exposed to the atmosphere:

    Where HA =

    HL = hm + hf

    Using equivalent length of pipes the minor loss in pipe fittings will be accounted as friction loss due to

    pipe lengths. Therefore HL = hf, where hf= 0.00826 x

    Then the equation will be

    - 0.00826 x

    Using the pump properties and assuming 95% efficiency of the pump, the computed value for was

    359.577m. Comparing the computed head to the actual elevation of the water tank of 90.069m

    from the bottom of the reservoir tank, it was shown that the 2 transfer pump at the pump room

    can deliver water trice as much the water system needed. Therefore at 95% efficiency of the 2

    pumps, the system is assured that it can maintain its water level even in peak loads of demand.

    5.1.2 Supply from the Elevated Cylindrical Water Tank to the Outlet Pipes on Each Floor

    The water will be supplied from the elevated water tank in two ways; 1. Pressurized Flow for 20th

    to 23rd

    floor and 2. Gravity Flow for the rest of the system. Separate down feeds were provided for each type of

    flow. Down feeds for gravity and pressurized flow has a diameter of 100 mm and 75 mm respectively.

  • 8/14/2019 Chapter v Analysis and Discussion

    3/8

    5.1.2.1 Flow rate Distribution in the Gravity Flow Zone

    Floor Level Elevation Roughness DesignPressure

    Diameter Friction lossCoefficient

    Discharge

    Ground 21680 120 372.8685 100

    2nd Floor 24680 120 343.4968 100

    3rd Floor 27680 120 314.1251 100

    4th Floor 30680 120 284.7535 100

    5th Floor 33680 120 255.3818 100

    6th Floor 36680 120 226.0101 100

    7th Floor 39680 120 196.6385 100

    8th Floor 42680 120 167.2668 100

    9th Floor 45680 120 137.8951 100

    10th Floor 48680 120 396.5175 100

    11th Floor 51680 120 367.1458 100

    12th Floor 54680 120 337.7741 100

    14th Floor 57680 120 308.4025 100

    15th Floor 60680 120 279.0308 100

    16th Floor 63680 120 249.6592 100

    17th Floor 66680 120 220.2875 10018th Floor 69680 120 190.9158 100

    19th Floor 72680 120 161.5442 100

    5.1.2.2 Flow rate Distribution in the Pressurized Zone

    Floor Level Elevation Roughness Design

    Pressure

    Diameter Friction loss

    Coefficient

    Pump head Discharge

    20th Floor 75680 120 270.0676 100

    21st Floor 78680 120 235.8007 100

    22nd Floor 81680 120 201.5337 100

    23rd Floor 84680 120 167.2668 100

    5.1.2.3 Comparison between the Design Demand and the Actual Discharge

    Floor Level Elevation Design Demand Actual Discharge

  • 8/14/2019 Chapter v Analysis and Discussion

    4/8

    5.2 Pressure Analysis of the System

    The system will be subjected to pressure testing, its reliability will be analyzed according to its capacity to

    carry large amount of pressure. In a high-rised condominium large pressures are expected due to its

    elevation, these pressures may cause failure in the system if not sophisticatedly addressed in the design.

    The Pressure test and Leak test are done in the system; the contractor must accomplish a Quality

    Assurance Inspection Checklist after installation. This checklist will be the basis of the system reliabilityin terms of pressure capacity. A sample of Quality Assurance Checklist is attached in this study (See

    Appendix)

    5.2.1 Pressure Testing for Waterlines

    Ground 21680

    2nd Floor 24680

    3rd Floor 27680

    4th Floor 30680

    5th Floor 33680

    6th Floor 36680

    7th Floor 39680

    8th Floor 42680

    9th Floor 45680

    10th Floor 48680

    11th Floor 51680

    12th Floor 54680

    14th Floor 57680

    15th Floor 60680

    16th Floor 63680

    17th Floor 66680

    18th Floor 69680

    19th Floor 72680

    20th Floor 75680

    21st Floor 78680

    22nd Floor 81680

    23rd Floor 84680

  • 8/14/2019 Chapter v Analysis and Discussion

    5/8

    Pressure Testing shall be done in accordance to the technical specifications for Plumbing layouts, where

    in after installation of pipes, the pipe and any valve section shall be subjected to hydrotastic pressure of 1

    of the designed working pressure of the system 200 psig, but in the project the hydrotastic pressure that

    was used for testing varies but the most commonly used was 180 psi, depending on what was specified by

    the Contractor (JCI) and approved by the Designer (NBFCE).

    The sections of the pipelines were solely filled by water and had been subjected to the testing pressure by

    means of a pump connected to the pipe. All valves were opened during the testing.

    Figure 5.1 Opening of valves before the hydro testing

  • 8/14/2019 Chapter v Analysis and Discussion

    6/8

    The result of testing for each floor is

    summarized at the Table below.

    Table 5.1- Pressure Test Report for Pipe and Pipe Fittings of HWL and CWL lines

    Floor Elevation (m) Test Pressure (psig) Design Pressure (psig) Remarks

    Ground 15.500 180 54.08 System passed the requirements

    2nd Floor 19.000 180 49.82 System passed the requirements

    3rd Floor 22.000 180 45.56 System passed the requirements

    4th Floor 25.000 180 41.3 System passed the requirements

    5th Floor 28.000 180 37.04 System passed the requirements

    6th Floor 31.000 180 32.78 System passed the requirements

    7th Floor 34.000 180 28.52 System passed the requirements

    8th Floor 37.000 180 24.26 System passed the requirements9th Floor 40.000 180 20 System passed the requirements

    10th Floor 43.000 190 57.51 System passed the requirements

    11th Floor 46.000 200 53.25 System passed the requirements

    12th Floor 49.000 180 48.99 System passed the requirements

    14th Floor 52.000 180 44.73 System passed the requirements

    15th Floor 55.000 180 40.47 System passed the requirements

    16th Floor 58.000 180 36.21 to be subjected for testing

    17th Floor 61.000 180 31.95 to be subjected for testing

    18th Floor 64.000 180 27.69 to be subjected for testing

    19th Floor 67.000 180 23.43 to be subjected for testing

    20th Floor 70.000 180 39.17 to be subjected for testing

    21st Floor 73.000 180 34.91 to be subjected for testing

    22nd Floor 76.500 180 29.94 to be subjected for testing

    23rd Floor 80.000 180 24.97 to be subjected for testing

    From 16th to 23rd floors pressure testing are not yet done because the installation of pipe and fittings are

    not yet finished. But based from the results shown from the ground floor to the 15 th floor it is shown that

    the pipe material used in the system can carry up to 180 psi of pressure load. Compared to the computed

    pressure load that the pipe will be experienced in actual operation it shows that the system is adequate in

    terms of pressure capacity.

    5.2.2 Leak Test

    Figure 5.2 Hydro Testing

  • 8/14/2019 Chapter v Analysis and Discussion

    7/8

    During Hydro testing leaks in the system is also examined, leaks are determined by the leak test. The

    pipes are filled with water and the pressure in the pipe sections is recorded. After the test duration of 2

    hours the pressure reading will be examined. If there is a pressure drop in the reading, therefore there

    were leaks in the system; the personnel handling the testing will now start to locate the leaks. Leaks are

    properly addressed and the pipe section will be subjected for retesting.

    The result of leak test is summarized in the Table below.

    Floor Initial Reading(psig) Final Reading(psig) Remarks

    Ground 180 180 No pressure drop

    2nd Floor 180 180 No pressure drop

    3rd Floor 180 180 No pressure drop

    4th Floor 180 180 No pressure drop

    5th Floor 180 180 No pressure drop

    6th Floor 180 180 No pressure drop

    7th Floor 180 180 No pressure drop

    8th Floor 180 180 No pressure drop

    9th Floor 180 180 No pressure drop

    10th Floor 190 190 No pressure drop

    11th Floor 200 200 No pressure drop

    12th Floor 180 180 No pressure drop

    14th Floor 180 180 No pressure drop

    15th Floor 180 180 No pressure drop

    16th Floor 180 - to be subjected for testing

    17th Floor 180 - to be subjected for testing

    18th Floor 180 - to be subjected for testing

    19th Floor 180 - to be subjected for testing

    20th Floor 180 - to be subjected for testing

    21st Floor 180 - to be subjected for testing

    22nd Floor 180 - to be subjected for testing

    23rd Floor 180 - to be subjected for testing

    The results show that the system was reliable in terms of quality of work in the installation of the

    pipelines. Since no leaks are recorded during the testing of each floor, it is expected that there will be no

    loss in the system during actual operation due to leaks.

  • 8/14/2019 Chapter v Analysis and Discussion

    8/8

    5.3 System Reliability against Problems Encountered in a Water Distribution System

    Since no water distribution system is perfect, the system will always encounter problems especially

    during actual operations. It must be noted that if we want to measure the reliability of a system we must

    examine its capability to avoid failures. These failures might occur in pipes, appurtenances and fittings,

    pumps and even in tanks. In the design of the system some of these failures must be considered.

    5.3.1 Water Hammer Failure

    Water hammer is large fluctuations develop in the system that produce pounding noises and vibration.

    This force is capable of bursting the pipe fittings and pipe lines, may cause leaks and may shorten the life

    span of the system.

    To avoid this damages due to excessive pressure the designer provide a means of regulating the pressure,

    that is by installing a pressure reducing valve in the system. The PRV is installed in the 10 th floor of the

    building where in it reduce the accumulated pressure from the top zone to a gage of 20 psi, which is the

    actual minimum pressure required for a water closet.

    The location of the installation of PRV is computed based from the maximum pressure criterion of 70 psi.

    The maximum pressure zone height is 115.5 ft or 9.6 floors. Therefore the desired location for the PRV is

    in the 10th floor based from the computed pressure zone height. (See Appendix for computation)