checked baggage 3a checked baggage...system architecture informs long term direction for system of...
TRANSCRIPT
Checked Baggage
Mario Wilson Division Director
Airport Consultants Council July 20, 2016
Innovating the Future of Aviation Security
Standards & Security | Updates to Detection Standards
Passenger Screening | Life Cycle Cost Estimates Revision Updates; Passenger Screening Experience
Test & Evaluation | New Qualification Process; Third Party Testing Update Deployment & Logistics |
Planning Guidelines and Design; Checkpoint Design Guide
Checked Baggage | Recap and Acquisition Plans
Cybersecurity | Cybersecurity Requirements; Technical Solutions
Innovation | Operational Improvements; New Technologies; Innovation Task Force
System Architecture | Update on Implementation of OSC System Architecture; Priorities for Fiscal Year (FY)17; Transportation Security Equipment (TSE) Connectivity
1 Enhancing Core Mission Delivery by Focusing on System of Systems
2 Integrating Principles of Risk-Based Security (RBS) in Capabilities, Processes, and Technologies
4 Increasing Transparency in Engagement with Stakeholders to Enable Innovation
3 Streamlining Acquisitions, Requirements, and Test and Evaluation Processes
Alignment to Strategic Five-Year Technology Investment Plan Themes:
The Office of Security Capabilities (OSC)
safeguards our Nation’s transportation systems
through the qualification and delivery
of innovative security capabilities and solutions.
Innovation
System Architecture Standards
& Security
Test & Evaluation
Deployment and Logistics
Checked Baggage
Passenger Screening
Cybersecurity
3 4
2 3 2 3
1 2 1 2 3 4
3 4
3 4 1 2 3
1
1 2
2
2
Key Topics
Electronic Baggage Screening Program (EBSP) Funding Priorities
FY16-18 Funding Activities High-Speed (HS) Explosive Detection Systems (EDS) Status
Useful Life Review Study Reimbursement
Strategic Roadmap
3
Priority Description
1. Program Operations and Management Manage the program (includes staffing, training, equipment testing, and other program support costs)
2. Equipment to Ensure 100% Screening Compliance
Procure and deploy TSE (EDS and Explosive Trace Detection (ETD) units) to maintain 100% screening compliance
3. Critical Operational Projects Execute unforeseen and urgent projects to quickly remedy unacceptable safety issues or security vulnerabilities
4. Fulfillment of Existing Obligations Fulfill projects with executed Letters of Intent (LOIs) or Other Transaction Agreements
(OTAs) Purchase and install equipment required for those projects
5. Threat Detection Capability Development Develop threat detection algorithms DOES NOT include the deployment of these capabilities
6. Recapitalization or Upgrade of Equipment Due for Useful Life Replacement
Replace or upgrade aging machines that have reached the end of useful life Deploy new threat detection algorithms and Risk-Based Security (RBS) capabilities Upgrade network equipment in support of capability enhancements
7. System-Level Capability and Operational Efficiencies
Develop and deploy EDS system improvements to increase EDS lifespan, create efficiencies, and decrease alarm rates
8. Airport-Level Capability and Operational Efficiencies
Install new in-line systems Implement Checked Baggage Inspection Systems (CBIS) improvements to facilitate Planning
Guidelines and Design Standards compliance Implement CBIS infrastructure enhancements to enable RBS capabilities
9. Reimbursement of Systems Completed without a Transportation Security Administration (TSA) Funding Agreement
Reimburse airport operators who had a reasonable expectation of reimbursement for costs incurred while developing and/or deploying in-line systems in the absence of an LOI or OTA funding agreement with TSA
Electronic Baggage Screening Program Funding Priorities
4
FY16 Planned Funding Activities
• Planned Purchases: 62 EDS • Planned Installations: 36 EDS
Purchase and Installation
• Test Activities • System Integration
• Business Operations (staffing and training)
• Engineering Support
Program Operation & Management (PO&M)
• Develop and deploy enhanced threat detection algorithms • Develop EDS upgrade kits • Enhance alarm resolution capabilities
Technical and Engineering Initiatives
• Planned Designs: 11 • Planned Facility Modifications : 9
Facility Modifications (OTAs)
FY16 Planned Activities
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
FY16
PO&M
Purchase andInstallation
OTAs
Technical andEngineeringInitiatives
5
FY16 Planned OTA Projects
Current status of the planned OTA projects for FY16
FY16 Planned New In-Line and Recapitalization OTAs New In-Line OTAs Recapitalization OTAs
Airport Terminal Airport Terminal
• Baltimore/Washington International Thurgood Marshall (FacMod) E • Burbank-Glendale-Pasadena (FacMod) A
(Nodes 1 & 2)
• Charleston AFB/International (Design) Main • Houston Intercontinental (Design Add) A
• El Paso International (Design/FacMod) Main • Chicago-O’Hare International (Design Add) T3
• Phoenix-Mesa Gateway (Design) Main • Fairbanks International (FacMod) Main
• Kona International at Keahole (FacMod) Main • Dallas/Fort Worth International (FacMod) A, B, C, D
• Louis Armstrong New Orleans International (FacMod) New • Chicago-O’Hare International (FacMod) T5
• Chicago O’Hare International (Design) T3-L • Saipan International Airport (Design) Main
• St. Petersburg-Clearwater International (Design) A
• Sitka Rocky Gutierrez (Design) Main
• Salt Lake City International (FacMod) New
• Albert J. Ellis (Design) Main
• Tri-Cities (Design) Main
• Savannah/Hilton Head International (Design) Main
Awarded
Added
Cancelled
6
FY17 Planned Funding Activities
• Planned Purchases: 46 Medium-Speed (MS) EDS and 70 Rapid Speed (RS) SEDS
• Planned Installation: 54 MSEDS and 64 RSEDS • Recap of CTX-5500s • Recap of Itemizer DX ETDs
Purchase and Installation
• Test Activities • System Integration
• Business Operations (staffing and training)
• Engineering Support
PO&M
• Develop/deploy EDS upgrade kits • Upgrade In-line EDS networks • Deploy information technology security enhancements
Technical and Engineering Initiatives
• Planned Designs: 2 • Planned Facility Modifications: 7
Facility Modifications (OTAs)
FY17 Planned Activities
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
PO&M
Purchase andInstallation
OTAs
Technical andEngineeringInitiatives
7
FY18 Planned Funding Activities
• Planned Purchases: 38 EDS and 31 ETD • Planned Installation: 48 EDS
Purchase and Installation
• Test Activities • System Integration
• Business Operations (staffing and training)
• Engineering Support
PO&M
• Develop and deploy enhanced threat detection algorithms • Deploy EDS upgrade kits and network upgrades • Enhance alarm resolution capabilities
Technical and Engineering Initiatives
• Planned Designs: 14 • Planned Facility Modifications: 19 • Recap of CTX-9000/9400s
Facility Modifications (OTAs)
FY18 Planned Activities
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
PO&M
Purchase andInstallation
OTAs
Technical andEngineeringInitiatives
8
High-Speed EDS Status
High-Speed (HS) SEDS currently in test: Smiths XCT HI-SCAN MDI CTX-9800 SEIO
Systems projected to be on Qualified Products List (QPL) by FY17/18
Consistent with FedBizOpps posting from August 2013, TSA does not prohibit
airports from designing or constructing for HS EDS
However, TSA will not fund such projects due to the risk
TSA Will Fund TSA Will Not Fund Purchase and install of qualified EDS Any BHS retrofit for HS EDS
Design/construction of new, approved HS CBIS systems once on QPL
Design/construction of any HS CBIS prior to QPL availability
9
Useful Life Review Study
In FY16, a review study was conducted to evaluate useful life of currently deployed TSE. − Evaluated Reliability, Maintainability, and Availability (RMA) data and age data
for the EDS and ETD fleet − The TSE age histograms, along with recent RMA data analysis, show the
lifespans have not exhibited significant changes since the last report in 2014
From FY11-16, EBSP has actively conducted recapitalization of EDS
From FY10-16, EBSP has actively conducted recapitalization of ETD
Actively Deployed Checked Baggage TSE Calendar Year 16 Useful Life Estimate
EDS 15 years ETD 10 years
10
Reimbursement
Reimbursement Review and Validation Plan for In-line Baggage Screening Systems approved on June 16, 2016
Timeline for submission, review, and validation of reimbursement claims
− August 2016
− November 2016
− January 2017
− January 2018
Reimbursement Justification Request application and instructions posted to FedBizOpps
Deadline for initial reimbursement applications TSA concludes application evaluations TSA will then evaluate the detailed project cost information to determine the amount eligible for reimbursement TSA completes all evaluations and ready to begin reimbursement
2016
20
17
2018
11
EBSP Strategic Roadmap Context - Notional
3
Outline path forward for EBSP to meet TSA’s goal to “Improve security effectiveness through a system of systems technological approach.”
Agreed upon pathways, interdependencies, and supporting roles to achieve targeted future state objectives.
2017 New
2018 2019 2020 2021 2022 2023 2024 2025 2026 2028 2029 2030 2027
System of Systems
Electronic Baggage Screening Program
Passenger Screening Program
Security Technology Integrated Program (STIP)
Objective
Outcomes
12
EBSP Strategic Roadmap Overview - Notional
2017 New Acquisition Program
2018 2019 2020 2021 2022 2023 2024 2025 2026 2028 2029 2030 2027
Future Concept Development (Pre-Need/Need) • Evolve screening technology to meet the changing threat landscape
Program Integration • Continue to integrate with the System Architecture team
Connected Technology • Cybersecurity (STIP 6.0)
• RBS Solution • Remote Monitoring
Increased Detection • Detection Algorithms
• Next Gen Alarm Resolution Tool • Improved Threat Discrimination
System of Systems
Implementation including Next
Generation Capability
Development
Common Approach • Common Image Format
• Common Network • Common Footprint
EDS CP2 OEM C Acquisition Contracts/CP2 Sole Source Omnibus IDIQ Tech Services Contract
13
MAD Development of 2027-2030 Capabilities (Need) • Advanced Algorithm Development
• Advanced Component Development • Advanced Architecture
EDS CP2 Baseline: ORD 3.4
• RTM Detection (5.8) • HME Capable (7.2) • UltraFAR (7.2R)
Detection Requirements
• Speed (BPH) • Reliability • Size • Safety • Core Functions • Image Archive, Alarm
Clearing, GUI Timer, FDRS Bag Count
• Common GUI 2.0 • STIP 5.0
System Requirements
Cybersecurity (STIP 6.0) (Deploy)
Common Image Format (Develop & Test)
RBS Solution (Deploy)
Algorithm (Dev & Test)
Common Network (IAN) (Develop & Test)
Common Footprint (Spec Development)
Cybersecurity (STIP 6.0) (Develop & Test)
Remote Monitoring (Develop & Test)
Program Acquisition of Developed Capabilities
2027-2030
• EBSP 2 TSE • EBSP 2 Capabilities
Next Gen Alarm Resolution Tool (EBSP Concept)
S&T Development of 2027-2030 Capabilities (Pre-Need) • Advanced Algorithm Development • Advanced Component Development
• Advanced Architecture
S&T Development of 2030-2040 Capabilities (Pre-Need)
MAD Development of 2030-2040 Capabilities
(Need)
• Capability upgrades for Next Gen CBT TSE
• Algorithm Development
S&T Development of 2040-20xx Capabilities
(Pre-Need)
System Architecture Informs Long Term Direction for System of Systems Approach
Open Threat Assessment Platform (OTAP) X-Ray
Improved Threat Discrimination (Concept)
Algorithm (Concept)
EDS CP2 OEM C Acquisition Contracts/CP2 Sole Source Omnibus IDIQ Tech Services Contract
System of Systems Implementation in
Conjunction w/ PSP
• Next Gen EDS • Common Footprint • Common Network
Next Gen Alarm Resolution Tool (EBSP Procure & Deploy)
RBS Solution (Concept)
Program Action
MAD Action
S&T Action
Critical Project
Common Arch.
RBS/Connect.
S&T Flow
Detection
MAD Flow
System Architecture
Legend
Common Image Format (Concept)
CIF (Deploy)
Common Network (IAN) (Concept)
CN (IAN) (Deploy)
CF (Concept)
Algorithm (Concept)
Algorithm (Concept)
Algorithm (Concept)
Algorithm (Concept)
Algorithm (Concept)
Algorithm (Concept)
Algorithm (Concept)
Algorithm (Deploy)
Algorithm (Dev & Test)
Algorithm (Dev & Test)
Algorithm (Dev & Test)
Algorithm (Dev & Test)
Algorithm (Dev & Test)
Algorithm (Dev & Test)
Algorithm (Dev & Test)
Algorithm (Deploy)
Algorithm (Deploy)
Algorithm (Deploy)
Algorithm (Deploy)
Algorithm (Deploy)
Algorithm (Deploy)
Next Gen Alarm Resolution Tool (EBSP Develop & Test)
RBS Solution (Develop & Test)
Remote Monitoring (Concept)
Remote Mon (Deploy)
Improved Threat Discrimination (Develop & Test)
ITD (Deploy)
2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2028 2029 2030 2027
Algorithm (Character)
Algorithm (Character)
Algorithm (Character)
Algorithm (Character)
Algorithm (Character)
Algorithm (Character)
Algorithm (Character)
Algorithm (Character)
Algorithm (Character)
Network Upgrades (Deploy)
HME FAR (Dev & Test)
HME FAR (Deploy)
HME (Deploy)
Hardware (Deploy)
TIP (Deploy
EBSP Strategic Roadmap - Notional Operational View (OV)
14
Algorithm Fleet
Retrofit
Algorithm OEM
Develop & Test
Algorithm OEM
Develop & Test
Algorithm OEM
Develop & Test
EBSP Strategic Roadmap - Notional Increased Detection – Detailed OV
2027 Increased Detection
Algorithm OEM
Develop & Test
Improved Threat Discrimination Requirement Development
Algorithm Requirement
Characterization
Next Gen Alarm Resolution Tool Procure and Deploy
Next Gen Alarm Resolution Tool
OEM Development
Improved Threat Detection Procure and Deploy
Algorithm Requirement
Characterization
Algorithm Requirement
Characterization
Algorithm Requirement
Characterization
Algorithm Requirement
Characterization
Algorithm Requirement
Characterization
Algorithm Requirement
Characterization
Algorithm Requirement
Characterization
Detection Standard
Detection Standard
Detection Standard
Detection Standard
Detection Standard
Detection Standard
Detection Standard
Detection Standard
Realized threat begins requirement characterization (S&T)
Certified Alg Certified Alg
Algorithm OEM
Develop & Test
Certified Alg Certified Alg
Algorithm OEM
Develop & Test
Algorithm OEM
Develop & Test
Certified Alg Certified Alg
Algorithm OEM
Develop & Test
Certified Alg Certified Alg
Algorithm Fleet Retrofit
Algorithm Fleet Retrofit
Algorithm Fleet Retrofit
Algorithm Fleet Retrofit
Algorithm Fleet Retrofit
Algorithm Fleet Retrofit
Algorithm Fleet
Retrofit
Fielded FOC Fielded FOC Fielded FOC Fielded FOC Fielded FOC Fielded FOC Fielded FOC
Next Gen Alarm Resolution Tool Requirement Development
Next Gen Alarm Resolution Tool
Testing
Requirement Document
Prototype ECP Fielded FOC
Improved Threat Detection
OEM Development
Improved Threat Detection Testing
Requirement Document Prototype ECP
Fielded FOC
Increased Detection initiatives focus on rapidly developing and deploying new threat detection
algorithms and enabling improved threat resolution technology,
ensuring TSA’s Security Mission is fulfilled
Fielded FOC
2017 2018 2019 2020 2021 2022 2023 2024 2025 2026
UltraFAR OEM
Develop & Test
UltraFAR Fleet Retrofit
HME Fleet Retrofit
Hardware (Inc. DR+ Kit, L3 Kit, Single Comp)
Procure and Deploy
Fielded FOC
13 15