1. During Commissioning of HP Separator first fill up the HP Separator(V-116001) with water. 2. After filling up the HP Separator drain out this water. 3. Again fill up the separator with water and pressurized it with nitrogen up to 7 bar(kg-f/cm 2 ). 4. Check the functioning, opening & closing of control valves and all instruments properly. 5. Do loop check of instruments.

Upload: naved-ahmed

Post on 04-Dec-2015

217 views

Category:

Documents


1 download

DESCRIPTION

hasgdfsdfkdghfhgdhjbka

TRANSCRIPT

Page 1: Chemical Injection

1. During Commissioning of HP Separator first fill up the HP Separator(V-116001) with water.2. After filling up the HP Separator drain out this water.3. Again fill up the separator with water and pressurized it with nitrogen up to 7 bar(kg-f/cm2).4. Check the functioning, opening & closing of control valves and all instruments properly.5. Do loop check of instruments.