chemical process design

Upload: audrey-patrick-kalla

Post on 15-Oct-2015

147 views

Category:

Documents


2 download

DESCRIPTION

chemical process design

TRANSCRIPT

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    1

    CHE 425 CHE 425

    Engineering Economics and Engineering Economics and Design PrinciplesDesign Principles

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    2

    CHAPTER 8CHAPTER 8

    Profitability AnalysisProfitability Analysis

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    3

    A Typical Cumulative Cash Flow Diagram for A Typical Cumulative Cash Flow Diagram for Evaluation of a New ProjectEvaluation of a New Project

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    4

    A Typical Cumulative Cash Flow Diagram for A Typical Cumulative Cash Flow Diagram for Evaluation of a New ProjectEvaluation of a New Project (cont.)(cont.)

    Project LifeProject Life

    Required for evaluation of profitability of a project.Required for evaluation of profitability of a project.

    Standardization of project life: Standardization of project life: When comparing different projects.When comparing different projects.

    Project lives of 10, 12 and 15 years are commonly used. Project lives of 10, 12 and 15 years are commonly used.

    Time value of money has to be considered when Time value of money has to be considered when evaluating profitability.evaluating profitability.

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    5

    Profitability Criteria for Project EvaluationProfitability Criteria for Project Evaluation

    3 Bases for Evaluation of Profitability

    n Time

    o Cash

    p Interest Rate i

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    6

    Profitability CriteriaProfitability Criteria

    Non-discounted method do not take account of time-value of money.

    Not recommended for evaluating new, large projects

    ProfitabilityProfitabilityCriteriaCriteria

    DiscountedDiscountedNonNon--

    DiscountedDiscounted

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    7

    NonNon--Discounted Profitability CriteriaDiscounted Profitability Criteria

    Time Criterion.

    The shorter the PBP, the better.

    Payback Period (PBP)

    PBP = Time required, after start-up, to recover the fixed capital investment, FCIL, for the project

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    8

    NonNon--Discounted Profitability Criteria (cont.)Discounted Profitability Criteria (cont.)

    Cash Criterion.

    Cumulative Cash Position (CCP)

    CCP = Worth of the project at the end of its life

    Cumulative Cash Ratio (CCR)

    CCR > 1 implies that the project is potentially profitable.

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    9

    NonNon--Discounted Profitability Criteria (cont.)Discounted Profitability Criteria (cont.)

    Interest Rate Criterion.

    Rate of Return on Investment (ROROI)

    The higher the value of ROROI, the better.

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    10

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    11

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    12

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    13

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    14

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    15

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    16

    Discounted Profitability CriteriaDiscounted Profitability Criteria

    Time CriterionTime Criterion.

    The project with the shortest DPBP is the most desirable.

    Discounted Payback Period (PBP)

    DPBP = Time required, after start-up, to recover the fixed capital investment, FCIL, required for the project with all cash-flows discounted back totime zero.

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    17

    NonNon--Discounted Profitability Criteria (cont.)Discounted Profitability Criteria (cont.)

    Cash CriterionCash Criterion.Net Present Value (NPV)

    NPV = Cumulative discounted cash position at the endof the project.

    Present Value Ratio (PVR)

    PVR > 1 implies that the project is potentially profitable.

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    18

    NonNon--Discounted Profitability Criteria (cont.)Discounted Profitability Criteria (cont.)

    Interest Rate Criterion.Interest Rate Criterion.

    Discounted Cash Flow Rate of Return (DCFROR)

    If DCFROR is higher than the internal discount rate,then the project is considered profitable .

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    19

    Example 8.2 (cont.)Example 8.2 (cont.)

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    20

    Example 8.2 (cont.)Example 8.2 (cont.)

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    21

    Example 8.2 (cont.)Example 8.2 (cont.)

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    22

    Example 8.2 (cont.)Example 8.2 (cont.)

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    23

    Example 8.2 (cont.)Example 8.2 (cont.)

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    24

    Example 8.3 Example 8.3

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    25

    Example 8.3 (cont.) Example 8.3 (cont.)

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    26

    Example 8.3 (cont.) Example 8.3 (cont.)

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    27

    Comparing Several Large ProjectsComparing Several Large Projects--Incremental Economic AnalysisIncremental Economic Analysis

    DCFROR tells us how efficiently we are using our DCFROR tells us how efficiently we are using our money.money.

    The higher the DCFROR, the more attractive the The higher the DCFROR, the more attractive the individual investment.individual investment.

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    28

    Example 8.4 Example 8.4

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    29

    Example 8.4 (cont.) Example 8.4 (cont.)

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    30

    Example 8.4 (cont.) Example 8.4 (cont.)

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    31

    Example 8.4 (cont.) Example 8.4 (cont.)

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    32

    Example 8.5Example 8.5

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    33

    Example 8.5 (cont.)Example 8.5 (cont.)

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    34

    Comparing Investment AlternativesComparing Investment Alternatives

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    35

    Algorithm for Incremental Investment AnalysisAlgorithm for Incremental Investment Analysis

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    36

    The Concept of RiskThe Concept of Risk

    Option 1Option 1 Option 2Option 2

    A A newnew product is to be product is to be produced which has produced which has never been made in never been made in large scale.large scale.

    A A secondsecond plant is to be plant is to be built in another region to built in another region to meet increasing meet increasing demand.demand.

    Pilot plant tests have Pilot plant tests have been made and product been made and product sent to potential sent to potential customers.customers.

    Company has dominant Company has dominant market position for this market position for this product.product.

    The calculated rate of The calculated rate of return is 33%.return is 33%.

    The rate of return is to The rate of return is to be 12%.be 12%.

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    37

    The Concept of RiskThe Concept of Risk (cont.)(cont.)

    Items that Favor Option 1Items that Favor Option 1 Items that Favor Option 2Items that Favor Option 2

    High return on the High return on the investmentinvestment

    Well established marketWell established market

    Opens new product Opens new product possibilitiespossibilities

    WellWell--known manufacturing known manufacturing costscosts

    Transportation costs will be Transportation costs will be lessless

    Matured technologyMatured technology

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    38

    The Concept of RiskThe Concept of Risk (cont.)(cont.)

    The high rate of return of option 1 is The high rate of return of option 1 is associated with high associated with high riskrisk..

    VPVPs Decision: Consider option 2 due to s Decision: Consider option 2 due to concern for lost market position.concern for lost market position.

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    39

    Evaluation of Equipment AlternativesEvaluation of Equipment Alternatives

    Factors to ConsiderFactors to Consider

    Capital Cost of the equipment.Capital Cost of the equipment.

    Operating cost of the equipment.Operating cost of the equipment.

    Lifetime of the equipment.Lifetime of the equipment.

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    40

    Equipment with the Same Expected Operating LivesEquipment with the Same Expected Operating Lives

    When capital cost and operating cost are When capital cost and operating cost are different but equipment lives are the same, then different but equipment lives are the same, then make choice based on NPV.make choice based on NPV.

    The choice with the The choice with the least negativeleast negative NPV value NPV value will be the best choice.will be the best choice.

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    41

    Example 8.6Example 8.6

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    42

    Example 8.6 (cont.)Example 8.6 (cont.)

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    43

    Equipment with Different Expected Operating LivesEquipment with Different Expected Operating Lives

    Three Methods.Three Methods. Capitalized Capital Cost MethodCapitalized Capital Cost Method Equivalent Annual Operating Cost (EAOC) MethodEquivalent Annual Operating Cost (EAOC) Method Common Denominator MethodCommon Denominator Method

    Effect of inflation is not considered in the above Effect of inflation is not considered in the above methods.methods.

    All of the methods consider both the capital and All of the methods consider both the capital and operating cost in minimizing expenses, thus maximizing operating cost in minimizing expenses, thus maximizing our profits.our profits.

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    44

    Capitalized Cost MethodCapitalized Cost Method

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    45

    Capitalized Cost MethodCapitalized Cost Method

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    46

    Capitalized Cost MethodCapitalized Cost Method

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    47

    Example 8.7Example 8.7

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    48

    Example 8.7 (cont.)Example 8.7 (cont.)

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    49

    Equivalent Annual Operating Cost (EAOC) MethodEquivalent Annual Operating Cost (EAOC) Method

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    50

    Equivalent Annual Operating Cost (EAOC) MethodEquivalent Annual Operating Cost (EAOC) Method

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    51

    Example 8.8Example 8.8

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    52

    Common Denominator MethodCommon Denominator Method

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    53

    Example 8.9Example 8.9

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    54

    Example 8.9 (cont.)Example 8.9 (cont.)

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    55

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    56

    CHE 425 CHE 425

    Engineering Economics and Engineering Economics and Design PrinciplesDesign Principles

    Prof. Adnan AlProf. Adnan Al--AmerAmer

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    57

    Incremental Analysis for Retrofitting FacilitiesIncremental Analysis for Retrofitting Facilities

    RetrofittingRetrofitting: Improving the profitability of a : Improving the profitability of a process by adding a piece of equipment to process by adding a piece of equipment to an existing operating plant. an existing operating plant.

    Continuous

    Types of Decision in Retrofitting

    Discrete(Yes or No)

    Combinationof Both

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    58

    Incremental Analysis for Retrofitting FacilitiesIncremental Analysis for Retrofitting Facilities

    Retrofitting ProcedureRetrofitting Procedure Identify available alternatives AIdentify available alternatives A11, A, A22 AAn.n.

    Know the project cost (PC) and yearly Know the project cost (PC) and yearly savings (YS) generated for each alternative.savings (YS) generated for each alternative.

    NOTENOTE: The : The do nothingdo nothing option, Aoption, A11, has no , has no capital cost and no savings.capital cost and no savings.

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    59

    Profitability CriteriaProfitability Criteria

    For small retrofit projects, non-discounted method may be sufficient.

    For larger retrofit projects, discounted profitability criteria should be used.

    ProfitabilityProfitabilityCriteriaCriteria

    DiscountedDiscountedNonNon--

    DiscountedDiscounted

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    60

    NonNon--Discounted Methods for Incremental AnalysisDiscounted Methods for Incremental Analysis

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    61

    ExampleExample 8.10 8.10

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    62

    ExampleExample 8.10 (cont.)8.10 (cont.)

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    63

    ExampleExample 8.10 (cont.)8.10 (cont.)

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    64

    Example 8.11Example 8.11

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    65

    ExampleExample 8.11 (cont.)8.11 (cont.)

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    66

    ExampleExample 8.128.12

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    67

    Discounted Methods for Incremental AnalysisDiscounted Methods for Incremental Analysis

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    68

    ExampleExample 8.138.13

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    69

    Discounted Methods for Incremental AnalysisDiscounted Methods for Incremental Analysis

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    70

    ExampleExample 8.148.14

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    71

    Concept of risk in evaluation of profitability Concept of risk in evaluation of profitability is introduced.is introduced.

    Techniques to quantify risk are illustratedTechniques to quantify risk are illustrated

    See Table 8.1.See Table 8.1.

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    72

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    73

    Forecasting Uncertainty in Chemical ProcessesForecasting Uncertainty in Chemical Processes

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    74

    Forecasting Uncertainty in Chemical Processes (cont.)Forecasting Uncertainty in Chemical Processes (cont.)

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    75

    Forecasting Uncertainty in Chemical Processes (cont.)Forecasting Uncertainty in Chemical Processes (cont.)

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    76

    Forecasting Uncertainty in Chemical Processes (cont.)Forecasting Uncertainty in Chemical Processes (cont.)

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    77

    Forecasting Uncertainty in Chemical Processes (cont.)Forecasting Uncertainty in Chemical Processes (cont.)

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    78

    Forecasting Uncertainty in Chemical Processes (cont.)Forecasting Uncertainty in Chemical Processes (cont.)

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    79

    Utilities - Refrigerated Water

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    80

    Quantifying Risk

    Methods ofMethods ofQuantifying RiskQuantifying Risk

    Scenario Scenario AnalysisAnalysis

    Sensitivity Sensitivity AnalysisAnalysis

    MonteMonte--CarloCarloMethodMethod

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    81

    Scenario AnalysisScenario Analysis

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    82

    Scenario AnalysisScenario Analysis

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    83

    Sensitivity AnalysisSensitivity Analysis

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    84

    Example 8.15Example 8.15

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    85

    Example 8.15 (cont.)Example 8.15 (cont.)

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    86

    Example 8.16Example 8.16

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    87

    Example 8.16Example 8.16

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    88

    MonteMonte--Carlo Method (Algorithm)Carlo Method (Algorithm)

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    89

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    90

    For processes using new technology, For processes using new technology, additional risks will be present.additional risks will be present.

    To account for the additional risk, assign To account for the additional risk, assign higher acceptable rate of return for projects higher acceptable rate of return for projects using new technology compared with those using new technology compared with those using matured technology.using matured technology.

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    91

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    92

    Profit Margin (PM)Profit Margin (PM)

    If PM < 0, the process will not be If PM < 0, the process will not be profitable.profitable.

    A PM > 0 does not guarantee that the A PM > 0 does not guarantee that the process will be profitable but does suggest process will be profitable but does suggest that further investigation may be warranted.that further investigation may be warranted.

  • Prof. Adnan AlamerChemical Engineering Dept., KFUPM.

    93

    Example 8.17Example 8.17

    A Typical Cumulative Cash Flow Diagram for Evaluation of a New Project A Typical Cumulative Cash Flow Diagram for Evaluation of a New Project (cont.) Profitability Criteria for Project EvaluationProfitability Criteria Non-Discounted Profitability Criteria Non-Discounted Profitability Criteria (cont.) Non-Discounted Profitability Criteria (cont.) Discounted Profitability Criteria Non-Discounted Profitability Criteria (cont.) Non-Discounted Profitability Criteria (cont.) Example 8.2 (cont.) Example 8.2 (cont.) Example 8.2 (cont.) Example 8.2 (cont.) Example 8.2 (cont.) Example 8.3 Example 8.3 (cont.) Example 8.3 (cont.) Comparing Several Large Projects-Incremental Economic Analysis Example 8.4 Example 8.4 (cont.) Example 8.4 (cont.) Example 8.4 (cont.) Example 8.5Example 8.5 (cont.)Comparing Investment AlternativesAlgorithm for Incremental Investment AnalysisThe Concept of RiskThe Concept of Risk (cont.)The Concept of Risk (cont.)Evaluation of Equipment AlternativesEquipment with the Same Expected Operating LivesExample 8.6Example 8.6 (cont.)Equipment with Different Expected Operating LivesCapitalized Cost Method Capitalized Cost Method Capitalized Cost Method Example 8.7Example 8.7 (cont.)Equivalent Annual Operating Cost (EAOC) MethodEquivalent Annual Operating Cost (EAOC) MethodExample 8.8Common Denominator MethodExample 8.9Example 8.9 (cont.)Profitability Criteria Non-Discounted Methods for Incremental Analysis Example 8.10 Example 8.10 (cont.)Example 8.10 (cont.)Example 8.11 Example 8.11 (cont.)Example 8.12Discounted Methods for Incremental Analysis Example 8.13Discounted Methods for Incremental Analysis Example 8.14