chen4530urs2report
TRANSCRIPT
1
YOTTA DESIGNS, INC.
Natural Gasoline Expansion
Natural Gasoline to LPG and Sales Gas
Curtis Edwards, Michael Polmear, Mark Colbenson CHEN 4530: Senior Design
Professor Clough
Mr. Sean Arendell – URS
5/5/2010
Wellhead
Gas
Outlet
Water
Outlet
Water
Oil
Oil
Inlet
Divertor
Mist
Extractor
Oil
Outlet
Baffle
Liquid
Level
Control
Figure 1 Three Phase Inlet Separator to Initiate the Magic (1).
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
2
Table of Contents
Executive Summary .........................................................................................................................6
Project Description and Scope ........................................................................................................7
Problem Statement ......................................................................................................................7
Scope ...........................................................................................................................................8
Design Criteria..............................................................................................................................9
Wellhead Conditions .................................................................................................................9
Wellhead Flow Rate to Facility ............................................................................................... 11
Gas Re-Injection ..................................................................................................................... 11
Pipeline Gas Production Specifications ................................................................................. 12
Minimum Air Temperature Constraints .................................................................................. 12
Product Specifications ............................................................................................................ 12
Economic Considerations ....................................................................................................... 13
Background Information................................................................................................................. 13
The Yamal Megaproject ............................................................................................................. 13
Definitions ................................................................................................................................... 15
Natural Gas Processing ............................................................................................................. 16
Alternatives to the Proposed Process........................................................................................ 18
Dehydration............................................................................................................................. 19
Heat Integration ...................................................................................................................... 21
Column Optimization .............................................................................................................. 22
Refrigeration Cycle ................................................................................................................. 22
Recycle Operators .................................................................................................................. 23
Safety, Environmental, and Health Considerations ...................................................................... 23
Plant Safety (16)......................................................................................................................... 23
Environmental Concerns (16) .................................................................................................... 24
MSDS Summaries...................................................................................................................... 25
Natural Gasoline (17).............................................................................................................. 25
Liquefied Petroleum Gas (18) ................................................................................................ 26
Natural Gas (19) ..................................................................................................................... 26
Triethylene Glycol (20) ........................................................................................................... 27
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
3
Project Premises and Corresponding Simulation Parameters...................................................... 27
Design Assumptions .................................................................................................................. 28
Economic Assumptions.............................................................................................................. 29
Overall Process Flow Diagrams .................................................................................................... 29
Natural Gasoline Process Flow Diagrams ................................................................................. 29
Natural Gasoline Expansion Process Flow Diagram ................................................................ 31
Process Descriptions ..................................................................................................................... 33
Inlet Separation and Natural Gasoline Recovery ...................................................................... 33
Natural Gasoline PFD ............................................................................................................. 33
Natural Gasoline Expansion PFD........................................................................................... 33
Approach................................................................................................................................. 34
Triethylene Glycol Dehydration.................................................................................................. 36
Triethylene Glycol Dehydration PFD ...................................................................................... 36
Approach................................................................................................................................. 37
Propane Refrigeration Cycle ...................................................................................................... 38
Propane Refrigeration Cycle PFD .......................................................................................... 38
Approach................................................................................................................................. 39
Sales Gas and LPG Recovery ................................................................................................... 40
PFD ......................................................................................................................................... 40
Approach................................................................................................................................. 41
Material and Energy Balances....................................................................................................... 43
Material and Energy Balances ................................................................................................... 43
Natural Gasoline Process Balances....................................................................................... 43
Expansion Process Balances ................................................................................................. 45
Process Description & Equipment Specifications ......................................................................... 50
Distillation Columns.................................................................................................................... 51
Estimating Column Pressure and Condenser Type............................................................... 51
Calculating Number of Trays .................................................................................................. 53
Determining the Dimensions of the Distillation Columns ....................................................... 54
Distillation Column Costing..................................................................................................... 58
Flash Drums ............................................................................................................................... 59
Three-Phase Separator .......................................................................................................... 59
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
4
Flash Drums............................................................................................................................ 61
Heat Exchangers ........................................................................................................................ 62
Design of the Heat Exchangers.............................................................................................. 63
Pumps ........................................................................................................................................ 67
Compressors .............................................................................................................................. 67
Valves ......................................................................................................................................... 70
Storage Tank .............................................................................................................................. 71
Utility Summary .............................................................................................................................. 72
Estimation of Capital Investment and Total Product Cost ............................................................ 77
Economic Premises ................................................................................................................... 77
Venture Guidance Appraisal .................................................................................................. 77
Variable Costs......................................................................................................................... 78
Fixed Costs ............................................................................................................................. 79
Cash Flow ............................................................................................................................... 79
Capital Investment ..................................................................................................................... 80
Cost Indices ............................................................................................................................ 80
Commodity Chemicals............................................................................................................ 81
Total Permanent Investment (TPI) ......................................................................................... 81
Working Capital (WC) ............................................................................................................. 91
Operating Cost ........................................................................................................................... 91
Variable Cost .......................................................................................................................... 92
Fixed Cost ............................................................................................................................... 95
Profitability Analysis ....................................................................................................................... 99
Profitability ................................................................................................................................ 100
Cost of Capital ...................................................................................................................... 100
Net Present Value................................................................................................................. 100
Internal Rate of Return ......................................................................................................... 100
Return on Investment ........................................................................................................... 100
Break-Even Point .................................................................................................................. 101
Benefit-Cost Ratio................................................................................................................. 101
Depreciation .......................................................................................................................... 101
Salvage Percent ................................................................................................................... 102
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
5
Accounts Receivable ............................................................................................................ 102
Corporate Income Tax .......................................................................................................... 102
Cash Flow Analyses ............................................................................................................. 102
Sensitivity Analysis................................................................................................................... 112
Present ROI and IRR for a +/- 100% Variation in TPI ......................................................... 112
Present ROI and IRR for a +/- 100% Variation in Fixed Operating Cost ............................ 113
Conclusion ................................................................................................................................... 113
Bibliography ................................................................................................................................. 115
Appendix A: Acronyms................................................................................................................. 118
Appendix B: Chemical Information .............................................................................................. 120
LPG MSDS (18) ............................................................................................................................ 120
Natural Gas MSDS (19) ................................................................................................................ 124
Natural Gasoline MSDS ............................................................................................................... 130
Propane MSDS............................................................................................................................ 130
TEG MSDS (20)............................................................................................................................ 130
Appendix C: Engineering Calculations ........................................................................................ 137
Design ...................................................................................................................................... 137
Costing ..................................................................................................................................... 160
Natural Gasoline Process ..................................................................................................... 160
Natural Gasoline Expansion Plant Process ......................................................................... 164
Appendix D: Computer Process Modeling .................................................................................. 173
Aspen HYSYS .......................................................................................................................... 173
Appendix E: Economic Spreadsheets ......................................................................................... 174
Total Capital Investment .......................................................................................................... 174
Natural Gasoline Process ........................................................................................................ 175
Natural Gasoline Expansion Plant ........................................................................................... 181
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
6
Executive Summary
Natural gas processing represents an opportunity to exploit natural resources to provide
energy sources for a profit. The Yamal Peninsula contains a significant and valuable reserve for
the Russian economy. The objective of this project was to design two processes that separate
natural gasoline from a natural gas wellhead. Whereas the first process re-injects the overhead
streams back into the well, the second process expands the initial process to negate re-injection
and instead separate the overhead products into sales gas and liquefied petroleum gas (LPG)
product streams. These products are nearly equal in value to natural gasoline, with selling
prices of $50/bbl and $55/bbl, respectively, as compared with natural gasoline at $80/bbl. Both
processes yield approximately 10,000 bpd of natural gasoline, a scaled-up value from the 2,500
bpd that were initially being produced.
Product specifications are stringent for safety and energetic quality purposes. Design
specifications ensure that machinery functions in the extreme climate encountered above the
Arctic Circle. All design and product specifications were met, including the mitigation of hydrate
formation. Plant safety and environmental considerations were characterized and deemed
achievable through diligent planning and adherence to local and federal laws.
The economics of the two processes were estimated for a 15-year plant lifetime with one
design year and two years of construction. In the following summaries, economic parameters of
the natural gasoline and re-injection process will precede those of the expansion process to
produce the additional product streams. The total permanent investments were $170,600k and
$36,600k, respectively. The expansion process equipment was designed to use the reinjection
process equipment, thus realizing significant savings in investment. The internal rates of return
with the aforementioned selling prices were 52% and 164%, respectively. The break-even
points were during the first year of operation, the startup year for both processes. The benefits-
cost ratios were 14 and 67, respectively. For these reasons, the expansion process presents
favorable profitability, assuming that the well capacity remains fruitful and the selling prices
remain competitive.
Several improvements to the process merit further consideration. Dehydration
technology exists to minimize the product water content if the specifications change upon
integration with the approaching pipeline. Each of the distillation columns contains a reboiler
and condenser that could be integrated into a heat exchange network that contains process
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
7
streams in an effort to reduce utility costs. The execution of the current design may be improved
by tightening convergence tolerances on columns and recycle functions.
Project Description and Scope
A plethora of natural gas reserves exist on and offshore of the Yamal Peninsula in
Northern Siberia, Russia. One of the clients of URS was initially recovering natural gasoline
from three wells on this peninsula, though due to the absence of a natural gas pipeline in the
area, they were flaring the excess natural gas. This client planned to expand their facility to
quadruple their production of natural gasoline, and initiate the recovery of liquefied petroleum
gas (LPG) and natural gas upon the imminent arrival of a natural gas pipeline. However, due to
the volatile nature of the Russian economy and the high cost of energy the client desired to
accomplish this expansion with minimal capital investment (2).
Problem Statement
Prior to the facility expansion project the client was producing natural gasoline from the
three remote wells. These wells are located far above the Arctic Circle on the Yamal Peninsula
in Northwestern Russia. There is little infrastructure in place in the area, and the natives sustain
themselves by hunting and fishing. The facility was producing approximately 2,500 BPD of
natural gasoline and burning all of the excess gas.
The expansions made to the facility were to consist of two phases. In the first, the
production of natural gasoline was to be increased to 10,000 BPD and the excess gas was to be
re-injected back into the reservoir instead of flared. As a natural gas pipeline was being routed
to the area and was to be in place within five years after the initiation of the expansion, the
second phase was to consist of the modification of the existing facility to include extra
processing equipment to separate and produce LPG and pipeline-quality natural “sales” gas
from the previously re-injected gas.
The remote location of the facility necessitated the consideration of several additional
factors that affected the design of the gas processing plant modifications. The most notable of
these was the extremely cold winter temperatures experienced at the location of the plant. The
wellheads are located in a region where permafrost exists, so the wellhead pipelines were
routed aboveground on piers to avoid degradation of the permafrost, and the equipment had to
be designed to a -60 °F design temperature. Also, due to the fact that electric power was
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
8
unavailable at the site, natural gas engine-driven compressors were to be utilized for gas re-
injection. These were provided by Caterpillar, who has a presence in Siberia (2).
Scope
The first phase of the project was to involve the design of equipment to separate the
hydrocarbon liquids, water, and natural gas in the feed stream, to stabilize the hydrocarbon
liquids to shipping specifications, and to re-inject the residue gas back into the reservoir as
illustrated by the block flow diagram shown in Figure 2.
Inlet
Separation
C5+
RecoveryHydrocarbons
Water
Overheads
Wellhead
Compression Re-Injection
C5+ $
-$
-$
Figure 2. Block flow diagram for natural gasoline production facility
This process is hereafter to be referred to as the natural gasoline process.
Subsequent to the arrival of the natural gas pipeline, the plant modifications were to
include equipment to dehydrate the gas, reduce its hydrocarbon dew point, and compress it for
delivery to the pipeline. From the initial plant configuration the design was to be made easily
convertible to production of pipeline-quality gas. The block flow diagram for the facility following
the second plant modification, hereafter to be referred to as the natural gasoline expansion
process or simply the expansion process is shown in Figure 3.
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
9
Inlet
Separation
C5+
Recovery
Hydrocarbons
Water
Overheads
Wellhead
Dehydration
C5+
Dry Gas
Water
LPG
Recovery
Sales Gas
LPG
C5+ Recycle
$
$
$
TEG
Compression
-$
-$
Refrigeration
HX
Cooled
Dry Gas
Propane
Figure 3. Block flow diagram for natural gasoline, sales gas, and LPG production (natural gasoline expansion
process)
The reduction in hydrocarbon dew point was to take place within the LPG recovery separation
train.
Additional requirements of the project included identifying and evaluating process
alternatives, identifying all the assumptions necessary for the design, and delineating the
requirements for the storage, shipping, and utility systems (2). Taken together, these factors
yielded a profitability analysis that favors expanding the process to produce sales gas and LPG.
Design Criteria
The following criteria and specifications were provided for the gas processing facility
expansion (2).
Wellhead Conditions
The conditions at the wellhead and inlet of the process are given in Table 1.
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
10
Table 1. Process inlet conditions
Inlet Conditions
Wellhead Pressure (bar g)
150
Wellhead Temperature Range (°F)
20 - 50
Process Inlet Pressure (bar g)
103
The wellhead compositions are listed in Table 2.
Table 2. Composition of the wellhead stream (excluding water)
Composition
Component Mole %
N2 0.405
CO2 0.305
CH4 86.121
C2H6 6.637
C3H8 2.484
iC4H10 0.359
nC4H10 0.415
C5+ 3.274
COS/CS2 0.0
H2S 0.0
For the 3.274 mol % of the wellhead stream that is composed of C5+, ASTM D86 data
were given, which is shown in Table 3. ASTM D86 is a standard distillation-based assay used to
characterize petroleum, in which the temperature is recorded at which successive fractions of
the oil mixture have evaporated.
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
11
Table 3. ASTM D86 oil characterization assay data of C5+ at wellhead
ASTM D86 Assay
Percent Evaporated (% Liquid Volume)
Temperature (°C)
Bubble Point 38.7
10 64.3
20 83.7
30 99.7
40 112
50 129
60 148.7
70 171.3
80 214.7
90 281
End Point 295
The data in Table 4 were also given for the C5+ content at the wellhead.
Table 4. Physical data for the C5+ at the wellhead
Natural Gasoline (C5+)
Density (g/cm3) 0.731
Average MW (Da) 101
Wellhead Flow Rate to Facility
The gas flow rate from the wellhead was to be determined based on a natural gasoline
(C5+) standard production rate of approximately 10,000 BPD. The flow rate of water in the
wellhead was to be found based on 1.5 bbl of water produced for every MMSCF of gas flow
from the inlet separator.
Gas Re-Injection
Before the plant modifications for LPG and natural gas recovery were implemented, in
the first phase of the facility expansions, gas was to be re-injected into the well at a pressure of
180 bar g.
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
12
Pipeline Gas Production Specifications
After the facility expansion for the production of LPG and sales gas, in the second phase
of the project, the sales gas was specified to have a hydrocarbon dew point of not more than 0
°F at a pressure of 55 bar g.
Minimum Air Temperature Constraints
Owing to the frigid climate of the Siberian Yamal Peninsula the process and mechanical
design was to allow for a minimum air temperature of -60 °F. Furthermore, all equipment was to
be designed from low-temperature carbon steel impact tested to -65 °F. And finally, any air
coolers were to be designed for the use of air at 85 °F to account for the hottest ambient air
temperature that would likely be reached during the summer months.
Product Specifications
The criteria for the purity and production rate of natural gasoline were based on Reid
Vapor Pressure (RVP), a common measure of purity in the natural gas processing industry, and
standard flow rates, as illustrated in Table 5.
Table 5. Natural gasoline purity and flow rate product specifications
Natural Gasoline (C5+)
Max Reid Vapor Pressure (RVP in psia) 10
Min Standard Flow rate (BPD) 8,000
Design Standard Flow rate (BPD) 10,000
Max Standard Flow rate (BPD) 11,000
The LPG product was to be characterized as having a True Vapor Pressure (TVP) of 210 psia
at 100 °F, and a C5+ content of no more than 2.0% by volume.
Finally, the sales gas product specifications were to be based on Hydrocarbon (HC) dew
point, the temperature at which hydrocarbons begin condensing out of the gas, as well as the
CO2 and H2O content of the gas as shown in Table 6.
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
13
Table 6. Sales gas purity product specifications
Sales Gas (Natural Gas)
Max Hydrocarbon Dew Point (°F)
0
Max CO2 Content (Mole %)
2.0
Max H2O Content (lbs/MMSCF)
4
Economic Considerations
The sales prices of each of the three products were given and tabulated in Table 7.
Table 7. Sales prices of products
Product Sales Prices
Sales Gas $50/bbl $1.19/US gal
LPG $55/bbl $1.31/US gal
Natural Gasoline $80/bbl $1.90/US gal
Also, the operating cost of gas re-injection was given as $1.50/1000 SCF, and the future gas
sales price was given as $4/MMBTU.
Background Information
In order to better understand the expansions that were to be made to the operating
natural gas processing facility it was useful to situate this expansion within the Russian
economic and political climate in the area, to research natural gas processing and the unit
operations that are utilized in the industry and the proposed process, and several processing
alternatives.
The Yamal Megaproject
Owing to the fact that the gas reservoir to be modified is located on the Yamal Peninsula
in Northern Siberia, Russian Federation, information on the nature of Russian gas reserves and
the economic and political climate in which the project will take place are relevant concerns.
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
14
Russia currently supplies one quarter of Europe’s natural gas, and plans to expand in this
market (3). However, over the last several years Russia has lost credibility with many of the
former Soviet Union countries and Europe as a reliable supplier of natural gas. In January of
2006 Russia cut off the gas supply to Ukraine and Moldova, and in late 2006 threatened to cut
supplies to Belarus and Georgia over pricing disputes (4). Then, again, in January of 2009,
fueled by ongoing political tensions between the two countries, Russia curtailed the flow of gas
through Ukraine during a particularly cold period of the winter, affecting in particular the Balkans
and Eastern Europe (3). These and other similar instances have encouraged some countries to
seek other sources of natural gas, and have incited criticism of Russia as using energy as a
political tool (4). However, petroleum and natural gas are vital to the Russian economy, and
Russia plans to further develop and expand the industry largely through the utilization of the
Yamal Peninsula. There are plans to increase production of natural gas from the peninsula by a
factor of almost 42 from 2011 to 2030, a reflection of the vast gas reserves present in the area
(5).
Russia owns approximately one third of the world’s gas reserves, which according to the
International Energy Agency consisted of 46.9 trillion cubic meters (tcm) of proven and probable
reserves at the beginning of 2001 (6). In the North Siberian Yamal Peninsula and adjacent
areas 11 gas and 15 oil, gas, and condensate fields have been discovered which contain
approximately 16 tcm of gas according to exploration and preliminary estimates. These fields
have even been projected to contain as much as 22 tcm of gas reserves (5). The majority of
these fields are owned and licensed to the corporation Gazprom, which is pursuing their
development under the ‘Yamal Megaproject.’
Gazprom is “one of the world’s largest energy companies,” and holds a monopoly in the
Russian gas market (5) (3). It is owned largely by the Russian government, though is a
privatized company which specializes in geological exploration, the production, transportation,
storage, processing, and marketing of hydrocarbons, and the marketing of heat and electric
power (5). In a 2007 initiative, Gazprom, in collaboration with the Yamal-Nenets Autonomous
Okrug (YaNAO) Administration, amended a 2002 draft program for the development of the
peninsula’s gas reserves with the aim of the expansion of the reserve fields and the construction
of gas pipelines on the Yamal Peninsula. The initiative plans for the launch of drilling at several
of the fields, the further development of the production capacities of the existing operational
fields, and the construction of a 2,500 km gas pipeline system. The company purports to be
taking into consideration the myriad environmental and social responsibility issues that the
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
15
project warrants including pollution concerns and the welfare of the indigenous people and
wildlife. Due to the fact that the Yamal Peninsula is the most explored region for gas
production, is located near existing gas pipelines, and has significant reserves, Gazprom
regards the Yamal Megaproject as central to the development of the Russian economy (5).
Definitions
There are three product streams from the proposed process, these being natural
gasoline, liquefied petroleum gas, and natural gas. Each of these distinct products requires
definition.
Natural Gasoline (C5+) – Natural gasoline is a liquid product consisting of pentane, and
all of the hydrocarbons heavier than pentane. For the purposes of this project the purity
of this product stream is defined by a Reid Vapor Pressure of 10 psia at 100 °F, and its
temperature was to be as close to an upper limit of 400 °F as possible to meet common
shipping requirements (2).
Liquefied Petroleum Gas (LPG) – LPG is a liquid product consisting primarily of propane,
n-butane, and isobutane. The purity specifications for this product are a maximum True
Vapor Pressure of 210 psia at 100 °F and a C5+ content of no more than 2.0 % by
volume (2).
Natural Gas (Sales Gas) – Natural gas must meet certain quality specifications before
injection into a pipeline to ensure that the pipeline operates properly. Gas that does not
meet specification can lead to deleterious hydrate formation, operational problems in the
pipeline, pipeline deterioration, or even pipeline rupture (7). These quality measures
often include specifications on the energy content of the gas per volume, its hydrocarbon
dew point temperature, maximum levels of contaminants such as hydrogen sulfide,
carbon dioxide, nitrogen, water vapor, and oxygen, and maximum amounts of particulate
solids and liquid water, as these can damage the pipeline (7). For the expansion of the
relevant natural gas processing plant the quality measures required to be met included a
hydrocarbon dew point of no more than 0 °F, a CO2 content of no more than 2.0 mol %,
and a maximum water content of 4 lbs/MMSCF of gas (2).
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
16
Natural Gas Processing
Natural gas exists in a variety of forms, its composition depending on the type, depth,
and location of the deposit as well as the geology of the area in which it is tapped. Oil and
natural gas are often found in the same reservoir, and natural gas is classified as associated-
dissolved when dissolved in crude oil, or non-associated when it occurs in the absence of oil.
The relevant raw gas being gathered for the proposed process is non-associated. The raw gas
most often consists of two to eight carbon hydrocarbons that are gaseous at underground
pressures, though condense to liquid at atmospheric pressure. These liquids are called
condensates or natural gas liquids (NGLs). The recovery of NGLs can involve any of several
initial processing steps depending on the particular composition of the well (7).
Due to the myriad possible compositions of the raw gas, these initial processing steps
can be quite complex. Producing areas can contain hundreds of wells, from which gas and
NGL is “gathered” via small-diameter pipes that connect the well to processing facilities. At the
wellhead the gas is often put through scrubbers to remove sand and any particulate matter
and/or heaters to ensure that the temperature does not drop low enough for hydrates to form in
the stream.
Hydrates are crystalline, ice-like solids that form with the water vapor in the stream, and
can pose serious risks to the process, as they have the potential to clog the valves and pipes
that the gas passes through during processing, thus leading to dead-heads. They form within a
certain temperature/pressure envelope, oftentimes above the freezing point of water, the limits
of which are dependent on the composition of the stream. Therefore, the avoidance of hydrate
formation was a concern in the design of the proposed process.
The various streams gathered at a given site can require differing initial processing steps
including heating, compression, scrubbing, carbon dioxide removal, and sulfur removal,
contributing to the complexity of the gathering process. After these steps are taken, the further
processing steps that are commonly performed include, but are not limited to the following (7).
Gas-Oil Separation
When natural gas is associated with crude oil it is first necessary to separate the gas
from the oil. Oftentimes pressure relief at the wellhead alone accomplishes this separation, and
just a simple closed tank is required. However, sometimes a multi-stage separation train is
required, in which a series of cylindrical shell, horizontal tanks are commonly utilized. These
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
17
include an inlet at one end, and top and bottom outlets for gas and oil respectively. Separation
is effected by compressing and expanding the feed between tanks, causing heating and cooling
of the stream (7). As mentioned previously, the wellhead stream for the proposed process
consists of non-associated gas, eliminating the need for this step.
Condensate Separation
Condensate separation is most often accomplished through the use of mechanical
separators. It is at times preceded by a slug catcher to remove any free water from the
wellhead stream, and is usually employed when gas-oil separation is not required (7). In the
proposed process this step is carried out by the three phase separator unit.
Dehydration
It is necessary to remove any free water from the natural gas stream to avoid the
formation of hydrates in the process. The most common method of dehydration, and the one
employed in the proposed process, is absorption of water by glycol, though a variety of other
processes have been used, several of which will be discussed in the Alternatives to the
Proposed Process section. Triethylene glycol is the most common type of glycol used for this
purpose (7).
Contaminant Removal
Contaminants that must be removed during processing include hydrogen sulfide and
other sulfur-containing compounds, carbon dioxide, water vapor, helium, and oxygen. To
remove sulfurous compounds flow is often directed through a tower containing a solution of
amines. The amines absorb sulfur compounds from the gas stream, and have the advantage of
being able to be used repeatedly. Desulfurization can then be followed by a series of filter tubes
where gravity, centrifugal force, and flocculation of particulates elicit the removal of other stream
contaminants (7). As the wellhead feed stream in the proposed process does not contain
sulfurous compounds, helium, or oxygen, and carbon dioxide is present at acceptable levels,
this step was not required.
Nitrogen Extraction
Nitrogen, the excessive presence of which can lower the energy content of the gas, is
most often removed from natural gas streams via a nitrogen rejection unit (NRU), which also
works to further dehydrate the gas using molecular sieve beds. Separation can occur through
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
18
the use of cryogenic methods, a column, and a brazed aluminum plate fin heat exchanger, or by
an absorbing solvent (7). Once again, since nitrogen was present at acceptable levels in the
wellhead inlet stream to the proposed process, this step was not needed.
Methane Separation
Methane is the primary component of sales gas, and can be separated from natural gas
streams either as part of the NRU unit or in a separate unit operation. If done separately, there
are two primary methods that are utilized for this purpose, these being cryogenic methods and
absorption. The cryogenic approach, which is better at extracting the lighter liquids in the
stream, such as ethane, is accomplished by lowering the temperature of the gas stream to
around -120 °F. This is often done through the use of a turbo expander in combination with
external refrigerants, and results in the condensation of all stream components besides
methane. The absorption method can be carried out by using absorption oil to absorb the
majority of the NGLs, which are subsequently distilled from the absorbing liquid oil (7). In the
proposed process the use of absorption oils was unnecessary, and methane separation was
achieved by the Sales Gas refluxed absorption column.
Fractionation
Fractionation is the process of separating the various NGLs by virtue of the differing
boiling points of the hydrocarbons in the stream. This is generally done through successive
distillation of the NGL stream, though to produce LPG in the proposed process just a single
distillation column was required (7).
Which of these steps are performed depends on the composition of the raw gas, and
multiple steps can be performed in a single unit operation, or at different locations (7).
Alternatives to the Proposed Process
In modeling the natural gasoline with re-injection and natural gasoline expansion
processes, a number of process alternatives were identified and considered. These included
both alternative processes to those utilized to simulate these two natural gas processing plant
configurations, as well as methods for eliminating various assumptions and simplifications that
were utilized. A description of each process alternative is outlined below.
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
19
Dehydration
Glycol Fluids Package
The Peng-Robinson fluids package was utilized to model both the natural gasoline with
re-injection and natural gasoline expansion processes. This fluids package is ideal for the
modeling of non-polar hydrocarbons, of which the vast majority of the process streams consist;
however, as triethylene glycol (TEG) is hydrophilic, it is not always modeled well by this
package (8). It was therefore considered to use the glycol fluids package in Aspen HYSYS for
the TEG dehydration cycle (9). This matter was discussed with Mr. Arendell, though for the
conditions and purposes of this simulation it was determined that the modeling of this cycle by
the Peng-Robinson fluids package would be sufficient. Mr. Arendell noted that the simplifying
assumption that the Peng-Robinson package accurately modeled TEG dehydration could result
in an underestimate of the amount of water absorbed by the TEG. Nevertheless, the amount of
water in the final sales gas stream came out to be about half of the maximum given specification
of 4 lbs/MMSCF, which was deemed an appropriate tolerance for any extra water that may have
been present in the stream due to an underestimate in its removal during dehydration.
Drizo®
The effectiveness with which a TEG dehydration cycle removes water from a natural gas
stream is dependent on the purity of the glycol upon regeneration. The GPSA section 20 on
dehydration quotes an achievable TEG purity of 98.6 wt% by reboiling TEG at 400°F at
atmospheric pressure (8). However, the proposed process achieves a purity of 99.0 wt% TEG
by reboiling at just below 400°F and just above atmospheric pressure. This very small
discrepancy may be due to the fact that TEG is modeled by the Peng-Robinson fluids package
rather than the glycol package, as discussed in the Glycol Fluids Package section; though as
the quoted value is nearly reproduced, the use of the Peng-Robinson package is further
justified. Various enhanced glycol recovery processes exist, each of which is based on the
principle of reducing the effective partial pressure of water in the vapor space of the lean (water-
deficient) glycol stream, allowing for higher glycol concentrations to be obtained at the same
temperature (8). This results in a greater water dew point depression than can generally be
achieved. The Drizo® process is among these enhanced dehydration processes.
The process regenerates glycol by solvent stripping as opposed to the conventional gas
stripping that is ordinarily employed (10). The solvent is obtained from the natural gas itself,
and is composed of paraffinic and aromatic hydrocarbons (BTEX) that exhibit a C5+ boiling point
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
20
range (10) (8). In the regeneration column for the process, heavy hydrocarbons and water are
condensed from the overhead while non-condensable species are vented to the atmosphere
nearly free of BTEX. The condensed hydrocarbons are separated from the water, vaporized,
and superheated before being routed to the lean-glycol stripping column where they serve as
the stripping gas (8). This results in glycol purities of up to 99.998 wt% according to the
manufacturer, yielding water dew point depressions of upwards of 100 °C (10). The process
can even be supplemented with drying of the solvent by a solid desiccant, which can yield glycol
purities of as high as 99.999 wt% and water dew point depressions of 121 °C (8).
Aside from the fact that this process is exceedingly complicated to model, the extent of
glycol regeneration achieved and the water dew point depressions reached are unnecessary to
meet the sales gas purity specifications of 4 lbs/MMSCF of water and a hydrocarbon dew point
of 0 °F for the proposed process (11). While the Drizo® dehydration system seems well-suited
to applications with very stringent water removal criteria, its implementation in the proposed
process was deemed superfluous.
Coldfinger®
Another proprietary process for achieving enhanced glycol purities upon regeneration is
the Coldfinger® process. In this process, a bundle of condensing tubes (the cold finger), in
which rich TEG is commonly utilized as the coolant, is inserted into the vapor space of a surge
tank half full of lean TEG. The cold finger continuously condenses equilibrium water vapor,
which is discharged from the unit via a collecting trough placed beneath the finger. This
continuous condensation maintains the partial pressure of water in the vapor below its
equilibrium vapor pressure, which works to further draw water out of the lean TEG liquid phase.
The process results in glycol regeneration of upwards of 99.7 wt% TEG in the lean glycol
stream (8). Due to the fact that this process is not in equilibrium, while Apsen HYSYS models
all unit operations as if they were in equilibrium, the Coldfinger® process could not be easily
modeled using this software (11). And further, the extent of glycol regeneration achieved was
again deemed unnecessary to reach the water removal specifications required by the natural
gasoline expansion process.
Advanced Prism® Membranes
A fairly novel process for natural gas dehydration is membrane separation technology.
Advanced Prism® Membranes utilize the principle of selective gas permeation, in which the
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
21
driving force for separation is differing gas partial pressures on either side of a membrane, to
separate water from a natural gas stream (12). These units consist of bundles of hundreds of
thousands of hollow-fiber membranes enclosed in a pressure-rated casing. The gas to be
dehydrated is passed through this casing on the outside of the hollow fibers. Due to the faster
permeation rate of water through these membranes as compared with the hydrocarbons in the
stream, water diffuses through to the inside of the fibers, in which a lower pressure is
maintained. The many fibers provide a large area for membrane separation, resulting in
significant water removal from the stream. These separators can be arranged in parallel, in
series, or in a cascade fashion, and can yield gas streams of up to 98% purity (13). These units
have the potential to incur lower maintenance costs and operate with less downtime than
comparable dehydration units as there are no moving parts involved in the separation. In
addition, raw material costs can be lowered through the use of membrane separation as no
chemical inventory is required for their operation (12).
While membrane-based dehydration systems show much potential for the economic
dehydration of natural gas, this avenue was not pursued due to the impossibility of modeling
these units in Aspen HYSYS. However, this technology could provide a very viable option for
dehydration in similar natural gas recovery processes to the proposed processes.
Heat Integration
The implementation of a heat exchange network to minimize the utilization of process
utilities was investigated in designing the proposed processes. However, heat integration
among utility streams was determined to be infeasible given the thermal properties of these
streams. For instance, the chilled water that is used in the condensers of each column, after
being heated to 90 °F, no longer possesses enough of a cooling capacity to be used for any
other heat exchange processes. Similarly, the low and high pressure steam utilized in the
reboilers of each of the columns, after being condensed, no longer possesses enough of a
heating capacity to be used for any other heat exchange processes.
Any feasible heat integration that could be performed on the proposed processes would
have to involve process streams as opposed to solely utility streams. Though, due to
inexperience in the natural gas processing industry, this option was not considered. A possible
route for heat exchange would be to use the overhead from the sales gas column to cool the
inlet to this column as mentioned by Mr. Arendell. Another option brought up by Mr. Arendell
would be to use the hot C5+ product stream to run the reboiler of one of the other distillation
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
22
columns. While configurations like these have the potential to reduce the utility costs of the
plant, process stream heat integration greatly complicates the startup and control of the given
processes (14). For this reason a cost/benefit analysis would need to be performed in order to
determine if this type of heat integration would be economical without overcomplicating the
control systems for the processes.
A final process alternative relating to heat exchange that was considered was the
expansion of the propane refrigeration cycle to include cooling streams to each of the column
condensers. As the propane, which is recycled, would replace non-recycled cooling water
utilities in each of these condensers, this option may have provided an economic advantage to
the proposed natural gasoline expansion process, however, without a full economic analysis on
this expanded refrigeration cycle, its economic feasibility cannot be determined. Unfortunately,
time constraints did not permit proper investigation of this alternative.
Column Optimization
Due to the numerous variables involved in distillation and absorber column design there
are a plethora of alternate configurations that each of these could assume. For example,
columns could have different numbers of trays, pressures, inlet temperatures, etc. Nonetheless,
by adjusting column parameters such that the design specifications were met, the column
designs were optimized towards the designs that would actually be implemented in industry.
Further optimization was performed by changing the number of trays and the feed tray location
such that reboiler duties were minimized, thus minimizing the amount of heating utility required
to run the column. Finally, the feed tray was chosen based on matching the temperature of the
inlet stream to the inlet tray temperature as closely as possible. This provides for a smoother
temperature profile up the length of the column and allows for better control of column dynamics
upon disturbances (14). The design of each of the distillation and absorption columns was
honed throughout the project by conversations and parameters suggested by Mr. Arendell and
Professor Clough.
Refrigeration Cycle
The propane in the propane refrigeration cycle was modeled as pure propane; however,
this is not entirely accurate. In actuality, refrigeration-grade propane consists of 98% propane
and 2% ethane by weight (15). While this simplifying assumption may have resulted in the
modeling of the processes in this cycle slightly differently due to the different composition of this
exchange fluid, it was determined upon the discovery of the actual composition of refrigeration
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
23
propane that modeling it as pure propane would be sufficient for the proposed process.
However, to model the heat exchange more accurately in this aspect of the simulation, the
correct composition of refrigeration-grade propane would need to be used.
Recycle Operators
Two recycle operators were used in the design of the natural gasoline expansion
process, one in the TEG dehydration cycle and one that recycles C5+ back from the LPG
recovery column to the C5+ column. During the implementation of these operators into the
design, the performance of intermittent mass and energy balances was overlooked, and these
were performed only when the natural gas expansion process was complete. It was then
discovered that the sensitivities for mass and energy flows aligning with one another on either
side of the recycle operators were not tight enough, resulting in a 5.6 % discrepancy in the
energy balance on the process. However, in attempting to tighten the tolerances of the recycle
operators it was found that this was impossible with a complete process including two of these
operators, and Aspen HYSYS was unable to converge with tightened tolerances. While
unfortunate, this discrepancy does not invalidate the proposed process as the mass balance
was very nearly closed. Though in modeling similar processes, it is advisable to tighten the
tolerances for mass and energy flows on any recycle operators while the process is being
modeled, rather than at the end, when it is already complete.
Safety, Environmental, and Health Considerations
Natural gas processing presents a wide variety of safety, environmental, and health
considerations. These are reviewed herein.
Plant Safety (16)
In order to safely operate a natural gas processing plant it is of the utmost concern that
all industry safety standards and protocols are strictly adhered to. Basic safety measures such
as extensive personnel training for the operation of equipment containing flammable and
explosive hydrocarbons under high pressures and at high temperatures must be implemented.
All equipment should be preventatively maintained on a regular schedule. The control systems
of the plant should be optimized for safety, and backup and emergency shutdown systems
should be included for all major unit operations. Systems should be in place to monitor all
equipment for leaks, fluid levels, pressure and temperature, such that any irregularities will
quickly become evident before any situations become critically dangerous. Risk assessment
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
24
protocols should be in place to identify and evaluate any and all potential risks associated with
new or modified process equipment. Also, emergency response procedures should be in place
for any emergency that might occur.
Furthermore, the operation of a natural gas processing plant in particular requires that
concern be paid to various extra safety matters relating to flammability, fire, and explosions.
Again, all industry standard protocols regarding these risks should be followed with care.
Processes should be appropriately segregated from flammable product storage areas, or if this
cannot be achieved, blast walls should be implemented where they are necessary. The plant
should be designed such that potential ignition sources are avoided, such as the elimination of
fixtures that could leak flammable material onto or near heated piping or equipment. Finally the
specific dangers associated with each flammable material in the process should be known and
accounted for. For instance, pressurized flammable gasses can result in jet fires, while
flammable liquid spills can lead to pool fires. The specific dangers of the hydrocarbons and
chemicals employed in the proposed processes will further be outlined in the MSDS summary
section below.
Environmental Concerns (16)
There are several environmental concerns associated with natural gas processing
including fugitive emissions, gas flaring, and wastewater treatment, each of which will be
implemented in the proposed processes.
Gas release to the environment is common in natural gas processing. Fugitive gas
emissions to the environment can occur from leaks in piping, valves, flanges, or other process
connections. In addition, emissions can occur during the loading and unloading of any
hydrocarbon streams or products. These emissions, which can include greenhouse gasses,
can be minimized through the installation of monitoring systems as well as by the maintenance
of stable tank pressures and vapor spaces. Oftentimes flammable gasses are flared from
natural gas processes either for byproduct disposal or as a safety measure for emergencies.
The proposed natural gasoline expansion process includes a Flare Gas stream in the TEG
regeneration cycle. For the sake of safety as well as the prevention of the release of
greenhouse gasses to the atmosphere, this process should be carried out in the most controlled
manner possible.
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
25
Wastewater treatment is also a concern for streams that are contaminated with
hydrocarbons or other chemicals. In the proposed processes the water separated from the inlet
separator, Water 1, as well as the overhead to the TEG Regeneration column, Water 2, are
wastewater streams. These would be treated with an onsite wastewater treatment unit, such
that no contaminated liquids were released into the environment. In addition, all plants that deal
with wastewater treatment should include secondary containment basins with impervious
surfaces to further prevent the release of deleterious compounds into groundwater or soil.
MSDS Summaries
The pertinent points of the MSDS for each of the products and chemicals in the process
are given below. While this information provides many of the key relevant safety issues
involved with working with these chemicals, it DOES NOT substitute for the actual MSDSs.
These should be reviewed and kept in an accessible location at the plant.
It is to be noted that the hazards of propane will not be summarized, as propane is
present in significant quantity in LPG, and the hazards can therefore be assumed to be the
same as for LPG.
Natural Gasoline (17)
May contain benzene, cyclohexane, xylene, and/or toluene
o Can be carcinogenic due to presence of benzene
Clear, colorless liquid with a distinct hydrocarbon odor
Flash point: -45 °F
Extinguishing media: dry chemical, foam, carbon dioxide
Unusual fire and explosion hazards:
o Flames impinging on a product storage vessel above the liquid level can cause
vessel failure within nine minutes, resulting in a boiling liquid expanding vapor
explosion.
o Liquid product will change to vapor quickly at temperatures well below ambient
and form flammable mixtures with air.
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
26
o Vapors are heavier than air, and can travel long distances to an ignition source.
Inhalation risk to respiratory and central nervous systems potentially resulting in death
Frostbite can occur
Liquefied Petroleum Gas (18)
May contain propane, propylene, and/or butane
Clear, colorless gas
Flash point: -156 °F; Autoignition temperature: 842 °F
Extinguishing media: dry chemical, foam, carbon dioxide, water spray
Unusual fire and explosion hazards:
o Containers of product may rupture upon exposure to heat or flame.
o Approach a flame-enveloped container only from the sides, and never from the
head ends.
o Vapors are heavier than air, and can travel long distances to an ignition source.
Inhalation risk to respiratory and central nervous systems potentially resulting in death
Freeze burns can occur
Natural Gas (19)
May contain natural gas, benzene, and/or n-hexane
o Can be carcinogenic due to presence of benzene
Clear, colorless gas
Flash point: <100 °F
Extinguishing media: dry chemical, foam, carbon dioxide, water fog
o Do not use a direct stream of water to extinguish, as natural gas will float, and
can reignite on the surface of water.
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
27
Unusual fire and explosion hazards:
o Do not weld, heat, or drill on or near containers of the product.
o Do not enter confined-space fire without full bunker gear including a face shield,
bunker coat, gloves, rubber boots, and a positive-pressure breathing apparatus.
o Vapors are heavier than air, and can travel long distances to an ignition source.
Inhalation risk to respiratory and central nervous systems potentially resulting in death
Triethylene Glycol (20)
Clear, colorless liquid with no odor
Slightly flammable
Skin irritant
Flash point: 351 °F; Autoignition temperature: 700 °F
Can form explosive mixture with air above flash point
Extinguishing media: dry chemical, alcohol foam, carbon dioxide
o Water or foam may cause frothing
Project Premises and Corresponding Simulation Parameters
The design specifications were given by Mr. Arendell and URS Corporation. Table 8
outlines these specifications and the corresponding simulation parameters.
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
28
Table 8. Project specifications and corresponding simulation and design parameters.
Design Specification Design Value Current Design Value
Wellhead Flow Rates to Facility
Adjusted by design group to produce approximately 10,000 BPD of natural gasoline.
Adjust 1
Natural gasoline and re-injection process dry wellhead flow rate (bpd): 1.068E5 Natural gasoline expansion dry wellhead flow rate (bpd): 1.068E5
Produced Water Rate
1.5 bbl water per MMSCF of gas flow out of the inlet separator. Adjust 2
Natural gasoline and re-injection process wet wellhead and water production flow rate from inlet separator (bpd):
360.4 344.7
Natural gasoline expansion wet wellhead and water production flow rates from inlet separator (bpd):
360.4 344.7
Gas Re-Injection
Normal gas injection pressure (bar g): 180 180 Future Pipeline Gas Product Specification
Maximum hydrocarbon dew point (°F) at 55 barg: 0 -41.2
Future pipeline gas delivery pressure (bar g): 55 55 Product Specifications
Natural Gasoline (C5+ product)
Maximum Reid Vapor Pressure (RVP) (psia): 10 10 Design standard flow rate (bpd): 8,000-11,000
Re-Injection standard flow rate (bpd): 9,202 Expansion standard flow rate (bpd): 9,869
Liquefied Petroleum Gas Maximum true vapor pressure (TVP) (psia) at 100°F: 210 208.2
C5+ content (% volume maximum): 2.0 0.98 Future Residue (Sales) Gas
Maximum CO2 content (mole %): 2.0 0.0032 H2O content (lbs/MMSCF): 4 2.0
Maximum hydrocarbon dew point (°F): 0 -41.2
These results demonstrate that every design and product specification was met.
The process was developed using the following assumptions and specifications with
regard to design and economics.
Design Assumptions
Peng-Robinson equation of state is valid for the entire process
Ignore light ends in Oil Manager
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
29
Mole fractions of C5+ hypothetical components are distributed equally in the Dry Well
inlet material stream
The dehydration step effectively removes enough water to negate hydrate formation
Economic Assumptions
The plant is an expansion on an existing process that has produced 2,500 bpd of natural
gasoline for an unknown duration of time
Conservatively, the salvage value of the current process is unknown and assumed to be
negligible
The purchase of land is not required
The plant is to be constructed in the Yamal Peninsula, Siberia, Russia
Plant is operated 90% of the year for 7,884 operating hours
No royalties
Overall Process Flow Diagrams
Process flow diagrams are linear representations of the process. Both processes were
modeled in Aspen HYSYS V7.0 (9).
Natural Gasoline Process Flow Diagrams
The current plant in the Yamal Peninsula produces 2,500 bpd of natural gasoline. The
overhead products from inlet separation and C5+recovery are reinjected into the well,
representing a significant cost for compression power and significant profit loss for the
contained sales gas and LPG products. Figure 4 is the final Aspen HSYSYS process flow
diagram (PFD) diagram.
30
Figure 4. Final simulation of “current” natural gasoline production.
Material streams are blue, energy streams are red, and special controls are illustrated in neon green. Large blue arrows represent
products.
31
Natural Gasoline Expansion Process Flow Diagram
The proposed design curtails the necessity for re-injection by expanding the separation
train to include sales gas and LPG recovery processes. The process builds off of the overhead
streams that were re-injected. The additional sales gas and LPG recovery streams required
dehydration, refrigeration, and heat exchange prior to the final separation steps.
32
Figure 5. Final simulation of “expanded” natural gasoline production.
Material streams are blue, energy streams are red, and special controls are illustrated in neon green. Large blue arrows represent
products.
33
Process Descriptions
Inlet Separation and Natural Gasoline Recovery
In the inlet separation and natural gasoline recovery portion of the process water in the
wellhead stream is separated from the liquid hydrocarbons and natural gas prior to natural
gasoline recovery in the C5+ distillation column.
Natural Gasoline PFD
Figure 6 depicts the process of inlet separation of the wellhead stream, natural gasoline
recovery, and natural gas compression for re-injection into the well:
1Wellhead
50 °F
2190 psia
2 3
Water 1
Hydrocarbons
C5+ Column
Overhead 1
Qheat
3-Phase Inlet
Separator
Overhead 2
4Qcomp1
Overhead 3
Qc1
Qr1
C5+
$C5+ Storage
C5+
Qcomp2
Overhead 2
Compressor
Re-Injection
Compressor 1
Qcomp3
Re-Injection
Compressor 2
5
Qcomp4
Re-Injection
Compressor 3
6 Re-Injection
105 °F
1505 psia
50 °F
155 psia
400 °F
160 psia
322 °F
2625 psia
69 °F
605 psia66 °F
605 psia
-$
-$
Figure 6. “Current” natural gasoline production process flow diagram with select stream conditions.
Natural Gasoline Expansion PFD
In the natural gasoline expansion process, inlet separation proceeds in a similar fashion
to the natural gasoline process; however, the natural gasoline recovery column includes a
recycled feed from the LPG recovery process. In this process the natural gas was not
compressed for re-injection, but rather simply piped to the TEG dehydration cycle as illustrated
in Figure 7.
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
34
1Wellhead
50 °F
2190 psia
2 3
Water 1
Hydrocarbons
C5+ Column
Overhead 1
Qheat
3-Phase Inlet
Separator
Overhead 2
4
Qcomp1
Overhead 3 to TEG Dehydration
Qc1
Qr1
C5+
$C5+ Storage
C5+
Overhead 2
Compressor
105 °F
1505 psia
50 °F
165 psia
393 °F
175 psia
69 °F
605 psia
C5+ Recycled
278 °F
200 psia
C5+ from Sales/LPG Recovery
300 °F
255 psia
-$
66 °F
605 psia
Figure 7. Natural gasoline expansion process flow diagram showing overhead to TEG dehydration, and
recycle from LPG recovery process.
Approach
Separation of the water, liquid hydrocarbons, and natural gas in wellhead natural gas
streams is often accomplished via mechanical three phase separation units (7). This is the
approach utilized in the both of the proposed processes. Consultation with Mr. Arendell
confirmed this method of inlet separation as being well-suited to the processes being modeled.
To assist in the modeling of C5+ recovery the GPSA section on fractionation as well as
specifications provided by Mr. Arendell were utilized (21). In addition, the GPSA section on
separation equipment was used to determine a residence time for vessel sizing of the inlet
separator (22). The specifications used to converge this phase of the process are as follows:
Hypothetical C5+ components in dry well stream of equal composition, adding to the total
mole fraction of C5+ in the stream as given by the problem statement
Dry Well and Water Well streams at 50 °F and 150 bar g as per the problem statement
Pressure drop across inlet heater and valve to 103 bar g as given in problem statement
Temperature reached after heating by inlet heater and expansion by inlet valve 105 °F in
stream 3 to avoid hydrate formation
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
35
Pressure drop of 62.05 psi across inlet separator as specified by Mr. Arendell
Pressure of 175 psia at the reboiler of the C5+ column, with a 10 psi pressure drop up
the column
Reid Vapor Pressure (RVP) column specification of 10 psia at reboiler stage of C5+
column as per the problem statement
Temperature column specification at condenser stage of 50 °F of C5+ column to avoid
hydrate formation
Feed stage 1 for natural gasoline process and stages 1 and 10 for the hydrocarbons and
C5+ Recycled streams, respectively, for the natural gasoline expansion process
Compression of C5+ overhead to 41.71 bar to match the pressure of the overhead from
the inlet separator before their combination
Gas pressure after Re-injection compressors 1, 2, and 3 of 77.35 bar, 129.4 bar, and
181 bar respectively, meeting the re-injection pressure specification of 180 bar g given in
the problem statement
For the inlet separation and C5+ recovery stage of both processes the flow rates of the
Dry Well and Well Water streams were determined by given downstream parameters. Adjust
operator 1 was implemented to set the flow rate of the Dry Well stream such that the flow rate of
the C5+ stream was 10,000 standard BPD, the design specification given in the problem
statement. Similarly, Adjust operator 2 and the Water Spreadsheet were introduced to set the
flow rate of the Water Well stream such that 1.5 bbl of water was produced from the inlet
separator for every MMSCF of gas flow from the inlet separator, another given specification.
Converging distillation columns in Aspen HYSYS requires the specification of two
process variables to account for the two degrees of freedom in the column. As the C5+ product
stream purity specification was a RVP of 10 psia, one of the column specifications for the C5+
column was that the reboiler stage has an RVP of 10 psia. Originally, the other specification to
account for the final degree of freedom in the column was a reflux ratio of 0.5 suggested by Mr.
Arendell. However, using this configuration hydrates were found in Overhead 2 of this column.
The second column specification was therefore changed to a 50 °F temperature at the
condenser stage of the column. This was found to eliminate hydrate formation in the overhead.
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
36
A storage tank was also modeled to hold one day’s worth of natural gasoline product, or 10,000
bbl.
The only difference in the inlet separation phase of the processes is that in the natural
gasoline process the combined overhead gasses are compressed for re-injection into the well,
whereas in the natural gasoline expansion process the combined overhead streams are simply
routed to the dehydration system. For the re-injection process three compressors were
modeled to bring the gas up to re-injection pressure so that the cost of these could be
determined using an available costing equation. Therefore, to size the compressors within the
maximum horsepower constraint of the costing equation Adjust functions 3 and 4 were used to
adjust the pressures of the respective outlet gas streams such that the a horsepower of 5990
was achieved in the first two re-injection compressors. The final re-injection compressor works
to bring the natural gas pressure up to re-injection specification. In reality, only one large
compressor would be used for re-injection; however, Mr. Arendell agreed that this alternate
configuration employed for economic convenience was adequate to model this portion of the
process.
Triethylene Glycol Dehydration
To produce sales-quality natural gas, excess water must be removed from the gas to
meet the common standards for sales gas as well as to protect the pipeline from damage.
Triethylene Glycol Dehydration PFD
In an effort to mitigate deleterious hydrate formation, dehydration is a crucial step to
remove water from the process. Here, triethylene glycol was used to absorb water in the TEG
contactor as shown in Figure 8.
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
37
Overhead 3 from
Inlet Separation
Dry Gas
Rich TEG
Lean TEG
TEG Flash Drum
5
Flare Gas
TEG Air Cooler
TEG
TEG Pump
3
TEG HX
69 °F
605 psia
95 °F
690 psia
75 °F
100 psia
Regenerated TEG
6
178 °F
15 psia
7
300 °F
90 psia
400 °F
16 psia
Qc2
Qr2
TEG
Regeneration
Column
300 °F
30 psia
Water 2
Propane HX
Propane Out to
Refrigeration
Cycle
Propane In from
Refrigeration
Cycle69 °F
593 psia
253 °F
15 psia
12 to Sales/LPG Recovery
-36 °F
18 psia
-38 °F
17 psia
-33 °F
590 psia
11
-40 °F
510 psia
Qpump
-$
-$
TEG Contactor
Figure 8. TEG dehydration to remove water from the overhead gas stream prior to sales gas and LPG
recovery.
Approach
Liquid desiccant dehydration equipment, more specifically triethylene dehydration, can
be easily automated for use in remote areas. The primary source for glycol dehydration was the
corresponding GPSA section (8). It was recommended by Mr. Arendell to model the dehydration
cycle with triethylene glycol (TEG) and to generate a flow diagram with the assistance of the
outlined GPSA unit operations.
TEG is the most common liquid desiccant used for natural gas dehydration. It was
recommended within the GPSA document that the design employ a 3 gal. TEG/lb water
absorbed ratio (8). The dehydration cycle was converged with the following specifications:
Circulation rate of TEG: 3 gal. TEG/ lb water absorbed
The TEG contactor was specified to have a 5 psia pressure drop.
The TEG regeneration column is run at atmospheric pressure with a 10 kPa pressure
drop up the column.
The reboiler on the TEG regeneration column is specified at a temperature of 400 °F.
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
38
Reflux ratio of the TEG regeneration column is specified as 0.50
Process stream pressure drop of 10 psi, air intake temperature of 85°F, and air intake
pressure of 14.7 psia for the air cooler
The pressure drop for the pump was specified to 684.5 psia
Commonly, an inlet scrubber is installed to prevent accidental dumping of large
quantities of water, hydrocarbons, or corrosion inhibitors into the TEG absorber (8). However, it
was decided to exclude the scrubber in the proposed process because the feed stream was
completely vapor. The first unit operation in the dehydration system is the TEG contactor in
which glycol enters on the top stage and absorbs the water from the counter-current vapor
stream. The water-rich TEG is then subjected to a flash drum which flashes off most of the
soluble gas and flares it. The water is then removed from the water-rich TEG stream within the
TEG regeneration column. The column removes the water from the TEG at atmospheric
pressure with heat (400 °F). The lean-TEG stream is then cooled with the bottoms of the flash
drum, which brings the TEG closer to the feed conditions for the TEG absorber. The lean-TEG
is then pumped and further cooled with an air cooler to return the stream to the absorber feed
conditions. The glycol dehydration is a crucial step in ensuring pipeline quality LPG and sales
gas.
Propane Refrigeration Cycle
The purpose of the propane refrigeration cycle is to cool the dehydrated gas stream prior
to entering the sales gas recovery column.
Propane Refrigeration Cycle PFD
Figure 9 illustrates the two-stage refrigeration cycle that was used to cool the dehydrated
gas stream prior to sales gas and LPG recovery:
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
39
Dry Gas from
TEG
Dehydration
69 °F
593 psia
Propane HX
Propane Out
Propane In
12 to Sales/LPG Recovery
-33 °F
590 psia
11
-40 °F
510 psia
-36 °F
18 psia
Liquid
-38 °F
17 psia
Liquid
Propane
Recycled Liquid
Propane
Flash Drum 1
Suction Drum
Propane Vapor
Qcomp3
Propane
Compressor 1
15
Propane Recycled Vapor
16
Qcomp4
17
Propane
Compressor 2Propane Air Cooler
67 °F
60 psia
24 °F
58 psia
Propane
Flash Drum 3
Economizer
24 °F
60 psia
55 °F
58 psia
155 °F
187 psia
18
Propane
Flash Drum 2
Accumulator
Propane
Liquid
19
95 °F
177 psia
26 °F
62 psia
Liquid Vent
Vapor Vent
Figure 9. Two-stage propane refrigeration cycle to reduce the temperature of the gas stream prior to sales
gas recovery in the reboiled absorber.
Approach
The cooling of the dehydrated gas stream to -33 °F partially condenses the stream to
enhance separation in the reboiled absorber (21). The primary guiding document for the
refrigeration cycle was the corresponding GPSA section (23). In concordance with this
document, it was recommended by Mr. Arendell to model a two-stage refrigeration cycle with an
economizer. This system saves on refrigeration costs by reducing compressor duty while not
investing in the additional equipment required for a three-stage system.
The cycle was simulated with pure propane; however, refrigeration-grade propane
contains 98% propane and 2% w/w ethane (15). Therefore, the refrigeration cycle is idealized
and adaptable once the exact composition of the on-site refrigerant is determined. The cycle
was built with minimal stream specifications. The specifications were as follow:
Vapor/Phase Fraction of 1.0 and temperature of -38 °F in Propane Out to allow for a 5 °F
approach temperature with process Stream 11
Inlet pressure drop of 1.5 psi in Suction Drum
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
40
Pressure of 60 psia in Stream 15
Process stream pressure drop of 10 psi, air intake temperature of 85°F, and air intake
pressure of 14.7 psia for the air cooler
Vapor/Phase Fraction of 0 and temperature of 95°F in Stream 18
Pressure of 62 psia in Stream 19
Inlet and vapor outlet pressure drops of 2 psi in the Economizer
In brief, the propane refrigerant undergoes four steps with the intent to evaporate in the
process heat exchanger, thereby cooling the process stream from 70 °F to -33 °F.
Coincidentally, the propane stream reduces from -35.6 °F to -38 °F during vaporization, allowing
for a five degree Fahrenheit approach. This represents the first of the four steps. The stream
then passes through a suction drum to knock out any liquids prior to compression. This was
initially modeled as a flash drum but was corrected to a tank to avoid background equilibrium
calculations. Secondly, the vapor is compressed in two different compressors. The second
compressor combines the vapor product from the economizer with the one-time compressed
vapor that is once-removed from the process heat exchanger. This is the energy saving step
that characterizes this system as a two-stage cycle. The propane stream is still in the
superheated vapor form following compression, thus giving way to the third step of
condensation in the air cooler. The stream completely condenses via heat exchange with air.
This step necessarily cools the stream to prepare for a two-step expansion via passing through
the economizer. There is a vapor vent potential in the accumulator to isolate liquid refrigerant
prior to expansion. Thus, the fourth and final step is expansion to reduce the pressure and
temperature of the refrigerant prior to heat exchange with the process stream.
Sales Gas and LPG Recovery
The sales gas and LPG portion of the natural gasoline expansion process purifies and
recovers natural sales gas and LPG, as well as removing excess C5+ from the natural gas and
recycling it back to the C5+ recovery column.
PFD
Figure 10 illustrates the configuration of the unit operations required to perform the
functions described above:
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
41
Dry Gas from
TEG Dehydration
Propane HX
Propane Out to
Refrigeration
Cycle
Propane In from
Refrigeration
Cycle
69 °F
593 psia
12
-36 °F
18 psia
-38 °F
17 psia
-33 °F
590 psia
11
-40 °F
510 psia
Sales Gas Column
Sales Gas
Qcomp4
Propane
Compressor 2
-40 °F
500 psia
LPG Column
Qc4
Qr4
Heavy LPG 13
Qr3
C5+ Recycle to Inlet Separation
237 °F
510 psia
184 °F
255 psia
LPG to Pipeline
115 °F
245 psia
300 °F
255 psia
Sales Gas Compressed to Pipeline
27.69 °F
812.4 psia
$
$
Figure 10. Sales gas recovery in the reboiled absorbed and LPG recovery in the distillation column. The
bottoms product of the LPG column recycles to the C5+ recovery column to enhance yield.
Approach
Sales gas recovery is often accomplished by an absorption tower in industry (7). Upon
suggestion by Mr. Arendell, a reboiled absorber specifically was implemented for this purpose.
In order to model LPG recovery, the GPSA section on fractionation as well as a patent by
Mealey were utilized to determine various operating parameters including relevant temperatures
to the process (21) (24). Using these sources as well as input from Mr. Arendell, sales gas and
LPG of appropriate qualities were recovered from the natural gasoline expansion process.
Following are the specifications that were used to achieve convergence of this portion of the
process:
Temperature and pressure of gas stream lowered to -40.01 °F and 510 psia,
respectively, with Propane Heat Exchanger and Sales Valve before entrance to Sales
Gas Column to meet ideal absorption conditions, as suggested by Mr. Arendell
Pressure of 510 psia at the reboiler of the sales gas absorption column, with a 10 psi
pressure drop up the column
Temperature column specification of 237 °F at the Sales Gas column reboiler
Sales gas pipeline injection pressure of 55 psig as specified in the problem statement
Pressure of 255 psia before entrance to LPG column
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
42
Pressure of 255 psia at the reboiler of the LPG column, with a 10 psi pressure drop up
the column
Temperature column specification in the LPG column of 300°F at the reboiler
Composition column specification on the LPG product stream of the LPG column of
1.420 X 10-2 fraction by volume of the lowest molecular weight hypothetical C5+
component
The convergence of the absorption and distillation columns in the sales gas and LPG
recovery portion of the process in such a way that all of the purity specifications on the two
product streams were met was a difficult process. As the specifications for sales gas and LPG
purity were given in terms of a hydrocarbon (HC) dew point and maximum vapor pressure
specification, respectively, these were first used as column convergence parameters. The
refluxed absorber, which has only one degree of freedom, was converged based on an a HC
dew point specification such that the HC dew point of the sales gas was below the given
maximum value of 0 °F. The LPG distillation column was then converged using specifications
for True Vapor Pressure (TVP) at 100 °F and reflux ratio. However, with this set of parameters,
it was impossible to meet the other purity specification of the LPG product stream, that it should
contain less than 2 % of C5+ species by volume.
Eventually, upon the suggestion of a reboiler temperature of 300 °F for the LPG column
by Mr. Arendell, all of the product purity specifications were met. First of all, one of the column
convergence parameters of the LPG column was set to meet the given reboiler temperature.
Then, in order to meet the C5+ content specification for the LPG product, a column parameter
controlling the composition of the highest boiling hypothetical C5+ component in the LPG stream
was created. By adjusting this parameter downwards, the stream was purified of C5+ to
acceptable levels. However, at this point the TVP specification of the stream was not being
met. This was accomplished by changing the convergence parameter of the Sales Gas column
to reboiler temperature, then adjusting this value upwards. This resulted in more heavy
hydrocarbons being reboiled into the Sales Gas stream, which increased the HC dew point of
this stream (within acceptable allowances), while decreasing the TVP of the LPG product. By
this method, and the fact that the water content specification of the Sales Gas stream was easily
met by previous TEG dehydration, all of the product specifications for both the Sales Gas and
the LPG were met.
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
43
Material and Energy Balances
The performance of material and energy balances was necessary to validate the accuracy with
which Aspen HYSYS was able to model the natural gas processes.
Material and Energy Balances
Material and energy balances for both processes were valid, except the overall energy
balance on the expansion process. This imbalance may be attributed to relaxed recycle
sensitivities. A suggestion from Professor Clough and Mr. Arendell to tighten the sensitivities
from 10 to less than unity and increase the number of iterations from 10 to over 100 arose
during the final presentation. This approach was explored and proved to be constrained by time.
At this point in the design, single iterations of one sensitivity unit were allowed to run for several
hours without completing an iteration. Therefore, it is recommended to investigate this approach
upon first reaching convergence of the recycle function. Overall and unit operation balances
were performed in an effort to pinpoint the imbalances.
Balances were completed about the entire processes to validate conservation of mass
and energy. The imbalance of the process, given by Equation 1, demonstrated the validity of
PFD convergence.
Equation 1. Equation to calculate imbalance for material and energy streams.
𝐼𝑚𝑏𝑎𝑙𝑎𝑛𝑐𝑒 = (𝑇𝑜𝑡𝑎𝑙 𝐹𝑙𝑜𝑤 𝑜𝑓 𝑂𝑢𝑡𝑙𝑒𝑡 𝑆𝑡𝑟𝑒𝑎𝑚𝑠) − (𝑇𝑜𝑡𝑎𝑙 𝐹𝑙𝑜𝑤 𝑜𝑓 𝐼𝑛𝑙𝑒𝑡 𝑆𝑡𝑟𝑒𝑎𝑚𝑠)
Furthermore, the relative imbalance, illustrated in Equation 2, normalizes the imbalance to the
total flow of inlet streams. The expected value of this figure is zero; however, HYSYS is
accurate to 0.02 % (9).
Equation 2. Equation to calculate relative imbalance for material and energy streams.
𝑅𝑒𝑙𝑎𝑡𝑖𝑣𝑒 𝐼𝑚𝑏𝑎𝑙𝑎𝑛𝑐𝑒 (%) =𝐼𝑚𝑏𝑎𝑙𝑎𝑛𝑐𝑒
𝑇𝑜𝑡𝑎𝑙 𝐹𝑙𝑜𝑤 𝑜𝑓 𝐼𝑛𝑙𝑒𝑡 𝑆𝑡𝑟𝑒𝑎𝑚𝑠× 100
A relative mass imbalance of zero percent demonstrates that the PDF is fully converged.
Natural Gasoline Process Balances
The mass balance for the natural gasoline process is shown in Table 9:
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
44
Table 9. Natural gasoline material balance
C5+ Material Streams
Inlet lb/hr Outlet lb/hr
Dry Well 5.58E+05 Water 1 5.10E+03
Water Well 5.38E+03 LNG 1.01E+05
C5+ Vapor Product 0
Re-Injection Gas 4.57E+05
Total (lb/hr) 5.64E+05 5.64E+05
Imbalance (lb/hr) 0
Relative Imbalance 0%
The relative imbalance is acceptable.
The energy balance for the natural gasoline process is shown in Table 10.
Table 10. Natural gasoline energy balance
C5+ Energy Streams
Inlet Btu/hr Outlet Btu/hr
Dry Well -9.75E+08 Water 1 -3.49E+07
Water Well -3.69E+07 Qc1 1.00E+05
Qheat 3.32E+07 LNG -7.73E+07
Qr1 2.08E+07 C5+ Vapor Product 0.00E+00
Qcomp1 6.04E+05 Re-Injection Gas -7.89E+08
Qcomp2 2.04E+07
Qcomp3 2.04E+07
Qcomp4 1.55E+07
Total -9.01E+08 -9.01E+08
Imbalance (Btu/hr) 4000
Relative Imbalance 0%
The relative imbalance is acceptable.
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
45
The unit operation balance exposed an imbalance about the C5+ column, as seen in
Table 11.
Table 11. Unit operation balances with C5+ column detail for natural gasoline process. Remarkable (>1)
imbalances denoted in red.
C5+ Process Imbalance
Unit Op Name Mass Flow (lb/hr) Energy Flow (Btu/hr) Volume Flow (bpd)
3-Phase Inlet Separator 1.59E-06 4.84E-07 1.09E-04
C5+ Column 3.97E-06 4.00E+03 2.72E-04
Inlet Heater 3.17E-06 1.36E-06 2.17E-04
Inlet Valve 2.38E-06 1.22E-06 1.63E-04
LNG Storage Tank 7.94E-06 3.41E-06 5.43E-04
Overhead 2 Compressor 4.76E-06 2.05E-06 3.26E-04
Overhead Mixer 7.94E-07 -3.54E-07 5.43E-05
Re-Injection Compressor 1 5.56E-06 2.39E-06 3.80E-04
Re-Injection Compressor 2 6.35E-06 2.73E-06 4.35E-04
Re-Injection Compressor 3 7.14E-06 3.07E-06 4.89E-04
Wellhead Mixer -1.13E-10 1.99E-07 -3.02E-11
Total 0 4000 0
C5+ Process C5+ Column Imbalance
Unit Op Name Mass Flow (lb/hr) Energy Flow (Btu/hr) Volume Flow (bpd)
Condenser -4.41E-12 -3.39E-01 7.07E-13
Main TS 1.59E-06 3.92E+03 1.09E-04
Reboiler 7.94E-07 9.43E00 5.43E-05
Total 0 4000 0
The energy imbalance observed in the C5+ column existed but was negated when normalized,
as seen in the overall energy balance.
Expansion Process Balances
Similarly, a material balance about the expansion process is shown in Table 12.
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
46
Table 12. Expansion process material balance
Expansion Process Material Streams
Inlet lb/hr Outlet lb/hr
Dry Well 5.58E+05 Water 1 5.10E+03
Water Well 5.38E+03 Flare Gas 1.45E+01
Water 2 3.02E+02
Sales Gas Compressed 4.39E+05
LPG 1.14E+04
Propane Liquid 0 0.00E+00
Propane Vapor 0 0.00E+00
LNG 1.08E+05
C5+ Vapor Product 6.54E+00
Total (lb/hr) 5.64E+05 5.64E+05
Imbalance (lb/hr) 23
Relative Imbalance 0%
The relative imbalance is acceptable.
The problematic energy balance for the natural gasoline process is shown in Table 13:
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
47
Table 13. Expansion energy balance
Expansion Process Energy Streams
Inlet Btu/hr Outlet Btu/hr
Dry Well -9.75E+08 Water 1 -3.49E+07
Water Well -3.69E+07 Qc1 1.35E+05
Qheat 3.32E+07 Flare Gas -2.48E+04
Qr1 2.08E+07 Qc2 1.35E+05
Qcomp1 5.88E+05 Water 2 -1.59E+06
Qr2 8.42E+05 Sales Gas Compressed -8.42E+08
Qpump 1.75E+04 Qc4 4.27E+07
Qcomp2 1.12E+07 LPG -1.30E+07
Qr4 4.19E+07 Propane Liquid 0 0
Qr3 4.62E+06 Propane Vapor 0 0
Qcomp3 7.65E+06 LNG -8.28E+07
Qcomp4 1.02E+07 C5+ Vapor Product -4.56E+03
Total (Btu/hr) -8.81E+08 -9.31E+08
Imbalance (Btu/hr) -4.97E+07
Relative Imbalance 5.6%
The relative imbalance of 5.6% is the point of discrepancy for the expansion process.
The unit operation balance exposed significant and numerous energy imbalances, as
seen in Table 14:
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
48
Table 14. Unit operation balances for the expansion process. Remarkable (>1) imbalances denoted in red.
Expansion Process Imbalance
Unit Op Name Mass Flow (lb/hr) Energy Flow (Btu/hr) Volume Flow (bpd)
3-Phase Inlet Separator 2.38E-06 8.25E-07 1.63E-04
C5+ Column 1.03E-05 -8.75E+03 7.06E-04
C5+ Recycle -4.68E+00 3.14E+03 -4.38E-01
C5+ Recycle Valve 7.14E-06 3.07E-06 4.89E-04
Inlet Heater 9.52E-06 4.09E-06 6.52E-04
Inlet Valve 3.17E-06 1.56E-06 2.17E-04
LNG Storage Tank 2.62E-05 1.12E-05 1.79E-03
LPG Column 1.19E-05 -2.40E+04 8.15E-04
LPG Valve 5.56E-06 2.39E-06 3.80E-04
Overhead 2 Compressor 1.27E-05 5.46E-06 8.70E-04
Overhead Mixer 7.94E-07 -3.54E-07 5.43E-05
Propane Air Cooler 2.54E-05 -4.93E+07 1.74E-03
Propane Compressor 1 1.43E-05 6.14E-06 9.78E-04
Propane Compressor 2 1.51E-05 6.48E-06 1.03E-03
Propane Flash Drum 1 1.75E-05 7.51E-06 1.20E-03
Propane Flash Drum 2 1.90E-05 8.19E-06 1.30E-03
Propane Flash Drum 3 1.83E-05 7.85E-06 1.25E-03
Propane HX 2.30E-05 -3.09E-01 1.58E-03
Propane Mixer 1.59E-06 6.82E-07 1.09E-04
Propane Valve 1 8.73E-06 3.75E-06 5.98E-04
Propane Valve 2 7.94E-06 3.41E-06 5.43E-04
Sales Compressor 1.35E-05 5.80E-06 9.24E-04
Sales Gas Column 2.38E-05 -1.14E+02 1.63E-03
Sales Valve 4.76E-06 2.05E-06 3.26E-04
TEG Air Cooler 2.46E-05 -3.05E+05 1.68E-03
TEG Contactor 1.59E-05 6.21E+01 1.09E-03
TEG Flash Drum 1.67E-05 7.17E-06 1.14E-03
TEG HX 2.22E-05 9.55E-06 1.52E-03
TEG Pump 1.98E-05 8.53E-06 1.36E-03
TEG Recycle 2.77E+01 -6.44E+04 1.69E+00
TEG Regeneration Column 1.11E-05 1.01E+00 7.61E-04
TEG Valve 1 3.97E-06 1.71E-06 2.72E-04
TEG Valve 2 6.35E-06 2.73E-06 4.35E-04
Wellhead Mixer -1.13E-10 1.99E-07 -3.02E-11
Total 0 -4.97E+07 0
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
49
The significant negative energy imbalance was caused by a combination of columns, recycle
functions, and an air cooler imbalance. The final value with a seventh-order magnitude exposes
the source of error.
Detailed column imbalances are shown in Table15.
Table 15. Column balance details for expansion process. Remarkable (>1) imbalances denoted in red.
C5+ Column Imbalance
Unit Op Name Mass Flow (lb/hr) Energy Flow (Btu/hr) Volume Flow (bpd)
Condenser -1.76E-12 7.48E-01 0
Main TS 1.59E-06 -8.68E+03 1.09E-04
Reboiler 7.94E-07 -6.89E+01 5.43E-05
Total 0 -9.00E+03 0
TEG Contactor
Unit Op Name Mass Flow (lb/hr) Energy Flow (Btu/hr) Volume Flow (bpd)
TS-1 -2.26E-10 62 0
TEG Regeneration Column
Unit Op Name Mass Flow (lb/hr) Energy Flow (Btu/hr) Volume Flow (bpd)
Condenser 1.59E-06 5.81E-07 1.09E-04
Main TS 7.94E-07 1.01E+00 5.43E-05
Reboiler 4.41E-12 1.71E-07 5.89E-14
Total 0 0 0
LPG Column
Unit Op Name Mass Flow (lb/hr) Energy Flow (Btu/hr) Volume Flow (bpd)
Condenser 1.59E-06 3.33E-01 1.09E-04
Main TS 7.94E-07 -2.40E+04 5.43E-05
Reboiler -1.13E-10 4.00E-01 -7.54E-12
Total 0 -24000 0
Sales Gas Column
Unit Op Name Mass Flow (lb/hr) Energy Flow (Btu/hr) Volume Flow (bpd)
Main TS -1.13E-10 -1.13E+02 -3.02E-11
Reboiler 7.94E-07 -1.51E+00 5.43E-05
Total 0 0 0
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
50
The additive effect of these imbalances was corroborated by the overall energy imbalance. This
analysis expands the imbalance beyond the recycle functions. However, both recycle balances
are shown in Table 16 to provide additional clarity to the imbalance:
Table 16. Recycle balances for the expansion process. Remarkable (>1) imbalances denoted in red.
C5+ Recycled Stream 14 C5+ Recycled Imbalance Relative Imbalance
Vapour 1.58E-01 1.58E-01 -2.62E-05 -0.02%
Temperature (°F) 2.78E+02 2.78E+02 -2.61E-02 -0.01%
Pressure (psia) 2.00E+02 2.00E+02 0.00E+00 0.00%
Molar Flow (lbmole/hr) 1.13E+02 1.13E+02 -8.42E-02 -0.07%
Mass Flow (lb/hr) 7.37E+03 7.36E+03 -4.68E+00 -0.06%
Std Ideal Liq Vol Flow (bpd) 7.69E+02 7.69E+02 -4.40E-01 -0.06%
Molar Enthalpy (Btu/lbmole) -5.48E+04 -5.48E+04 -1.30E+01 0.02%
Molar Entropy (Btu/lbmole-F) 2.94E+01 2.94E+01 1.02E-02 0.03%
Heat Flow (Btu/hr) -6.22E+06 -6.22E+06 3.14E+03 -0.05%
Total -0.21%
TEG Recycle
Stream 10 Lean TEG Imbalance Relative Imbalance
Vapour 0.00E+00 0.00E+00 0.00E+00 0.00%
Temperature (°F) 9.50E+01 9.50E+01 0.00E+00 0.00%
Pressure (psia) 6.90E+02 6.90E+02 0.00E+00 0.00%
Molar Flow (lbmole/hr) 4.96E+01 4.98E+01 1.99E-01 0.40%
Mass Flow (lb/hr) 6.92E+03 6.95E+03 2.77E+01 0.40%
Std Ideal Liq Vol Flow (bpd) 4.21E+02 4.22E+02 1.68E+00 0.40%
Molar Enthalpy (Btu/lbmole) -3.24E+05 -3.24E+05 1.31E-01 0.00%
Molar Entropy (Btu/lbmole-F) 3.52E+01 3.52E+01 -1.18E-05 0.00%
Heat Flow (Btu/hr) -1.61E+07 -1.62E+07 -6.44E+04 0.40%
Total 1.60%
The imbalances observed in the recycle functions were primarily energy parameters, except for
the mass flow in the TEG Recycle function. This value was apparently negligible; an imbalance
was not observed in the overall mass balance.
Process Description & Equipment Specifications
Equipment was designed to accommodate the greater demand of 10,000 bpd, for both
the natural gasoline and re-injection and expansion project.
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
51
Distillation Columns
In the re-injection process there is only one column, which is responsible for the
recovery of natural gasoline at a standard flow rate of 9182 bpd. In the expansion process,
which is capable of recovering natural gasoline, LPG, and sales gas there are a total of five
columns. The purpose of the first distillation column in the separation train (the C5+ Column) is
to separate the heavier hydrocarbons (C5 and above) from the lighter hydrocarbons. An
absorption column and a distillation column are pertinent unit operations within the glycol
dehydration step of the process. The first column in the dehydration step is an absorption
column which acts to remove the remaining water from the process stream by contacting the
stream with a TEG stream. The vapor outlet of the TEG contactor goes on to undergo further
separation to produce LPG and sales gas. The bottoms product from the TEG contactor is the
feed for the TEG regeneration distillation column. The purpose of the TEG regeneration column
is to remove the water from the glycol restoring it to a purity of 99.0 wt%. A refluxed absorber
column is used to separate the heavier hydrocarbons from the sales gas product. The bottoms
stream from the refluxed absorber column is the feed to the LPG recovery distillation column.
The LPG distillation column separates the LPG product from the heavier hydrocarbons (C5+).
The heavier hydrocarbons are then recycled back to the C5+Column.
Estimating Column Pressure and Condenser Type
The column operating conditions are important for obtaining the desired product
specifications. In conjunction with recommendations from Mr. Arendell and Professor Clough,
the diagram in Figure 11 was followed to determine an appropriate column pressure and
condenser type.
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
52
Calculate bubble-
point pressure (PD)
of distillate at
120°F
Start
Distillate and bottoms
are known or estimated
Calculate bubble-
point pressure (PD)
of distillate at
120°F
PD > 215 psia
Choose a
refrigerant so as to
operate partial
condenser at
415 psia
PD > 365 psia
Estimate bottoms
Pressure
(PB)
PD < 365 psia
Use partial condenser
PD < 215 psia
Use total condenser
(reset PD to 30 psia
If PD <30 psia)
Calculate bubble-
point temperature
(TB) of bottoms at
PB
Lower pressure
PD appropriately
TB > bottoms
decomposition or critical temperature
TB < bottoms
decomposition or
critical temperature
Figure 11. Decision tree to determine column pressures and condenser types.
The final column operating parameters are shown in Table 17 where the number of trays and
feed tray locations were iterated and optimized to reduce the reboiler duty.
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
53
Table 17. Final column operating temperatures and pressures.
Column Inlet
Temperature (oC)
Inlet Pressure
(kPa)
Distillate Temperature
(oC)
Distillate Pressure
(kPa)
Bottoms Temperature
(oC)
Bottoms Pressure
(kPa)
C5+
Recovery 19.09 136.6 4171 1379 10.09 1138 213 1207
TEG Contactor Absorber
35 20.55 4757 4171 20.90 4089 20.77 4123
TEG
Regeneration 148.6 206.8 122.9 101.3 204 110.0
Sales Gas Refluxed
Absorber -40 3516 -39.77 3447 113.9 3516
LPG
Recovery 84.46 1758 45.90 1689 148.9 1758
Calculating Number of Trays
In order to determine the number of trays that each distillation column needs, the
distillation columns were first attempted as shortcut distillation columns in Aspen HYSYS.
However, after being unable to make the columns converge another method was utilized. A
trial-and-error method which included changing the number of trays until the duty of the
condensers and reboilers were minimized was utilized instead. The number of trays that yielded
the minimum duty was chosen as the actual number of trays. The resulting number of trays and
reflux ratios, if applicable, can be seen below in Table 18.
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
54
Table 18. Final column operating tray and reflux ratio specifications.
Column Number of
Trays
Number of
Distillate Trays
Number of
Bottoms Trays
Reflux
ratio
C5+ Recovery 10 4 6 1.43x10-3
TEG
Absorber 5 2 3 N/A
TEG Regeneration 5 2 3 0.50
Sales Gas
Refluxed Absorber 12 5 7 N/A
LPG Recovery 12 5 7 25.8
Determining the Dimensions of the Distillation Columns
The determination of the diameter for a distillation column is a relatively straightforward process
requiring only vapor flow rate, G, liquid flow rate, L, pressure, liquid density, ρL, and vapor
density, ρG. Using the aforementioned properties, the flow ratio parameter is calculated using
Equation 3, seen below.
Equation 3.Flow ratio parameter of liquid and vapor flow rates
𝐹𝐿𝐺 = (𝐿
𝐺) ∗ (
𝜌𝐺
𝜌𝐿
)0.5
The parameter CSB is estimated using the obtained value for the flow ratio parameter,
18-in. tray spacing, and a correlation established by Fair in 1961 (25).
Using the parameter CSB, the empirical capacity parameter, C, is calculated for use in
the determination of the flooding velocity. The appropriate equation includes a surface tension
factor, FST, a foaming factor, FF, and a hole-area factor, FHA. Equation 4 demonstrates the
calculation of this parameter:
Equation 4.Empirical capacity parameter calculation
𝐶 = 𝐶𝑆𝐵 ∗ 𝐹𝑆𝑇 ∗ 𝐹𝐹 ∗ 𝐹𝐻𝐴
The flooding velocity, Uf , is computed from the empirical capacity parameter, based on a force
balance on a suspended liquid droplet which can be referenced below in Equation 5 (25).
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
55
Equation 5. Flooding velocity
𝑈𝑓 = 𝐶 ∗ (𝜌𝐿 − 𝜌𝐺
𝜌𝐺
)0.5
The inner diameter of the tower, DT, is computed using tower cross-sectional diameter, At,
downcomer area, AD, and flooding fraction, f. The equation can be referenced in Equation 6:
Equation 6. Inner tower diameter.
𝐷𝑇 = [4𝐺
(𝑓𝑈𝑓)𝜋 (1 − (𝐴𝐷
𝐴𝑡) 𝜌𝐺 )
]
0.5
Following the calculation for the diameter of the column, it is necessary to calculate the
length and thickness of the column, which are pertinent components in the costing of distillation
columns.
The thicknesses of each of the distillation columns in the process were calculated to
ensure column rigidity and strength to stand up to potential earthquake hazards and wind loads.
While the Yamal Peninsula is not in a particularly earthquake-prone location, it was determined
prudent to overdesign the columns for this situation, which does not require an over-excess of
additional carbon steel for construction.
To calculate the column thicknesses, the thickness of steel needed for the top of the
columns was first determined. This requires the determination of the inner diameter of the
column, the design pressure, the maximum allowable stress of the steel, and the weld efficiency
for construction. The inner diameter was found using Equation 6, as shown in the section
above, and the design pressure was calculated using Equation 7:
Equation 7. Design pressure calculation
𝑃𝑑 = exp (0.60608 + 0.91615[𝐿𝑛(𝑃𝑜)] + 0.0015655[𝐿𝑛(𝑃𝑜)]2 )
Since none of the components being distilled are corrosive, it was deemed sufficient to
construct the columns from Grade C carbon steel, for which the maximum allowable stress is
12650 psig (26) (27) (28). For carbon steel up to 1.25 in. thick, only a 10% spot X-ray check of
the welds are necessary and Seider et al. cite a weld efficiency of 0.85 to be sufficient (25).
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
56
With these parameters defined it was then possible to calculate the thickness of carbon steel at
the top of the columns necessary to withstand the internal pressure, tp, as shown in Equation 8:
Equation 8.Thickness at top of column
𝑡𝑝 =𝑃𝑑𝐷𝑖
2𝑆𝐸 − 1.2𝑃𝑑
Here Pd is the design pressure, Di is the internal diameter of the column, S is the
maximum allowable stress of Grade C carbon steel, and E is the weld efficiency. When the
calculated thicknesses were not sufficient for rigidity, an increased thickness was used to
sustain the columns.
The next step in the process was to calculate tw, the excess necessary thickness of the
column at the bottom to withstand earthquake and wind load. For this, the approximate outer
diameter of the column, the column length, and the maximum allowable stress are required.
The lengths of the columns were calculated as the sum of the space between the trays and that
required for a sump below the trays and a disengagement space above the trays. Seider et al.
cite 10 ft. and 4 ft. for sump and disengagement spaces respectively for a column with 2 ft. tray
spacing (25). These were scaled for the 18 in. tray spacing used for each of the columns in the
process according to Equation 9:
Equation 9.Column length
𝐿 = (𝑁 − 1)𝐻𝑡,2 +10𝐻𝑡,2
𝐻𝑡,1
+4𝐻𝑡,2
𝐻𝑡,1
In this equation L is the column length, N is the number of trays, Ht,1 is the tray spacing
requiring 10 ft. and 4 ft. sump and disengagement spaces respectively, and Ht,2 is the tray
spacing of the columns in the process. To calculate the approximate outer diameter of the
column, Seider et al. recommend utilizing a conservative estimate for the total thickness of the
column wall, twall, to ensure that the column can stand up to any earthquake or high winds that
may occur (25). The approximate outer diameters of the columns, Do, were calculated using
Equation 10:
Equation 10. Outer column diameter calculation
𝐷𝑜 = 𝐷𝑖 + 2𝑡𝑤𝑎𝑙𝑙
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
57
The excess thickness required for earthquake and wind hazards, tw, was calculated using
Equation 11:
Equation 11. Excess thickness calculation
𝑡𝑤 =0.22(𝐷𝑜 + 18)𝐿2
𝑆𝐷𝑜2
The variable S in Equation 11 is again the maximum allowable stress of Grade C carbon
steel. From this excess thickness required at the bottom of the column, the total wall thickness
at the bottom of the column, tw allbottom, was calculated using Equation 12:
Equation 12. Thickness of bottom of column
𝑡𝑤𝑎𝑙𝑙𝑏𝑜𝑡𝑡𝑜𝑚 = 𝑡𝑝 + 𝑡𝑤
To find the thickness of the columns to use for costing purposes it was then necessary to
find the average thickness of the columns over their lengths, tv , for which Equation 13 was used:
Equation 13. Average thickness of column throughout length
𝑡𝑣 =𝑡𝑝 + 𝑡𝑤𝑎𝑙𝑙𝑏𝑜𝑡𝑡𝑜𝑚
2
Despite the chemicals being distilled not being cited as being corrosive, for the sake of
prudence in design an allowance for corrosion was nevertheless added to the average wall
thickness to account for any corrosion that might occur over the planned 18 year lifespan of the
plant. The final calculated thickness was determined using Equation 14:
Equation 14.Corrosion insurance to find column thickness
𝑡𝑓 = 𝑡𝑣 + 𝑡𝑐
In Equation 14 tf is the final calculated column wall thickness, tv is the average wall
thickness, and tc is the excess thickness allowed for corrosion. Taking into account the fact that
steel is manufactured in set increments, the thickness of each of the columns was adjusted
accordingly.
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
58
The calculated column dimensions can be referenced below in Table 19. Worth noting
is the fact that a design diameter was used for calculation of the purchase cost of the distillation
columns. The actual diameter was rounded up to the next whole meter diameter.
Table 19. Final column design parameters.
Distillation Column Diameter
(m)
Design Diameter
(m)
Number of Trays
Length (m)
Thickness (m)
C5+ Recovery 1.87 2.00 10 7.32 0.022
TEG Contactor
Absorber 2.25 3.00 5 5.03 0.069
TEG Regeneration 0.26 0.50 5 5.03 0.0095
Sales Gas
Refluxed Absorber 3.31 4.00 12 8.23 0.083
LPG Recovery 3.92 4.00 12 8.23 0.051
Distillation Column Costing
All of the distillation columns were modeled with a carbon steel shell, carbon steel sieve
trays, and 68 kg steel couplings, flanged manholes, and flanged nozzles. The cost of the
columns (distillation and absorption) is based off a design diameter and the length of the
column, whereas the cost of the trays is only based upon the column diameter.
The costs of the connections were calculated using the thickness of the respective
distillation column. It was estimated that each column needed five couplings, three flanged
manholes, and five flanged nozzles. All of the estimated costs can be clearly seen in Table 20.
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
59
Table 20. Final column costs
Distillation Column
Purchase Cost of Column
Installation Cost of Trays
Couplings Cost
Flanged Manholes
Cost
Flanged Nozzles
Cost
Total Cost of
Distillation Column
C5+ Recovery $ 132,000 $ 17,000 $ 5,000 $ 28,000 $ 21,000 $ 203,000
TEG Contactor Absorber
$ 158,000 $21,000 $ 3,000 $ 40,000 $ 27,000 $ 249,000
TEG
Regeneration $ 32,000 $5,000 $ 5,000 $ 19,000 $ 14,000 $ 75,000
Sales Gas Refluxed
Absorber $ 285,000 $39,000 $ 3,000 $ 50,000 $ 35,000 $ 412,000
LPG Recovery $ 285,000 $39,000 $ 5,000 $32,000 $31,000 $ 392,000
Total Purchase Cost of Columns $ 1,330,000
Expansion Purchase Cost $ 1,130,000
Flash Drums
Three-Phase Separator
The three-phase separator is the first unit operation in natural gasoline recovery
process. Intuitively, it has three product streams, a vapor stream and two liquid streams. The
primary purpose of the three-phase separator is to remove most of the water from the feed
stream. The vapor stream is primarily composed of methane, the hydrocarbon stream is
composed of mostly larger hydrocarbons with some water and smaller hydrocarbons, and the
water stream contains 99.99% water. The amount of water in the feed was determined using an
Adjust function in Aspen HYSYS, such that there was 1.5 bbl of water for every MMSCF of
vapor out of the three-phase separator. The feed conditions can be seen below in Table 21.
Table 21. Feed conditions to the three-phase inlet separator in Stream 3.
Stream Temperature
(oC) Pressure
(kPa) Mass Flow Rate (kg/hr)
3 (Feed to 3-Phase Separator)
40.56 1.038x104 2.556x105
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
60
The feed compositions can be seen below in Table 22.
Table 22. Composition of Stream 3, the inlet material stream to the three-phase inlet separator.
Stream Mole
%
N2
Mole %
CO2
Mole %
CH4
Mole %
C2H6
Mole %
C3H8
Mole %
iC4H10
Mole %
nC4H10
Mole %
C5+
Mole %
H20
3 0.4 0.3 85.13 6.56 2.46 0.35 0.41 3.24 1.15
After the three-phase separator the liquid hydrocarbon stream is subjected to a
distillation column in order to separate natural gasoline (C5+) from lighter hydrocarbons and
water. The natural gasoline is the first product in the expansion plant and the sole product in the
re-injection plant. The vapor stream from the three-phase separator was combined with the
overhead of the natural gasoline recovery column. The water stream from the three-phase
separator was subject to treatment to remove all organic components. The product stream
conditions can be seen below in Table 23.
Table 23. Product stream conditions for the three phase inlet separator.
Stream Temperature
(oC) Pressure
(kPa) Mass Flow Rate
(kg/hr)
Overhead 1 ( Vapor Stream) 19.09 4171 2.039x105
Water 1 (Water Stream) 19.09 4171 4.938x104 Hydrocarbons (Hydrocarbon Stream) 19.09 4171 2313
The compositions of each of the resulting streams can be seen in Table 24.
Table 24. Product stream compositions from the three-phase inlet separator.
Stream Mole
%
N2
Mole %
CO2
Mole %
CH4
Mole %
C2H6
Mole %
C3H8
Mole %
iC4H10
Mole %
nC4H10
Mole %
C5+
Mole %
H20
Overhead 1 0.42 0.31 89.17 6.66 2.30 0.29 0.31 0.47 0.06
Water 1 0.00 0.01 0.00 0.00 0.00 0.00 0.00 0.00 99.99
Hydrocarbons 0.03 0.16 17.20 5.95 6.44 1.86 2.72 65.59 0.03
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
61
Flash Drums
Flash drums were only necessary in the expansion plant process. Three flash drums
were used in the propane refrigeration cycle and one was used in the TEG dehydration cycle.
The TEG flash drum was used to remove the hydrocarbons which contaminated the water-rich
glycol stream. Two of the flash drums in the propane refrigeration cycle are primarily safety
precautions these being the suction drum and accumulator (23 p. 13). The other flash drum in
the propane refrigeration cycle is an economizer, which is responsible for separating vapor and
liquid propane before the liquid propane is again used as a utility fluid for the overhead gas heat
exchanger.
Calculating the Diameter and Height of the Flash Drums
In order to calculate the diameter and height of the flash drums, a 3 to 1 length to
diameter ratio was used. The volume was calculated using the volumetric flow rate and a
residence time of 5 minutes. The calculation of the volume can be seen in Equation 15.
Equation 15. Calculation of Flash Drum Volume
𝑉 = �̇� (𝑚3
𝑚𝑖𝑛)∗ 5 𝑚𝑖𝑛
Using the 3 to 1 length to diameter ratio, the diameter was solved for using the volume of
a cylinder equation, which can be seen below in Equation 16.
Equation 16. Calculation of Flash Drum Diameter
𝐷 = 2 ∗ (𝑉
6𝜋)
13
The length of the flash drums was calculated by simply multiplying the diameter by a
factor of three. The thickness of the flash drum was calculated using the same method utilized
for the distillation columns.
Calculating the Weight of the Flash Drums using the Diameter, Height, and Thickness
In order to calculate the costs of the flash drums it was necessary to find the weight of
the flash drums which is a function of the diameter, height, and thickness. The weight of the
shell and the two elliptical heads was calculated using an equation from Seider et al., which can
be seen below in Equation 17. The diameter, length, and thickness must all be in meters.
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
62
Equation 17. Weight of shell and two elliptical heads
𝑊 = 𝜋(𝐷 + 𝑡𝑠) ∗ (𝐿 + 0.8𝐷) ∗ 𝑡𝑠 ∗ 17304.17𝑙𝑏
𝑚3
Flash Drum Costing
Since most of the cost of flash drums were unable to be estimated using the costing
worksheet, the cost of the vessels was estimated using the Matches website (29). The three-
phase separator was modeled as a carbon steel air sweep, dry, without a motor separator. The
remaining flash drums were modeled as either large or medium carbon steel vertical pressure
vessels. In addition, three 68 kg couplings were used for each flash drums. The specifications
and costs of each of the flash drums can be seen in Table 25.
Table 25. Final flash drum design parameters and costs.
Flash Separator
Diameter (m)
Length (m)
Thickness (m)
Weight of Vessel (lb)
Couplings Cost
Total Cost of Flash
Separator
TEG Flash Drum 0.52 1.57 0.013 753 $ 3,000 $ 17,000
Propane Flash Drum 1
10.8 32.4 0.013 3.13x105 $ 3,000 $ 712,000
Propane Flash Drum 2 2.16 6.47 0.013 1.26x104 $ 3,000 $ 73,000
Propane Flash Drum 3 5.28 15.8 0.013 7.49x104 $ 3,000 $ 250,000
Three-Phase Separator
2.47 7.42 0.013 1.65x104 $ 3,000 $ 121,000
Total Purchase Cost of Flash Drums $ 1,170,000
Expansion Purchase Cost $ 1,050,000
Heat Exchangers
Heat exchangers are vital unit operations in most industrial processes. Choosing the
materials of construction and dimensions are important in ensuring safe operation and proper
heat exchange. In the process, double pipe heat exchangers were used when there was a small
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
63
heat transfer area and fixed-tube sheet and floating head shell-and-tube heat exchangers were
used when the heat transfer area was large. In addition to the aforementioned heat exchangers,
air-cooled heat exchangers were used for some process streams. For all of the heat exchangers
used in the process carbon steel was used as the material of choice due to each of the utilized
chemicals non-corrosive properties as well as to design for the frigid temperatures of Siberia.
Design of the Heat Exchangers
The log mean temperature difference method was used to determine the area necessary
for proper heat exchange. For the log mean temperature difference method, the duty and log
mean temperature difference are taken directly from Aspen HYSYS. The log mean temperature
difference was checked using Equation 18.
Equation 18. Log mean temperature difference for shell-and-tube heat exchanger
∆𝑇𝐿𝑀 =∆𝑇1 − ∆𝑇2
ln (∆𝑇1
∆𝑇2)
Where ∆𝑇1 is 𝑇ℎ,𝑖𝑛 − 𝑇𝑐 ,𝑜𝑢𝑡 and ∆𝑇2 = 𝑇ℎ,𝑜𝑢𝑡 − 𝑇𝑐,𝑖𝑛.
In order to solve for the heat transfer area, an overall heat transfer coefficient, U, was
estimated using the typical range of overall heat transfer coefficients that are relevant to the
fluids flowing through the heat exchanger, which was obtained from literature (25). Once the U
value was selected, the heat transfer area was calculated using Equation 19.
Equation 19. Heat exchange area calculation
𝐴 =𝑄
𝑈𝐹𝑇∆𝑇𝐿𝑀
In the Equation 19, A is the heat transfer area, Q is the required duty, and FT is the correction
factor, which is also found within the HYSYS interface. The correction factor was either less
than or equal to 1 for all of the heat exchangers in the process.
Heat Exchanger Costing
The material of construction for all of the exchangers in the system is carbon steel
because there is no risk of corrosion. Chilled water is used as the utility fluid for each of the
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
64
columns with condensers. Both low and high pressure steam are used as the utility fluid for
each of the columns with reboilers. Low pressure steam was used as the utility fluid for the inlet
heater. Both the propane and TEG heat exchangers utilize utility fluid that is the same as the
process stream. In each of the heat exchangers found within the process, the process stream is
run through the tubes of the heat exchanger. The flow rates of both the process stream and the
utility fluid dictate the size of the heat exchangers. Each of the heat exchangers were priced
using the costing equations provided in the costing spreadsheet.
The observed operating conditions for each of the heat exchangers can be seen in Table
26:
Table 26. Heat exchanger operating conditions and corresponding utility requirements
Heat Exchanger
Mass Flow Rate
(kg/hr)
Inlet Temperature
(oC)
Outlet Temperature
(oC)
Inlet Pressure
(kPa)
Outlet Pressure
(kPa) Fluid
Inlet Heater
2.556x105 9.912 113.9 1.510x104 1.509x104 Process
4.104x104 147.6 146.7 446.1 436.1 50 psig
Steam
TEG Heat
Exchanger
3277 24.03 148.9 689.5 620.5 TEG
3140 204.0 81.26 110 106.6 TEG
Propane Heat
Exchanger
2.076x105 20.90 -36.17 4089 4068 Process
9.759x104 -37.53 -38.89 123.7 116.8 Propane
TEG Air Cooler
3140 79.84 35.00 4826 4757 TEG
4.179x105 29.44 30.21 101.4 101.4 Air
Propane Air Cooler
1.354x105 68.28 35 1289 1220 Propane
1.589x106 29.44 61.75 101.4 101.4 Air
The observed operating conditions for each of the condensers can be seen in Table 27:
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
65
Table 27. Condenser operating conditions
Condenser Mass
Flow Rate (kg/hr)
Inlet Temperature
(oC)
Outlet Temperature
(oC)
Inlet Pressure
(kPa)
Outlet Pressure
(kPa) Fluid
C5+
Condenser
3815 28.10 9.99 1138 1128 Process
3945 7.22 15.56 1138 1090 Chilled Water
TEG Regeneration
Condenser
199.2 99.33 99.00 101.3 101.3 Process
837.8 7.22 32.22 101.3 101.3 Chilled Water
LPG Condenser
1.384x105 62.97 45.86 1689 1679 Process
4.127x105 7.22 32.22 1689 1641 Chilled Water
The observed operating conditions for each of the reboilers can be seen in Table 28.
Table 28. Reboilers operating conditions.
Reboiler Mass
Flow Rate (kg/hr)
Inlet Temperature
(oC)
Outlet Temperature
(oC)
Inlet Pressure
(kPa)
Outlet Pressure
(kPa) Fluid
C5+
Reboiler
8.032x104 137.9 200.7 1207 1193 Process
1.136x104 207.3 207.0 1793 1783 245.3 psig
Steam
TEG Regeneration
Reboiler
3380 144.1 204.0 110.0 100 Process
471.8 214.6 214.3 2068 2058
285.3 psig
Steam
LPG Reboiler
1.555x105 133.5 148.9 1758 1748 Process
2.211x104 185.7 185.3 1136 1126 150 psig
Steam
Sales Gas Reboiler
2.810x104 95.67 113.9 3516 3506 Process
2286 147.6 146.7 446.1 436.1 50 psig
Steam
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
66
The equipment costs for the heat exchangers were determined using the calculated heat
transfer area and the appropriate costing equation. The heat transfer area and the
corresponding cost for the heat exchangers can be found in Table 29.
Table 29. Heat exchanger cost.
Heat Exchanger ∆T lm
(oF)
U (Btu/ft2-hr-
oF)
Duty (Btu/hr)
Heat Transfer Area (m2)
Purchased Cost
Inlet Heater 132.10 250.00 8.35x107 234.92 $ 37,000
TEG Heat Exchanger 91.24 40 1.00x106 25.49 $2,000
Propane Heat Exchanger
28.11 200.00 3.15x107 519.95 $ 110,000
TEG Air Cooler 36.23 20.00 3.05x105 39.16 $ 24,000
Propane Air Cooler 12.82 10.00 5.01x107 26313.35 $ 494,000
Total Purchase Cost of Heat Exchangers $ 667,000
Expansion Purchase Cost $ 630,000
The heat transfer area and the corresponding cost for the condensers can be found in
Table 30.
Table 30. Condenser cost.
Condenser ∆T lm
(oF)
U (Btu/ft2-hr-
oF)
Duty (Btu/hr)
Heat Transfer Area (m2)
Purchased Cost
C5+ Condenser 9.55 140 1.34x105 9.33 $ 2,000
TEG Regeneration Condenser
141.80 140 8.57x104 0.40 $ 1,000
LPG Condenser 58.25 140 4.22x107 480.39 $ 72,000
Total Purchase Cost of Condensers $ 75,000
The heat transfer area and the corresponding cost for the reboilers can be found in
Table 31.
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
67
Table 31. Reboiler costs
Reboiler ∆T lm
(oF) U
(Btu/ft2-hr-oF) Duty
(Btu/hr) Heat Transfer
Area (m2) Purchased
Cost
C5+
Reboiler 47.99 250 2.09x107 161.76 $ 32,000
TEG Regeneration Reboiler
56.69 300 8.55x105 4.67 $ 2,000
LPG Reboiler
78.92 250 4.24x107 199.45 $ 41,000
Sales Gas Reboiler 75.09 250 4.65x106 23.02 $ 2,000
Total Purchase Cost of Reboilers $ 77,000
Pumps
The process does not heavily rely on the use of pumps. The pump used for the process
was a cast steel centrifugal pump with an explosion-proof alternating current electric motor. The
volumetric flow rate (Q) and the power requirement were obtained from the Aspen HYSYS
simulation. The pump operates at 75% efficiency. The pump operating conditions and 2010 cost
adjusted purchase costs can be referenced in Table 32.
Table 32. Pump operating conditions and cost
Pump Q
(gal/min) ∆P
(psi) Head (ft)
Power Requirement
(kW)
Purchase Cost of Pump
Purchase Cost of Motor
Total Purchase Cost of Pump
1 12.27 684.5 1458.1 5.116 $ 6,000 $ 2,000 $ 8,000
Compressors
Compressors are a pivotal unit operation in both the re-injection process and the
expansion plant process. Both processes use a total of four compressors. The compressors in
the process are used to increase the pressure of a vapor streams, essentially acting as a pump
for vapor streams. The compressors used in both processes were modeled as carbon steel gas
engine reciprocating compressors with a pressure rating of 7000kPa. The operating conditions
for the compressors in the re-injection process can be seen in Table 33:
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
68
Table 33. Compressor operating conditions (re-injection process)
Compressor Mass Flow
Rate
(kg/hr)
Inlet Temperature
(oC)
Inlet Pressure
(kPa)
Outlet Temperature
(oC)
Outlet Pressure
(kPa)
Inlet Vapor
Fraction
Outlet Vapor
Fraction
Overhead 2 Compressor
3525 10.09 1138 106.4 4171 0.999 1.000
Re-Injection Compressor
1
2.075x105 20.49 4171 75.95 7735 1.000 1.000
Re-Injection Compressor
2
2.075x105 75.95 7735 126.4 1.294x104 1.000 1.000
Re-Injection Compressor
3
2.075x105 126.4 1.294x104 161.2 1.810x104 1.000 1.000
The operating conditions for the compressors in the expansion plant process can be
seen in Table 34:
Table 34. Compressor operating conditions (expansion plant process)
Compressor Mass Flow
Rate
(kg/hr)
Inlet Temperature
(oC)
Inlet Pressure
(kPa)
Outlet Temperature
(oC)
Outlet Pressure
(kPa)
Inlet Vapor
Fraction
Outlet Vapor
Fraction
Overhead 2 Compressor
3801 10.04 1138 104.3 4171 0.999 1.000
Propane Compressor
1
9.759x104 -39.16 106.5 19.18 413.7 1.000 1.000
Propane Compressor
2
1.354x105 12.49 399.9 68.28 1289 1.000 1.000
Sales Compressor
1.991x105 -39.77 3447 -2.39 5601 1.000 1.000
The cost of the compressors for each of the processes was estimated using the power
requirement and the costing equations. The adiabatic efficiency of each of the compressors is
75% and the polytropic efficiency calculated with the Shultz polytropic method is between 76-
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
69
77%. The power requirement, as well as the cost for each of the gas engine reciprocating
compressors for the re-injection process can be seen in Table 35:
Table 35. Compressor operating conditions and cost (re-injection process)
Compressor Mass Flow
Rate (kg/hr)
Adiabatic Efficiency
Power Requirement
(kW)
Purchase Cost
Overhead 2 Compressor 3525 75.0% 167 $ 272,000
Re-Injection
Compressor 1 2.075x105 75.0% 5989 $ 8,050,000
Re-Injection
Compressor 2 2.075x105 75.0% 5988 $ 8,040,000
Re-Injection
Compressor 3 2.075x105 75.0% 4537 $ 6,190,000
Total Purchase Cost of Compressors $ 22,550,000
The power requirement, as well as the cost for each of the gas engine reciprocating
compressors for the expansion plant process can be seen in Table 36:
Table 36. Compressor operating conditions and cost (expansion process)
Compressor Mass Flow
Rate (kg/hr)
Adiabatic Efficiency
Power Requirement
(kW)
Purchase Cost
Overhead 2 Compressor 3801 75.0% 172 $ 280,000
Propane
Compressor 1 9.759x104 75.0% 2241 $ 3,172,000
Propane
Compressor 2 1.354x105 75.0% 2993 $ 4,172,000
Sales Compressor 1.991x105 75.0% 3279 $ 4,548,000
Total Purchase Cost of Compressors $ 12,171,000
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
70
Valves
Valves are necessary for the reduction of pressure and temperature of the streams for which
they are implemented. Valves were used on the following streams in the expansion process:
Three-phase separator feed (1.508x104 kPa 1.038x104 kPa)
Feed stream to the TEG flash drum (4123 kPa 689.5 kPa)
Feed stream to the TEG regeneration column (620.5 kPa 206.8 kPa)
Feed stream to the Sales Gas column (4068 kPa 3516 kPa)
Feed stream to the LPG column (3516 kPa 1758 kPa)
C5+ recycle stream (1758 kPa 1379 kPa)
Propane liquid stream (1220 kPa 427.5 kPa)
Propane recycled liquid stream (413.7 kPa 123.7 kPa)
The only valve utilized in the re-injection process is the valve on the three-phase separator
feed. Most of the valves were modeled as carbon steel butterfly construction diaphragm valves,
the cost of which is based on their nominal diameter. In order to find the nominal diameter, the
cross–sectional area was calculated using the velocity, ν, and volumetric flow rate, Q, obtained
from HYSYS. The calculation for cross-sectional area, Ac, can be seen in Equation 20.
Equation 20. Cross-sectional area calculation
𝐴𝑐 =𝑄
𝑣
Using the equation for cross-sectional area the nominal diameters were calculated. The
two propane valves were modeled as carbon steel gated flanged valves, the cost of which is
also based on their nominal diameter. The calculation of the nominal diameter was performed in
the same way as for diaphragm valves. The valve specifications and purchase costs can be
seen in Table 37.
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
71
Table 37. Valve operating conditions and costs
Valve Velocity
(m/s)
Volumetric Flow Rate (m3/s)
Cross Sectional Area (m2)
Diameter (m)
Purchase Cost
Inlet Valve 232.80 0.64 0.0028 0.059 $ 2,000
TEG Valve 1 0.41 0.0011 0.0027 0.059 $ 2,000
TEG Valve 2 0.46 0.0020 0.0043 0.074 $ 2,000
Sales Valve 581.8 1.34 0.0023 0.054 $ 2,000
LPG Valve 3.01 0.028 0.0094 0.109 $ 2,000
C5+ Recycle Valve
0.97 0.0058 0.0060 0.087 $ 2,000
Propane Valve 1
40.21 1.15 0.029 0.191 $ 3,000
Propane Valve 2
25.82 1.78 0.069 0.256 $ 2,000
Total Purchase Cost of Valves $ 17,000
Expansion Purchase Cost $15,000
Storage Tank
A storage tank was necessary in both processes for the storage of natural gasoline. The
storage tank was modeled to hold the daily production volume of natural gasoline. In order to
calculate the daily production volume the volumetric flow rate (gallons/min) was multiplied by the
amount of minutes in a day (1440 min/day), which can be seen in Equation 21.
Equation 21. Calculation of the Daily Production Volume
𝑉𝐷𝑃 = �̇� (𝑔𝑎𝑙𝑙𝑜𝑛𝑠
𝑚𝑖𝑛) ∗ 1440
𝑚𝑖𝑛
𝑑𝑎𝑦
The daily production volume was calculated to be 508,511 gallons, the tank was
assumed to have a volume equal to the daily production value. The storage tank was sized with
the assistance of an API standard tank sizing sheet provided by Sean Arendell. The dimensions
were specified using a design volume of 540,000 gallons, which was the daily production
volume for the expansion plant. Utilizing the larger tank initially saves from having to re-
purchase a new storage tank following the expansion of the plant. The cost of the storage tank
was estimated utilizing the online cost estimate website Matches (29). The storage tank was
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
72
modeled as a carbon steel API floating roof storage tank. The storage tank dimensions and
costs for the expansion plant can be seen in Table 38.
Table 38. Storage tank operating conditions and cost
Storage Tank
Volumetric Flow Rate (gallons/min)
Volume of Tank
(gallons)
Diameter (m)
Length (m)
Total Cost of Storage Tank
LNG Storage
Tank 374.73 5.396x105 14.63 12.19 $ 435,000
Utility Summary
Utility requirements were calculated for both the natural gasoline re-injection and the
expansion plant processes based on annual consumption rates. One exception in the expansion
plant process was the propane refrigeration cycle which is responsible for cooling the overhead
from the TEG dehydration cycle. For the refrigeration cycle, the cost of propane was a one-time
capital expense. The residence time of a unit of propane within the refrigeration determined the
required amount of propane. The residence time was estimated to be one hour (McKetta, 1994).
This scaling factor was multiplied by the hourly flow rate to yield a total consumption term. The
cost of propane is $50/ bbl. The initial glycol necessary for the TEG dehydration cycle was
calculated using a residence time of one hour, which was estimated to be 6949 lb. Unlike the
propane refrigeration cycle, the TEG dehydration loses approximately 36.5 lb/hr; therefore it
was necessary to purchase additional glycol as a utility to compensate for the hourly losses of
glycol.
Table 39 defines pertinent conversion factors. Importantly, the plant operated for 90 % of
the year or 7,884 hours of the 8,760 hours per year.
Table 39. Conversion table for utility summary
Conversion Factors
Factor Value Units
Operating Time 0.90
Volumetric Conversion 264.17 US gallons/m3
Density Water, 20oC 998.2 kg/m3
Hours in a Year 8,760 h/yr
Operating Time 7,884 h/yr
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
73
Each of the condensers used in both processes utilized chilled water as the utility fluid.
The reboilers were serviced by low and high pressure steam. The inlet heater present in both
processes used low pressure steam as the utility fluid. In addition to heat exchangers, the
expansion plant process required electricity to run the air coolers and the pump in the process.
On-site sales gas was used to power the compressors in both of the proposed processes.
In order to properly dispose of the organic impurities found within the two water product
streams, it was necessary to subject the streams to waste water treatment. This is done in
accordance with the U.S. Clean Water Act of 1977 (25). The treatment costs were determined
to be $0.15 per pound of organic impurities.
Table 40 shows the utility summary for the natural gasoline re-injection process, which
excluded the use of propane refrigeration and TEG dehydration.
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
74
Table 40. Utility summary for the natural gasoline re-injection process
Condensers
Condenser Utility Type Mass (ton) Yearly Mass Requirement
(ton-day)
Unit Cost
($/ton-day)
Annualized Utility Cost
($)
C5+ Condenser Chilled Water 11.2 3680 $ 1.20 $ 4,000
Reboilers
Reboiler Utility Type Mass flow
Rate (kg/hr)
Yearly Mass Requirement
(kg)
Unit Cost ($/1000 kg)
Annualized Utility Cost
($)
C5+ Reboiler 245.3 psig
Steam
1.14x104 8.96x107 $ 0.012 $ 1,050,000
Heat Exchangers
Heat Exchanger
Utility Type Mass flow
Rate (kg/hr)
Yearly Mass Requirement
(kg)
Unit Cost ($/1000 kg)
Annualized Utility Cost
($)
Inlet Heater 50 psig
Steam
4.10x104 3.24x108 $ 0.0066 $ 2,140,000
Compressors
Compressor Utility Type
Heat Flow
Rate (MMBTU/hr)
Yearly Heat
Requirement (MMBTU)
Unit Cost ($/MMBTU)
Annualized
Utility Cost ($)
Overhead 2 Compressor
Sales Gas 1.79 1.41x104 $ 4.00 $ 57,000
Re-Injection Compressor 1
Sales Gas 64.3 5.07x105 $ 4.00 $ 2,030,000
Re-Injection
Compressor 2 Sales Gas 64.3 5.07x105 $ 4.00 $ 2,030,000
Re-Injection
Compressor 3 Sales Gas 48.7 3.84x105 $ 4.00 $ 1,540,000
Waste Water Treatment
Waste Stream Wastewater
Treatment
Mass Flow
Rate (lb/hr)
Yearly Mass Requirement
(lb)
Unit Cost ($/lb organic
removed)
Annualized
Utility Cost ($)
Three-Phase Separator
Organic Impurities
0.72 5.71x103 $ 0.15 $ 856
Total Utilities Cost $ 8,850,000
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
75
Table 41 shows the utility summary for the expansion plant process, which includes the
use of propane refrigeration and TEG dehydration.
Table 41. Utility summary for the expansion plant process
Condensers
Condenser Utility
Type Mass (ton)
Yearly Mass Requirement
(ton-day)
Unit Cost
($/ton-day)
Annualized Utility Cost
($)
C5+Condenser Chilled Water
11.2 3680 $ 1.20 $ 4,000
TEG Condenser
Chilled Water
7.14 2340 $ 1.20 $ 3,000
LPG Condenser
Chilled Water
3510 1.15x106 $ 1.20 $1,390,000
Reboilers
Reboiler Utility Type
Mass flow Rate (kg/hr)
Yearly Mass Requirement (kg)
Unit Cost ($/1000 kg)
Annualized Utility Cost
($)
C5+ Reboiler 245.3 psig
Steam
1.14x104 8.96x107 $ 0.012 $ 1,050,000
TEG Reboiler 285.3 psig
Steam
4.72x102 3.72x106 $ 0.012 $ 46,000
LPG Reboiler 150 psig
Steam
2.21x104 1.74x108 $ 0.011 $ 1,830,000
Sales Gas
Reboiler
50 psig
Steam
2.29x103 1.80x107 $ 0.0066 $ 119,000
Heat Exchangers
Heat Exchanger
Utility Type
Mass flow Rate (kg/hr)
Yearly Mass Requirement (kg)
Unit Cost ($/1000 kg)
Annualized Utility Cost
($)
Inlet Heater 50 psig
Steam
4.10x104 3.24x108 $ 0.0066 $ 2,140,000
Air Coolers
Air Cooler Utility Type
Power
Requirement (kW)
Yearly Power
Requirement (kW-hr)
Unit Cost ($/kW-hr)
Annualized
Utility Cost ($)
Propane Air
Cooler
Electricity 1.47x102 1.16x106 $ 0.06 $ 70,000
TEG Air Cooler Electricity 9.10x10-1 7.17x103 $ 0.06 $ 430
Pumps
Pump Utility Type
Power Requirement
(kW)
Yearly Power Requirement
(kW-hr)
Unit Cost ($/kW-hr)
Annualized Utility Cost
($)
TEG Pump Electricity 5.08 4.00x104 $ 0.06 $ 2,000
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
76
Compressors
Compressor Utility Type
Heat Flow
Rate (MMBTU/hr)
Yearly Heat
Requirement (MMBTU)
Unit Cost ($/MMBTU)
Annualized
Utility Cost ($)
Overhead 2 Compressor
Sales Gas 1.85 1.46x104 $ 4.00 $ 58,000
Propane Compressor 1
Sales Gas 24.0 1.90x105 $ 4.00 $ 760,000
Propane Compressor 2
Sales Gas 32.1 2.53x105 $ 4.00 $ 1,010,000
Sales Compressor
Sales Gas 35.2 2.77x105 $ 4.00 $ 1,110,000
Waste Water Treatment
Waste Stream Utility Type
Mass Flow
Rate (lb/hr)
Yearly Mass
Requirement (lb)
Unit Cost
($/lb organic removed)
Annualized
Utility Cost ($)
Three-Phase Separator
Wastewater Treatment
0.72 5.71x103 $ 0.15 $ 856
TEG Regeneration
Column
Wastewater
Treatment 35.7 2.82x105 $ 0.15 $ 42,000
Utility Fluid
Utility Fluid Utility Type Volumetric Flow Rate
(bbl/hr)
Required Utility Fluid Volume
(bbl)
Unit Cost ($/bbl)
Annualized Utility Cost
($)
Propane (Startup)
Refrigeration 4.03x104 4.03x104 $ 50.00 $ 2,010,000
Utility Fluid Utility Type Mass Flow
Rate
(kg/hr)
Required Utility Fluid
Mass (kg)
Unit Cost ($/kg)
Annualized Utility Cost
($)
TEG (Startup)
Dehydration 6950 6950 $ 0.65 $ 5,000
TEG (Regeneration)
Dehydration 27 2.16x105 $ 0.65 $ 141,000
Total Utilities Cost (First Year Startup) $ 11,800,000
Total Utilities Cost (Second Year Operating and Onward) $ 9,800,000
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
77
The total utility cost of the natural gasoline re-injection process is cheaper than that of
the expansion plant process, which can be justified by the addition of several extra unit
processes. The total utility cost for the natural gasoline re-injection process is $ 8,850,000. In
comparison, the expansion plant has first-year start up utilities cost of $ 11,800,000.
Subsequent years will be $ 9,800,000, which does not include the previously purchased
propane and TEG. The broader points of economics are discussed in the forthcoming variable
cost section.
Estimation of Capital Investment and Total Product Cost
Rigorous economic analyses provided keen insight on process design and projected
profit margins. All parameters were obtained from the course textbook, Seider’s Product
Process and Design Principles, and from the course notes, compliments of Dr. Sani at 8 AM on
Tuesdays and Thursdays during the fall semester 0f 2009. Analyses were completed in Dr.
Zartman’s Economics 2008 15 yr Oct 08 macro-enabled Excel® spreadsheet, which was
provided for Homework #9 in CHEN 4520 on the CULearn course website. This spreadsheet
will hereafter be referred to as the economics spreadsheet. There were minor disconnects and
semantics between Seider and Zartman’s discussions of profitability; however, both outlines tout
a 50% accuracy range. Rigorous profitability analyses were completed for both processes and
the expansion project is a solid investment in terms of profitability.
Economic Premises
Venture Guidance Appraisal
Site factor for the Yamal Peninsula is 1.65 per Mr. Arendell
Miscellaneous equipment costs are 10% of total engineering equipment/purchased and
delivered
Field maintenance, labor, and insulation are 5%, 10%, and 10%, respectively, of
purchased equipment and delivered cost
Equipment foundations, supports, and platforms are 10% of field maintenance, labor,
and insulation costs
Factored piping, instruments, and electrical were 22%, 9%, and 7%, respectively, of
installed equipment cost
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
78
The labor material split was 40% and 60%, respectively, of direct installed cost
Freight, quality insurance, and sales taxes were 12% of material costs
Contractor labor distributives were 44% of labor costs
Additional indirect costs were 15% of direct installed cost plus indirect freight, quality
insurance, taxes, and overhead
Buildings and structures were 20% of direct equipment costs
Power, general, and services were 2% of direct equipment costs plus building and
structures costs
Dismantling and rearranging were 2% direct equipment costs plus building and
structures costs
Site development was 5% of direct equipment costs plus building and structures for an
expansion project
Contingency was 35% of the direct permanent investment
Working conditions were 3% of labor costs
Inflation was 2.625% for every year
Start-up spare parts were 10% of total permanent investment
Variable Costs
High-pressure steam (285.3 psig) costs $12.30 per 1,000 kg from interpolated values
Mid-pressure steam (245.3 psig) costs $11.77 per 1,000 kg from interpolated values
Mid-pressure steam (150 psig) costs $10.50 per 1,000 kg
Low-pressure steam (50 psig) costs $6.6 per 1,000 kg
Chilled water costs $1.2 per ton-day
Electricity costs $0.06 per kW-hr
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
79
Triethylene glycol costs $0.65 per lb (29).
Sales gas costs $4 per MMBTU
Wastewater treatment is $0.15 per lb organic removed
LPG costs $1.31 per US gal
Fixed Costs
Number of operators is 5 for the C5+ process and 15 for the expansion process
Annual wages are $72,800 at $35 per operator-hr
Five shifts per day
Employee benefits are 15% of wages
Operating supervision is 17% of wages at annual wage of $60,000 per operator per shift
Operating supplies are 6% of wages
Maintenance is 3.5% of total permanent investment
Maintenance labor is 25% of total maintenance
Maintenance material is 100% of total maintenance
General overhead is 22.8% of operators’ wages plus maintenance labor plus operator
supervision
Lab and technical support is 6.91% of total permanent investment at $65,000 per
operator per shift
Sales and administration is 2% of total permanent investment
Research and development is 5% of total permanent investment
Insurance and local taxes are 3% of total permanent investment
Cash Flow
C5+ costs $1.90 per US gallon
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
80
Five years MACR depreciation
Interest of capital is 15%
Salvage percent is zero from the current process that produces 2,500 bpd
Accounts receivable are 30 days
Corporate income tax is 34%
Plant capacity is 50% in the first year, 75% in the second year, and 90% in the following
years
The lifetime of the plant is 15 years
The design period is one year and the construction period is two years
Capital Investment
The purpose of capital investment is to investigate the total capital investment (TCI).
This value factored into the internal rate of return (IRR), net present value (NPV), return of
investment (ROI), payback period (PBP), benefit-cost ratio (BCR), and break-even point (BEP),
which will be discussed in turn, to determine profitability. The net cash flow, the final calculation
of the aforementioned factor, resolved the viability of expanding on a current process to
maintain natural gasoline production and add sales gas and LPG recovery trains.
Cost Indices
Also pertinent to determining the capital investment is the cost index to account for
inflation. These indices are applicable for a month or two and are then obsolete as progress
charges onward. Here, the Chemical Engineering (CE) Plant Cost Index was used with an
overall value of 532.9 from April 2010, which was the most current value (30). The cost index is
used in determining the purchase cost in Equation 30.
Equation 22. Purchase cost adjustment with cost index. I was the current cost index, with a CE value of 532.9
from April 2010
𝐶𝑜𝑠𝑡 = 𝐵𝑎𝑠𝑒 𝐶𝑜𝑠𝑡 (𝐼
𝐼𝑏𝑎𝑠𝑒
)
This index accounts for the entire processing plant, including labor and materials of equipment
fabrication, delivery, and installation.
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
81
Commodity Chemicals
As aforementioned, the process produced energy products with market-sensitive prices
that were applied in the economic analyses.
Table 42 shows the current value of the natural gasoline product stream.
Table 42. Capacity and current market value of natural gasoline product stream
Unit LNG
Capacity (bpd) 1.21E+04
Capacity (bph) 504
Capacity (USgph) 21189
Sales Price ($/bbl) $ 80.00
Sales ($/h) $ 40,400
Sales ($/yr) $ 318,200,000
Table 43 shows the current value of cumulative product streams based on the flow rates
and market values of sales gas, LPG, and natural gasoline.
Table 43. Current market value of product streams
Unit Sales Gas Unit LPG C5+ Unit
Capacity 8.42E+08 BTU/hr 1662 1.28E+04 bpd
Capacity (units/hr) 842 MMBTU/hr 69 535 bph
Capacity (units/hr) N/A N/A 2908.5 22470 US gal/hr
Capacity (units/yr) 6634386 MMBTU/yr 22930614 177153480 US gal/yr
Sales Price $ 4.00 $/MMBTU $ 1.31 $ 1.90 $/US gal
Sales Price $ 4.00 $/MMBTU $ 55.00 $ 80.00 $/bbl Total
Sales ($/hr) $ 3,400 $/hr $ 4,000 $ 42,800.00 $/hr $ 50,000
Sales ($/yr) $ 26,500,000 $/yr $ 30,000,000 $ 337,400,000 $/yr $ 394,000,000
Total Permanent Investment (TPI)
The total permanent investment (TPI) of the natural gasoline separation process in an
expansion plant reflected a singular expense for the design, construction, and startup. As
published in the course textbook from Busche, the TPI was composed of sixteen separate costs
that covered the aforementioned expenses (31). In brief, any new project, including a grass-
roots plant, has a TPI containing these cumulative costs with the take home message that there
is never a free lunch. The Excel® spreadsheet Example_Economics2008 15 yr Oct 08 provided
values within the Venture Guidance Appraisal (VGA) that were beyond the scope of the course
textbook and were cited as such (32).
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
82
Both the natural gasoline scale-up and expansion projects were investigated for
profitability. A conservative approach was taken to estimate the bare-module costs of the
equipment; the salvage value of the current process that produces 2,500 bpd was assumed to
be zero. In this way, new equipment was designed for the scaled-up process that produces
10,000 bpd. The salvage value of the equipment used in the natural gasoline process was
assumed to be 100% for overlapping equipment in expanding the plant to produce sales gas
and LPG product streams.
Estimates from the natural gasoline and then the expansion process will be presented
sequentially. The following discussion outlines the methodology behind the VGA.
Bare-Module Cost
Bare-Module Cost (BMC)/Direct Installed Cost (DIC) are reflected in the total bare-
module investment (TBM).The BMC may be primarily divided into process equipment and
fabricated machinery within the VGA sheet within the economic spreadsheet with other related
costs.
Process machinery with standard designs, such as valves and storage tanks, was
chosen from a standard supply list and is shown in Table 44:
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
83
Table 44. Process machinery with approximate costs
Unit C5+
Approximate Cost (k)
Expansion
Approximate Cost (k)
Valves $ 2 $ 16
Storage Tank $ 435 -
Total Engineered
Equipment/Purchased & Delivered $ 437 $ 16
Associated costs of process equipment are presented in Table 45:
Table 45. Indirect costs associated with purchase and installation
Cost Percentage
(%) Associated Cost Source
C5+ Cost
(k)
Expansion
Cost (k)
Misc Equipment 10
Total Engineered Equipment/Purchased
& Delivered (32) $ 44 $ 2
Subtotal/Purchased Equipment & Delivered $ 481 $ 18
Field Material 5
Subtotal/Purchased Equipment &
Delivered (32) $ 24 $ 1
Labor 10
Subtotal/Purchased Equipment &
Delivered (32) $ 48 $ 2
Insulation 10 Subtotal/Purchased
Equipment &
Delivered (32) $ 48 $ 48
Field Erected Equipment
0
Subtotal/Purchased Equipment &
Delivered (32) $ 0 $ 0
Equipment Foundations,
Supports,
Platforms
10
Subtotal/Purchased Equipment &
Delivered and Field
Mtl/Labor/Insulation
(32) $ 61 $ 61
Installed Equipment $ 672 $ 25
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
84
Factored Piping 22 Installed Equipment (32) $ 148 $ 5
Factored
Instruments 9 Installed Equipment (32) $ 60 $ 2
Factored Electrical
7 Installed Equipment (32) $ 47 $ 2
No Identified Piping,
Instruments, or
Electrical
0 - (32) - -
Subtotal, Direct Installed Cost $ 927 $ 34
Labor Split 40 Subtotal, Direct
Installed Cost (32) $ 371 $ 14
Material Split 60 Subtotal, Direct
Installed Cost (32) $ 556 $ 20
Freight, Quality Assurance, Sales
Taxes 12 Material (32) $ 67 $ 2
Contractor Labor
Distributives 44 Labor (32) $ 163 $ 6
Subtotal (Direct Installed Cost + Indirect Freight, QA, Taxes, &
Overhead $ 1,157 $ 42
Engg+Home Office (Additional
Indirect) 15
Subtotal (Direct Installed Cost +
Indirect Freight, QA,
Taxes, & Overhead
(32) $ 174 $ 6
Subtotal (DIC Equipment Calculated from Bare Module using PE) $ 1,331 $ 49
Fabricated machinery is specific to the process at hand, such as the distillation columns,
flash drums, air coolers, heat exchangers, and the pump. These unit operation costs contain a
module cost to account for the piece of equipment and the installation, including piping to and
from, concrete foundation, ladders and other supporting structures, instruments, controllers,
lighting, electrical wiring, insulation, and painting. This factor also assumed free on board (f.o.b.)
delivery where the purchase cost did not include the price of delivery to the plant site. This is a
liberal approach where the delivery charge to the Yamal Peninsula may be augmented due to
the remoteness.
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
85
The bare-modules used here in Table 46 were obtained from Guthrie (33).
Table 46. Bare-module factors for process to account for design costs above those encountered in
purchasing process machinery
Unit
Bare-Module Factor
(FBM)
C5+ PE
Cost (k)
Expansion
PE Cost (k)
C5+ Bare-Module
Cost (k)
Expansion Bare-Module
Cost (k)
Distillation
Columns 4.16 $ 199 $ 1,132 $ 828 $ 1,701
Compressors 2.15 $ 22,547 - $ 48,476 -
Flash Drums 4.16 $ 121 $ 1,052 $ 503 $ 4,376
Air Coolers 2.17 - $ 518 - $ 1,124
Heat Exchangers
(Double Pipe) 1.8 $ 2 $ 7 $ 4 $ 13
Heat Exchangers
(Shell and Tube) 3.17 $ 69 $ 223 $ 219 $ 707
Pumps 3.3 - 8 - $ 26
Subtotal (DIC from Total Bare Module Cost w/FBM Factors) $ 50,030 $ 10,955
As can be seen in Figure 12, compression is the primary bare module cost for the
natural gasoline process.
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
86
Figure 12. Bare-module distribution for natural gasoline process
The compressors serve to re-inject the overhead gas. These compressors were designed to the
maximum limit of the provided costing equations. Therefore, compressors with a larger power
capacity may be available and this is a conservative cost estimate. Fewer and larger
compressors would decrease the presented price.
By salvaging the compressors and other process units from the natural gasoline
process, the expansion process has a more evenly distributed bare module cost allocation, as
seen in Figure 13:
Compressors96%
Distillation Columns2%
Flash Drums1%
Total Engineered Equipment / Purchased &
Delivered1% Heat Exchnagers
(Shell and Tube)0%
Heat Exchangers (Double Pipe)
0%
Bare Module Costs for C5+ Process
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
87
Figure 13. Bare-module distribution for expansion process
The drums used in the propane refrigeration cycle were designed as vessels without internals;
however, lower price options may be available.
Associated costs of fabricated equipment are presented in Table 47:
Table 47. Fabricated equipment-associated miscellaneous cost
Cost Percentage
(%) Associated Cost Source
C5+ Cost
(k)
Expansion
Cost (k)
Miscellaneous
Equipment 10
Subtotal (DIC from Total Bare Module Cost
w/FBM Factors) (32) $ 5,003 $ 1,096
Subtotal (DIC Equipment from Bare Module Costs) or Subtotal (DIC
Equipment Costs) $ 56,363 $ 12,100
Purchase costs were estimated using the Excel® spreadsheet Formated cost eqns Basis
CE500 Oct 2008, which was provided for Homework #9 on the CULearn course website and
matche.com, an online sizing and costing resource (29). All unit operating parameters aligned
Heat Exchangers (Double Pipe)
0%
Total Engineered Equipment /
Purchased
& Delivered0%
Pump0% Heat Exchnagers
(Shell and Tube)7%
Air Coolers10%
Flash Drums40%
Distillation Columns43%
Bare Module Costs for Expansion Process
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
88
with or were below the prescribed ranges, and the purchase costs were adjusted to the current
CE index.
Site Preparation
Site preparation included land surveys, dewatering and drainage, surface clearing, rock
blasting, excavation, grading, and piling (25). Upon construction, fencing, roads, sidewalks,
railroad sidings, sewer lines, fire protection facilities, and landscaping were also included in this
cost. Table 48 tabulates the site preparation costs for an expansion plant:
Table 48. Site preparation for an expansion plant
Cost Percentage
(%) Associated Cost Source
C5+ Cost
(k)
Expansion
Cost (k)
Buildings,
Structure 20
Subtotal (DIC
Equipment Costs) (32) $ 11,273 $ 2,240
Subtotal $67,636 $ 24,520
Service Facilities
Service facilities included utility lines, control rooms, laboratories for quality control,
maintenance shops, and other buildings (25). For the expansion process at hand, the growth of
administrative offices, medical facilities, cafeterias, garages, and warehouses was also
considered, as shown in Table 49:
Table 49. Service facilities for an expansion plant
Cost Percentage
(%) Associated
Cost Source
C5+ Cost (k)
Expansion Cost (k)
Power, General, &
Services (PG&S) 2 Subtotal (32) $ 1,353 $ 290
Dismantling &
Rearranging (D&R) 2 Subtotal (32) $ 1,353 $ 290
Site Development 5 Subtotal Expansion
(25) $ 3,382 $ 726
Subtotal (DPI) $ 73,723 $ 15,826
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
89
Contingencies and Contractor’s Fee
Contingencies and contractor’s fee were unanticipated costs incurred during
construction that were augmented from 15% of DPI to 35% for a student team design (25), as
shown in Table 50:
Table 50. Contingencies and contractor’s fee for an expansion plant
Cost Percentage
(%) Associated
Cost Source
C5+ Cost (k)
Expansion Cost (k)
Contingency 35 Subtotal
(DPI) Student design
team (34) $ 25,803 $ 5,539
Subtotal $ 99,526 $ 21,366
Working Conditions 3 Labor
Contractor’s Fees useful
estimate (34) $ 1,194 $ 256
Net Total $ 100,720 $ 21,622
Minor Changes, Field Indirects,
Spares and
Portables
0 Subtotal (32) - -
Direct Total $ 100,720 $ 21,622
Total Equipment, Total (Current USGC) $ 100,720 $ 21,622
Investment Site Factor
The investment site factor, FISF, accounted for the nuances of location, such as
availability of labor, the efficiency of the workforce, local rules and customs, and union status
among other contributing factors (25). The proposed plant operating site is on the Yamal
Peninsula, Russia with a FISF of 1.65, thus augmenting the total permanent investment.
Equation 23 shows how the site affects the total permanent investment.
Equation 23. Corrected total permanent investment to account for building and operating in the Yamal
Peninsula, Russia with a FISF of 1.65
𝐶𝑇𝑃𝐼𝑐𝑜𝑟𝑟𝑒𝑐𝑡𝑒𝑑 = 𝐹𝐼𝑆𝐹𝐶𝑇𝑃𝐼
Table 51 illustrates the contribution of the site factor to total cost:
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
90
Table 51. Site factor for plant operating in the Yamal Peninsula, Russia (FISF=1.65) (25)
Cost Percentage
(%) Associated Cost Source
C5+ Cost
(k)
Expansion
Cost (k)
Site
Factor 100
Total (Current
USGC)
Siberia, Russia
(1.65) $ 166,188 $ 35,676
Inflation
Inflation is the change in value of currency over time and serves as a predictive measure
for the long-term viability of the process. Seeing as depreciation allowances are not adjusted for
inflation, an inflation analysis is required. Furthermore, revenues and costs increase with
inflation, causing gross earning to increase, yielding a higher income tax. Average inflation rates
for pertinent goods are shown in Table 52:
Table 52. Average inflation rates
Cost Inflation (%)
Raw materials and price of products 2.5
Utilities 2.5
Processing Equipment 2.5
Hourly labor 3.0
Average 2.625
The effect of inflation according to Equation 24 on the process is shown in Table53.
Equation 24.Inflation calculation
𝐹 = 𝑃(1 + 𝑖)𝑛
Where F is future worth, P is corrected CTPI, i is inflation rate, and n is number of years.
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
91
Table 53. Inflation table with average inflation rates
Cost Percentage
(%) Associated Cost Source
C5+ Cost
(k)
Expansion Cost
(k)
Inflation 2.625 for 1
year
Total (Current
USGC) (25) $ 170,550 $ 36,612
Scope
Growth 0 Inflation (32) - -
Total Project-Level Cost $ 170,550 $ 36,612
GRAND TOTAL (TPI) $ 170,600 $ 36,600
The TPI represents a major component of the appraisal and later serves as a benchmark for
sensitivity analyses.
Working Capital (WC)
Working capital funds covered expenses incurred during the startup period before a
profit was realized, i.e. year four. These expenses included cost of inventory and funds to cover
accounts receivable, and the values are shown in Table 54:
Table 54.Working capital
Cost Quantity Associated
Cost Source
C5+ Cost
(k)
Expansion
Cost (k)
TEG 7000 lb $ 0.65 (29) - $ 5
Refrigeration Propane
40,231 bbl
$ 50 Project
Proposal - $ 2,011
Total - $ 2,015
Start-Up Spare Parts
10 % GRAND TOTAL
(TPI)
Typical Estimate
(34) $ 17,060 $ 3,660
Total Working Capital $ 17,060 $ 5,675
Operating Cost
The total annual cost of manufacture (COM) reflects the sum of (1) direct manufacturing
stocks: utilities; (2) operating overhead: labor-related operations and maintenance; and (3) fixed
costs: property taxes, insurance, and depreciation.
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
92
Variable Cost
Utilities were assessed on a consumption basis. The itemized list may be referenced in
Table 55:
Table 55. Utility summary in annual costs and normalized costs to natural gasoline production
Utility C5+ Annual
Cost (k) C5+ Cost per Gal
of Product Expansion Annual
Cost (k)
Expansion Cost per Gal of
Product
Sales Gas $5,640,000 $0.03 $2,940,000 $ 0.02
LP Steam
(50 psig) $2,135,000 $0.01 $2,254,000 $ 0.01
HP Steam (150 Psig)
- - $1,830,000 $ 0.01
HP Steam (245.3 Psig)
$1,054,000 $0.01 $1,054,000 $ 0.01
Chilled Water $4,000 $0.00 $1,393,000 $ 0.01
Electricity - - $72,000 $ 0.00
TEG - - $141,000 $ 0.00
HP Steam
(285.3 Psig) - - $46,000 $ 0.00
Waste Water Treatment
$1,000 $0.00 $43,000 $ 0.00
Subtotal Utilities $8,834,000 $0.053 $ 9,773,000.00 $ 0.055
A distribution of the utilities within the two processes is illustrated in Figures 14 and 15,
respectively:
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
93
Figure 14. Utility distribution within the natural gasoline process.
Sales gas required to run the re-injection compressors dominated the cost. On the other
hand, the expansion process manifests a more even distribution of utilities, as seen in Figure
15:
SALES GAS64%
HP STEAM (245.3 psig)
12%
LP STEAM (50 psig)
24%
CHILLED WATER0% WASTE WATER
TREATMENT0%
Utilities Cost of C5+ Process
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
94
Figure 15. Utility distribution within the expansion process
These utility allocations merit additional consideration for an integrated heat exchange
approach with process streams or an expanded propane cycle.
The sales gas and LPG product streams were accounted for as byproduct credits within
the variable cost of the profitability analysis. Table 56 illustrates the gained revenue in isolating
the sales gas and LPG products in the expansion process:
Table 56. Byproduct credits gained from sales gas and LPG streams in the expansion process
Byproduct Expansion Annual Cost (k) Expansion Cost per Gal of Product
Sales Gas -$ 26,500 -$ 0.15
LPG -$ 30,000 -$ 0.17
Total Variable Costs
-$ 0.264
($46,838)
The additional credits from the byproducts offset the utility costs and are demarcated as
a profit.
SALES GAS30%
LP STEAM (50 psig)
23%
HP STEAM (150 psig)
19%
HP STEAM (245.3 psig)
11%
CHILLED WATER14%
ELECTRICITY1%
TEG1%
HP STEAM (285.3 psig)
1% WASTE WATER TREATMENT
0%
Utilities Costs for Expansion Process
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
95
Fixed Cost
Labor-related operations account for the lab hours required to produce the annual
capacity. Annual wages were assessed at the hourly scale for plant operators and at the annual
salary scale for technical assistance and control laboratory operators.
Operating Labor and Benefits
The natural gasoline process was operated as a single operation. On the other hand, the
expansion process was divided into four fluids processing sections, each with a single operator
requirement that varied based on unit multiplicity (25).
Table 57 outlines the operating and pay parameters for a 24-hour, seven-days-a-week
schedule. The required number of weekly shifts is 4.2; however, rounding this figure up to 5
shifts per week was required due to illness, vacations, holidays, training, special assignments,
and overtime during startups (25).
Table 57. Labor-related operations parameters used to calculate fixed costs
The required number of operators was determined by counting the engineered, process
support, and key process pieces of equipment within each separation process. Firstly, it was
assumed that ¼ of an operator was required for each engineered and each process support
piece of equipment. Secondly, it was assumed that each key process piece of equipment, such
as columns, required a whole operator.
Labor-Related Operations Parameters
Plant operation 7 dy/wk
Plant operation 24 hr/dy
Plant operation 168 hr/wk
Full-time workforce 40 hr/(wk-operator)
Required shifts 4.2 shifts/wk
Rounded up required shifts 5 shifts/wk
Hourly wage for operators $ 35.00 /operator-hr
Full-time workforce 40 hr/wk
Full-time pay 52 wk/yr
Full-time pay 2080 hr/yr
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
96
Operator requirements for the natural gasoline and expansion processes are shown in
Tables 58 and 59, respectively.
Table 58. Operator requirement for the natural gasoline process
Number of Units
Equipment Inlet Separation
Engineered 3
Purchase Support 7
Key 2
Operators 4.5
Table 59. Operator requirement for the expansion process
Number of Units
Equipment Inlet
Separation TEG
Dehydration Propane
Refrigeration Sales/LPG Recovery
Total
Engineered 3 2 2 2 9
Purchase Support 4 5 6 4 19
Key 2 3 1 2 8
Operators 3.75 4.75 3 3.5 15
Table 60 illustrates total labor-related annual cost. The expenses herein include
technical assistance to manufacturing with an annual salary of $60,000 and the control
laboratory with an annual salary of $65,000, each at one operator per shift for five per week,
yielding ten in total (25).
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
97
Table 60. Operating labor and benefits
Cost Percentage
(%)
Associated
Cost Source
C5+ Cost
(k)
Expansion Cost
(k)
Annual Wages N/A N/A N/A $ 364 $ 1,092
Employee
Benefits 15 Wages (25) $ 55 $ 164
Operating
Supervision
$300𝑘
$1,820𝑘= 16.5%
Wages (25) $ 62 $ 186
Subtotal operating labor $ 480 $1,441
Operating
Supplies 6 Wages (25) $ 22 $ 66
Maintenance
Maintenance is required to keep all processing equipment in acceptable working order
according to a preventative maintenance schedule. This requires spares and parts represented
by material and labor. Table 61 outlines the expenses related to maintenance. Maintenance
labor is best utilized during the down time, here 5% of the year. The purpose of this labor is to
clean heat exchangers to curtail fouling, and the lubrication and replacement of mechanical
seals in pumps, and compressors (25).
Table 61. Maintenance on complete distillation process
Cost Percentage
(%) Associated
Cost Source
C5+ Cost (k)
Expansion Cost (k)
Total maintenance
3.5 Investment (25) $ 5,971 $ 1,281
Maintenance
labor 25
Total
maintenance (25) $ 1,493 $ 320
Maintenance
material 100
Total
maintenance (25) $ 5,971 $ 1,281
Overhead
Overhead costs are non-plant operational expenses. Instead, these costs account for
cafeteria; employment and personnel; fire protection, inspection, and safety; first aid and
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
98
medical; industrial relations; janitorial; purchasing, receiving, and warehousing; automotive and
other transportation; and recreation. These costs are categorized into four sections that sum to
the general overhead cost as shown in Table 62. Employee appreciation mantivities are
included in the recreation cost within the business services expense (35).
Table 62. Overhead on complete distillation process
Cost Percentage (%) Associated
Cost Source
C5+ Cost (k)
Expansion Cost (k)
General plant overhead 7.1
Operator Wages +
Maintenance Labor + Operator
Supervision
(25) - -
Mechanical department 2.4 (25) - -
Employee relations
department 5.9 (25) - -
Business services 7.4 (25) - -
General Overhead
(sum of above costs) 22.8 (25) $ 437 $ 364
Lab and technical support $325𝑘
$4,700𝑘= 6.9% Investment (25) $ 11,771 $ 2,525
Corporate Overhead
Corporate overhead costs cover sales and administration expenses to ensure that the
products earn a fair market price. Additionally, investments are made in research and
development to maintain a competitive edge and improve efficiencies. The salary of the
proposed CEO, Mr. Wolff MS, is included in this category. These expenses are outlined in Table
63:
Table 63. Corporate overhead on complete distillation process
Cost Percentage
(%)
Associated
Cost Source
C5+ Cost
(k)
Expansion
Cost (k)
Sales and
administration 2 Investment (25)
$ 3,412 $ 732
Research and development
4.8 Investment (25) $ 8,530
$ 1,830
Subtotal corporate overhead $ 11,492 $ 2,562
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
99
Insurance and Local Taxes
Annual property taxes are levied by the Yamal Peninsula municipality separate from
those from the Russian equivalent to the Internal Revenue Service (IRS) (25). A local tax of 2%
on the investment was assumed (25). In reality, Gazprom’s relations with the Kremlin may
confound this assumption. Insurance is assessed based on pressure and temperature levels of
plant operations. The use of hazardous materials may also augment the insurance cost. In this
way, the process operated in a well-controlled manner for an insurance rate of 1% on the
investment. Table 64 defines these costs:
Table 64.Insurance and local taxes assessed annually
Cost Percentage
(%)
Associated
Cost Source
C5+ Cost
(k)
Expansion
Cost (k)
Insurance and
local taxes 3 Investment (25) $ 5,118 $ 1,098
Royalties 0 Per kg annual
capacity - -
Depreciation 0 Investment (32) - -
Total fixed cost (for cash flow calculations) ($0.21 per Gal)
Total fixed cost (for ROI calculations) ($0.21 per Gal) $ 35,742 $ 9,338
Royalties are null for this process seeing as there were no known intellectual property
infringements. Likewise, the total fixed cost was used in the cash flow calculation; therefore,
depreciation was not assessed. Nevertheless, typical values are 8% of total depreciable capital
for a 12-year plant life.
Profitability Analysis
Suffice it to say that profitability was the crux determination of feasibility. The primary
concern was to determine whether the investment to expand the current operation to yield sales
gas and LPG product streams was favorable over 15-year plant operation expectancy. These
factors will be discussed in turn.
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
100
Profitability
Profitability was assessed for current market selling prices of natural gasoline, sales gas,
and LPG. Finance terms are defined herein to characterize the arguments.
Cost of Capital
Fittingly, the cost of capital is an annual discount rate that reflects the cost of borrowing.
Therefore, the cost of capital is equal to the lender’s required return on investment.
Net Present Value
Net present value (NPV) gives the value of an investment by using a discount rate and a
series of future payments and income. Equation 25 gives the definition of NPV:
Equation 25. Net present value using cost of capital rate.
𝑁𝑃𝑉 = ∑𝑣𝑎𝑙𝑢𝑒𝑠𝑖
(1 + 𝑟𝑎𝑡𝑒) 𝑖
𝑛
𝑖=1
Here, the rate was the cost of capital, values were net cash flows, and inflation, i, was 2.625%,
as previously described. Each component of the summation represents one discounted cash
flow. The NPV is sensitive to changing interest rates due to the exponential denominator.
Internal Rate of Return
The internal rate of return is the interest rate that yields a net present value of zero
based on payments and income that occur at regular periods, i.e. yearly. This is an iterative
process to yield the value, 𝑁𝑃𝑉{𝑟} = 0. The Excel® function requires a guess that is close to the
expected IRR. The macro breaks down if the guess is too far astray.
Return on Investment
The return on investment (ROI) is the annual interest rate made by the profits of the
original investment. Equation 26 gives the broad definition of ROI (25).
Equation 26. ROI definition
𝑅𝑂𝐼 =𝑛𝑒𝑡 𝑒𝑎𝑟𝑛𝑖𝑛𝑔𝑠
𝑡𝑜𝑡𝑎𝑙 𝑐𝑎𝑝𝑖𝑡𝑎𝑙 𝑖𝑛𝑣𝑒𝑠𝑡𝑚𝑒𝑛𝑡
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
101
This is a profitability measurement that does not account for the size of the venture. In other
words, it may behoove a large company with hefty capital to invest in a separate solvent waste
recovery process. Whereas the large company possesses the capital to minimize loans and
earn a greater ROI, the smaller venture must borrow and realize a smaller ROI to account for
the loan payments. Here, the third year, the first year of full operating capacity serves as the
benchmark for the ROI.
Break-Even Point
The break-even point (BEP) is the time required for the cumulative annual earnings to
equal the original investment, as defined by the total depreciable capital divided by the cash
flow. BEP is widely used to compare alternatives but not to make final decisions due to the
inability to account for plant operation after the BEP.
Benefit-Cost Ratio
A benefit-cost ratio (BCR) seeks to evaluate the service life of the project by dividing
positive by negative, non-discounted cash flows. A company may rank potential projects by
BCC and reject any project with a value of less than unity.
Depreciation
Depreciation is a tax shield in that a company may treat depreciation as a cost of
production. This cost is the decline of the book value of each piece of capital equipment with
time, thereby reducing income tax liability, although there is no representative cash outflow from
the company. In this way, the age-old mantra that “a dollar today is more valuable than a dollar
tomorrow” supports the notion to wisely invest in a process today with the intent to reap the
profits tomorrow (36). The analysis used Modified Accelerated Cost Recovery System (MACRS)
on a five-year schedule, as shown in Table 65:
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
102
Table 65. MACRS Tax-Basis Depreciation
Percent of total depreciable capital (CTDC)
Year 5 Year
1 20.00
2 32.00
3 19.20
4 11.52
5 11.52
6 5.76
Total 100.00
MACRS is an initially accelerated depreciation model to allow companies to recoup a
greater percentage of capital investment, compared to straight-line depreciation which is
calculated by dividing the fixed costs by the number of years of operation (25).
Salvage Percent
Salvage percent is the value of the capital equipment at the end of the plant lifetime as a
percentage of the initial investment. A value of zero percent means that there is no worth to the
equipment upon plant retirement. The profitability analyses assumed that there was no salvage
value to the current process that produces 2,500 bpd.
Accounts Receivable
Accounts receivable are cash reserves to cover operating costs while the plant waits for
customers to fulfill obligation for product sales. A 30-day accounts receivable accounts for
8.22% of the annual sales of all products.
Corporate Income Tax
Current corporate income tax rate for companies making over $18,333,333 is 35% (37).
Cash Flow Analyses
The lifetime of the plant for natural gasoline, sales gas, and LPG was 15 years with one
initial design and two construction years. The profitability parameters are juxtaposed in Table
66. The cash flows of both processes were generated using parameters in Table 66.
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
103
Table 66. Profitability comparison of the different processes
Input C5+ Expansion
Cost of Capital (%) (25) 15 15
Inflation of all Costs (%) (25) 2.625 2.625
Inflation to Selling Price of Product (%) (25) 2.5 2.5
Accounts Receivable (dys) (25) 30 30
Income Tax (%) (37) 35 35
Land (38) - -
Total Capital Cost (k) $ 170,600 $ 36,600
Salvage Percent (%) (32) - -
Selling Price of Natural Gasoline $ 1.90 $ 1.90
Output C5+ Expansion
NPV (Cash Flows at End of Each Period) (k) $ 474,000 $ 823,000
NPV (Cash Flows at Beginning of Each Period) (k) $ 546,000 $ 947,000
IRR (%) 51.7 164.1
ROI (%) 69.5 314.5
Payback Period (yrs) 1.4 0.3
BEP (yrs) 3-4 3-4
BCR 14 87
The five pertinent benchmarks were drawn from the IRR, ROI, payback period, BEP,
BCR, and net profit. Whereas the ROI, payback period, and BEP are initial estimators for
profitability, the IRR, and BCR shows the profitability over the course of the plant lifetime. For
these reasons, it is highly recommended to pursue the expansion project.
Natural Gasoline Production
The capital investment allocation chart for the natural gasoline process in Figure 16
illustrates the contributions of operating parameters:
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
104
Figure 16. Capital investment allocation for the natural gasoline process.
The TPI represents the greatest share of the capital investment. Therefore, any savings
in this parameter would enhance profitability.
Non-discounted cash flows of the natural gasoline process are presented in Figure 17:
TPI79%
TOTAL FIXED
COST (for ROI
calculations):17%
TOTAL VARIABLE COST
4%
Capital Investment Allocation for Natural Gasoline
105
Figure 17. Non-discounted cash flows for the natural gasoline and re-injection process with a selling price of $1.90 for natural gasoline
The negative cash flows incurred during the first three years represent the cost of design, construction, and working capital. The cash
flows become positive in 2013 upon production at 50% capacity and then increase as capacity jumps to 90%. This increase in
-$150,000
-$100,000
-$50,000
$0
$50,000
$100,000
$150,000
$200,000
$250,000
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027
Non-Discounted Cash Flow for Natural Gasoline Process
106
capacity reflects the progress of the manufacturing team as unforeseen nuances are resolved.
The overall upward trend upon startup suggests that production ought to continue, so long as
demand exists for a profitable selling price.
Figure 18 illustrates the BEP where the curve crosses the abscissa. Cash flows are
given at the end of the year with no clear delineation of more regular cash flows, i.e. monthly.
107
Figure 18. Non-discounted net values plotted against the years of operation to demonstrate the BEP occurring in the third year
Accordingly, the BEP is somewhere in the third year, a highly favorable estimate for investment.
-150000
-100000
-50000
0
50000
100000
150000
200000
250000
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027
No
n-D
isco
un
ted
Net
Val
ue
($k)
Non-Discounted Net Value vs. Year of Operation for Natural Gasoline and Re-Injection Process
108
Expansion Process
The capital investment allocation chart for the expansion process in Figure 19 illustrates
the contributions of operating parameters:
Figure 19. Capital investment allocation for the expansion process
Again, the TPI represents the primary contributor to capital investment, albeit to a lesser extent
than observed in the natural gasoline process.
Non-discounted cash flows of the natural gasoline process are presented in Figure 20:
TPI66%
TOTAL VARIABLE COST17%
TOTAL FIXED COST (for ROI calculations):
17%
Capital Investment Allocation for Expansion Proces
109
Figure 20. Cash flow for the expansion process with a selling price of $1.90/gal for natural gasoline
The negative cash flows incurred during the first three years represent the cost of design, construction, and working capital. The cash
flows become positive in 2013 upon production at 50% capacity and then increase as capacity jumps to 90%. This increase in
capacity reflects the progress of the manufacturing team as unforeseen nuances are resolved. Again, the overall upward trend upon
startup suggests that production ought to continue, so long as demand exists for a profitable selling price.
-$50,000
$0
$50,000
$100,000
$150,000
$200,000
$250,000
$300,000
$350,000
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027
Ca
sh F
low
($
k)
Non-Discounted Cash Flow for Expansion Process
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
110
Discounted cash flows represent the current investment required to meet the IRR of the process. These flows are shown in
Figure 21:
Figure 21. Discounted cash flows for the expansion process at an IRR of 164.1%
At an IRR of 164.1%, there is a clear effect of the time value of money such that a modest investment with long-range
foresight continually compounds to match the non-discounted cash flows of the process. These discounted cash flows are used to
calculate the IRR; therefore, the limit at the plant lifetime is zero.
Figure 22 illustrates the BEP where the curve crosses the abscissa. Cash flows are given at the end of the year with no clear
delineation of more regular cash flows, i.e. monthly.
-6000
-4000
-2000
0
2000
4000
6000
8000
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027
Dis
cou
nte
d C
ash
Flo
w (
$k)
Discounted Cash Flows vs. Year of Operation for Expansion Process
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
111
Figure 22. Non-discounted net values plotted against the years of operation to demonstrate the BEP occurring in the third year for the expansion
process
Accordingly, the BEP is somewhere in the third year, a highly favorable predictor for investment.
-500000
0
500000
1000000
1500000
2000000
2500000
3000000
3500000
4000000
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027
No
n-D
isco
un
ted
Ne
t V
alu
e (
$k)
Non-Discounted Net Value vs. Year of Operation
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
112
Sensitivity Analysis
Sensitivity analyses demonstrate the strength of the process in the face of changing
variables. Due to the volatility of the Russian political landscape, the sensitivity analyses were
ranged for 100% variability. All analyses were performed with the base parameter of $1.90 per
gallon of natural gasoline for a 164.1% IRR.
Present ROI and IRR for a +/- 100% Variation in TPI
The sensitivity analysis of a ±100% variation in TPI on ROI and IRR is shown in Figure
23:
Figure 23. Variation of ROI and IRR with respect to a 100% variation in TPI
Figure 23 demonstrates that both the ROI and the IRR non-linearly decrease with an
increasing TPI. Nevertheless, 100% variability in TPI, rooted in equipment purchase costs, still
yields favorable IRR and ROI rates.
0.00%
100.00%
200.00%
300.00%
400.00%
500.00%
600.00%
700.00%
800.00%
0 10000 20000 30000 40000 50000 60000 70000 80000
IRR
& R
OI
TPI ($k)
IRR & ROI vs. 100% Variability in TPI Sensitivity Analysis
IRR
ROI
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
113
Present ROI and IRR for a +/- 100% Variation in Fixed Operating Cost
The sensitivity analysis of a ±100% variation in TPI on ROI and IRR is shown in Figure
24:
Figure 24. Variation of ROI and IRR with respect to a 100% variation in Fixed Costs
The interpretation of these analyses follows the same reasoning as for variations in TPI.
However, here, both relationships are linear. As seen in Equation 26, fixed costs comprise the
denominator in the ROI calculation, thus increasing fixed costs, i.e. hiring more operators,
decreases ROI; there is no variable for worker efficiency and output. The IRR also decreases
with increased fixed costs such as hiring more operators, as this would result in greater costs as
a result of the increase in the number of salaries to be paid out with the same products being
produced, and thus a decrease in the internal rate of return to the company. Again, favorable
rates are observed for 100% variability in fixed costs.
Conclusion
The purpose of this endeavor to investigate the feasibility of expanding a natural
gasoline production facility to produce sales gas and LPG was achieved. The perpetual demand
0%
50%
100%
150%
200%
250%
300%
350%
400%
0 5000 10000 15000 20000
IRR
& R
OI
Fixed Costs ($k)
IRR & ROI vs. 100% Variability in Fixed Costs Sensitivity Analysis
IRR
ROI
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
114
for these products suggests that the investment is highly favorable. Safety and environmental
concerns are reasonable and practicable through adherence to local and federal requirements.
Two complete designs were generated and assessed for profitability. Both designs converged
with mostly closed material and energy balances. The outlier here was the energy balance on
the expansion process. Dissected balances suggest that recycle parameters and loose column
convergence parameters propagated to yield the energy imbalance. Both designs are capable
of producing product streams within specification. All units comprising the processes were
designed and specified via cited physical properties and assumptions. Neither of the processes
presents glaring manufacturing difficulties. Utility streams remain to be optimized by integration
with process streams for heat exchange demands.
The economic indicators for both processes were highly favorable. The variable costs
comprise a reasonable fraction of operating costs, as discerned by comparison with functioning
processes. It was determined that 15 operators working over five shifts with appropriate
supervision and control laboratory assistance are capable of generating a profit with highly
competitive profitability markers. A rigorous profitability analysis of both designs determined that
re-injection costs would readily be offset by selling byproduct credits on sales gas and LPG
product streams. In fact, these credits offset variable costs completely. The analysis used cited
parameters for each variable; nevertheless, these approaches are accurate to just 50%. In this
way, the ultimate decision selection relies on the nuances of investment. Companies rank
capital investment projects in order of any number of metrics. The presented profitability
discussion reveals that the expansion process yields favorable IRR, ROI, BCR, PBP, and BEP.
Sensitivity analyses with 100% changeability of the expansion process align with theory and
demonstrate the robustness of the process to market variability in TPI and fixed costs. Yotta
Designs strongly recommends the investment in the Yamal Peninsula expansion project.
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
115
Bibliography
1. National Energy Technology Laboratory (NETL). Produced Water Management Technology
Descriptions . The Energy Lab. [Online] 2010. [Cited: April 30, 2010.]
http://www.netl.doe.gov/technologies/pwmis/techdesc/sep/index.html.
2. URS Corporation. Proposed Natural Gasoline Facility Expansion Process Selection Study. Denver : s.n.,
2010. Project Description.
3. Lynch, David J. USA Today. Cutoff Highlights Europe's Reliance on Russian Natural Gas. [Online]
January 8, 2009. [Cited: February 15, 2010.] http://www.usatoday.com/money/world/2009-01-07-
europe-russia-natural-gas_N.htm.
4. Gelb, Bernard A. Russian Natural Gas: Regional Dependence. s.l. : The Library of Congress, 2007.
5. Gazprom. Gazprom. Yamal Megaproject. [Online] 2003-2010. [Cited: February 14, 2010.]
http://www.gazprom.com/production/projects/mega-yamal/.
6. Feygin, Vladimir and Rykov, Yuri. Russian Gas Supply and Some Prospects of Small Scale LNG Units.
The Netherlands : Kluwer Academic Publishers, 2004.
7. Energy Information Administration, Office of Oil and Gas. Natural Gas Processing: The Crucial Link
Between Natural Gas Production and Its Transportation to Market. 2006. Special Report.
8. GPSA. Section 20: Dehydration. Tulsa : GPSA, 2004.
9. Aspen Technology, Inc. Aspen HYSYS. Software. s.l. : polar Engineering and Consulting, 2009.
10. Prosernat: IFP Group Technologies. Drizo™. Technologies and Equipment for Oil and Gas Treatment.
[Online] Prosernat: IFP Group Technologies. http://www.prosernat.com/en/processes/gas-
dehydration/drizo/.
11. Process Simulation of Glycol Regeneration. Øi, Lars Erik and Selstø, Elisabeth Tyvand. Bergen : s.n.,
2002.
12. Air Products and Chemicals, Inc. Advanced PRISM® Membranes for Natural Gas Dehydration. s.l. :
Air Products and Chemicals, Inc., 2002. Brochure.
13. —. Advanced Prism® Membrane Systems For Cost Effective Gas Separations. s.l. : Permea, Inc., 1999.
14. Clough, David. Column Convergence Conversation. Boulder, February 2010.
15. Studies show effects of composition on propane refrigeration. Blackburn, G A and George, B A. 9,
US : Oil gas Journal, 2009, Vol. 77.
16. IFC International Finance Corporation. Environmental, Health, and Safety Guidelines for Natural Gas
Processing. Arlington : World Bank Group, 2007.
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
116
17. MarkWest Energy Partners, L.P. MSDS: Natural Gasoline. [Online] MarkWest Energy Partners, L.P.
[Cited: May 3, 2010.] http://www.markwest.com/fi les/DataSheets/NaturalGasolineMSDS.pdf.
18. Pacific Energy Group. MSDS: Liquified Petroleum Gas. [Online] [Cited: May 3, 2010.]
http://hazard.com/msds/f2/ckt/cktxf.html.
19. MSDS: Natural Gas. [Online] [Cited: May 3, 2010.]
http://www.equivashellmsds.com/getsinglemsds.asp?ID=170681.
20. Mallinckrodt Baker, Inc. MSDS: Triethylene Glycol. [Online] Mallinckrodt Baker, Inc., February 12,
2004. [Cited: May 3, 2010.] http://www.jtbaker.com/msds/englishhtml/t5382.htm.
21. GPSA. Section 19: Fractionation and Absorption. Engineering Data Book. Tulsa : GPSA, 2004.
22. —. Section 7: Separation Equipment. Engineering Data Book. Tulsa : GPSA, 2004.
23. —. Section 14: Refrigeration. Engineering Data Book. Tulsa : GPSA, 2004, Vol. I & II.
24. Mealey, W Brent. System and Method for Liquefied Petroleum Gas Recovery. 6,658,893 B1 United
States, December 9, 2003.
25. Seider, Warren D., et al. Product and Process Design Principles: Synthesis, Analysis, and Evaluation.
Hoboken, NJ : John Wiley & Sons, Inc., 2009.
26. Mallinckrodt Baker Inc. Material Safety Data Sheet: Toluene. [Online] September 16, 2009. [Cited:
November 23, 2009.] http://www.jtbaker.com/msds/englishhtml/t3913.htm.
27. Mallinckrodt Baker, Inc. Material Safety Data Sheet: Acetonitrile. [Online] September 16, 2009.
[Cited: November 23, 2009.] http://www.jtbaker.com/msds/englishhtml/a0518.htm.
28. Brownell, Lloyd E and Young, Edwin H. Process Equipment Design. Hoboken : John Wiley & Sons,
Inc., 1959.
29. Matches. Matches' Process Equipment and Cost Estimates. Equip Costs. [Online] Matches, October
15, 2003. http://www.matche.com/EquipCost/.
30. ICIS. INDICATIVE CHEMICAL PRICES A-Z. CHEMICAL PRICES. [Online] ICIS, 2010. [Cited: May 2, 2010.]
http://www.icis.com/staticpages/a-e.htm.
31. Chemical Engineering. Economic Indicators - Chemical Engineering Plan Cost Index (CEPCI). Chemical
Engineering News. April, November 2010, p. 64.
32. Busche, R. M. Venture Analysis: A Framework for Venture Planning - Course Notes. Wilmington,
Delaware : Bio-en-gene-er Associates, 1995.
33. Sani, Robert. Example_Economics2008_15_yr_Oct_08. Boulder, Colorado, U.S.A. : University of
Colorado at Boulder, October 2008.
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
117
34. Bauman, H. C. Process Plant Estimating, Evaluation, and Control. Solano Beach, California :
Craftsman, 1974.
35. Sani, Robert. CHEN 4520 Chemical Process Synthesis. Class 17 Estimating Total Capital Investment
(C_TCI). Boulder, Colorado, U.S.A. : University of Colorado at Boulder, 2009.
36. Bastar IV, Richard G. Inspiration. University of Colorado at Boulder, Boulder, Colorado : 2009.
37. Emmerling, Joey. Financier. Boulder, Colorado, Decmeber 7, 2009.
38. Dunn, Dave. 2009 Corporate Tax Rates. Samarak. [Online] November 14, 2008. [Cited: December 5,
2009.] http://www.samarak.com/2009-corporate-tax-rates/.
39. Sani, Robert. Minor Design Project. CHEN 4520 Chemical Process Synthesis. Boulder, Colorado,
U.S.A. : University of Colorado at Boulder, Fall 2009.
40. Mogck, Drew. Mini Design. Boulder, Colorado, December 3, 2009.
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
118
Appendix A: Acronyms
Acronym Stands For
BCR Benefit-Cost Ratio
BEP Break-Even Period
BMC Bare-Module Cost
BTEX Paraffinic and Aromatic Hydrocarbons
BTU British Thermal Unit
CE Chemical Engineering Plant Cost Index
COM Cost of Manufacture
DIC Direct Installed Cost
f.o.b. Free on Board
HC Hydrocarbon
IRR Investor’s Rate of Return
IRS Internal Revenue Service
MACRS Modified Accelerated Cost Recovery
System
MMBTU Million British Thermal Units
MMSCF Million Standard Cubic Feet
MSDS Material Safety Data Sheets
NFPA National Fire Protection Association
NGL Natural Gas Liquids
NPV Net Present Value
PBP Payback Period
PFD Process Flow Diagram
ROI Return on Investment
RVP Reid Vapor Pressure
SCF Standard Cubic Feet
TBM Total Bare-Module Investment
TCI Total Capital Investment
tcm Trillion Cubic Meters
TPI Total Permanent Investment
TVP True Vapor Pressure
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
119
VGA Venture Guidance Appraisal
WC Working Capital
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
120
Appendix B: Chemical Information
LPG MSDS (18)
PEG, INC. DBA PACIFIC ENERGY GROUP A DIVISION OF -- LIQUIFIED PETROLEUM GAS, LP-GAS, LPG, PROPANE -- - ===================== Product Identification =====================
Product ID:LIQUIFIED PETROLEUM GAS, LP-GAS, LPG, PROPANE
MSDS Date:08/01/1996
FSC:NIIN:Submitter:N EN
Status Code:A
MSDS Number: CKTXF
=== Responsible Party ===
Company Name:PEG, INC. DBA PACIFIC ENERGY GROUP A DIVISION OF
Address:UNITED LIQUID GAS CO.
Box:398
City:PASO ROBLES
State:CA
ZIP:93446
Country:US
Info Phone Num:(800) 726-5747; (805) 239-2182
Emergency Phone Num:(800) 633-8253 (PERS, INC)
CAGE:TO802
=== Contractor Identification ===
Company Name:PEG INC. DBA PACIFIC ENERGY GROUP (DIV OF UNITED LIQUID
GAS)
Box:398
City:PASO ROBLES
State:CA
ZIP:93446
Country:US
Phone:800-726-5747;805-239-2182
CAGE:TO802
============= Composition/Information on Ingredients =============
Ingred Name:PROPANE
CAS:74-98-6
RTECS #:TX2275000
= Wt:92.
OSHA PEL:1000 PPM
ACGIH TLV:SIMPLE ASPHYXIANT
Ingred Name:PROPYLENE
CAS:115-07-1
RTECS #:UC6740000
= Wt:5.
Ingred Name:BUTANE
CAS:106-97-8
RTECS #:EJ4200000
= Wt:3.
===================== Hazards Identification =====================
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
121
Routes of Entry: Inhalation:YES Skin:YES Ingestion:YES
Reports of Carcinogenicity:NTP:NO IARC:NO OSHA:NO
Health Hazards Acute and Chronic:PRODUCT IS A SIMPLE ASPHYXIANT IN HIGH
CONCENTRATIONS. INHALATION: EXPOSURE MAY PRODUCE RAPID BREATHING,
HEADACHE, DIZZINESS, DISTURBANCES, MUSCULAR WEAKNESS, TREMORS,
NARCOSIS, UNCONCIOUSNESS AND DEA TH, DEPENDING ON DURATION AND
CONCENTRATION OF EXPOSURE. EYE CONTACT: THIS GAS IS NON-IRRITATING,
BUT DIRECT CONTACT WITH LIQUIFIED, PRESSURIZED GAS OR FROST
PARTICLES MAY PRODUCE SEVERE AND POSSIBLE PERMANENT EYE DAMAGE
FROM FREEZE BURNS. SKIN CONTACT: THIS MATERIAL IS NOT EXPECTED TO
BE ABSORBED THROUGH THE SKIN. NON-IRRITATING; BUT SOLID AND LIQUID
FORMS OF THIS MATERIAL AND PRESSURIZED GAS CAN CAUSE FREEZE
BURNS.(EFFECTS OF OVEREXP)
Explanation of Carcinogenicity:PRODUCT IS NOT LISTED AS A CARCINOGEN OR
POTENTIAL CARCINOGEN BY NTP, IARC OR OSHA.
Effects of Overexposure:HEALTH HAZARDS ACUTE AND CHRONIC (CONT):
INGESTION: SOLID AND LIQUID FORMS OF THIS MATERIAL AND THE
PRESSURIZED GAS CAN CAUSE FREEZE BURNS.
Medical Cond Aggravated by Exposure:SPECIAL HEALTH EFFECTS: PERSONNEL
WITH PRE-EXISTING CHRONIC RESPIRATORY DISEASES SHOULD AVOID
EXPOSURE TO THIS MATERIAL.
======================= First Aid Measures =======================
First Aid:INHALATION: IMMEDIATELY MOVE PERSONNEL TO FRESH AIR. FOR
RESPIRATORY DISTRESS, GIVE AIR, OXYGEN OR ADMINISTER CPR
(CARDIOPULMONARY RESUSCITATION) IF NECESSARY. OBTAIN MEDICAL
ATTENTION IF BREATHING DI FFICULTIES CONTINUE. EYE CONTACT:
VAPORSARE NOT EXPECTED TO PRESENT AN EYE IRRITATION HAZARD. IF
CONTACTED BY LIQUID/SOLID, IMMEDIATELY FLUSH EYE(S) GENTLY WITH
WARM WATER FOR AT LEAST 15 MINUTES. SEE K MEDICAL ATTENTION IF PAIN
OR REDNESS PERSISTS. INGESTION: INDUCE VOMITING WITH WARM WATER
(QT.) ONLY IF PATIENT CONSCIOUS. IMMEDIATELY OBTAIN MEDICAL
ATTENTION. SKIN CONTACT: FLUSH WITH COPIOUS AMOU NTS OF WATER.
CONTACT A PHYSICIAN
===================== Fire Fighting Measures =====================
Flash Point:=-104.4C, -156.F
ESTIMATED
Autoignition Temp:=450.C, 842.F
Lower Limits:2.1%
Upper Limits:9.5%
Extinguishing Media:DRY CHEMICAL, WATER SPRAY, FOAM, CO2.
Fire Fighting Procedures:USE NIOSH-APPROVED SCBA AND FULL PROTECTIVE
EQUIPMENT . EVACUATE AREA. SHUT OFF SOURCE OF GAS, IF POSSIBLE.
NOTIFY FIRE DEPTARTMENT. REMAIN UP-WIND OF VAPORS. ALLOW ONLY
PROPERLY PROTECTED PERSO NNEL IN AREA. READILY FORMS EXPLOSIVE WITH
AIR AND OXIDIZERS. ALLOW FIRE TO BURN UNTIL GAS FLOW IS SHUT OFF.
(EXPLO HAZ)
Unusual Fire/Explosion Hazard:FIRE FIGHT PROC (CONT): USE WATER SPRAY
TO COOL EXPOSED EQUIPMENT AND VAPOR SPACE OF CONTAINERS, CONTAINERS
MAY RUPTURE IF EXPOSED TO HEAT OR FLAME. APPROACH A
FLAME-ENVELOPED CONTAINER FROM SIDE NEV ER FROM THE HEAD ENDS. FOR
MASSIVE, UNCONTROLLABLE FIRES AND WHEN FLAME IS IMPINGING ON VAPOR
SPACE (OTHER INFORMATION)
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
122
================== Accidental Release Measures ==================
Spill Release Procedures:PRODUCT IS EXTREMELY FLAMMABLE. VAPOR IS
HEAVIER THAN AIR AND MAY COLLECT AT LOWER LEVELS. IF THERE IS A
LEAK BUT NO FIRE, DO NOT IGNITE THE ESCAPED GAS. ELIMINATE ALL
IGNITION SOURCES. WATER SPRAY CA N BE USED TO HELP DILUTE VAPOR
CONCENTRATION IN AIR. IF POSSIBLE, REMOVE LEAKING CONTAINER TO SAFE
AREA.
====================== Handling and Storage ======================
Handling and Storage Precautions:STORE AND USE CYLINDERS AND TANKS IN A
WELL VENTILATED AREA, AWAY FROM HEAT AND SOURCES OF IGNITION. NO
SMOKING NEAR STORAGE OR USE. FOLLOW STANDARD PROCEDURES FOR
HANDLING CYLINDERS, TANKS, LOADING/U NLOADING. FIXED STORAGE
CONTAINERS MUST BE GROUNDED AND BONDED DURING TRANSFER OF PRODUCT.
============= Exposure Controls/Personal Protection =============
Respiratory Protection:FOR EXCESSIVE GAS CONCENTRATIONS, USE ONLY NIOSH
(APPROVED - ) SELF-CONTAINED BREATHING APPARATUS.
Protective Gloves:INSULATED, IMPERVIOUS PLASTIC OR NEOPRENE COATED
CANVAS GLOVES.
Eye Protection:USE (ANSI APPROVED - ) CHEMICAL-TYPE GOGGLES AND FACE
SHIELD (SUPP SAFETY)
Other Protective Equipment:EYEWASH AND DELUGE SHOWER MEETING ANSI
DESIGN CRITERIA . USE INSULATED, IMPERVIOUS PLASTIC OR NEOPRENE
COATED CANVAS PROTECTIVE GEAR (APRON, FACE SHIELD, ETC.) TO PROTECT
HANDS & OTHER SKIN AREAS.
Work Hygienic Practices:PREVENT POTENTIAL SKIN CONTACT WITH COLD
LIQUID/SOLID/VAPORS.
Supplemental Safety and Health
EYE PROTECT (CONT): WHEN HANDLING LIQUEFIED GASES. (ANSI APPROVED - )
SAFETY GLASSES AND/OR FACE SHIELD ARE RECOMMENDED WHEN HANDLING
HIGH PRESSURE CYLINDERS AND PIPING SYSTEM AND WHENEVER VAPORS ARE
DISCHARGED.
================== Physical/Chemical Properties ==================
Boiling Pt:=-42.2C, -44.F
Vapor Pres:208 PSIG @ 100 F.
Vapor Density:1.55 AIR=1
Spec Gravity:.508 (H2O=1)
Evaporation Rate & Reference:NA GAS @STD TEMP & PRESS.
Solubility in Water:SLIGHT.
Appearance and Odor:COLORLESS LIQUEFIED PETROLEUM GAS. ODOR: (OTHER
INFO)
Percent Volatiles by Volume:100%
================= Stability and Reactivity Data =================
Stability Indicator/Materials to Avoid:YES
STRONG OXIDIZING AGENTS.
Hazardous Decomposition Products:COMBUSTION MAY PRODUCE CARBON MONOXIDE
AND OTHER HARMFUL SUBSTANCES.
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
123
=================== Toxicological Information ===================
Toxicological Information:OCCUPATIONAL EXPOSURE LIMITS: ACGIH LISTS AS
A SIMPLE ASPHYIXIANT. OSHA TWA 1000 PPM. STATE REGS (CONT):
REPRODUCTIVE HARM." THE BENZENE AND TOULENE ARE DESTROYED WHEN
PROPANE IS BURNED. RADON DOES NOT BURN BUT IS RELEASED WITH THE
COMBUSTION BY-PRODUCTS. RADON AND PROPANE COMBUSTION BY-PRODUCTS
CAN GENERALLY BE REMOVED THROUGH APPLIANCE VENTS AND OTHER EXHAUST
SYSTEMS. WHEN PROPANE IS PROCESS ED IN SOME DEHYDRATORS, BENZENE
AND TOULENE CAN BE RELEASED TO THE ENVIRONMENT. A WARNING ODORANT
IS ADDED TO PROPANE SO LEAKS OF UNBURNED GAS CAN BE QUICKLY
DETECTED. IF GAS ODOR IS DETECTED, YOUR SU PPLIER SHOULD BE
CONTACTED PROMPTLY.
===================== Ecological Information =====================
Ecological:ENVIRONMENTAL EFFECTS: AVOID UNCONTROLLED RELEASES OF THIS
MATERIAL. LIQUID RELEASE WILL HAVE POSSIBLE EFFECT ON PLANT AND
ANIMAL LIFE. LARGE LIQUID RELEASE WILL QUICKLY VAPORIZE TO PRODUCE
A LARGE V APOR CLOUD. VAPOR CLOUD IS BOTH A FIRE AND ASPHYXIATION
HAZARD.
==================== Disposal Considerations ====================
Waste Disposal Methods:DISPOSAL OF GAS IN ACCORDANCE WITH APPLICABLE
LAWS AND REGULATIONS. VENT VAPOR IN SAFE LOCATION AND INSURE THAT
GAS DISSIPATES BELOW THE LOWER FLAMMABLE LIMIT. CONTROLLED BURNING
IS PREFERRED.
=================== MSDS Transport Information ===================
Transport Information:D.O.T. HAZARD CLASS: FLAMMABLE GAS. D.O.T. ID NO
(UN/NA): UN 1075 LIQUEFIED PETROLEUM GAS (LPG). D.O.T. SHIPPING
NAME: PROPANE OR LIQUEFIED PETROLEUM GAS. IMO SHIPPING NAME:
PROPANE BUTANE. IMO HA ZARD CLASS: 2.1. IMO LABEL: FLAMMABLE GAS.
===================== Regulatory Information =====================
State Regulatory Information:PROPOSITION 65 [PUBLIC WARNING] THE SAFE
DRINKING WATER AND TOXIC ENFORCEMENT ACT 1986, COMMONLY REFERRED TO
AS PROPOSITION 65, REQUIRES THEN GOVERNOR TO PUBLISH A LIST OF
CHEMICALS "KNOWN TO THE STAT E TO CAUSE CANCER, BIRTH DEFECTS OR
REPRODUCTIVE HARM." IT ALSO REQUIRES CALIFORNIA BUSINESSES TO WARN
THE PUBLIC QUARTERLY OF POTENTIAL EXPOSURE TO THESE CHEMICALS WHICH
RESULT FROM THEIR OPERATIONS. LIQUIFIED PETROLEUM GAS (PROPANE),
IN ITS ORIGINAL STATE, CONTAINS RADON AND BENZENE, CHEMICALS "KN
OWN TO STATE OF CALIFORNIA TO CAUSE CANCER." ALSO CONTAINS TOULENE,
A CHEMICAL "KNOWN TO STATE OF CALIFORNIA TO CAUSE (TOXICOLOGICAL)
======================= Other Information =======================
Disclaimer (provided with this information by the compiling agencies):
This information is formulated for use by elements of the Department
of Defense. The United States of America in no manner whatsoever,
expressly or implied, warrants this information to be accurate and
disclaims all liability for its use. Any person utilizing this
document should seek competent professional advice to verify and
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
124
assume responsibility for the suitability of this information to their
particular situation.
Natural Gas MSDS (19) MATERIAL SAFETY DATA SHEET
EQUILON MSDS: 55277E-04 11/16/98
CONDENSATE (NATURAL GAS) - FLAMMABLE
TELEPHONE NUMBER:
24 HOUR EMERGENCY ASSISTANCE GENERAL MSDS ASSISTANCE
EQUIVA SERVICES: 877-276-7283 877-276-7285
CHEMTREC: 800-424-9300
NAME AND ADDRESS
EQUILON ENTERPRISES LLC
PRODUCT STEWARDSHIP
P.O. BOX 674414
HOUSTON, TX 77267-4414
_____________________________________________________________________________
__
SECTION I NAME
_____________________________________________________________________________
__
PRODUCT: CONDENSATE (NATURAL GAS) - FLAMMABLE
CHEM NAME: NATURAL GAS CONDENSATE
CHEM FAMILY: PETROLEUM HYDROCARBON
SHELL CODE: 87879 82966 82977 80491 87594 87596 87597 87598
87599 87605 87606 87755 89433 89726 89870
HEALTH HAZARD: 2 FIRE HAZARD: 3 REACTIVITY: 0
_____________________________________________________________________________
__
SECTION II-A PRODUCT/INGREDIENT
_____________________________________________________________________________
__
NO. COMPOSITION CAS NO. PERCENT
--- ----------- ------- -------
P CONDENSATE (NATURAL GAS) - FLAMMABLE
1 CONDENSATE* 64741-47-5 100
A NATURAL GAS 8006-14-2 VARIABLE
B BENZENE 71-43-2 VARIABLE
C N-HEXANE 110-54-3 VARIABLE
THIS IS 1 OF 8 MSDS'S BASED ON FLASHPOINT AND SULFUR CONTENT. LABEL CODE IS
0008695.
*THIS CHEMICAL IS A COMPLEX SUBSTANCE WHICH MAY CONTAIN CONSTITUENTS
IDENTIFIED
AS A, B, C, ABOVE THAT ARE NOT INTENTIONALLY ADDED TO THE PRODUCT.
_____________________________________________________________________________
__
SECTION II-B ACUTE TOXICITY DATA
_____________________________________________________________________________
__
NO. ACUTE ORAL LD50 ACUTE DERMAL LD50 ACUTE INHALATION LC50
--- --------------- ----------------- ---------------------
P NOT AVAILABLE
_____________________________________________________________________________
__
SECTION III HEALTH INFORMATION
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
125
_____________________________________________________________________________
__
THE HEALTH EFFECTS NOTED BELOW ARE CONSISTENT WITH REQUIREMENTS UNDER THE
OSHA HAZARD COMMUNICATION STANDARD (29 CFR 1910.1200).
EYE CONTACT: BASED ON SIMILAR PRODUCT TESTING PRODUCT IS MINIMALLY
IRRITATING TO THE EYES.
SKIN CONTACT: PROLONGED AND REPEATED LIQUID CONTACT CAN CAUSE DEFATTING AND
DRYING OF THE SKIN RESULTING IN SKIN IRRITATION AND DERMATITIS.
INHALATION: WARNING. NATURAL GAS, AND OTHER HAZARDOUS VAPORS MAY EVOLVE
AND COLLECT IN THE HEADSPACE OF STORAGE TANKS OR OTHER ENCLOSED
VESSELS. NATURAL GAS IS EXTREMELY FLAMMABLE AND A SIMPLE
ASPHYXIANT. INHALATION OF OTHER LIGHT HYDROCARBONS MAY CAUSE
PULMONARY IRRITATION AND RESULT IN CNS DEPRESSION. PROLONGED
AND REPEATED INHALATION OF N-HEXANE MAY PRODUCE PERIPHERAL
NEUROPATHY. PRODUCT MAY BE IRRITATING TO THE NOSE, THROAT AND
RESPIRATORY TRACT. PROLONGED AND REPEATED EXPOSURE TO BENZENE
MAY CAUSE SERIOUS INJURY TO BLOOD FORMING ORGANS AND IS LINKED
TO LATER DEVELOPMENT OF ACUTE MYELOGENOUS LEUKEMIA.
INGESTION: THIS PRODUCT MAY BE HARMFUL OR FATAL IF SWALLOWED. INGESTION
OF PRODUCT MAY RESULT IN VOMITING; ASPIRATION (BREATHING) OF
VOMITUS INTO THE LUNGS MUST BE AVOIDED AS EVEN SMALL QUANTITIES MAY
RESULT IN ASPIRATION PNEUMONITIS.
SIGNS AND SYMPTOMS: IRRITATION AS NOTED ABOVE. EARLY TO MODERATE CNS
(CENTRAL NERVOUS SYSTEM) DEPRESSION MAY BE EVIDENCED BY
GIDDINESS, HEADACHE, DIZZINESS AND NAUSEA; IN EXTREME CASES,
UNCONCIOUSNESS AND DEATH MAY OCCUR. ASPHYXIATION AND
H2S TOXICITY MAY BE NOTED BY A SUDDEN LOSS OF CONSCIOUSNESS;
DEATH MAY QUICKLY FOLLOW. ASPIRATION PNEUMONITIS MAY BE
EVIDENCED BY COUGHING, LABORED BREATHING AND CYANOSIS
(BLUISH SKIN); IN SEVERE CASES DEATH MAY OCCUR.
PERIPHERAL NERVE DAMAGE MAY BE EVIDENCED BY MUSCULAR
WEAKNESS AND LOSS OF SENSATION IN THE ARMS AND LEGS.
DAMAGE TO BLOOD FORMING ORGANS MAY BE EVIDENCED BY EASY
FATIGABILITY AND PALLOR (RBC EFFECT), DECREASED
RESISTANCE TO INFECTION (WBC EFFECT) AND EXCESSIVE BRUISING AND
BLEEDING (PLATELET EFFECT).
AGGRAVATED MEDICAL CONDITIONS:
PREEXISTING EYE, SKIN, AND RESPIRATORY DISORDERS OR PREEXISTING IMPAIRED
BLOOD FORMING FUNCTIONS MAY BE AGGRAVATED BY EXPOSURE TO THIS PRODUCT.
OTHER HEALTH EFFECTS:
BENZENE IS LISTED BY THE NATIONAL TOXICOLOGY PROGRAM, THE INTERNATIONAL
AGENCY FOR RESEARCH ON CANCER, AND OSHA AS A CHEMICAL CAUSALLY ASSOCIATED
WITH CANCER (ACUTE MYELOGENOUS LEUKEMIA) IN HUMANS.
SEE SECTION VI FOR ADDITIONAL HEALTH INFORMATION.
_____________________________________________________________________________
__
SECTION IV OCCUPATIONAL EXPOSURE LIMITS
_____________________________________________________________________________
__
COMP OSHA ACGIH
NO. PEL/TWA PEL/CEILING TLV/TWA TLV/STEL OTHER
--- ------- ----------- ------- -------- -----
P* 300 PPM 300 PPM 500 PPM 500 PPM**
B 1 PPM 10 PPM*** 5 PPM**
C 50 PPM 50 PPM
*GASOLINE **OSHA PEL/STEL ***CLASSIFIED BY ACGIH AS A "SUSPECTED HUMAN
CARCINOGEN" (A2)
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
126
_____________________________________________________________________________
__
SECTION V EMERGENCY AND FIRST AID PROCEDURES
_____________________________________________________________________________
__
EYE CONTACT: FLUSH WITH WATER FOR 15 MINUTES WHILE HOLDING EYELIDS OPEN.
GET MEDICAL ATTENTION.
SKIN CONTACT: FLUSH WITH WATER WHILE REMOVING CONTAMINATED CLOTHING AND
SHOES. FOLLOW BY WASHING WITH SOAP AND WATER. DO NOT REUSE CLOTHING
OR SHOES UNTIL CLEANED. IF IRRITATION PERSISTS, GET MEDICAL
ATTENTION.
INHALATION: REMOVE VICTIM TO FRESH AIR AND PROVIDE OXYGEN IF BREATHING IS
DIFFICULT. GIVE ARTIFICIAL RESPIRATION IF NOT BREATHING. GET
MEDICAL ATTENTION.
INGESTION: DO NOT INDUCE VOMITING. IF VOMITING OCCURS SPONTANEOUSLY KEEP
HEAD BELOW HIPS TO PREVENT ASPIRATION OF LIQUID INTO THE LUNGS.
GET MEDICAL ATTENTION.*
NOTE TO PHYSICIAN: *IF MORE THAN 2.0 ML PER KG HAS BEEN INGESTED AND
VOMITING HAS NOT OCCURRED, EMESIS SHOULD BE INDUCED WITH MEDICAL
SUPERVISION. KEEP VICTIM'S HEAD BELOW HIPS TO PREVENT
ASPIRATION. IF SYMPTOMS SUCH AS LOSS OF GAG REFLEX,
CONVULSIONS OR UNCONSCIOUSNESS OCCUR BEFORE EMESIS,
GASTRIC LAVAGE USING A CUFFED ENDOTRACHEAL TUBE SHOULD BE
CONSIDERED.
_____________________________________________________________________________
__
SECTION VI SUPPLEMENTAL HEALTH INFORMATION
_____________________________________________________________________________
__
WHILE THERE IS NO EVIDENCE THAT EXPOSURE TO INDUSTRIALLY ACCEPTABLE LEVELS OF
HYDROCARBON HAVE PRODUCED CARDIAC EFFECTS IN HUMANS, ANIMAL STUDIES HAVE
SHOWN THAT INHALATION OF HIGH LEVELS OF NATURAL GAS VAPORS PRODUCED CARDIAC
SENSITIZATION. SUCH SENSITIZATION MAY CAUSE FATAL CHANGES IN HEART RHYTHMS.
THIS LATTER EFFECT WAS SHOWN TO BE ENHANCED BY HYPOXIA OR THE INJECTION OF
ADRENALIN-LIKE AGENTS. ANIMAL STUDIES ON BENZENE HAVE DEMONSTRATED
IMMUNOTOXICITY, TESTICULAR EFFECTS AND ALTERATIONS IN REPRODUCTIVE CYCLES,
EVIDENCE OF CHROMOSOMAL DAMAGER OR OTHER CHROMOSOMAL CHANGES, AND
EMBRYO/FETOTOXICITY BUT NOT TERATOGENICITY. STUDIES ON N-HEXANE IN LABORATORY
ANIMALS HAVE SHOWN MILD, TRANSITORY EFFECTS ON THE SPLEEN AND BLOOD (WHITE
BLOOD CELLS), AND EVIDENCE OF LUNG DAMAGE. IN ADDITION, FETOTOXICITY HAS
BEEN DEMONSTRATED AT LEVELS PRODUCING MATERNAL TOXICITY. AT HIGH LEVELS,
INHALATION EXPOSURE HAS RESULTED IN TESTICULAR AND EPIDIDYMAL ATROPHY.
_____________________________________________________________________________
__
SECTION VII PHYSICAL DATA
_____________________________________________________________________________
__
BOILING POINT (DEG F): SPECFIC GRAVITY (H2O = 1): VAPOR PRESSURE (MM HG):
-4 TO 356 APPROX. >0.7 7-14.5 PSI
(REID)
MELTING POINT (DEG F): SOLUBILITY IN WATER: VAPOR DENSITY (AIR =
1):
NOT AVAILABLE NEGLIGIBLE >1
% VOLATILE BY
VOL=
100 (@ 415 DEG.
F)
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
127
EVAPORATION RATE (NORMAL BUTYL ACETATE = 1):NOT AVAILABLE
APPEARANCE AND ODOR:AMBER TO DARK COLORED LIQUID. HYDROCARBON ODOR.
PHYS/CHEM PROPERTIES: SEE ABOVE FOR DETAILS
_____________________________________________________________________________
__
SECTION VIII FIRE AND EXPLOSION HAZARDS
_____________________________________________________________________________
__
FLASH POINT AND METHOD: <100 DEG F (PMCC)
FLAMMABLE LIMITS/PERCENT VOLUME IN AIR: LOWER: N/AV HIGHER: N/AV
EXTINGUISHING MEDIA: USE WATER FOG, FOAM, DRY CHEMICAL OR CO2. DO NOT USE A
DIRECT STREAM OF WATER. PRODUCT WILL FLOAT AND CAN BE REIGNITED ON SURFACE
OF WATER. SPECIAL FIRE FIGHTING PROCEDURES AND PRECAUTIONS: WARNING.
FLAMMABLE. CLEAR FIRE AREA OF UNPROTECTED PERSONNEL. DO NOT ENTER
CONFINED FIRE SPACE WITHOUT FULL BUNKER GEAR (HELMET WITH FACE SHIELD, BUNKER
COATS, GLOVES AND RUBBER BOOTS), INCLUDING A POSITIVE PRESSURE NIOSH APPROVED
SELF-CONTAINED BREATHING APPARATUS. COOL FIRE EXPOSED CONTAINERS WITH WATER.
UNUSUAL FIRE AND EXPLOSION HAZARDS: VAPORS ARE HEAVIER THAN AIR ACCUMULATING
IN LOW AREAS AND TRAVELING ALONG THE GROUND AWAY FROM THE HANDLING SITE. DO
NOT WELD, HEAT OR DRILL ON OR NEAR CONTAINER. HOWEVER, IF EMERGENCY
SITUATIONS REQUIRE DRILLING, ONLY TRAINED EMERGENCY PERSONNEL SHOULD DRILL.
_____________________________________________________________________________
__
SECTION IX REACTIVITY
_____________________________________________________________________________
__
STABLITY: STABLE HAZARDOUS POLYMERIZATION WILL NOT OCCUR
CONDITIONS AND MATERIALS TO AVOID: AVOID HEAT, SPARKS, OPEN FLAMES AND STRONG
OXIDIZING AGENTS. PREVENT VAPOR ACCUMULATION. HAZARDOUS DECOMPOSITION
PRODUCTS: THERMAL DECOMPOSITION PRODUCTS ARE HIGHLY DEPENDENT ON THE
COMBUSTION CONDITIONS. A COMPLEX MIXTURE OF AIRBORNE SOLID, LIQUID,
PARTICULATES AND GASES WILL EVOLVE WHEN THIS MATERIAL UNDERGOES PYROLYSIS OR
COMBUSTION. CARBON MONOXIDE AND OTHER UNIDENTIFIED ORGANIC COMPOUNDS MAY BE
FORMED UPON COMBUSTION.
_____________________________________________________________________________
__
SECTION X EMPLOYEE PROTECTION
_____________________________________________________________________________
__
RESPIRATORY PROTECTION:
AVOID BREATHING VAPOR. IF EXPOSURE MAY OR DOES EXCEED OCCUPATIONAL
EXPOSURE LIMITS (SEC. IV) USE A NIOSH-APPROVED RESPIRATOR TO PREVENT
OVEREXPOSURE. IN ACCORD WITH 29 CFR 1910.134 AND 1910.1028 USE EITHER AN
ATMOSPHERE-SUPPLYING RESPIRATOR OR AN AIR-PURIFYING RESPIRATOR FOR ORGANIC
VAPORS. PROTECTIVE CLOTHING AVOID CONTACT WITH EYES. WEAR CHEMICAL GOGGLES
IF THERE IS LIKELIHOOD OF CONTACT WITH EYES. AVOID CONTACT WITH SKIN AND
CLOTHING. WEAR CHEMICAL-RESISTANT GLOVES AND PROTECTIVE CLOTHING.
ADDITIONAL PROTECTIVE MEASURES: USE EXPLOSION-PROOF VENTILATION AS REQUIRED
TO CONTROL VAPOR CONCENTRATIONS.
_____________________________________________________________________________
__
SECTION XI ENVIRONMENTAL PROTECTION
_____________________________________________________________________________
__
SPILL OR LEAK PROCEDURES:
WARNING. FLAMMABLE. ELIMINATE ALL IGNITION SOURCES. HANDLING EQUIPMENT
MUST BE GROUNDED TO PREVENT SPARKING. *** LARGE SPILLS *** EVACUATE THE
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
128
HAZARD AREA OF UNPROTECTED PERSONNEL. WEAR APPROPRIATE RESPIRATOR AND
PROTECTIVE CLOTHING. SHUT OFF SOURCE OF LEAK ONLY IF SAFE TO DO SO. DIKE
AND CONTAIN. IF VAPOR CLOUD FORMS, WATER FOG MAY BE USED TO SUPPRESS;
CONTAIN RUN-OFF. REMOVE WITH VACUUM TRUCKS OR PUMP TO STORAGE/SALVAGE
VESSELS. SOAK UP RESIDUE WITH AN ABSORBENT SUCH AS CLAY, SAND OR OTHER
SUITABLE MATERIAL; PLACE IN NON-LEAKING CONTAINERS FOR PROPER DISPOSAL.
FLUSH AREA WITH WATER TO REMOVE TRACE RESIDUE; DISPOSE OF FLUSH SOLUTIONS
AS ABOVE. *** SMALL SPILLS *** TAKE UP WITH AN ABSORBENT MATERIAL AND PLACE
IN NON-LEAKING CONTAINERS; SEAL TIGHTLY FOR PROPER DISPOSAL.
_____________________________________________________________________________
__
SECTION XII SPECIAL PRECAUTIONS
_____________________________________________________________________________
__
KEEP LIQUID AND VAPOR AWAY FROM HEAT, SPARKS AND FLAME. SURFACES THAT ARE
SUFFICIENTLY HOT MAY IGNITE EVEN LIQUID PRODUCT IN THE ABSENCE OF SPARKS OR
FLAME. EXTINGUISH PILOT LIGHTS, CIGARETTES AND TURN OFF OTHER SOURCES OF
IGNITION PRIOR TO USE AND UNTIL ALL VAPORS ARE GONE. VAPORS MAY ACCUMULATE
AND TRAVEL TO IGNITION SOURCES DISTANT FROM THE HANDLING SITE; FLASH-FIRE CAN
RESULT. KEEP CONTAINERS CLOSED WHEN NOT IN USE. USE WITH ADEQUATE
VENTILATION. CONTAINERS, EVEN THOSE THAT HAVE BEEN EMPTIED, CAN CONTAIN
EXPLOSIVE VAPORS. DO NOT CUT, DRILL, GRIND, WELD OR PERFORM SIMILAR
OPERATIONS ON OR NEAR CONTAINERS. STATIC ELECTRICITY MAY ACCUMULATE AND
CREATE A FIRE HAZARD. GROUND FIXED EQUIPMENT. BOND AND GROUND TRANSFER
CONTAINERS AND EQUIPMENT. WASH WITH SOAP AND WATER BEFORE EATING, DRINKING,
SMOKING, APPLYING COSMETICS, OR USING TOILET FACILITIES. LAUNDER
CONTAMINATED CLOTHING BEFORE REUSE.
_____________________________________________________________________________
__
SECTION XIII TRANSPORTATION REQUIREMENTS
_____________________________________________________________________________
__
DEPARTMENT OF TRANSPORTATION CLASSIFICATION:
CLASS 3 (FLAMMABLE LIQUID), PACKING GROUP MUST BE DETERMINED ON A
CASE-BY-CASE BASIS.
DOT PROPER SHIPPING NAME:FLAMMABLE LIQUID, N.O.S. (PETROLEUM CONDENSATE)
OTHER REQUIREMENTS:UN1993, GUIDE 128
_____________________________________________________________________________
__
SECTION XIV OTHER REGULATORY CONTROLS
_____________________________________________________________________________
__
THIS PRODUCT IS LISTED ON THE EPA/TSCA INVENTORY OF CHEMICAL SUBSTANCES.
IN ACCORDANCE WITH SARA TITLE III, SECTION 313, THE ENVIRONMENTAL DATA SHEET
(EDS) SHOULD ALWAYS BE COPIED AND SENT WITH THE MSDS.
_____________________________________________________________________________
__
SECTION XV STATE REGULATORY INFORMATION
_____________________________________________________________________________
__
THE FOLLOWING CHEMICALS ARE SPECIFICALLY LISTED BY INDIVIDUAL STATES; OTHER
PRODUCT SPECIFIC HEALTH AND SAFETY DATA IN OTHER SECTIONS OF THE MSDS MAY
ALSO BE APPLICABLE FOR STATE REQUIREMENTS. FOR DETAILS ON YOUR REGULATORY
REQUIREMENTS YOU SHOULD CONTACT THE APPROPRIATE AGENCY IN YOUR STATE.
STATE LISTED COMPONENT CAS NO PERCENT STATE CODE
_____________________________________________________________________________
__
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
129
NATURAL GAS 8006-14-2 VARIABLE MA, PA
BENZENE 71-43-2 VARIABLE CA, CT, FL, IL,
LA, MA, ME, MN,
NJ, PA, RI,
CA65C/R
N-HEXANE 110-54-3 VARIABLE CA, CT, FL, IL,
LA, MA, ME, MN,
PA, RI
CA = CALIFORNIA HAZ. SUBST. LIST; CA65C, CA65R, CA65C/R = CALIFORNIA SAFE
DRINKING WATER AND TOXICS ENFORCEMENT ACT OF 1986 OR PROPOSITION 65 LIST; CT
=
CONNECTICUT TOXIC. SUBST. LIST; FL = FLORIDA SUBST. LIST; IL = ILLINOIS TOX.
SUBST. LIST; LA = LOUISIANA HAZ. SUBST. LIST; MA = MASSACHUSETTS SUBST.
LIST; ME = MAINE HAZ. SUBST. LIST; MN = MINNESOTA HAZ. SUBST. LIST; NJ =
NEW JERSEY HAZ. SUBST. LIST; PA = PENNSYLVANIA HAZ. SUBST. LIST; RI = RHODE
ISLAND HAZ. SUBST. LIST.
CALIFORNIA PROPOSITION 65 FOOTNOTE: CA65C = THE CHEMICAL IDENTIFIED WITH THIS
CODE IS KNOWN TO THE STATE OF CALIFORNIA TO CAUSE CANCER. CA65R = THE
CHEMICAL IDENTIFIED WITH THIS CODE IS KNOWN TO THE STATE OF CALIFORNIA TO
CAUSE BIRTH DEFECTS OR OTHER REPRODUCTIVE HARM. CA65C/R = THE CHEMICAL
IDENTIFIED WITH THIS CODE IS KNOWN TO THE STATE OF CALIFORNIA TO CAUSE BOTH
CANCER AND BIRTH DEFECTS OR OTHER REPRODUCTIVE HARM.
_____________________________________________________________________________
__
SECTION XVI SPECIAL NOTES
_____________________________________________________________________________
__
MSDS REVISED IN SECTION XV - STATE REGULATORY INFORMATION.
_____________________________________________________________________________
__
THE INFORMATION CONTAINED IN THIS DATA SHEET IS BASED ON THE DATA AVAILABLE
TO US AT THIS TIME, AND IS BELIEVED TO BE ACCURATE BASED UPON THAT DATA. IT
IS PROVIDED INDEPENDENTLY OF ANY SALE OF THE PRODUCT, FOR PURPOSE OF HAZARD
COMMUNICATION. IT IS NOT INTENDED TO CONSTITUTE PRODUCT PERFORMANCE
INFORMATION, AND NO EXPRESS OR IMPLIED WARRANTY OF ANY KIND IS MADE WITH
RESPECT TO THE PRODUCT, UNDERLYING DATA OR THE INFORMATION CONTAINED
HEREIN. YOU ARE URGED TO OBTAIN DATA SHEETS FOR ALL PRODUCTS YOU BUY,
PROCESS, USE OR DISTRIBUTE, AND ARE ENCOURAGED TO ADVISE THOSE WHO MAY
COME IN CONTACT WITH SUCH PRODUCTS OF THE INFORMATION CONTAINED HEREIN.
TO DETERMINE THE APPLICABILITY OR EFFECT OF ANY LAW OR REGULATION WITH
RESPECT TO THE PRODUCT, YOU SHOULD CONSULT WITH YOUR LEGAL ADVISOR OR THE
APPROPRIATE GOVERNMENT AGENCY. WE WILL NOT PROVIDE ADVICE ON SUCH
MATTERS, OR BE RESPONSIBLE FOR ANY INJURY FROM THE USE OF THE PRODUCT
DESCRIBED HEREIN. THE UNDERLYING DATA, AND THE INFORMATION PROVIDED HEREIN
AS A RESULT OF THAT DATA, IS THE PROPERTY OF EQUIVA SERVICES, LLC AND IS NOT
TO BE THE SUBJECT OF SALE OR EXCHANGE WITHOUT THE EXPRESS WRITTEN CONSENT OF
EQUIVA SERVICES, LLC.
_____________________________________________________________________________
__
ENVIRONMENTAL DATA SHEET
EQUILON EDS: 55277E
CONDENSATE (NATURAL GAS) - FLAMMABLE
TELEPHONE NUMBER:
24 HOUR EMERGENCY ASSISTANCE GENERAL MSDS ASSISTANCE
EQUIVA SERVICES: 877-276-7283 877-276-7285
CHEMTREC: 800-424-9300
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
130
NAME AND ADDRESS
EQUILON ENTERPRISES
PRODUCT STEWARDSHIP
P.O. BOX 674414
HOUSTON, TX 77267-4414
PRODUCT CODE: 89870
Natural Gasoline MSDS
The hazards of natural gasoline are similar to those of LPG.
Propane MSDS
The hazards of propane are similar to those of natural gas.
TEG MSDS (20)
MSDS Number: T5382 * * * * * Effective Date: 11/09/06 * * * * * Supercedes: 02/12/04
TRIETHYLENE GLYCOL
1. Product Identification
Synonyms: Ethanol, 2,2'-[1,2-ethanediylbis(oxy)]bis-; triglycol; ethylene glycol dihydroxy-diethyl ether
CAS No.: 112-27-6
Molecular Weight: 150.20
Chemical Formula: C6H14O4
Product Codes:
J.T. Baker: W660
Mallinckrodt: 2735
2. Composition/Information on Ingredients
Ingredient CAS No Percent
Hazardous
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
131
--------------------------------------- ------------ ------------ ---
------
Triethylene Glycol 112-27-6 90 - 100%
Yes
3. Hazards Identification
Emergency Overview
--------------------------
WARNING! CAUSES EYE IRRITATION. MAY CAUSE SKIN IRRITATION.
SAF-T-DATA(tm) Ratings (Provided here for your convenience)
-----------------------------------------------------------------------------------------------------------
Health Rating: 0 - None
Flammability Rating: 1 - Slight
Reactivity Rating: 0 - None
Contact Rating: 2 - Moderate
Lab Protective Equip: GOGGLES; LAB COAT; PROPER GLOVES
Storage Color Code: Green (General Storage)
-----------------------------------------------------------------------------------------------------------
Potential Health Effects
----------------------------------
Inhalation:
No adverse health effects expected from inhalation.
Ingestion:
No adverse effects expected.
Skin Contact:
Prolonged exposure may cause skin irritation.
Eye Contact:
Splashing in eye causes irritation with transitory disturbances of corneal epithelium. However, these
effects diminish and no permanent injury is expected. Vapors are non-irritating.
Chronic Exposure:
Possible skin irritation.
Aggravation of Pre-existing Conditions:
No information found.
4. First Aid Measures
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
132
Inhalation:
Remove to fresh air. Not expected to require first aid measures.
Ingestion:
If large amounts were swallowed, give water to drink and get medical advice.
Skin Contact:
In case of contact, immediately flush skin with plenty of water for at least 15 minutes. Remove
contaminated clothing and shoes. Wash clothing before reuse. Call a physician if irritation develops..
Eye Contact:
If splash occurs, immediately flush eyes with plenty of water for at least 15 minutes, lifting upper and
lower eyelids occasionally. Call a physician.
5. Fire Fighting Measures
Fire:
Flash point: 177C (351F) CC
Autoignition temperature: 371C (700F)
Flammable limits in air % by volume:
lel: 0.9; uel: 9.2
Slight fire hazard when exposed to heat or flame.
Explosion:
Above the flash point, explosive vapor-air mixtures may be formed.
Fire Extinguishing Media:
Water spray, dry chemical, alcohol foam, or carbon dioxide. Water or foam may cause frothing.
Special Information:
In the event of a fire, wear full protective clothing and NIOSH-approved self-contained breathing
apparatus with full facepiece operated in the pressure demand or other positive pressure mode.
6. Accidental Release Measures
Ventilate area of leak or spill. Wear appropriate personal protective equipment as specified in Section 8.
Isolate hazard area. Keep unnecessary and unprotected personnel from entering. Contain and recover
liquid when possible. Collect liquid in an appropriate container or absorb with an inert material (e. g.,
vermiculite, dry sand, earth), and place in a chemical waste container. Do not use combustible materials,
such as saw dust. Do not flush to sewer!
7. Handling and Storage
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
133
Keep in a tightly closed container, stored in a cool, dry, ventilated area. Protect against physical damage.
Isolate from heat, ignition sources and oxidizing agents. Protect from freezing. Containers of this
material may be hazardous when empty since they retain product residues (vapors, liquid); observe all
warnings and precautions listed for the product.
8. Exposure Controls/Personal Protection
Airborne Exposure Limits:
None established.
Ventilation System:
Not expected to require any special ventilation.
Personal Respirators (NIOSH Approved):
Not expected to require personal respirator usage.
Skin Protection:
Wear protective gloves and clean body-covering clothing.
Eye Protection:
Use chemical safety goggles. Maintain eye wash fountain and quick-drench facilities in work area.
9. Physical and Chemical Properties
Appearance:
Clear, colorless liquid.
Odor:
Odorless.
Solubility:
Miscible in water.
Specific Gravity:
1.1274 @ 15C/4C
pH:
No information found.
% Volatiles by volume @ 21C (70F):
100
Boiling Point:
285C (545F)
Melting Point:
-5C (23F)
Vapor Density (Air=1):
5.17
Vapor Pressure (mm Hg):
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
134
< 0.01 @ 20C (68F)
Evaporation Rate (BuAc=1):
0.01
10. Stability and Reactivity
Stability:
Stable under ordinary conditions of use and storage. Hygroscopic.
Hazardous Decomposition Products:
Carbon dioxide and carbon monoxide may form when heated to decomposition.
Hazardous Polymerization:
Will not occur.
Incompatibilities:
Strong oxidizers.
Conditions to Avoid:
Heat, flames, ignition sources and incompatibles.
11. Toxicological Information
Oral rat LD50: 17 gm/kg; investigated as a reproductive effector.
--------\Cancer Lists\-----------------------------------------------------
-
---NTP Carcinogen---
Ingredient Known Anticipated IARC
Category
------------------------------------ ----- ----------- ------------
-
Triethylene Glycol (112-27-6) No No None
12. Ecological Information
Environmental Fate:
When released into the soil, this material is expected to readily biodegrade. When released into the soil,
this material is expected to leach into groundwater. When released into the soil, this material is not
expected to evaporate significantly. When released into water, this material is expected to readily
biodegrade. When released into water, this material is not expected to evaporate significantly. This
material has a log octanol-water partition coefficient of less than 3.0. This material is not expected to
significantly bioaccumulate. When released into the air, this material is expected to be readily degraded
by reaction with photochemically produced hydroxyl radicals. When released into the air, this material is
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
135
expected to have a half-life of less than 1 day.
Environmental Toxicity:
This material is expected to be slightly toxic to aquatic life. The LC50/96-hour values for fish are between
10 and 100 mg/l.
13. Disposal Considerations
Whatever cannot be saved for recovery or recycling should be managed in an appropriate and approved
waste disposal facility. Processing, use or contamination of this product may change the waste
management options. State and local disposal regulations may differ from federal disposal regulations.
Dispose of container and unused contents in accordance with federal, state and local requirements.
14. Transport Information
Not regulated.
15. Regulatory Information
--------\Chemical Inventory Status - Part 1\-------------------------------
--
Ingredient TSCA EC Japan
Australia
----------------------------------------------- ---- --- ----- --------
-
Triethylene Glycol (112-27-6) Yes Yes Yes Yes
--------\Chemical Inventory Status - Part 2\-------------------------------
--
--Canada--
Ingredient Korea DSL NDSL Phil.
----------------------------------------------- ----- --- ---- -----
Triethylene Glycol (112-27-6) Yes Yes No Yes
--------\Federal, State & International Regulations - Part 1\--------------
--
-SARA 302- ------SARA 313----
--
Ingredient RQ TPQ List Chemical
Catg.
----------------------------------------- --- ----- ---- ------------
--
Triethylene Glycol (112-27-6) No No No No
--------\Federal, State & International Regulations - Part 2\--------------
--
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
136
-RCRA- -TSCA-
Ingredient CERCLA 261.33 8(d)
----------------------------------------- ------ ------ ------
Triethylene Glycol (112-27-6) No No No
Chemical Weapons Convention: No TSCA 12(b): No CDTA: No
SARA 311/312: Acute: Yes Chronic: No Fire: No Pressure: No
Reactivity: No (Pure / Liquid)
Australian Hazchem Code: None allocated.
Poison Schedule: None allocated.
WHMIS:
This MSDS has been prepared according to the hazard criteria of the Controlled Products Regulations
(CPR) and the MSDS contains all of the information required by the CPR.
16. Other Information
NFPA Ratings: Health: 1 Flammability: 1 Reactivity: 0
Label Hazard Warning:
WARNING! CAUSES EYE IRRITATION. MAY CAUSE SKIN IRRITATION.
Label Precautions:
Avoid contact with eyes, skin and clothing.
Wash thoroughly after handling.
Label First Aid:
In case of contact, immediately flush eyes or skin with plenty of water for at least 15 minutes. Call a
physician.
Product Use:
Laboratory Reagent.
Revision Information:
MSDS Section(s) changed since last revision of document include: 3.
Disclaimer:
*************************************************************************************
***********
Mallinckrodt Baker, Inc. provides the information contained herein in good faith but makes no
representation as to its comprehensiveness or accuracy. This document is intended only as a guide to
the appropriate precautionary handling of the material by a properly trained person using this
product. Individuals receiving the information must exercise their independent judgment in
determining its appropriateness for a particular purpose. MALLINCKRODT BAKER, INC. MAKES NO
REPRESENTATIONS OR WARRANTIES, EITHER EXPRESS OR IMPLIED, INCLUDING WITHOUT LIMITATION
ANY WARRANTIES OF MERCHANTABILITY, FITNESS FOR A PARTICULAR PURPOSE WITH RESPECT TO
THE INFORMATION SET FORTH HEREIN OR THE PRODUCT TO WHICH THE INFORMATION REFERS.
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
137
ACCORDINGLY, MALLINCKRODT BAKER, INC. WILL NOT BE RESPONSIBLE FOR DAMAGES RESULTING
FROM USE OF OR RELIANCE UPON THIS INFORMATION.
*************************************************************************************
***********
Prepared by: Environmental Health & Safety
Phone Number: (314) 654-1600 (U.S.A.)
Appendix C: Engineering Calculations
Design
The diameters calculated in the column design tables represent examples of how each tray diameter
was calculated. The diameter that was used to cost each column was the largest necessary tray
diameter, and is shown in the following tables.
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
164
Natural Gasoline Expansion Plant Process
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
173
Appendix D: Computer Process Modeling
Aspen HYSYS
Natural Gasoline Expansion Plant Heat Exchangers
Yotta Designs CHEN 4530 Senior Design Project May 5, 2010
174
Appendix E: Economic Spreadsheets
Total Capital Investment
Total bare-moldule costs CFE
Process machinery CPM
Spares Cspare
Storage and surge tanks Cstorage
Initial catalyst charges Ccatalyst
Computers, software, distributed control systems,
instruments, and alarms Ccomp
Total bare-module investment, TBM CTBM,
CBMC
Cost of site preparation Csite
Cost of service facilities Cserv
Allocated costs for utility plants and related facilities Calloc
Total direct permanent investment, DPI CDPI
Cost of contingencies and contractor’s fee Ccont
Total depreciable capital, TDC CTDC
Cost of land Cland
Cost of royalties Croy al
Cost of plant startup Cstartup
Total permanent investment, TPI CTPI
Working capital, WC CWC
Total capital investment, TC CTCI