Speaker(s): Clareice & Clyneice Chaney When: April 21, 2016
Company: MITRE & Quality squared Time: 3:30 pm - 4:30 pm
CHICAGO April 18th — April 22th
Testing Deliverables:
Define, Align, Document and Approve
Testing DeliverablesDefine, Align, Document, and Approve
QAI QUEST Chicago, IL
Clareice Chaney, MITRE Corporation, CPCM, PMP
Clyneice Chaney, MITRE Corporation, CQMgr, PMP
April 21, 2016
Approved for Public Release; Distribution Unlimited. Case Number 16-0366
The author's affiliation with The MITRE Corporation is provided for identification purposes only, and is not intended to convey or imply MITRE's concurrence with, or support for, the positions, opinions or viewpoints expressed by the author.
About the Speakers
Clareice Chaney has over 30 years of experience in commercial and government contracting with an emphasis in information technology contracting and specific expertise in performance-based contracting techniques.
Clyneice Chaney brings over 25 years of testing, quality assurance, and process improvement experience. Clyneice holds certifications from the American Society for Quality as a Certified Quality Manager, QAI Global Institute's Certified Quality Analyst, and Project Management Institute's Professional Project Manager.
QAI Quest 2016 April 18-22 Chicago, IL
Deliverables … What We Know...
PRODUCTS
OUTCOMES
DOCUMENTS
RESULTS
OUTPUTS
ARTIFACTS
CONTRACTUAL
SW
Deliverables come in different shapes, sizes, and attributes
RELEASES
Deliverables differ from project milestones
Deliverables are often contractual in nature
QAI Quest 2016 April 18-22 Chicago, IL
Deliverables don’t show up magically
like a rabbit in a hat
Where do they come from? How do you ensure they fit
the assigned work? What can you do ?
Why do they
matter?
QAI Quest 2016 April 18-22 Chicago, IL
SW Methodology Impact
Deliverables
SIMILARITIES DIFFERENCES/EXPECTATIONS
WATERFALL • Testing Strategy• Test Plans• Test Cases
Documents• Test Scripts• Test Data• Test Results/
Reports
• Install/Configurations Guides• Defect Report• Release notes• Test Traceability Matrix• Defect Reports• Release Notes
AGILE/RAPID • Testing Strategy• Test Plans• Test Cases
Documents• Test Scripts• Test Data• Test
Results/Reports
• Test Automation• Release Planning (Test Plan) • Participate in story sizing• Sprint QA Activities• Infrastructure Considerations
(Test environment/SW)• Pair tests (Dev + QA)• Reviews (stories, requirements,
test cases with customer, programmer)QAI Quest 2016 April 18-22 Chicago, IL
Quality of Service Quality of Product
Release Quality
Defect Density
Meeting Product “Doneness”
Number of Defects
Schedule
Release Quality
Test Planning Effectiveness
Defect Detection
Adapted from James Bach, Rapid Software Testing.
Project and Test Team Goals Impact Deliverables
QAI Quest 2016 April 18-22 Chicago, IL
Testing Approaches Impact Deliverables
QAI Quest 2016 April 18-22 Chicago, IL
Project Schedules Impact Deliverables
QAI Quest 2016 April 18-22 Chicago, IL
Regulations & Standards Impact Deliverables
• 508 Compliance
• FISMA/Security Requirements
• ECLC
QAI Quest 2016 April 18-22 Chicago, IL
Documents: Legal, Contractual, and Planning Impact Deliverables
QAI Quest 2016 April 18-22 Chicago, IL
Considerations for Identifying Deliverables
• What is the purpose and goal of the project? oWhat are the test objectives?
• What does the client or stakeholders want at project end?
• Is the project goal tangible or intangible?
• Are there various elements that must be approved within the project?
• Will the project require many levels of work prior to completion
Adapted from: Understanding Project Management Deliverables – Tips on Managing and Monitoring PM Deliverableshttp://www.brighthubpm.com/risk-management/69108-defining-project-management-deliverables/
QAI Quest 2016 April 18-22 Chicago, IL
Sources Checked for Potential Deliverables?Now What?
Potential Deliverables…. Do they mean the same to everyone?
QAI Quest 2016 April 18-22 Chicago, IL
DEFINING DELIVERABLES…Filling in the Expectations.. Reality GAP
Client Needs
RFP/SOW/Task
Project Objectives
EXPECTATIONS
REALITY
QAI Quest 2016 April 18-22 Chicago, IL
Deliverables have standards and specifications for completion
Deliverables have stakeholders
Deliverables have quality components
Deliverables may be associated with phases
Deliverables may have dependencies
Deliverables may be defined differently by different stakeholders
Considerations for Defining Test Deliverables
QAI Quest 2016 April 18-22 Chicago, IL
Testing Deliverables Are Changing
Traditional Test Deliverables
Alternative Test Deliverables
QAI Quest 2016 April 18-22 Chicago, IL
Align to: Business Requirements
Align to:High Level Scope & Vision Statements
Align to:Product Requirements
Align to:Process Requirements
CONTRACT
Testing objectives for the project and each release or testing effort should be clearly stated and understood by the testing team
Align to:Stakeholder Needs
ALIGN…Filling in the Expectations.. Reality GAP
QAI Quest 2016 April 18-22 Chicago, IL
DOCUMENT:…Filling in the Expectations.. Reality GAP
Work Packages
Tasks
Deliverables: Formal/ Informal
SW
Tool-based
EXPECTATIONS
REALITY
QAI Quest 2016 April 18-22 Chicago, IL
Document Deliverable Expectations
• Deliverable Description - high-level overview of the deliverable objective and scope, the methodology for creating the deliverable, applicable standards, deliverable requirements, and deliverable format
• Deliverable Acceptance Criteria - high-level overview of the deliverable acceptance criteria
• Deliverable Schedule - timeframes for client reviews and acceptance, frequency of submissions, and submission dates
• Resources Required – who is involved and how much time for deliverable preparation and reviews
QAI Quest 2016 April 18-22 Chicago, IL
Document Deliverables?Format and Content Considerations
• Document Name• Assigned• Contributors• Prerequisites/Dependencies• Purpose and Audience• Recommended Accomplishments
• List of deliverables content, related activities, and decisions that should be accomplished before completion
• Assumptions specific to each testing phase• Risks• Expected Results (behavior expected after a test case step that
requires verification or validation)• Schedule
QAI Quest 2016 April 18-22 Chicago, IL
APPROVE…Filling in the Expectations.. Reality GAP
Reviews
QA Activities
Sign-Offs
Informal or Formal
Consensus
"Done"
EXPECTATIONS
REALITY
QAI Quest 2016 April 18-22 Chicago, IL
References
1. Formulating a Test Strategy for an Agile Software Project http://www.slideshare.net/tharindakasun/agile-testing-strategy
2. Agile Testing: A Beginners Guide http://www.guru99.com/agile-testing-a-beginner-s-guide.html
3. Understanding Project Management Deliverables – Tips on Managing and Monitoring PM Deliverables http://www.brighthubpm.com/risk-management/69108-defining-project-management-deliverables/
4. Software Testing Deliverables: From Test Plans to Status Reports David W. Johnson, http://searchsoftwarequality.techtarget.com/tip/Software-testing-deliverables-From-test-plans-to-status-reports
5. James, Bach, Rapid Software Testing