chilled water system presentation
TRANSCRIPT
-
8/8/2019 Chilled Water System Presentation
1/119
COMMERCIAL BUILDING SERVICES FLOW THINKING
Chilled Water System Presentation
-
8/8/2019 Chilled Water System Presentation
2/119
COMMERCIAL BUILDING SERVICES FLOW THINKING
Constant Volume DistributionConstant Volume Distribution
-
8/8/2019 Chilled Water System Presentation
3/119
COMMERCIAL BUILDING SERVICES FLOW THINKING
Air-conditioning System Components
-
8/8/2019 Chilled Water System Presentation
4/119
COMMERCIAL BUILDING SERVICES FLOW THINKING
Constant Volume System Components
-
8/8/2019 Chilled Water System Presentation
5/119
COMMERCIAL BUILDING SERVICES FLOW THINKING
Typical 3-way Valve Zone
-
8/8/2019 Chilled Water System Presentation
6/119
COMMERCIAL BUILDING SERVICES FLOW THINKING
Full Load Condition
-
8/8/2019 Chilled Water System Presentation
7/119
COMMERCIAL BUILDING SERVICES FLOW THINKING
Fully Loaded Coil
Supply water temperature 45F
Design return water temp. 55F
Coil design flow 100 GPM
Coil design pressure drop 20 FT
Load (flow x 10F x 500) 500,000 Btuh
Coil P @ design flow 20 FT Bypass flow 0 GPM
Bypass P 3-way valve closed
3-way valve pressure drop 10 FT
Pump flow and head 100 GPM @ 30 FT
Actual return water temp 55 F
-
8/8/2019 Chilled Water System Presentation
8/119
COMMERCIAL BUILDING SERVICES FLOW THINKING
Unloaded Condition
-
8/8/2019 Chilled Water System Presentation
9/119
COMMERCIAL BUILDING SERVICES FLOW THINKING
Unloaded Coil
Supply water temperature 45F Design return water temp. 55F
Coil design flow 0 GPM
Coil design pressure drop 3-way valve closed
Load (flow x 10F x 500) 0.0 Btuh Coil P @ design flow 0 FT
Bypass flow 100 GPM
Bypass P 20 FT 3-way valve pressure drop 10 FT
Pump flow and head 100 GPM @ 30 FT
Actual return water temp 45 F
-
8/8/2019 Chilled Water System Presentation
10/119
COMMERCIAL BUILDING SERVICES FLOW THINKING
So What?
When the load on the coil is zero, the valve is returning unusedchilled water at essentially supply temperature.
Cold return water unloads the chillers, causing them to operateinefficiently.
-
8/8/2019 Chilled Water System Presentation
11/119
COMMERCIAL BUILDING SERVICES FLOW THINKING
Part Load Condition
-
8/8/2019 Chilled Water System Presentation
12/119
COMMERCIAL BUILDING SERVICES FLOW THINKING
Partially Loaded Coil
Supply water temperature 45F
Design return water temp. 55F
Coil design flow 50 GPM
Coil design pressure drop 20 FT
Load (flow x 10F x 500) 250,000 Btuh Coil P @ design flow 5 FT
Bypass flow ??? GPM
Bypass P 3-way partially closed
3-way valve pressure drop 10 FT
Pump flow and head ??? GPM @ 30 FT
Actual return water temp ?? F
-
8/8/2019 Chilled Water System Presentation
13/119
COMMERCIAL BUILDING SERVICES FLOW THINKING
125
100
75
50
25
0
% Valve Stroke25 50 75 100
%F
low
1/2 Through Coil
1/2 Through Bypass
FullF
low
ThroughCoil
FullF
low
ThroughByp
ass
3-way Valve Characteristic
-
8/8/2019 Chilled Water System Presentation
14/119
COMMERCIAL BUILDING SERVICES FLOW THINKING
Whats Really Happening?
-
8/8/2019 Chilled Water System Presentation
15/119
COMMERCIAL BUILDING SERVICES FLOW THINKING
Coil with 3-way Valve at Mid-position
Supply water temperature 45 F
Design return water temp. 55 F
Load (flow x 10F x 500) 250,000 Btuh
Coil design pressure drop 20 FT
Coil flow 62.5 GPM
Coil P @ 62.5% flow 7.8 FT
Coil leaving water temp 53 F
Bypass flow 62.5 GPM
Bypass P 7.8 FT
3-way valve pressure drop 10 FT Pump flow and head 125 GPM @ 30 FT
Actual return water temp 49 F (62.5 GPM @ 53 F+62.5 GPM @ 45 F)
-
8/8/2019 Chilled Water System Presentation
16/119
COMMERCIAL BUILDING SERVICES FLOW THINKING
Head2 = Head1(Flow2/ Flow1)2
Head2 = 20(.625/1)2
Head2 = 20(.3906 )
Head2
= 7.8
-
8/8/2019 Chilled Water System Presentation
17/119
COMMERCIAL BUILDING SERVICES FLOW THINKING
T = Load/ Flow X 500
T = 250,000/62.5 X 500
T = 8
Therefore, LWTcoil = 45 + 8 = 53
-
8/8/2019 Chilled Water System Presentation
18/119
COMMERCIAL BUILDING SERVICES FLOW THINKING
RWT = (Flow1
X EWT + Flow2
X LWT)/ Flow1 + 2
RWT = (62.5 X 45 + 62.5 X 53)/125
RWT = 49
-
8/8/2019 Chilled Water System Presentation
19/119
-
8/8/2019 Chilled Water System Presentation
20/119
COMMERCIAL BUILDING SERVICES FLOW THINKING
1.Low return water temperatures.2.Robs chilled water from other coils at part
load conditions.3.Increases flow in primary piping.4.Adds additional chillers on line.
5.Chiller performance is reduced.
3-way Valve System Deficiencies
-
8/8/2019 Chilled Water System Presentation
21/119
COMMERCIAL BUILDING SERVICES FLOW THINKING
1.1
20 30 40 50 60 70 80 90 10010
1.0
0.9
0.8
0.7
0.6
0.5
KWperTon
Percent Load
Chiller Performance Curve
-
8/8/2019 Chilled Water System Presentation
22/119
COMMERCIAL BUILDING SERVICES FLOW THINKING
Pump Sizing
Select for full chiller flow
Head must be adequate for:
Chiller evaporator
Longest circuit
Coil
Three way valve Air separator
-
8/8/2019 Chilled Water System Presentation
23/119
COMMERCIAL BUILDING SERVICES FLOW THINKING
System Configuration
Constant Volume
-
8/8/2019 Chilled Water System Presentation
24/119
Any Questions?
-
8/8/2019 Chilled Water System Presentation
25/119
Variable Volume Constant Speed
-
8/8/2019 Chilled Water System Presentation
26/119
COMMERCIAL BUILDING SERVICES FLOW THINKING
Primary Secondary System
Primary Includes Chillers & Primary Pump.Circuit Constant water flow through the chiller
is maintained and chilled water is
produced
Secondary Chilled water is circulated to theCircuit demand area (load) by using
Secondary pumps.
Variable Volume Constant Speed
-
8/8/2019 Chilled Water System Presentation
27/119
COMMERCIAL BUILDING SERVICES FLOW THINKING
PRIMARY - SECONDARY
-
8/8/2019 Chilled Water System Presentation
28/119
COMMERCIAL BUILDING SERVICES FLOW THINKING
Other Famous Names of Primary-Secondary
Primary Production Loop
Secondary Distribution Loop
-
8/8/2019 Chilled Water System Presentation
29/119
COMMERCIAL BUILDING SERVICES FLOW THINKING
Fundamental Idea
-
8/8/2019 Chilled Water System Presentation
30/119
COMMERCIAL BUILDING SERVICES FLOW THINKING
No Secondary Flow
-
8/8/2019 Chilled Water System Presentation
31/119
COMMERCIAL BUILDING SERVICES FLOW THINKING
Primary = Secondary
FLOW THINKING
-
8/8/2019 Chilled Water System Presentation
32/119
COMMERCIAL BUILDING SERVICES FLOW THINKING
Primary > Secondary
FLOW THINKING
-
8/8/2019 Chilled Water System Presentation
33/119
COMMERCIAL BUILDING SERVICES FLOW THINKING
Primary < Secondary
COMMERCIAL BUILDING SERVICES FLOW THINKING
-
8/8/2019 Chilled Water System Presentation
34/119
COMMERCIAL BUILDING SERVICES FLOW THINKING
Control Valve in Secondary
COMMERCIAL BUILDING SERVICES FLOW THINKING
-
8/8/2019 Chilled Water System Presentation
35/119
COMMERCIAL BUILDING SERVICES FLOW THINKING
Use the flow of the largest chiller
Chiller staging at half of this flow is common
Head loss in common
-
8/8/2019 Chilled Water System Presentation
36/119
COMMERCIAL BUILDING SERVICES FLOW THINKING
Variable flow through coilConstant flow through system
Three Way Valve
Variable flow through coilVariable flow through system
Two Way Valve
Control Valve in Secondary
COMMERCIAL BUILDING SERVICES FLOW THINKING
-
8/8/2019 Chilled Water System Presentation
37/119
COMMERCIAL BUILDING SERVICES FLOW THINKING
PRIMARY SECONDARY CIRCUITVariable Volume Constant Speed
COMMERCIAL BUILDING SERVICES FLOW THINKING
-
8/8/2019 Chilled Water System Presentation
38/119
COMMERCIAL BUILDING SERVICES FLOW THINKING
Head
F1 F2 F3
H1
H2
H3
Flow
Control Valves Change the Secondary
System Curve
COMMERCIAL BUILDING SERVICES FLOW THINKING
-
8/8/2019 Chilled Water System Presentation
39/119
FLOW THINKING
% Flow
125
100
75
50
25
150
25 50 75 100
HDVarying differential pressureabsorbed by control valve
System resistance
TDH of pump
Pump curve
Head Absorbed by 2-way Valves
COMMERCIAL BUILDING SERVICES FLOW THINKING
-
8/8/2019 Chilled Water System Presentation
40/119
FLOW THINKING
HP
125
100
75
50
25
150
25 50 75 100
% Design Flow
Primary Pumps = V/V
Secondary Pumps +
Constant Flow Primary Pumps, only
Pump Horsepower Comparison
COMMERCIAL BUILDING SERVICES FLOW THINKING
-
8/8/2019 Chilled Water System Presentation
41/119
FLOW THINKING
% F low
90
80
70
60
50
40
30
2010
0 10 1009080706050403020
100
110
120
130
140
150
BaseDesignHP %
% Full Load(Design) HP
Pump Ove r-haded by 150%Constant Flow, C/S Pump
(3 Way Valve)
Constant Flow, C/S Pump
(3 Way Valve)
C/S Pump(2 Way Valve)
Pump HD Matchedto System @Design Flow
C/SPump
(2Wa
yValv
e)
Constant vs Variable Volume
-
8/8/2019 Chilled Water System Presentation
42/119
Any Questions?
-
8/8/2019 Chilled Water System Presentation
43/119
Step Function of Chillers
COMMERCIAL BUILDING SERVICES FLOW THINKING
-
8/8/2019 Chilled Water System Presentation
44/119
Production = Distribution
COMMERCIAL BUILDING SERVICES FLOW THINKING
-
8/8/2019 Chilled Water System Presentation
45/119
Distribution > Production
COMMERCIAL BUILDING SERVICES FLOW THINKING
-
8/8/2019 Chilled Water System Presentation
46/119
Production > Distribution
COMMERCIAL BUILDING SERVICES FLOW THINKING
-
8/8/2019 Chilled Water System Presentation
47/119
Loading a Chiller
A chiller is a heat transfer device. Like most equipment, it is
most efficient at full load.
To load a chiller means:
Supply it with its rated flow of water
Insure that water is warm enough to permit removal of rated Btu
without freezing the water
COMMERCIAL BUILDING SERVICES FLOW THINKING
-
8/8/2019 Chilled Water System Presentation
48/119
Chiller Performance Curve
1.1
20 30 40 50 60 70 80 90 10010
1.0
0.9
0.8
0.7
0.6
0.5
KWpe
rTon
Percent Load
COMMERCIAL BUILDING SERVICES FLOW THINKING
-
8/8/2019 Chilled Water System Presentation
49/119
Check Valve in Common?
COMMERCIAL BUILDING SERVICES FLOW THINKING
-
8/8/2019 Chilled Water System Presentation
50/119
What can we do?
COMMERCIAL BUILDING SERVICES FLOW THINKING
-
8/8/2019 Chilled Water System Presentation
51/119
What else can we do?
Reset Supply Temperature
Lower chiller set point when mixing occurs to maintain a constant
temperature to the system.
Expect increases in cost of chiller operation at lower set point: 1-3% perdegree of reset.
Delays start of the next chiller.
COMMERCIAL BUILDING SERVICES FLOW THINKING
-
8/8/2019 Chilled Water System Presentation
52/119
What else can we do?
Coils that are selected at higher supply temperatures will not beimpaired by small changes.
Loads that require fixed temperatures may use a small chiller toreverse the effects of mixing.
COMMERCIAL BUILDING SERVICES FLOW THINKING
-
8/8/2019 Chilled Water System Presentation
53/119
Multiple Chillers
COMMERCIAL BUILDING SERVICES FLOW THINKING
-
8/8/2019 Chilled Water System Presentation
54/119
60/40 Chiller Split to Help Minimize Low Part Load Operation
COMMERCIAL BUILDING SERVICES FLOW THINKING
-
8/8/2019 Chilled Water System Presentation
55/119
0-10 30-40 60-70 90-1000
5
10
15
20
25
30
0-10 30-40 60-70 90-100
%
Time
% Load
Typical Load Profile
COMMERCIAL BUILDING SERVICES FLOW THINKING
-
8/8/2019 Chilled Water System Presentation
56/119
Three Unequally Sized Chillers
COMMERCIAL BUILDING SERVICES FLOW THINKING
-
8/8/2019 Chilled Water System Presentation
57/119
% Load
Time
Approaching Flow = Load
-
8/8/2019 Chilled Water System Presentation
58/119
Any Questions?AlternatePumping Methods
Comparison
COMMERCIAL BUILDING SERVICES FLOW THINKING
T Pi Di t R t
-
8/8/2019 Chilled Water System Presentation
59/119
Two Pipe Direct Return
COMMERCIAL BUILDING SERVICES FLOW THINKING
T Pi R R t
-
8/8/2019 Chilled Water System Presentation
60/119
Two Pipe Reverse Return
COMMERCIAL BUILDING SERVICES FLOW THINKING
-
8/8/2019 Chilled Water System Presentation
61/119
Primary-Secondary Pumping.
Simplest to install.
Simplest to operate.
Flexible in design for present and future. Efficient to operate.
May over-pressurize near zones.
COMMERCIAL BUILDING SERVICES FLOW THINKING
P i S d T ti
-
8/8/2019 Chilled Water System Presentation
62/119
Primary-Secondary-Tertiary
COMMERCIAL BUILDING SERVICES FLOW THINKING
-
8/8/2019 Chilled Water System Presentation
63/119
Primary-Secondary-Tertiary Pumping.
Best piping flexibility.
Best expansion flexibility.
Provides hydraulic decoupling.
Efficient to operate.
May require added horsepower.
Requires additional pumps and piping. Increased controls complexity.
-
8/8/2019 Chilled Water System Presentation
64/119
COMMERCIAL BUILDING SERVICES FLOW THINKING
-
8/8/2019 Chilled Water System Presentation
65/119
Primary-Secondary-Tertiary Hybrid Pumping.
Low present horsepower.
Low future horsepower.
Good piping flexibility.
Good expansion flexibility.
Provides hydraulic decoupling.
May require added horsepower Requires additional pumps and piping.
Increased controls complexity.
COMMERCIAL BUILDING SERVICES FLOW THINKING
Primary-Secondary Zone Pumping
-
8/8/2019 Chilled Water System Presentation
66/119
Primary-Secondary Zone Pumping
COMMERCIAL BUILDING SERVICES FLOW THINKING
-
8/8/2019 Chilled Water System Presentation
67/119
Primary-Secondary Zone Pumping.
Low built out horsepower.
Low system head.
Increased control complexity.
Present horsepower total higher due to future needs.
Present pumps sized for future requirements.
Difficult to apply in retrofits projects.
-
8/8/2019 Chilled Water System Presentation
68/119
Any Questions?
-
8/8/2019 Chilled Water System Presentation
69/119
Variable Volume Variable Speed
COMMERCIAL BUILDING SERVICES FLOW THINKING
-
8/8/2019 Chilled Water System Presentation
70/119
Why Do We Need Variable SpeedSecondary Pumps ???
For Energy Saving.
For better & optimise operation.
COMMERCIAL BUILDING SERVICES FLOW THINKING
-
8/8/2019 Chilled Water System Presentation
71/119
How Do We Achieve This Reduction In PowerConsumption ??
By Using Variable Frequency Drive and Logic controller
with the Secondary Pumps.
COMMERCIAL BUILDING SERVICES FLOW THINKING
-
8/8/2019 Chilled Water System Presentation
72/119
Power Comparison at Reduced Speed
COMMERCIAL BUILDING SERVICES FLOW THINKING
-
8/8/2019 Chilled Water System Presentation
73/119
Basic Law which helps in achieving this Affinitylaw
1. Flow2 = Flow1(Speed2/ Speed1)
2. Head2 = Head1(Speed2/ Speed1)2
3. BKW2
= BKW1(Speed
2/ Speed
1)3
If Diameter of Impeller is to be trimmed then instead ofspeed the same can be used in above formulas.
COMMERCIAL BUILDING SERVICES FLOW THINKING
Operating Cost
-
8/8/2019 Chilled Water System Presentation
74/119
0
50
100
150
200
250
300
350
400
450
50 100 150 200 250 300 350 400 450 500
Motor Horsepower
AnnualOperatingCost$1000
$0.10/kWh
p g
COMMERCIAL BUILDING SERVICES FLOW THINKING
Variable flow system
-
8/8/2019 Chilled Water System Presentation
75/119
Head
Flow
PumpCurve
System
Curve
System Curveas two wayvalves close
Variable flow system
COMMERCIAL BUILDING SERVICES FLOW THINKING
Energy savings offset
-
8/8/2019 Chilled Water System Presentation
76/119
Q
H
Pump
Curve
System Curve
at design flow
System Curveat part load
Increasedhead loss
Energy savings offset
COMMERCIAL BUILDING SERVICES FLOW THINKING
Pumps in parallel
-
8/8/2019 Chilled Water System Presentation
77/119
Head
Flow
SinglePump
Pumps inParallel
SystemCurve
p p
COMMERCIAL BUILDING SERVICES FLOW THINKING
Parallel pumping power savings
-
8/8/2019 Chilled Water System Presentation
78/119
Horsepower%
100
90
80
70
60
50
40
30
20
10
00 10 20 30 40 50 60 70 80 90 100
Flow%
Single Large Pump
Two ParallelPumps
Single ParallelPump
COMMERCIAL BUILDING SERVICES FLOW THINKING
Theoretical Savings
-
8/8/2019 Chilled Water System Presentation
79/119
g
COMMERCIAL BUILDING SERVICES FLOW THINKING
Establishing Efficiency Curves
-
8/8/2019 Chilled Water System Presentation
80/119
12 0
11 0
10 0
90
80
50
40
30
20
10
70
60
0100 200 300 400 500 600 700 800 900 10000
100 %
90 %
80 %
70 %
60 %
50%
40 %
30 %
80 %
85 %80 %70 %60 %
50 %
85 %
% Speed Curves
ConstantEfficiencyCurve
% Efficiency
He
ad,
Feet
GPM
COMMERCIAL BUILDING SERVICES FLOW THINKING
Variable Speed Efficiencies
-
8/8/2019 Chilled Water System Presentation
81/119
750
900 1150 1450 1770600
900
1150
1450
1770
600
A
B
C
D
E
4500 gpm @ 100 FT, 85.9 %
COMMERCIAL BUILDING SERVICES FLOW THINKING
No Valve System Curve
-
8/8/2019 Chilled Water System Presentation
82/119
Flow
piping headloss curve
Distribution
PumpTDH
Overallsystem curve
Head
80
60
40
20
110
0200 400 600 800 1000 1200 1400 16000
100
Set Point
25 FT Differential Head
Maintained Across Load(Set Point)
COMMERCIAL BUILDING SERVICES FLOW THINKING
Effect of Constant Set Point110
-
8/8/2019 Chilled Water System Presentation
83/119
piping headloss curve
Distribution
PumpT
DH
Overall system curve
Head
80
60
40
20
0200 400 600 800 1000 1200 1400 16000
Flow
100
Control curveSet point,
25 FT
COMMERCIAL BUILDING SERVICES FLOW THINKING
Control curve
-
8/8/2019 Chilled Water System Presentation
84/119
100%
75%
50%
Flow
Head
ControlCurve
VariableHead
LossP
P1 P2
COMMERCIAL BUILDING SERVICES FLOW THINKING
Large systems, long pipe runs
-
8/8/2019 Chilled Water System Presentation
85/119
Annual
OperatingCost
($1000/year
@
$0.10/kwh)
50
45
40
35
30
25
20
15
10
05
001000 2000 3000 4000 5000
Total Equivalent Pipe Length(feet)
SingleC/SPump,NoOverheading
Sing
leC/S
Pum
p,200
%Ove
rhea
ded
VariableSpe
edPump
COMMERCIAL BUILDING SERVICES FLOW THINKING
Variable Head Loss Ratio
-
8/8/2019 Chilled Water System Presentation
86/119
PercentDe
signBHP
% Flow
90
80
70
60
50
40
30
20
10
0 10 1009080706050403020
100C/S, Constant Flow System Pump Head Matched to
System at Design Flow
C/S, Variable Flow
V/S, 0% Variable Hd Loss, 100% Constant Hd
V/S, 25% Variable Hd Loss, 75% Constant Hd
V/S, 50% Variable Hd Loss, 50% Constant Hd
V/S, 75% Variable Hd Loss, 25% Constant Hd
V/S, 100% Variable Hd Loss, 0% Constant
Hd
Base
COMMERCIAL BUILDING SERVICES FLOW THINKING
Variable Head Ratio w/ Overheading
150 P OH d d b 150%C Fl C/S P
-
8/8/2019 Chilled Water System Presentation
87/119
90
80
70
60
50
40
30
20
10
0 10 1009080706050403020
100110
120
130
140
150
BaseDesignHP %
% Full Load(Design) HP
Pump OHeaded by 150%Constant Flow, C/S Pump(3 Way Valve)
Constant Flow, C/S Pump
(3 Way Valve)
C/S Pump(2 Way Valve)
Pump HD Matchedto System @Design Flow
* 25/75 Means:25 % Variable HD Loss75 % Constant HD Loss
C/SPump(2
WayV
alve)
V/S,100%ConstantHD
V/S,25/7
5*
V/S,50/5
0
V/S,75/2
5
V/S,
100%V
ariab
leHD
COMMERCIAL BUILDING SERVICES FLOW THINKING
Locations of Sensor
-
8/8/2019 Chilled Water System Presentation
88/119
Where to install the Sensor?
What type of Sensor?
COMMERCIAL BUILDING SERVICES FLOW THINKING
Single Point Pressure Sensor
-
8/8/2019 Chilled Water System Presentation
89/119
Chillers
Primary Pumps
SecondaryPumps
Load
Balancing Valve 2 WayValve
Panel withPLC & VFD`s
Air -Separator
Com
mon
Single Point PressureSensing
COMMERCIAL BUILDING SERVICES FLOW THINKING
Single Point Pressure Sensor
-
8/8/2019 Chilled Water System Presentation
90/119
Is Single Point Pressure Sensor Correct?
Wrong !!
Why?
-Pump is a differential pressure device.
-A single point is only influence by pressure. This is good for booster only.
-In a closed loop system, system pressure rises due to thermal expansion,
pumps will slow down.
-When static pressure decrease, pumps will speed up.
-This is self-defeating since now the pump speed is not influence by the
system load changes, but rather by system water pressure.
-Therefore, single pressure sensor are a misapplication in a closed loop
HVAC system.
COMMERCIAL BUILDING SERVICES FLOW THINKING
Single Point Differential Pressure Sensor
-
8/8/2019 Chilled Water System Presentation
91/119
Chillers
Primary Pumps
SecondaryPumps
Load
Balancing Valve 2 WayValve
Panel withPLC & VFD`s
Air -Separator
Com
mon
Primary - Secondary Circuit With Variable SpeedSecondary Pumps
DPT
COMMERCIAL BUILDING SERVICES FLOW THINKING
2 Way Valve Control
-
8/8/2019 Chilled Water System Presentation
92/119
Opening/Closing of 2- Way Valve-Signal from the sensor, installed at load
regulates the valve opening & closing.
-This way differential across 2-way valve also
changes & accordingly output signal is given to
PLC.
``
`
Temperature Sensor
Load
Output to PFU from DPT
-
8/8/2019 Chilled Water System Presentation
93/119
Question:
Can we put the DPT across coilalone?
-
8/8/2019 Chilled Water System Presentation
94/119
Question:
Across the pumps?
-
8/8/2019 Chilled Water System Presentation
95/119
COMMERCIAL BUILDING SERVICES FLOW THINKING
System Control Curve
-
8/8/2019 Chilled Water System Presentation
96/119
piping headloss curve
Distribution
Pum
pTDH
Overallsystem curve
FtHd
80
60
40
20
110
0
200 400 600 800 1000 1200 1400 16000
Flow, gpm
100
Control curve
Set point,25 FT
COMMERCIAL BUILDING SERVICES FLOW THINKING
Variable vs Constant Head Loss
-
8/8/2019 Chilled Water System Presentation
97/119
COMMERCIAL BUILDING SERVICES FLOW THINKING
The Active Zone
-
8/8/2019 Chilled Water System Presentation
98/119
Zone set points do not have to be the same.
Pump controller scans all zones often, comparing processvariable to set point in each case.
Pumps are controlled to satisfy the worst case.
What happens to the rest of the zones?
COMMERCIAL BUILDING SERVICES FLOW THINKING
Basic Concept
-
8/8/2019 Chilled Water System Presentation
99/119
PFU
PMU
4 20 mA
Set Value
From FieldSensor (DPT)
PFU Pump Functional Unit
PMU Pump Management Unit
Output
To
VFD/Pump
COMMERCIAL BUILDING SERVICES FLOW THINKING
Different Sensor Signal To Common PFU Panel
Multi Point Differential Pressure Sensor
-
8/8/2019 Chilled Water System Presentation
100/119
ChillersSecondary
Pumps
Balancing Valve
DPTDPT
Co
mmon
Panel withPLC & VFD`s
Load
Different Sensor Signal To Common PFU Panel
COMMERCIAL BUILDING SERVICES FLOW THINKING
POSSIBILITY OF MULTIPLE PROCESS
Multi Point Differential Pressure Sensor
-
8/8/2019 Chilled Water System Presentation
101/119
PFU
PMU
Set Value
Multiple Process SignalsFrom Field Sensors
POSSIBILITY OF MULTIPLE PROCESSSIGNALS FROM DIFFERENT ZONES
All zones can have different set values
Module
VFD
VFD
COMMERCIAL BUILDING SERVICES FLOW THINKING
POSSIBILITY OF MULTIPLE PROCESS
Multi Point Differential Pressure Sensor
-
8/8/2019 Chilled Water System Presentation
102/119
PFU
PMU
Set ValueMultiple Process SignalsFrom Field Sensors
POSSIBILITY OF MULTIPLE PROCESSSIGNALS FROM DIFFERENT ZONES
All zones can havedifferent set values
SignalComparator
VFD
VFD
SignalComparator
4 20 mA Sig
COMMERCIAL BUILDING SERVICES FLOW THINKING
HVAC Control System
-
8/8/2019 Chilled Water System Presentation
103/119
DPT Signal Comparator
-
8/8/2019 Chilled Water System Presentation
104/119
COMMERCIAL BUILDING SERVICES FLOW THINKING
HVAC Control System
DPT Si l C t
-
8/8/2019 Chilled Water System Presentation
105/119
DPT Signal Comparator
Benefits
1) We are able to supply VFD systems with multiple inputs signals ranges to compete
with our competitors.
2) We are able to use Grundfos PFU 2000 as the main processor to control the full systemoperations.
3) We will be minimising outsourcing or external controller in order to serve the HVAC
market.
4) The MM allows us to integrate into the system multiple sensor control at a more cost
effective price.
COMMERCIAL BUILDING SERVICES FLOW THINKING
HVAC System
-
8/8/2019 Chilled Water System Presentation
106/119
Other Types of
Systems
COMMERCIAL BUILDING SERVICES FLOW THINKING
DPT
Separate System for Each Zone
-
8/8/2019 Chilled Water System Presentation
107/119
Chillers
Primary Pumps
BalancingValve
SecondaryPumps
Air -Separator
ExpansionTank
Load
Panel with
PLC & VFD`s
Commo
n
DPT
2 WayValve
DPT
COMMERCIAL BUILDING SERVICES FLOW THINKING
Systems In Multi - Zones
Separate System for Each Zone
-
8/8/2019 Chilled Water System Presentation
108/119
Systems In Multi Zones
Two options:
1. Separate Systems can be used fordifferent zones. So each zone willhave its own sensor.
2. Signal from different zone sensors isgiven to the common PFU and most
deviated signal, from the set point, isgiven as output.
COMMERCIAL BUILDING SERVICES FLOW THINKING
DPTVFD pumps For Each Zone
Tertiary Pumping System
-
8/8/2019 Chilled Water System Presentation
109/119
Chillers
Primary Pumps
BalancingValve
Air -Separator
ExpansionTank
Load
Commo
n
DPT
2 WayValve
DPT
E-pumpsE-pumps
SecondaryPump
COMMERCIAL BUILDING SERVICES FLOW THINKING
Reverse Return Pumping
Load
-
8/8/2019 Chilled Water System Presentation
110/119
Load
Air -Separator
Chillers
PrimaryPumps
SecondaryPumps
Balancing Valve
Panel withPLC & VFD`s
Common
DPT
COMMERCIAL BUILDING SERVICES FLOW THINKING
Reverse Return Pumping
-
8/8/2019 Chilled Water System Presentation
111/119
Benefits :
1) Equalize the pressure drops of each zone.
2) Selections of the sensor becomes easier.
3) If load are similar or symmetrical, 1 centrally located sensor
is adequate.
4) As in direct return system, multiple sensor can still provide a
benefit to the end user.
COMMERCIAL BUILDING SERVICES FLOW THINKING
-
8/8/2019 Chilled Water System Presentation
112/119
Type of VFD Systems
COMMERCIAL BUILDING SERVICES FLOW THINKING
Possible Options of Variable Speed panels
-
8/8/2019 Chilled Water System Presentation
113/119
Possible Options of Variable Speed panels
Type ME - Multiple Pumps &Multiple VFDs.
Type MF - Common VFD for MultiplePumps.
COMMERCIAL BUILDING SERVICES FLOW THINKING
System with Multi Pumps & Multi VFDs
-
8/8/2019 Chilled Water System Presentation
114/119
Signal from FieldSensor(s) (DPT)
Panel with
PFU & PMU
VFD - 1 VFD - 2
Secondary Pumps
COMMERCIAL BUILDING SERVICES FLOW THINKING
System with Common VFD for All Pumps
-
8/8/2019 Chilled Water System Presentation
115/119
Signal from Field Sensor(s) (DPT)
VFD
Panel with
PFU & PMU
Secondary Pumps
System with Common VFD for All Pumps
COMMERCIAL BUILDING SERVICES FLOW THINKING
APPROVAL FROM INTERNATIONALAGENCIES
-
8/8/2019 Chilled Water System Presentation
116/119
AGENCIES
Approval from CE, U/LConforms to - Electromagnetic compatibility
(89/336/EEC) to standard EN 50 081 1 and EN 50082 2 and Electrical equipment design 73/23/EECstandard to EN 60 204-1.
COMMERCIAL BUILDING SERVICES FLOW THINKING
Single PMU For Control of 8 Zones/Pumps
-
8/8/2019 Chilled Water System Presentation
117/119
PFU
PMU
Single PMU For Control of 8 Zones/Pumps
PFU
COMMERCIAL BUILDING SERVICES FLOW THINKING
Single PMU For Control of 8 Zones/Pumps
-
8/8/2019 Chilled Water System Presentation
118/119
PFU
PMU
S g e U o Co t o o 8 o es u ps
PFUPFU PFU
-
8/8/2019 Chilled Water System Presentation
119/119
The End