Chapter 18Synchronous Manufacturing and the Theory of Constraints
Goldratt’s Rules
Goldratt’s Goal of the Firm
Performance Measurement
Capacity and Flow issues
Synchronous Manufacturing
![Page 2: Chp. 18 - TOC S](https://reader036.vdocuments.net/reader036/viewer/2022062308/55cf9330550346f57b9c8e3d/html5/thumbnails/2.jpg)
2Slides used in class may be different from slides in student pack
Goldratt’s Rules of Production Scheduling Do not balance capacity balance the flow. The utilization of a nonbottleneck resource is
not determined by its own potential but by some other constraint in the system.
Utilization and activation of a resource are not the same.
An hour lost at a bottleneck is an hour lost for the entire system.
An hour saved at a nonbottleneck is a mirage.
![Page 3: Chp. 18 - TOC S](https://reader036.vdocuments.net/reader036/viewer/2022062308/55cf9330550346f57b9c8e3d/html5/thumbnails/3.jpg)
3Slides used in class may be different from slides in student pack
Goldratt’s Rules of Production Scheduling (Continued) Bottlenecks govern both throughput and
inventory in the system. Transfer batch may not and many times
should not be equal to the process batch. A process batch should be variable both along
its route and in time. Priorities can be set only by examining the
system’s constraints. Lead time is a derivative of the schedule.
![Page 4: Chp. 18 - TOC S](https://reader036.vdocuments.net/reader036/viewer/2022062308/55cf9330550346f57b9c8e3d/html5/thumbnails/4.jpg)
4Slides used in class may be different from slides in student pack
Goldratt’s Theory of Constraints (TOC)
![Page 5: Chp. 18 - TOC S](https://reader036.vdocuments.net/reader036/viewer/2022062308/55cf9330550346f57b9c8e3d/html5/thumbnails/5.jpg)
5Slides used in class may be different from slides in student pack
Goldratt’s Goal of the Firm
The goal of a firm is to make money.
![Page 6: Chp. 18 - TOC S](https://reader036.vdocuments.net/reader036/viewer/2022062308/55cf9330550346f57b9c8e3d/html5/thumbnails/6.jpg)
6Slides used in class may be different from slides in student pack
Performance Measurement:Financial
Net profit–
Return on investment–
Cash flow–
![Page 7: Chp. 18 - TOC S](https://reader036.vdocuments.net/reader036/viewer/2022062308/55cf9330550346f57b9c8e3d/html5/thumbnails/7.jpg)
7Slides used in class may be different from slides in student pack
Performance Measurement:Operational
1. Throughput
2. Inventory
3. Operating expenses
![Page 8: Chp. 18 - TOC S](https://reader036.vdocuments.net/reader036/viewer/2022062308/55cf9330550346f57b9c8e3d/html5/thumbnails/8.jpg)
8Slides used in class may be different from slides in student pack
Productivity
Does not guarantee profitability
–
–
–
![Page 9: Chp. 18 - TOC S](https://reader036.vdocuments.net/reader036/viewer/2022062308/55cf9330550346f57b9c8e3d/html5/thumbnails/9.jpg)
9Slides used in class may be different from slides in student pack
Unbalanced Capacity
In earlier chapters, we discussed balancing assembly lines.–
Synchronous manufacturing views constant workstation capacity as a bad decision.
![Page 10: Chp. 18 - TOC S](https://reader036.vdocuments.net/reader036/viewer/2022062308/55cf9330550346f57b9c8e3d/html5/thumbnails/10.jpg)
10Slides used in class may be different from slides in student pack
The Statistics of Dependent Events
Rather than balancing capacities, the flow of product through the system should be balanced.
Process Time (B)Process Time (A)
![Page 11: Chp. 18 - TOC S](https://reader036.vdocuments.net/reader036/viewer/2022062308/55cf9330550346f57b9c8e3d/html5/thumbnails/11.jpg)
11Slides used in class may be different from slides in student pack
Capacity Related Terminology
Capacity is the available time for production. Bottleneck is what happens if capacity is
less than demand placed on resource. Nonbottleneck is what happens when
capacity is greater than demand placed on resource.
Capacity-constrained resource (CCR) is a resource where the capacity is close to demand placed on the resource.
![Page 12: Chp. 18 - TOC S](https://reader036.vdocuments.net/reader036/viewer/2022062308/55cf9330550346f57b9c8e3d/html5/thumbnails/12.jpg)
12Slides used in class may be different from slides in student pack
Capacity Example Situation 1
X Y Market
Case A
X YBottleneck Nonbottleneck
Demand/month 200 units 200 unitsProcess time/unit 1 hour 45 minsAvail. time/month 200 hours 200 hours
There is some idle production in this set up. How much?
![Page 13: Chp. 18 - TOC S](https://reader036.vdocuments.net/reader036/viewer/2022062308/55cf9330550346f57b9c8e3d/html5/thumbnails/13.jpg)
13Slides used in class may be different from slides in student pack
Capacity Example Situation 2
Y X Market
Case B
X YBottleneck Nonbottleneck
Demand/month 200 units 200 unitsProcess time/unit 1 hour 45 minsAvail. time/month 200 hours 200 hours
Is there is going to be a build up of unnecessary production in Y?
![Page 14: Chp. 18 - TOC S](https://reader036.vdocuments.net/reader036/viewer/2022062308/55cf9330550346f57b9c8e3d/html5/thumbnails/14.jpg)
14Slides used in class may be different from slides in student pack
Capacity Example Situation 3
X Y
Assembly
Market
Case C
X YBottleneck Nonbottleneck
Demand/month 200 units 200 unitsProcess time/unit 1 hour 45 minsAvail. time/month 200 hours 200 hours
Is there going to be a build up in unnecessary production in Y?
![Page 15: Chp. 18 - TOC S](https://reader036.vdocuments.net/reader036/viewer/2022062308/55cf9330550346f57b9c8e3d/html5/thumbnails/15.jpg)
15Slides used in class may be different from slides in student pack
Capacity Example Situation 4
X Y
Market Market
Case D
X YBottleneck Nonbottleneck
Demand/month 200 units 200 unitsProcess time/unit 1 hour 45 minsAvail. time/month 200 hours 200 hours
If we run both X and Y for the same time, will we produce any unneeded production?
![Page 16: Chp. 18 - TOC S](https://reader036.vdocuments.net/reader036/viewer/2022062308/55cf9330550346f57b9c8e3d/html5/thumbnails/16.jpg)
16Slides used in class may be different from slides in student pack
Components of Production Throughput Time
Setup time is the time that a part spends waiting for a resource to be set up to work on this same part.
Process time is the time that the part is being processed.
Queue time is the time that a part waits for a resource while the resource is busy with something else.
![Page 17: Chp. 18 - TOC S](https://reader036.vdocuments.net/reader036/viewer/2022062308/55cf9330550346f57b9c8e3d/html5/thumbnails/17.jpg)
17Slides used in class may be different from slides in student pack
Wait time is the time that a part waits not for a resource but for another part so that they can be assembled together.
Idle time is the unused time. It represents the cycle time less the sum of the setup time, processing time, queue time, and wait time.
Components of Production Throughput Time (Cont’d)
![Page 18: Chp. 18 - TOC S](https://reader036.vdocuments.net/reader036/viewer/2022062308/55cf9330550346f57b9c8e3d/html5/thumbnails/18.jpg)
18Slides used in class may be different from slides in student pack
Saving Time
Bottleneck Nonbottleneck
What are the consequences of saving time at each process?
Rule:
Rule:
Rule:
![Page 19: Chp. 18 - TOC S](https://reader036.vdocuments.net/reader036/viewer/2022062308/55cf9330550346f57b9c8e3d/html5/thumbnails/19.jpg)
19Slides used in class may be different from slides in student pack
Drum, Buffer, Rope
A B C D E F
Bottleneck (Drum)
Inventorybuffer
(time buffer)Communication
(rope)
Market
Exhibit 18.9Exhibit 18.9
![Page 20: Chp. 18 - TOC S](https://reader036.vdocuments.net/reader036/viewer/2022062308/55cf9330550346f57b9c8e3d/html5/thumbnails/20.jpg)
20Slides used in class may be different from slides in student pack
Quality Implications of synchronous manufacturing
More tolerant than JIT systems–
Except for the bottleneck–
![Page 21: Chp. 18 - TOC S](https://reader036.vdocuments.net/reader036/viewer/2022062308/55cf9330550346f57b9c8e3d/html5/thumbnails/21.jpg)
21Slides used in class may be different from slides in student pack
Inventory Cost Measurement:Dollar Days Dollar Days is a measurement of the value
of inventory and the time it stays within an area.
Dollar Days = (value of inventory)(number of days within a department)
Example
![Page 22: Chp. 18 - TOC S](https://reader036.vdocuments.net/reader036/viewer/2022062308/55cf9330550346f57b9c8e3d/html5/thumbnails/22.jpg)
22Slides used in class may be different from slides in student pack
Benefits from Dollar Day Measurement
Marketing–
Purchasing–
Manufacturing–
![Page 23: Chp. 18 - TOC S](https://reader036.vdocuments.net/reader036/viewer/2022062308/55cf9330550346f57b9c8e3d/html5/thumbnails/23.jpg)
23Slides used in class may be different from slides in student pack
Comparing Synchronous Manufacturing to MRP MRP uses backward scheduling.
Synchronous manufacturing uses forward scheduling.
![Page 24: Chp. 18 - TOC S](https://reader036.vdocuments.net/reader036/viewer/2022062308/55cf9330550346f57b9c8e3d/html5/thumbnails/24.jpg)
24Slides used in class may be different from slides in student pack
Comparing Synchronous Manufacturing to JIT JIT is limited to repetitive manufacturing
JIT requires a stable production level
JIT does not allow very much flexibility in the products produced
![Page 25: Chp. 18 - TOC S](https://reader036.vdocuments.net/reader036/viewer/2022062308/55cf9330550346f57b9c8e3d/html5/thumbnails/25.jpg)
25Slides used in class may be different from slides in student pack
Comparing Synchronous Manufacturing to JIT (Continued) JIT still requires work in process when used
with kanban so that there is "something to pull."
Vendors need to be located nearby because the system depends on smaller, more frequent deliveries.
![Page 26: Chp. 18 - TOC S](https://reader036.vdocuments.net/reader036/viewer/2022062308/55cf9330550346f57b9c8e3d/html5/thumbnails/26.jpg)
26Slides used in class may be different from slides in student pack
Relationship with Other Functional Areas
Accounting’s influence
Marketing and production