chunnel ppt

23
The Chunnel Project A learning out of Failure By Garvit Bharadwaj Piyush Tyagi Pranay Karthik Rachit Anand Rajesh Bhatia Sankarshan Joshi Sumeet Gupta

Upload: sankarshanjoshi

Post on 03-Dec-2014

3.557 views

Category:

Business


4 download

DESCRIPTION

Project Management,

TRANSCRIPT

Page 1: Chunnel ppt

The Chunnel ProjectA learning out of Failure

By

Garvit Bharadwaj

Piyush Tyagi

Pranay Karthik

Rachit Anand

Rajesh Bhatia

Sankarshan Joshi

Sumeet Gupta

Page 2: Chunnel ppt
Page 3: Chunnel ppt

Channel + Tunnel = Chunnel

Page 4: Chunnel ppt

The Chunnel

One of the world’s Largest Privately Funded construction project involving 2 Governments – French and British

220 banks

Numerous contractors

Regulatory Agencies (IGC)

The project was bid at $5.5 b but completed at $14.9 b

$8.4b

Scope creep

19 Months Delay

Page 5: Chunnel ppt

The Chunnel - Contracts

French + BritishGovt

BOT-Contract CTG/FM

CTG/FM Contract TML

Page 6: Chunnel ppt

Next 15 Minutes

Inception

Development

Execution

Closeout

Page 7: Chunnel ppt

What is expected?

• Proper risk management

• Engineering risks

• Process risks

• Approval risks

• Financial risks

• Business risks

Page 8: Chunnel ppt

Inception Development Execution Closeout

• Inception

• Historical background of the project

• Objective

• Political climate

• Pre-feasibility study

Page 9: Chunnel ppt

Inception Development Execution Closeout

• Scope:

• Fixed transportation (51.5kms)

• Economic development

• Pressures causing mishaps:

• Lack of scope causes resource planning, cost estimating & budgeting difficult.

• Air-conditioning costs

• Formation of intergovernmental commission

Page 10: Chunnel ppt

Inception Development Execution Closeout

• Finance aspects:

• Treaty says to no government aid

• Pursued via equity &loan capital markets.

• Scheduling:

• Activities related to activity definition, activity

sequencing, activity duration estimates.

• Planning 3 tunnels which required 46 contractors to

complete the design requirements.

• Changing safety rules created negative variances.

Page 11: Chunnel ppt

Inception Development Execution Closeout

• Incompatibility issues could have been avoided by stating Initial quality requirement in more detail.

• Areas of improvement There was much interpretation for the agency like IGC .The IGC decision to change 600mm doors to 700mm doors itself delay the project to 9 months.

• Teamwork & cooperation considering the scope of the project was very important.

• Contractual agreements made teamwork a complex activity.

• It was very difficult to come to a mutually agreeable solution to material issues due to incomplete requirements, scope changes and thus , risk response strategies should have been considered.

Page 12: Chunnel ppt

Inception Development Execution Closeout

• Efficient communication is very important in

preplanning, contract negotiations, financing and

technical issues during the inception stage.

• Communication seemed to breakdown in case of issues

regarding organizational structure , finance and

contracts as the issues were not timely solved.

Page 13: Chunnel ppt

Inception Development Execution Closeout

• Communication plan addressing horizontal and vertical communication channels should be in place.

• Plan should also include information sharing, issue tracking and performance reporting.

• Although , advanced project management tools and techniques were used, the decision-making ability to address critical issues from centralized position seemed insufficient

Page 14: Chunnel ppt

Inception Development Execution Closeout

Some critical aspects in development phase:

• Massive communication barriers.

• Problems due to huge scope of the project.• IGC played critical and detrimental role.

• Cost planning.• Banks played an important role from start.

• Scheduling was well done but project still faltered on deliver date.• IGC’s highest standard norm.

Page 15: Chunnel ppt

Inception Development Execution Closeout

• Better risk management could have been done.

• Lack of investment in team building.• Two Government's denial to provide financial

guarantee.

• Project office’s work lacked detail.

• All in all, given the facts, the project delay and cost overrun were almost foregone conclusions

Page 16: Chunnel ppt

Too Early A Start

Design

Construction

Approval Issues

Enggineering Risks

Underground Construction

New Technology

Risk

Inception Development Execution Closeout

Page 17: Chunnel ppt

Bureaucratic Pressures

French + BritishGovt. Pressures

Control CostsFixed Price

Implications for TML

“Winner Takes All” Issue

Low Bid Prices with Best Case

Scenario

Squeezing Revenue via

Change orders

Project cost Rise from $4.3 billion

TO $7 billion

Inception Development Execution Closeout

Page 18: Chunnel ppt

Controls in Wrong Hands

Controls

Financing Banks

Profit Maximization

ConstructionCompanies

Risk Minimization

NO IMPORTANCE TO OPERATIONS

Inception Development Execution Closeout

Page 19: Chunnel ppt

Communication Issues

InternalCommunication

Limited

Different Countries

Different Cultures Different

Specification

Inception Development Execution Closeout

Page 20: Chunnel ppt

Inception Development Execution Closeout

The immense amount of Litigation and Claim against project.

• Scope: Scope of the project increases due to overall changes request through out the life of project.

• Cost & Schedule Management: Max. Efforts to analyzing the source of overrun cost and blaming participating organization.

• Team work and Communication: Team work and communication had broken down in several key area. Like Financial banker focus on minimizing their losses ,so they refused to negotiate any settlement. Clearly win-win negotiation far from mind between the parties.

Page 21: Chunnel ppt

Inception Development Execution Closeout

• Time Over shoot: the greatest impact of ROI.

• Quality of project: Quality of a project is up to the mark as per engineering design and expectation. Even no. of accident was less as per industrial avg. during project running time.

• Effective Change Management: They ready to make changes as per demand without additional funding during close out.

Page 22: Chunnel ppt

Learning's

• Equal importance should be give to the technical as well as functional aspects of project management.

• Project contracts and financing agreements should not be rushed and should provide for contingency.

• External Stakeholders should only play monitoring role and should not take part in day-to-day operations.

• Large projects like Chunnel Construction requires leveraging of new technology and lessons learned from existing project.

Page 23: Chunnel ppt

Thank You!!!! No Questions Please.

We Know You Cant Control, So Go Ahead And Shoot Your

Questions!

If learned from, Mistakes can be converted into Experiences.