City of East Point Comprehensive Floodplain Management Program GAFM 2012, 7’ th Annual Technical Conference March, 28, 2012 Reza Aral, CFM, CPESC (City of East Point, GA) Shayne Wood, P.E. (CDM Smith)

Upload: lydung

Post on 13-Jul-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: City of East Point Comprehensive Floodplain … of East Point Comprehensive Floodplain Management Program GAFM 2012, 7’th Annual Technical Conference March, 28, 2012 Reza Aral, …

City of East Point Comprehensive Floodplain Management Program

GAFM 2012, 7’th Annual Technical Conference

March, 28, 2012

Reza Aral, CFM, CPESC (City of East Point, GA)

Shayne Wood, P.E. (CDM Smith)

Page 2: City of East Point Comprehensive Floodplain … of East Point Comprehensive Floodplain Management Program GAFM 2012, 7’th Annual Technical Conference March, 28, 2012 Reza Aral, …

Agenda

• Overview of City’s Master Plan

• Value of an Updated Master Plan

• Floodplain Management Program

• Implementation Completed to Date

• Funding – Evaluating a Stormwater Utility

• Summary

• Questions

City of East Point Comprehensive Floodplain Management Program

4/10/20122

Page 3: City of East Point Comprehensive Floodplain … of East Point Comprehensive Floodplain Management Program GAFM 2012, 7’th Annual Technical Conference March, 28, 2012 Reza Aral, …

The Foundation

• City had a Stormwater Master Plan completed in 2001

• Stormwater Master Plan Update completed in 2010: Included data collection and surveying

Utilized LIDAR

Updated H&H models to existing conditions and future land use

o 100-acre hydrologic units!

Additional surveying and modeling for several critical reaches

Developed prioritized recommendations for the City’s CIP

City of East Point Comprehensive Floodplain Management Program

4/10/20123

Page 4: City of East Point Comprehensive Floodplain … of East Point Comprehensive Floodplain Management Program GAFM 2012, 7’th Annual Technical Conference March, 28, 2012 Reza Aral, …

Why Update the Stormwater Master Plan?

• Accounts for system changes over time

• Utilize more accurate and current data New data – survey, LiDAR, updated land use, recent large storm events

Accounted for additional area that contributes runoff to the City’s stormwater management system

• Add detail and resolution to stormwater model

• Reassess and reprioritize issues/problem areas

• Assisted in City’s effort to update its floodplain maps

• Accurately pinpoint problem areas and implement cost effective solutions $$ Savings

City of East Point Comprehensive Floodplain Management Program

4/10/20124

Page 5: City of East Point Comprehensive Floodplain … of East Point Comprehensive Floodplain Management Program GAFM 2012, 7’th Annual Technical Conference March, 28, 2012 Reza Aral, …

Original Stormwater Master Plan –2001

Stormwater Master Plan Update –2010

City of East Point Comprehensive Floodplain Management Program

4/10/20125

New LIDAR data

Additional Survey and Detail

Page 6: City of East Point Comprehensive Floodplain … of East Point Comprehensive Floodplain Management Program GAFM 2012, 7’th Annual Technical Conference March, 28, 2012 Reza Aral, …

Stormwater Master Plan Update – Fast Facts

• 5,851 acres of total watershed area added

• 41 total miles of creeks/ditches in the model

• 9 total miles of culverts/pipes in the model

• 581 total nodes of which 157 new nodes added

• 18 bridges of which 12 new bridges added

• 267 culverts/pipes of which 41 new culverts were added

City of East Point Comprehensive Floodplain Management Program

4/10/20126

Page 7: City of East Point Comprehensive Floodplain … of East Point Comprehensive Floodplain Management Program GAFM 2012, 7’th Annual Technical Conference March, 28, 2012 Reza Aral, …

Implementation of Stormwater Master Plan Recommendations

• Completed 2 construction projects to address critical issues

• Priority Stormwater Design Projects to address 5 critical problem areas

• Several preliminary engineering analysis to prioritize and address critical problem areas which included additional surveying

City of East Point Comprehensive Floodplain Management Program

4/10/20127

Page 8: City of East Point Comprehensive Floodplain … of East Point Comprehensive Floodplain Management Program GAFM 2012, 7’th Annual Technical Conference March, 28, 2012 Reza Aral, …

Floodplain Management Program

The Comprehensive Floodplain Management Program started in January 2011 with the following goals:

Mitigate flood risk

Maintain existing infrastructure

Identify at-risk properties

Update FEMA flood insurance rate maps

Join FEMA’s CRS program

Educate, inform and engage community residents and stakeholders

Identify and pursue federal funding for projects

City of East Point Comprehensive Floodplain Management Program

4/10/20128

Page 9: City of East Point Comprehensive Floodplain … of East Point Comprehensive Floodplain Management Program GAFM 2012, 7’th Annual Technical Conference March, 28, 2012 Reza Aral, …

Floodplain Management Program

What’s been completed to date

Floodplain Models and Maps updated

Community Rating System (CRS) Roadmap developed

Ordinance Revisions developed for consideration/recommendation

Peer reviews completed for proposed developments

Stormwater Utility Advisory Committee

City of East Point Comprehensive Floodplain Management Program

4/10/20129

Page 10: City of East Point Comprehensive Floodplain … of East Point Comprehensive Floodplain Management Program GAFM 2012, 7’th Annual Technical Conference March, 28, 2012 Reza Aral, …

FEMA Flood Map Modernization

• City of East Point is in the Upper Chattahoochee River Basin

• City of East Point Floodplain Management Program study/modeling leveraged into the GA DNR/FEMA Map Mod effort

City of East Point Comprehensive Floodplain Management Program

4/10/201210

Page 11: City of East Point Comprehensive Floodplain … of East Point Comprehensive Floodplain Management Program GAFM 2012, 7’th Annual Technical Conference March, 28, 2012 Reza Aral, …

New stream miles mapped

during updated study

Creek/River Effective (miles)

Camp Creek 20.8

South-Flint 3.1

Utoy Creek 7.4

Total 31.3

Stream miles in Effective and Updated Study

Total(miles)

25.7

5.9

13.6

45.2

Updated(miles)

4.9

2.8

6.2

13.9

Utoy Creek

Camp Creek

South River

Flint River

4/10/201211

Page 12: City of East Point Comprehensive Floodplain … of East Point Comprehensive Floodplain Management Program GAFM 2012, 7’th Annual Technical Conference March, 28, 2012 Reza Aral, …

Public Outreach – Floodplain Map Update Process

Introduce maps to community

Answer any questions

Have one on one work sessions with residents at workshops

Encourage residents to meet with their insurance agents

Be Proactive!!

• Media Outreach – EPTV

• GIS Portal - East Point website allows residents to view maps online

City of East Point Comprehensive Floodplain Management Program

4/10/201212

• Community meetings publicized

• Workshops conducted in each of the City’s four wards

Page 13: City of East Point Comprehensive Floodplain … of East Point Comprehensive Floodplain Management Program GAFM 2012, 7’th Annual Technical Conference March, 28, 2012 Reza Aral, …

Preparing for CRS

• Benefits of entering the CRS program: Safer better prepared community

Flood insurance discounts

Potential insurance premium savings $15,000 to $140,000 total

Range of savings per policy holder $80 to $700 per year (depending on CRS Rating achieved)

• Developed short-term and long-term implementation activities for the CRS program

• Public Outreach

City of East Point Comprehensive Floodplain Management Program

4/10/201213

Page 14: City of East Point Comprehensive Floodplain … of East Point Comprehensive Floodplain Management Program GAFM 2012, 7’th Annual Technical Conference March, 28, 2012 Reza Aral, …

Stormwater Utility – Stormwater Advisory Committee

• Approximately 20 members comprised of church representatives, non-profit organizations, businesses, and residents from each ward

• Goal was to evaluate the stormwater needs for the City and carry forward the community’s and SWAC’s recommendation for a stormwater utility

City of East Point Comprehensive Floodplain Management Program

• Participated in monthly meetings from June through January and participated in a field trip to view stormwater problems and solutions in the City

4/10/201214

Page 15: City of East Point Comprehensive Floodplain … of East Point Comprehensive Floodplain Management Program GAFM 2012, 7’th Annual Technical Conference March, 28, 2012 Reza Aral, …

Stormwater Utility – Stormwater Advisory Committee Recommendations

Focused on Four Areas:

• Level of Service (what size stormwater program do we want)

• Funding Source

• Future Role of the Committee

• Public Information and Education

City of East Point Comprehensive Floodplain Management Program

4/10/201215

Page 16: City of East Point Comprehensive Floodplain … of East Point Comprehensive Floodplain Management Program GAFM 2012, 7’th Annual Technical Conference March, 28, 2012 Reza Aral, …

Stormwater Utility – Level of Service

Goal: Establish a utility that will fund a stormwater program for Fiscal Year 2013 – Range being considered $1.7M up to $2.2M

Basis

This level will provide sufficient

funding for all of the following:• Personnel

• Regulatory compliance and required inspections

• Stormwater system maintenance program

• One or two capital projects or emergency projects per year

• CRS program enrollment and pursuit of grant opportunities

Range ofaffordableoptions

Ultimate

Level of

Service

Administration Capital

Projects

Operation &

Maintenance

Existing

16

City of East Point Comprehensive Floodplain Management Program

4/10/2012

Page 17: City of East Point Comprehensive Floodplain … of East Point Comprehensive Floodplain Management Program GAFM 2012, 7’th Annual Technical Conference March, 28, 2012 Reza Aral, …

Stormwater Utility – Funding Source

• Fees would be subject to change (pending Council approval) depending on the City’s needs

• Impervious area is the equitable basis for a user fee

• SWAC prefers ERU methodology because it treats all residents equally

• Resulting revenues shall be used for stormwater program only

17 4/10/2012City of East Point Comprehensive Floodplain Management Program

Page 18: City of East Point Comprehensive Floodplain … of East Point Comprehensive Floodplain Management Program GAFM 2012, 7’th Annual Technical Conference March, 28, 2012 Reza Aral, …

Anticipated Future Steps

• Interim and short-term implementation of CRS Roadmap• Flood prone structure evaluation and ranking• Grant application• Stormwater management system evaluation – CIP focused

4/10/201218City of East Point Comprehensive Floodplain Management Program

Page 19: City of East Point Comprehensive Floodplain … of East Point Comprehensive Floodplain Management Program GAFM 2012, 7’th Annual Technical Conference March, 28, 2012 Reza Aral, …

Stormwater Master Plan

Floodplain Management

Program

Fund your program

Stormwater Utility

Summary

• Build a strong foundation with a “Living” Master Plan

• Build upon the Master Plan to Implement Desired Program Goals

• Find a way to fund your program – dedicated and recurring funding is the key

City of East Point Comprehensive Floodplain Management Program

4/10/201219

Page 20: City of East Point Comprehensive Floodplain … of East Point Comprehensive Floodplain Management Program GAFM 2012, 7’th Annual Technical Conference March, 28, 2012 Reza Aral, …

Questions?

4/10/201220City of East Point Comprehensive Floodplain Management Program