city of laredo - north american development bank · 2 city of laredo water utilities engineering...
TRANSCRIPT
1
CITY OF LAREDO WATER UTILITIES ENGINEERING DIVISION
5816 Daugherty Laredo, Texas 78041
Tel. (956) 721-2000 Fax (956) 721-2001
April 21, 2011
HOUSE TO LINE CONNECTIONS FOR
RANCHO PEÑITAS WEST, LOS MINERALES, LOS MINERALES ANNEX AND ANTONIO SANTOS, CITY OF LAREDO, TEXAS
WEBB COUNTY
Addendum No 3
This addendum forms a part of the contract described above. The original contract documents and
any prior addenda remain in full force and affect except as modified by the following which shall
take precedence over any contrary provisions in prior documents.
Contract Documents
The following are questions asked by the bidders. Responses are shown in Bold.
1. How do we abandon the existing septic tanks or cesspools?
Septic Tank or Cesspools will be abandoned according to the specifications of the
City of Laredo Health Department and Environmental Health Services Division.
The septic tanks and cesspools will be vacuumed at the discretion of the Health
Department Inspector. The contractor can use different kinds of materials such as
sand, slit, clay, gravel, concrete or combination of any of those materials as backfill.
If a cesspool condition exists, the same criteria apply for the abandonment of the
cesspool.
The contractor will be responsible to complete the form of the Septic Tank –
Cesspool – Pit Privy Elimination Program; a copy of the form was given to all
bidders present at the pre-bid meeting.
2. What kind of grinder pumps should be used?
The contractor will be responsible for designing and constructing the grinder
pumps as necessary and as proposed on their bid. The submittal should be provided
to the Utilities Department for their approval prior to installation. Design should be
signed and sealed by a professional engineer.
3. How many working days does the contract have?
The contract time is 283 working days. Working days are Monday through Friday,
8:00 a.m. to 5:00 p.m. Inspector’s time on weekends or holidays will be paid by the
contractor as overtime. Contractor should notify Utilities Department 24 hours in
advance if they are going to be working on weekends or after 5: 00 and the inspector
is required to be on-site.
Addendum No. 3
2
CITY OF LAREDO WATER UTILITIES ENGINEERING DIVISION
5816 Daugherty Laredo, Texas 78041
Tel. (956) 721-2000 Fax (956) 721-2001
4. Can the Licensed Plumber be an employee of a company or an independent License
Plumber?
The Licensed Plumber can be either an employee or an independent contractor; in
either case, they need to be present at the jobsite at all times to inspect the work
performed.
5. What kind of material do we need to use?
The contractor can use PVC Schedule 40 or copper from the meter to the house.
The contractor needs to use copper type “S” for any new tap to the existing main
line to the meter.
The contractor needs to use SDR-26 for the sanitary sewer line.
6. What kind of permit will be necessary?
The contractor needs to get the construction permit under the City of Laredo and
Webb County. There will only be one permit issued for the entire project; a permit
will not be issued per lot.
7. What lots will be part of the contract?
Only the lots with dots on the plans will be part of the contract.
8. What will be done in case of existing grass, utilities, concrete driveway and
sidewalks?
As part of the right of entry, the contractor will not be responsible for any damage
caused to existing trees, vegetation or landscaping that are in conflict with the
alignment of the water and sewer pipe line installation; however, the contractor will
be responsible for any damages to the existing utilities. Repairs to concrete
driveways or sidewalks are part of a bid item per square footage. Contractor is
responsible for verifying the location of any utility and identifying any conflict with
any improvements done by the owner or utility company.
9. What about a soil investigation?
We have encountered type II and type III soils on our recently installation of Septic
Tanks approved by our Health Department and Environmental. Due to the lack of
time given to the testing laboratory to perform the soil investigations, the bidder
should include the price for every kind of soil that exists in the areas of Minerales
and Peñitas in order to have the unit price quote for any kind of soil. The soil
investigation will be performed during the execution of the contract and payment
for any septic tank will be paid for the type of soil found on the property.
10. Can the bidder request his own right of entry?
The right of entry will be provided to the contractor by the City of Laredo Utilities
Department. The City of Laredo has no objection if the contractor wants to obtain
his right of entry, but the contractor can’t obligate the property owner to sign
another right of entry. Addendum No. 3
3
CITY OF LAREDO WATER UTILITIES ENGINEERING DIVISION
5816 Daugherty Laredo, Texas 78041
Tel. (956) 721-2000 Fax (956) 721-2001
11. How much is the estimated budget for the contract?
The estimated budget is approximately 1.3 million dollars. Bidders can use a
general contractor for bonding purposes.
12. What are the specifications for the lift station or septic tank requirements for those
dwellings that are to low and no gravity flow is available to connect the sewage line?
You have the option to do a grinder pump or a septic tank, but both options require
being design by a Professional Engineer, so the design built requirements will be
responsibility of the contractor and should be provided as part of the submittals.
13. Why some dwellings are not included in the set of plans?
Dwellings that have an exiting meter should connect to the sanitary sewer 30 days
after the installation of the meter as part of the service agreement between the City
of Laredo and the customer, dwellings that we can’t get access to verify the
plumbing inside of the dwelling, dwellings that doesn’t have bathroom and
dwellings that didn’t provide the right-of –way weren’t included as part of the
plans. Any additional dwelling should be approved by Utilities and NADBANK.
14. Who will be the project manager and the inspector?
The project manager will be Humberto Serradell, the inspectors will be Mario
Elizondo and Rafael Cisneros.
15. Replace Attachment 1, Volume I. iv Bid and Price Schedules. Contractor shall use
this price schedule or bid submittal.
(Attachment 1, Volume I. iv Bid and Price Schedules attached)
Each bidder is requested to acknowledge receipt of this addendum by his/her signature affixed
hereto and to file same with and attached to his/her bid.
Gloria P. Saavedra, P.E.
Utilities Engineering
Manager
The undersigned acknowledges receipt of this addendum and the bid submitted herewith is in
accordance with the information and stipulations set forth.
. _______ _____________
Date Signature of Bidder
Addendum No. 3