CIVIL ENGINEERING SOFTWARE BFC 43201
Name: Dr Riduan Bin Yunus Office: M-004-16 (FKAAS’s Office) Phone number: 07-4564227 /012-9200530 E-mail: [email protected]
1
Lecture Plan
CIVIL ENGINEERING SOFTWARE BFC 43201
2 17/11/2014
17/11/2014 3
http://www.microsoftproject.com.my/?gclid=CNiRuf2D17wCFWlT4godXyEAWw
1. Primavera Contractor
2. SureTrak Project Manager
3. Expedition® 9.0
4. Primavera Project Planner® (P6®) Oracle's Primavera P6 Enterprise Project Portfolio Management is the most powerful, robust, and easy-to-use solution for globally prioritizing, planning, managing, and executing projects, programs, and portfolios. Primavera P6 Enterprise Project Portfolio Management is an integrated project portfolio management (PPM) solution comprising role-specific functionality to satisfy each team member's needs, responsibilities, and skills. It provides a single solution for managing projects of any size, adapts to various levels of complexities within a project, and intelligently scales to meet the needs of various roles,
functions, or skill levels in your organization and on your project team
Other Planning & Scheduling Softwares
17/11/2014 5
Planning & Scheduling Definitions • Project Planning:
– “Process of choosing the one method and order of work to be adopted for a project from all the various way and sequences in which it could be done”.
• Project Scheduling: – “Determination of the timing and sequence of operation
mentioned previously, scheduling focuses on one part of the planning effort”.
• Therefore, project planning is a pre-requirement to project scheduling. Only after each activities identify the precedence, start date and finish date can be identified.
6 Antill & Woodhead-1990 DRY2013 17/11/2014
7 DRY2013 17/11/2014
COST
QUALITY
PROJECT GOAL PLAN M
ON
ITOR
EVALUATE REV
ISED
/CO
NTR
OL
What is Project Management? • a method for organizing tasks
• a structured framework to help a group work productively
• tools to aid in task sequencing, dependency analysis, resource allocation, scheduling, etc.
• tools to track progress relative to plan
Goodman, E., 1999
Why Need Project Management?
• Complex project needs coordination of:
– Multiple people
– Multiple resources (labs, equipment, etc.)
– Multiple tasks – some must precede others
– Multiple decision points – approvals
– Phased expenditure of funds
– Matching of people/resources to tasks
Task Dependencies and the Critical Path
• Sometimes task B cannot be started before task A is completed
• Other types of constraints – calendar, lags, etc.
• Critical path – any slippage slips whole project
• Helpful to know what tasks are on the critical path
• Useful to try to shorten the critical path
Suggested Steps in Project Management
• Generate a formal definition of the project, with goals, constraints, assumptions
• Identify project start/end dates, any mandatory milestones, including reports, signoffs, deliverables, etc.
• List constraints – money, equipment availability, holidays, etc.
• Identify tasks to be accomplished – high level (i.e., by categories), then details within each, using brainstorming method – green light
Suggested Steps, cont.
• Refine detailed task list, dropping/ combining, adding things omitted
Then, for each task in list:
• Estimate time (person hours, calendar period)
• Identify dependencies among tasks
• Identify resources (people, money, parts, etc.)
Suggested Steps, cont.
Organize task groups roughly by starting date
List dependencies that should or MUST hold
Use MS Project to make a GANTT chart
• First capture tasks and task groups, milestones
• Identify critical path, see if it can be shortened (get more “slack”)
• Assign person-hours and specific team member(s) to each task – identify “task leads”
Suggested Steps, cont.
As project progresses:
• Monitor, record progress on all tasks, at least weekly – use “Tracking Gantt Chart”
• Pay particular attention to those on critical path
• Revise plan as needed to take into account changes, adapt to meet milestones
Project Management Using Microsoft Project
• Allows many different ways of entering and observing information
• includes many features to help identify problems with a plan
• regular use can help a group refine plans to make meeting targets more realistic
PLANNING TOOL
• Microsoft Project/Primavera-planning tools
• Uses to do the planning and for project monitoring and control
• Types of planning file:
– baseline file (initial planning)
– tracking file (Monitoring and control)
– new baseline file/Schedule Updating (Revise program)
MSP 2010 FOR CONSTRUCTION
Creating the Baseline File Steps Open New File-set the Project Information (New project: Reset the Project
Start Date according to Contract Start Date. Set The Working Schedule (Working Time/Holidays) Create the Working List according to WBS List
indent and out dent sub activities accordingly Identify activities which requires different types of payment (initial cost,
prorated, recurring cost, on completion) WBS codes
Create The Relationship/Link (Predecessor Or Successor) for subtask. Assign Durations (3rd Party Job Create As Milestone, Duration=0)
Effort Driven Scheduling Activity Duration Estimate
MSP 2010 FOR CONSTRUCTION
Assign fixed cost for sub activities
Set Project as Baseline File
Creating the Financial S-Curve
Creating the Physical S-curve
Project Information
• Project Title: Construction of Dream House at Parit Raja
• Project Start Date: 7th October 2014
• Project Finish Date : 7th March 2015
• Project Duration: 6 months
• Contract Sum: RM 200,000.00
• Working Calendar: Sunday is non-working day
• Holiday: State and Federal
OPEN NEW PROJECT
File>New>Blank Project
Open File for a New Project
17/11/2014
21
Set the Project Information
17/11/2014 22
Set the Project Information
17/11/2014 23
Click OK
Project>Project Information>Select the Start Date (7/10/2013)>ok!
17/11/2014 24
The Timeline shows 1 week from the start date of the project
Set the Working Calendar
17/11/2014 25
Key in the Holiday Information
Project>Change Working Time>Exceptions> List all the agreed public holidays for project
Modify the Working Time
17/11/2014 26
Default working time is from 8.00am to 5.00pm
SET THE WORKING SECHEDULE
Project>Change Working Time>Work Week>Details> Choose Saturday and Set Day(s) to specific working times> type the time using “clock” format>ok!
Work Breakdown Structure
Level 4
(Task – WBS)
Level 3
(Sub-activity – WBS)
Level 2
(Activity – Deliverable Breakdown Structure)
Level 1
(Phase – Product Breakdown Structure)
Project
A
A1
A1.1
A2
B
B1
17/11/2014 28
WBS List Bungalow in Parit Raja
• Project Start
• Preliminaries – Performance Bond/Insurance
– Establish and Removal of Site Office
– Progress Report
• Land Acquisition
• Earthwork – Site Clearing
– Excavation , Backfilling and Leveling
• Piling Work • Building Work
– Structure
Sub Structure
Super Structure
Roof Trusses
- Architecture Wall Floor Finishes Painting
Internal external
- M&E Electrical
Wiring Switches and Sockets
Plumbing Piping Sanitary Fixtures
• Infrastructure - Road and drainage - TNB and Water Meter Supply
• Testing and Commissioning • Project Finish
Create the WBS List
Task>Choose Task in Column>Indent/Outdent
• Id no 1 (Project name)
• Id no 2 (Project Start-critical milestone)
• Final Id (Project Finish-critical milestone)
Adjusting WBS Level
• List all task and subtask (indent/outdent according to its level)
• All authority and 3rd party job create as milestone (duration=0)
• Set the task mode as auto schedule Task> Highlight Task Mode Column>Auto Schedule
WBS Level/System Coding
Insert Column>Scroll for WBS
• WBS Level 1 (project name)
• WBS level 2 (activities)
• WBS level 3 (sub-activities)
• WBS level 4 (Work Tasks)
• WBS level 5 (Sub Work Tasks)
• And So on..
Project Scope Planning
I) Task/Activity
Individual work that defines a piece of work that is necessary to complete a project
Clearly define the work that needs to be accomplished
Has a START and FINISH date
Duration> “0 days”
Contains 4M (Money, Manpower, Material and Machinery)
Project Scope Planning
II) Milestones Special event/Major event/significant point in
the project that the planner want/need to monitor.
Every project has at least 2 milestone (START & FINISH)
Duration = 0 days (takes no time and show as date only).
Use no resources (4M=0)
Project Scope Planning
III) External Dependency Milestone
Task that have work but done by third parties
Contractors do not know the scope of this work and when the date of completion.
Should be shown in the work program of the main contractor for the purpose of the application of EOT.
Duration of work = “0 days”
Project Scope Planning/Milestones
• Project Start (0 days)
• Land acquisition (0days)
• TNB and Water Meter Supply (0days)
• Project Finish (0days)
Recurring Task
Highlight Task to recurrent>Task Ribbon>Scroll Task Symbol>Recurring Task
Recurring Task is the task that occur at a fixed frequency and continuously
RECURRING TASK
• Recurring is task that occur at a fixed frequency and continuously
• e.g: weekly staff meetings, quarterly reports or monthly budget review.
• Enables you to create the meeting task once and assign a frequency and timing to it.
Retype the task name
Decide duration allocated for the
preparation of the document
Choose frequency of the recurrent
Decide reporting
date in the calendar Set the range
in between the contract
period (project start
date) Set the range in between the contract period (finish
date)
RECURRING TASK
Activity Sequencing
How to decide? Experience Method Statements Drawings Detail Bill of Quantity (BQ)
How to show the relationship/link for every task/activity? Predecessor-Activity before Successor-Activity after
4 Types of relationship in CPM Network Finish to Start (FS) Finish to Finish (FF) Start to Finish (SF) Start to Start (SS)
CREATING THE RELATIONSHIP
ASSIGN THE DURATION-Experience • Using Experience
• Parametric Estimation
D=Q/PR
ASSIGN THE DURATION-Parametric Estimation
Resource Allocation Quantity Risk Consideration Duration Estimates
Building Works
Earthwork Earthwork team [1] 10,000m3 +10% 11 days
Structural Works Structural Team [2] 2000m3
Testing +7 days 17 days
Architectural Works
Architectural Team [2] 3,000m2
Delivery + 5 days 20 days
M&E Works M&E Team [2] 400nos Procurement + 5 days
25 days
Resource available (gang) Production rate
Earthwork Team [1] 1000m3/day/gang
Structure Team [2] 100m3/day/gang
Architecture Team [2] 100m2/day/gang
M&E Team [2] 10nos/day/gang
Resource Planning
ASSIGN THE DURATION-PE
Value of Work Work Value (RM)
Preliminaries Performance Bond/Insurance 10,000 Establish and Removal of Site Office 10,000 Progress Report 3,000
Earthwork 10,000 Piling 12,000 Building Work
Sub Structure 25,000 Super Structure 30,000 Roofing 7,000
Architecture
Wall 28,000 Floor 20,000 Painting 5,000
M&E Electrical 15,000 Plumbing 15,000
Road and Drainage 10,000 Total 200,000
INSERTING THE COST
View>Table>Cost
Insert all cost to specific task in
Fixed Cost Column
Payment Method, choose Start, Prorated or
End
INSERTING THE COST
Total Cost Must Equal to Contract
Sum
View Total Cost
17/11/2014 48
Resource Allocation
17/11/2014 49
Resource Allocation
17/11/2014 50
Resource Allocation
17/11/2014 51
17/11/2014 52
Resource Allocation
Set Baseline
17/11/2014 53
SET BASELINE FILE
Project>Set Baseline>Set Baseline
Cost Calculated (Baseline) must equal to Total
Cost
Visual Reports
17/11/2014 55
Visual Reporting: S-Curve (Financial)
Project>Visual Report>Cash Flow Report>View
Visual Reporting: S-Curve (Financial)
MSP transfer data to Excel
58
Visual Reporting: Expand the S-Curve (Financial)
Financial S-Curve
0
50000
100000
150000
200000
250000
0
2000
4000
6000
8000
10000
12000
14000
Week 9Week 10Week 11Week 12Week 13Week 14Week 15Week 16Week 17Week 18Week 19Week 20Week 21Week 22Week 23Week 24Week 25Week 26Week 27Week 28Week 29Week 30Week 31Week 32Week 33Week 34Week 35Week 36Week 37
Q1 Q2 Q3
2013
Cu
mu
lati
ve C
ost
Co
st
Cash Flow Report
Cost Cumulative Cost
View Tracking Tables
17/11/2014 60
Visual Reporting: S-Curve (Physical)
View>Tasks>Tracking
Set % Complete for
id no 1 as 100%
17/11/2014 62
Visual Reporting: S-Curve (Physical)
View>Task Usage>Detail Styles>insert the Percent Complete and Cumulative Percent Complete > ok!
Double Click on Details Section
17/11/2014 64
data copied to excel and manually create the graph
% complete 0 1% 3% 3% 2% 4% 2% 2% 2% 3% 2% 2% 2% 2% 4% 5% 3% 2% 6% 5% 4% 5% 8% 5% 3% 5% 2% 6% 2% 1% cum % complete 0 1% 4% 7% 9% 13% 15% 18% 20% 24% 26% 28% 31% 33% 37% 42% 45% 48% 53% 58% 62% 67% 75% 80% 83% 88% 91% 97% 99% 100%
0
0.2
0.4
0.6
0.8
1
1.2
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Physical S-Curve
% complete
cum % complete
Add item
Physical S-Curve
0
0.2
0.4
0.6
0.8
1
1.2
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Physical S-Curve
% complete
cum % complete